1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 11111906 MGR.NO. 053 PAGE 001 CONT 6233 SEC 06 JOB 001 RES ENGR METCALF, STEPHEN PROJ RMC - 623306001 HWY US0080 300 E. LOOP 390 MARSHALL CNTY HARRISON DIST 19 CONTRACT PRICE $ 109,911.00 REPORT DATE 03/25/2013 08.49.34 CONTRACTOR TERRY ENTERPRISES 10469 EST PERIOD MAY 17,2012 TO NOV 30,2012 EST NO 008 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN MAY 17, 2012 TIME COMPUTED FROM MAY 24, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 77 168 26 142 BROUGHT FORWARD ADDL DAYS GRANTED = 0 NOV 12 1 1 TIME SUSPENDED TOTAL DAYS ALLOWED = 77 2 1 TIME SUSPENDED DATE WORK COMPLETED 11/30/12 3 1 SATURDAY DAYS CHARGED TO DATE = 26 4 1 SUNDAY ASSESSED LIQ DAMAGES = 0 5 1 TIME SUSPENDED LIQ DAMAGE RATE $ 590 6 1 TIME SUSPENDED 7 1 TIME SUSPENDED LIQUIDATED DAMAGES 8 1 TIME SUSPENDED 0 DAYS AT $ 590 PER DAY 9 1 TIME SUSPENDED TOTAL = $ .00 10 1 SATURDAY 11 1 SUNDAY CERTIFIED AS CORRECT AND 12 1 TIME SUSPENDED ONE COPY HAS BEEN GIVEN 13 1 TIME SUSPENDED TO THE CONTRACTOR 14 1 TIME SUSPENDED 15 1 TIME SUSPENDED 16 1 TIME SUSPENDED ---------------------------- 17 1 SATURDAY AREA/PROJECT ENGINEER 18 1 SUNDAY 19 1 TIME SUSPENDED 20 1 TIME SUSPENDED 21 1 TIME SUSPENDED 22 1 TIME SUSPENDED 23 1 TIME SUSPENDED 24 1 SATURDAY 25 1 SUNDAY 26 1 TIME SUSPENDED 27 1 TIME SUSPENDED 28 1 TIME SUSPENDED 29 1 TIME SUSPENDED 30 1 WORK COMPLETED AND ACCEPTED 0 ----- ----- ----- 198 26 172 4 SATURDAY 4 SUNDAY 0 HOLIDAY 21 TIME SUSPENDED 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 11111906 MGR.NO. 053 PAGE 001 CONT 6233 SEC 06 JOB 001 RES ENGR METCALF, STEPHEN PROJ RMC - 623306001 HWY US0080 300 E. LOOP 390 MARSHALL CNTY HARRISON DIST 19 CONTRACT PRICE $ 109,911.00 REPORT DATE 03/25/2013 08.49.34 CONTRACTOR TERRY ENTERPRISES 10469 EST PERIOD MAY 17,2012 TO NOV 30,2012 EST NO 008 & FINAL DIST. 19 COUNTY HARRISON CONTROL 6233-06-001 PROJECT RMC - 623306001 HIGHWAY US0080 0LIMITS- VARIOUS . 0TYPE OF WORK- ROW MOWING & LITTER PICKUP - TRACT 6 0 0005 PREPARED BY ROBERT H. RATCLIFF, P.E. 0 0055 MOWING RIGHT OF WAY TRACT 6 NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 FULL-WIDTH MOWING - TRACT (6) AC 4,066.000 4,066.000 23.500 95,551.00 0065 0734 LITTER REMOVAL CYC 1.000 1.000 11,360.000 11,360.00 0070 0734 LITTER REMOVAL(SPOT) AC 150.000 0.000 20.000 .00 0 SUBTOTAL BID ITEMS $ 106,911.00 0 TOTAL AMOUNT WORK DONE MOWING RIGHT OF WAY TRACT 6 $ 106,911.00 0 TOTAL AMOUNT WORK DONE CONTROL 6233-06-001 $ 106,911.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 11111906 MGR.NO. 053 PAGE 001 CONT 6233 SEC 06 JOB 001 RES ENGR METCALF, STEPHEN PROJ RMC - 623306001 HWY US0080 300 E. LOOP 390 MARSHALL CNTY HARRISON DIST 19 CONTRACT PRICE $ 109,911.00 REPORT DATE 03/25/2013 08.49.35 CONTRACTOR TERRY ENTERPRISES 10469 EST PERIOD MAY 17,2012 TO NOV 30,2012 EST NO 008 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 . DATE WORK BEGAN MAY 17, 2012 WORKING DAYS USED 26 PERCENT COMPLETE 100.00 PERCENT TIME USED 33.70 DATE COMPLETED NOV 30 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6233-06-001 RMC - 623306001 19 US0080 HARRISON - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING - TRACT (6) AC 4,066.000 4,066.000 23.500 95,551.00 0734 LITTER REMOVAL CYC 1.000 1.000 11,360.000 11,360.00 0 SUBTOTAL BID ITEMS $ 106,911.00 0 CONTRACT TOTAL ALL ITEMS $ 106,911.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 11111906 MGR.NO. 053 PAGE 001 CONT 6233 SEC 06 JOB 001 RES ENGR METCALF, STEPHEN PROJ RMC - 623306001 HWY US0080 300 E. LOOP 390 MARSHALL CNTY HARRISON DIST 19 CONTRACT PRICE $ 109,911.00 REPORT DATE 03/25/2013 08.49.35 CONTRACTOR TERRY ENTERPRISES 10469 EST PERIOD MAY 17,2012 TO NOV 30,2012 EST NO 008 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 103 RMC - 623306001 6233-06-001 106,911.00 .00 106,911.00 .00 .00 106,911.00 106,911.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 106,911.00 .00 106,911.00 .00 .00 106,911.00 106,911.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 11111906 MGR.NO. 053 PAGE 001 CONT 6233 SEC 06 JOB 001 RES ENGR METCALF, STEPHEN PROJ RMC - 623306001 HWY US0080 300 E. LOOP 390 MARSHALL CNTY HARRISON DIST 19 CONTRACT PRICE $ 109,911.00 REPORT DATE 03/25/2013 08.49.35 CONTRACTOR TERRY ENTERPRISES 10469 EST PERIOD MAY 17,2012 TO NOV 30,2012 EST NO 008 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6233-06-001 RMC - 623306001 19 US0080 HARRISON -LIMITS - VARIOUS . - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 106,911.00