1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 12061435 MGR.NO. 585 PAGE 001 CONT 6153 SEC 46 JOB 001 RES ENGR MILLER, LESLIE PROJ SUP - 615346001 HWY IH0035 7901 N. IH 35 AUSTIN, TEX CNTY TRAVIS DIST 14 CONTRACT PRICE $ 254,782.32 REPORT DATE 04/23/2008 14.26.55 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JAN 01,2007 TO MAR 31,2008 EST NO 017 & FINAL EASTER-SEALS CENTRAL TEXAS, INC. 10984 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JAN 03, 2007 TIME COMPUTED FROM JAN 01, 2007 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 425 425 0 BROUGHT FORWARD ADDL DAYS GRANTED = 91 MAR 08 1 1 TOTAL DAYS ALLOWED = 456 2 1 DATE WORK COMPLETED 03/31/08 3 1 DAYS CHARGED TO DATE = 456 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 450 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 450 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 31 1 ----- ----- ----- 456 456 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 12061435 MGR.NO. 585 PAGE 001 CONT 6153 SEC 46 JOB 001 RES ENGR MILLER, LESLIE PROJ SUP - 615346001 HWY IH0035 7901 N. IH 35 AUSTIN, TEX CNTY TRAVIS DIST 14 CONTRACT PRICE $ 254,782.32 REPORT DATE 04/23/2008 14.26.56 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JAN 01,2007 TO MAR 31,2008 EST NO 017 & FINAL EASTER-SEALS CENTRAL TEXAS, INC. 10984 DIST. 14 COUNTY TRAVIS CONTROL 6153-46-001 PROJECT SUP - 615346001 HIGHWAY IH0035 0LIMITS- VARIOUS LOCATIONS IN TRAVIS COUNTY . 0TYPE OF WORK- LITTER PICKUP AND DISPOSAL 0 0005 PREPARED BY BECKY SMITH 01-03-2007 0 0055 LITTER PICKUP AND DISPOSAL NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0734 LITTER REMOVAL - TRACT (1) AC 9,724.000 10,472.000 7.390 77,388.08 0060 0734 ADJ EST QUANTITY TO DATE 12,155.000 0065 0734 LITTER REMOVAL - TRACT (2) AC 2,756.000 3,286.000 6.180 20,307.48 0065 0734 ADJ EST QUANTITY TO DATE 3,392.000 0070 0734 LITTER REMOVAL - TRACT (3) AC 12,324.000 14,220.000 6.310 89,728.20 0070 0734 ADJ EST QUANTITY TO DATE 15,405.000 0075 0734 LITTER REMOVAL - TRACT (4) AC 8,632.000 9,296.000 7.010 65,164.96 0075 0734 ADJ EST QUANTITY TO DATE 10,790.000 0080 0734 LITTER REMOVAL - TRACT (5) AC 3,016.000 3,306.000 7.590 25,092.54 0080 0734 ADJ EST QUANTITY TO DATE 3,770.000 0085 0734 LITTER REMOVAL - TRACT (6) AC 624.000 720.000 7.570 5,450.40 0085 0734 ADJ EST QUANTITY TO DATE 768.000 0090 9001*SHOP RATE INCREASE EFFECTIVE 7/24/07 LS 1.000 1.000 303.400 303.40 0095 9001*SHOP/WAGE RATE INCREASE - AUGUST 2007 LS 1,095.740 0.000 1.000 .00 0100 9001*SHOP/WAGE RATE INCREASE - AUGUST 2007 LS 1.000 1.000 1,095.740 1,095.74 0105 9001*SHOP/WAGE RATE INCREASE - SEPT 2007 LS 1.000 4,007.160 1.000 4,007.16 0110 9001*SHOP/WAGE RATE INCREASE SUPPL.AGMT. 2 EA 66,744.790 3,228.230 1.000 3,228.23 0 SUBTOTAL BID ITEMS $ 291,766.19 0 TOTAL AMOUNT WORK DONE LITTER PICKUP AND DISPOSAL $ 291,766.19 0 TOTAL AMOUNT WORK DONE CONTROL 6153-46-001 $ 291,766.19 1 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 12061435 MGR.NO. 585 PAGE 001 CONT 6153 SEC 46 JOB 001 RES ENGR MILLER, LESLIE PROJ SUP - 615346001 HWY IH0035 7901 N. IH 