1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 5091901 MGR.NO. 055 PAGE 001 CONT 6194 SEC 10 JOB 001 RES ENGR ICENHOWER, KENNY PROJ RMC - 619410001 HWY IH0030 520 SOWELL LANE TEXARKANA CNTY BOWIE DIST 19 CONTRACT PRICE $ 33,799.48 REPORT DATE 11/06/2009 14.45.39 CONTRACTOR C.B. INDUSTRIES 14280 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 004 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 17, 2009 TIME COMPUTED FROM JUL 06, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 253 87 66 21 BROUGHT FORWARD ADDL DAYS GRANTED = 0 OCT 09 1 1 TOTAL DAYS ALLOWED = 253 2 1 DATE WORK COMPLETED 3 1 DAYS CHARGED TO DATE = 89 4 1 SUNDAY ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 425 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 425 PER DAY 9 1 TOTAL = $ .00 10 1 SATURDAY 11 1 SUNDAY CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 SATURDAY AREA/PROJECT ENGINEER 18 1 SUNDAY 19 1 20 1 21 1 22 1 23 1 24 1 SATURDAY 25 1 SUNDAY 26 1 27 1 28 1 29 1 30 1 31 1 SATURDAY ----- ----- ----- 118 89 29 4 SATURDAY 4 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 5091901 MGR.NO. 055 PAGE 001 CONT 6194 SEC 10 JOB 001 RES ENGR ICENHOWER, KENNY PROJ RMC - 619410001 HWY IH0030 520 SOWELL LANE TEXARKANA CNTY BOWIE DIST 19 CONTRACT PRICE $ 33,799.48 REPORT DATE 11/06/2009 14.45.39 CONTRACTOR C.B. INDUSTRIES 14280 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 004 DIST. 19 COUNTY BOWIE CONTROL 6194-10-001 PROJECT RMC - 619410001 HIGHWAY IH0030 0LIMITS- VARIOUS . 0TYPE OF WORK- DEBRIS REMOVAL-NORTH 0 0005 PREPARED BY ROBERT H. RATCLIFF, P.E. 0 0055 DEBRIS REMOVAL - NORTH NET LENGTH124.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0735 DEBRIS REMOVAL (CNTR MEDIANS/MAINLANES) CYC 52.000 10.000 649.990 6,499.90 0 SUBTOTAL BID ITEMS $ 6,499.90 0 TOTAL AMOUNT WORK DONE DEBRIS REMOVAL - NORTH $ 6,499.90 0 TOTAL AMOUNT WORK DONE CONTROL 6194-10-001 $ 6,499.90 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 5091901 MGR.NO. 055 PAGE 001 CONT 6194 SEC 10 JOB 001 RES ENGR ICENHOWER, KENNY PROJ RMC - 619410001 HWY IH0030 520 SOWELL LANE TEXARKANA CNTY BOWIE DIST 19 CONTRACT PRICE $ 33,799.48 REPORT DATE 11/06/2009 14.45.39 CONTRACTOR C.B. INDUSTRIES 14280 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 004 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 . DATE WORK BEGAN JUL 17, 2009 WORKING DAYS USED 89 PERCENT COMPLETE 19.23 PERCENT TIME USED 35.10 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6194-10-001 RMC - 619410001 19 IH0030 BOWIE - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0735 DEBRIS REMOVAL (CNTR MEDIANS/MAINLANES) CYC 52.000 10.000 649.990 6,499.90 0 SUBTOTAL BID ITEMS $ 6,499.90 0 CONTRACT TOTAL ALL ITEMS $ 6,499.90 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 5091901 MGR.NO. 055 PAGE 001 CONT 6194 SEC 10 JOB 001 RES ENGR ICENHOWER, KENNY PROJ RMC - 619410001 HWY IH0030 520 SOWELL LANE TEXARKANA CNTY BOWIE DIST 19 CONTRACT PRICE $ 33,799.48 REPORT DATE 11/06/2009 14.45.39 CONTRACTOR C.B. INDUSTRIES 14280 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 004 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 19 RMC - 619410001 6194-10-001 6,499.90 .00 6,499.90 .00 .00 6,499.90 5,199.92 1,299.98 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 6,499.90 .00 6,499.90 .00 .00 6,499.90 5,199.92 1,299.98 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 5091901 MGR.NO. 055 PAGE 001 CONT 6194 SEC 10 JOB 001 RES ENGR ICENHOWER, KENNY PROJ RMC - 619410001 HWY IH0030 520 SOWELL LANE TEXARKANA CNTY BOWIE DIST 19 CONTRACT PRICE $ 33,799.48 REPORT DATE 11/06/2009 14.45.40 CONTRACTOR C.B. INDUSTRIES 14280 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 004 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6194-10-001 RMC - 619410001 19 IH0030 BOWIE -LIMITS - VARIOUS . LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0735 DEBRIS REMOVAL (CNTR CYC 52.000 2.000 649.990 1,299.98 MEDIANS/MAINLANES) --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 1,299.98 0 TOTAL AMOUNT WORK DONE TO DATE - $ 6,499.90