1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 11081909 MGR.NO. 058 PAGE 001 CONT 6183 SEC 86 JOB 001 RES ENGR WISINGER, GLEN PROJ RMC - 618386001 HWY US0259 406 MCCOY BLVD. S. NEW BO CNTY BOWIE DIST 19 CONTRACT PRICE $ 86,843.40 REPORT DATE 02/01/2010 13.04.42 CONTRACTOR BRADFORD MOWING CO. 8680 EST PERIOD JUN 08,2009 TO DEC 14,2009 EST NO 008 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 08, 2009 TIME COMPUTED FROM JUN 08, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 21 176 32 144 BROUGHT FORWARD ADDL DAYS GRANTED = 0 DEC 09 1 1 RAIN TOTAL DAYS ALLOWED = 21 2 1 TOO WET DATE WORK COMPLETED 07/08/09 3 1 TOO WET DAYS CHARGED TO DATE = 21 4 1 ASSESSED LIQ DAMAGES = 0 5 1 SATURDAY LIQ DAMAGE RATE $ 400 6 1 SUNDAY 7 1 PHASE II 8 1 RAIN CONTRACT WORK DAYS = 21 9 1 TOO WET ADDL DAYS GRANTED = 0 10 1 TOO WET TOTAL DAYS ALLOWED = 21 11 1 DATE WORK COMPLETED 12/14/09 12 1 SATURDAY DAYS CHARGED TO DATE = 15 13 1 SUNDAY ASSESSED LIQ DAMAGES = 0 14 1 WORK COMPLETE/ACCEPTED TRACT 8 /TRACT 6LIQ DAMAGE RATE $ 400 0 CONTRACT TOTALS CONTRACT WORK DAYS = 42 ADDL DAYS GRANTED = 0 TOTAL DAYS ALLOWED = 42 DAYS CHARGED TO DATE= 36 ASSESSED LIQ DAMAGES= 0 0 LIQUIDATED DAMAGES 0 DAYS AT $ 400 PER DAY 0 DAYS AT $ 400 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR 0 ----- ----- ----- 190 36 154 ---------------------------- AREA/PROJECT ENGINEER 2 SATURDAY 2 SUNDAY 0 HOLIDAY 2 RAIN 4 TOO WET 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 11081909 MGR.NO. 058 PAGE 001 CONT 6183 SEC 86 JOB 001 RES ENGR WISINGER, GLEN PROJ RMC - 618386001 HWY US0259 406 MCCOY BLVD. S. NEW BO CNTY BOWIE DIST 19 CONTRACT PRICE $ 86,843.40 REPORT DATE 02/01/2010 13.04.43 CONTRACTOR BRADFORD MOWING CO. 8680 EST PERIOD JUN 08,2009 TO DEC 14,2009 EST NO 008 & FINAL DIST. 19 COUNTY BOWIE CONTROL 6183-86-001 PROJECT RMC - 618386001 HIGHWAY US0259 0LIMITS- VARIOUS . 0TYPE OF WORK- MOWING RIGHT OF WAY TRACT 8 0 0005 ROBERT H. RATCLIFF, P.E. 0 0055 MOWING RIGHT OF WAY TRACT 8 NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 FULL-WIDTH MOWING - TRACT (8) AC 4,060.000 4,060.000 21.390 86,843.40 0065 0730*FULL-WIDTH MOWING - TRACT (6) AC 2,200.000 2,200.000 21.390 47,058.00 0 SUBTOTAL BID ITEMS $ 133,901.40 0 SPECIAL DEDUCTIONS - 0 LINE MATRL. NO MATERIAL DESCRIPTION UNIT QUANTITY UNIT AMOUNT NO. PRICE($) ($) - 0075 00000000775 DELINEATOR/OBJECT MARKER EA 8.000 60.000 -480.00 0 TOTAL SPECIAL DEDUCTIONS - $ -480.00 0 TOTAL AMOUNT WORK DONE MOWING RIGHT OF WAY TRACT 8 $ 133,901.40 TOTAL SPECIAL DEDUCTIONS MOWING RIGHT OF WAY TRACT 8 $ -480.00 0 TOTAL AMOUNT WORK DONE CONTROL 6183-86-001 $ 133,901.40 0 TOTAL SPECIAL DEDUCTIONS CONTROL 6183-86-001 $ -480.00 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 11081909 MGR.NO. 058 PAGE 001 CONT 6183 SEC 86 JOB 001 RES ENGR WISINGER, GLEN PROJ RMC - 618386001 HWY US0259 406 MCCOY BLVD. S. NEW BO CNTY BOWIE DIST 19 CONTRACT PRICE $ 86,843.40 REPORT DATE 02/01/2010 13.04.43 CONTRACTOR BRADFORD MOWING CO. 8680 EST PERIOD JUN 08,2009 TO DEC 14,2009 EST NO 008 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 . DATE WORK BEGAN JUN 8 , 2009 WORKING DAYS USED 36 PERCENT COMPLETE 100.00 PERCENT TIME USED 85.70 DATE COMPLETED DEC 14 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6183-86-001 RMC - 618386001 19 US0259 BOWIE - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING - TRACT (8) AC 4,060.000 4,060.000 21.390 86,843.40 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 00730* FULL-WIDTH MOWING - TRACT (6) AC 2,200.000 2,200.000 21.390 47,058.00 0 SUBTOTAL BID ITEMS $ 133,901.40 0 CONTRACT TOTAL ALL ITEMS $ 133,901.40 SPECIAL DEDUCTIONS 0 UNIT AMOUNT MATRL. NO. MATERIAL DESCRIPTION UNIT QUANTITY PRICE ($) ($) 0 00000000775 DELINEATOR/OBJECT MARKER EA 8.000 60.000 -480.00 0 TOTAL SPECIAL DEDUCTIONS $ -480.00 0 CONTRACT TOTAL SPECIAL DEDUCTIONS $ -480.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 11081909 MGR.NO. 058 PAGE 001 CONT 6183 SEC 86 JOB 001 RES ENGR WISINGER, GLEN PROJ RMC - 618386001 HWY US0259 406 MCCOY BLVD. S. NEW BO CNTY BOWIE DIST 19 CONTRACT PRICE $ 86,843.40 REPORT DATE 02/01/2010 13.04.43 CONTRACTOR BRADFORD MOWING CO. 8680 EST PERIOD JUN 08,2009 TO DEC 14,2009 EST NO 008 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 19 RMC - 618386001 6183-86-001 133,901.40 .00 133,901.40 480.00 .00 133,421.40 133,421.40 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 133,901.40 .00 133,901.40 480.00 .00 133,421.40 133,421.40 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 11081909 MGR.NO. 058 PAGE 001 CONT 6183 SEC 86 JOB 001 RES ENGR WISINGER, GLEN PROJ RMC - 618386001 HWY US0259 406 MCCOY BLVD. S. NEW BO CNTY BOWIE DIST 19 CONTRACT PRICE $ 86,843.40 REPORT DATE 02/01/2010 13.04.43 CONTRACTOR BRADFORD MOWING CO. 8680 EST PERIOD JUN 08,2009 TO DEC 14,2009 EST NO 008 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6183-86-001 RMC - 618386001 19 US0259 BOWIE -LIMITS - VARIOUS . - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 133,901.40