35 AUSTIN, TEX CNTY TRAVIS DIST 14 CONTRACT PRICE $ 254,782.32 REPORT DATE 04/23/2008 14.26.56 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JAN 01,2007 TO MAR 31,2008 EST NO 017 & FINAL EASTER-SEALS CENTRAL TEXAS, INC. 10984 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATIONS IN TRAVIS COUNTY 0 . DATE WORK BEGAN JAN 3 , 2007 WORKING DAYS USED 456 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED MAR 31 2008 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6153-46-001 SUP - 615346001 14 IH0035 TRAVIS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0734 LITTER REMOVAL - TRACT (1) AC 9,724.000 10,472.000 7.390 77,388.08 0734 ADJ EST QUANTITY TO DATE 12,155.000 0734 LITTER REMOVAL - TRACT (2) AC 2,756.000 3,286.000 6.180 20,307.48 0734 ADJ EST QUANTITY TO DATE 3,392.000 0734 LITTER REMOVAL - TRACT (3) AC 12,324.000 14,220.000 6.310 89,728.20 0734 ADJ EST QUANTITY TO DATE 15,405.000 0734 LITTER REMOVAL - TRACT (4) AC 8,632.000 9,296.000 7.010 65,164.96 0734 ADJ EST QUANTITY TO DATE 10,790.000 0734 LITTER REMOVAL - TRACT (5) AC 3,016.000 3,306.000 7.590 25,092.54 0734 ADJ EST QUANTITY TO DATE 3,770.000 0734 LITTER REMOVAL - TRACT (6) AC 624.000 720.000 7.570 5,450.40 0734* ADJ EST QUANTITY TO DATE 768.000 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 09001* SHOP RATE INCREASE EFFECTIVE 7/24/07 LS 1.000 1.000 303.400 303.40 9001* SHOP/WAGE RATE INCREASE - AUGUST 2007 LS 1.000 1.000 1,095.740 1,095.74 9001* SHOP/WAGE RATE INCREASE - SEPT 2007 LS 1.000 4,007.160 1.000 4,007.16 9001* SHOP/WAGE RATE INCREASE SUPPL.AGMT. 2 EA 66,744.790 3,228.230 1.000 3,228.23 0 SUBTOTAL BID ITEMS $ 291,766.19 1 CONTRACT TOTAL ALL ITEMS $ 291,766.19 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 12061435 MGR.NO. 585 PAGE 001 CONT 6153 SEC 46 JOB 001 RES ENGR MILLER, LESLIE PROJ SUP - 615346001 HWY IH0035 7901 N. IH 35 AUSTIN, TEX CNTY TRAVIS DIST 14 CONTRACT PRICE $ 254,782.32 REPORT DATE 04/23/2008 14.26.56 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JAN 01,2007 TO MAR 31,2008 EST NO 017 & FINAL EASTER-SEALS CENTRAL TEXAS, INC. 10984 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 227 SUP - 615346001 6153-46-001 291,766.19 .00 291,766.19 .00 .00 291,766.19 291,766.19 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 291,766.19 .00 291,766.19 .00 .00 291,766.19 291,766.19 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 12061435 MGR.NO. 585 PAGE 001 CONT 6153 SEC 46 JOB 001 RES ENGR MILLER, LESLIE PROJ SUP - 615346001 HWY IH0035 7901 N. IH 35 AUSTIN, TEX CNTY TRAVIS DIST 14 CONTRACT PRICE $ 254,782.32 REPORT DATE 04/23/2008 14.26.56 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JAN 01,2007 TO MAR 31,2008 EST NO 017 & FINAL EASTER-SEALS CENTRAL TEXAS, INC. 10984 ********************************************************************************************************** - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6153-46-001 SUP - 615346001 14 IH0035 TRAVIS -LIMITS - VARIOUS LOCATIONS IN TRAVIS COUNTY . - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 291,766.19