1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 11081905 MGR.NO. 058 PAGE 001 CONT 6183 SEC 82 JOB 001 RES ENGR JONES, TOMMIE PROJ RMC - 618382001 HWY FM0251 689 SH 8 LINDEN CNTY CASS DIST 19 CONTRACT PRICE $ 112,511.70 REPORT DATE 11/06/2009 16.46.20 CONTRACTOR BRADFORD MOWING CO. 8680 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 006 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN MAY 20, 2009 TIME COMPUTED FROM MAY 18, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 30 136 28 108 BROUGHT FORWARD ADDL DAYS GRANTED = 0 OCT 09 1 1 TOTAL DAYS ALLOWED = 30 2 1 DATE WORK COMPLETED 06/30/09 3 1 SATURDAY DAYS CHARGED TO DATE = 24 4 1 SUNDAY ASSESSED LIQ DAMAGES = 0 5 1 TOO WET LIQ DAMAGE RATE $ 400 6 1 TOO WET 7 1 TOO WET PHASE II 8 1 TOO WET CONTRACT WORK DAYS = 1 9 1 RAIN ADDL DAYS GRANTED = 0 10 1 SATURDAY TOTAL DAYS ALLOWED = 1 11 1 SUNDAY DATE WORK COMPLETED 07/13/09 12 1 TOO WET DAYS CHARGED TO DATE = 0 13 1 RAIN ASSESSED LIQ DAMAGES = 0 14 1 TOO WET LIQ DAMAGE RATE $ 300 15 1 TOO WET 16 1 TOO WET PHASE III 17 1 SATURDAY CONTRACT WORK DAYS = 30 18 1 SUNDAY ADDL DAYS GRANTED = 0 19 1 TOTAL DAYS ALLOWED = 30 20 1 DATE WORK COMPLETED 21 1 TOO WET DAYS CHARGED TO DATE = 8 22 1 RAIN ASSESSED LIQ DAMAGES = 0 23 1 TOO WET LIQ DAMAGE RATE $ 400 24 1 SATURDAY 25 1 SUNDAY CONTRACT TOTALS 26 1 RAIN CONTRACT WORK DAYS = 61 27 1 TOO WET ADDL DAYS GRANTED = 0 28 1 RAIN TOTAL DAYS ALLOWED = 61 29 1 RAIN DAYS CHARGED TO DATE= 32 30 1 RAIN ASSESSED LIQ DAMAGES= 0 31 1 SATURDAY ----- ----- ----- LIQUIDATED DAMAGES 167 32 135 0 DAYS AT $ 400 PER DAY 0 DAYS AT $ 300 PER DAY 0 DAYS AT $ 400 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND 1 ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER 5 SATURDAY 4 SUNDAY 0 HOLIDAY 11 TOO WET 7 RAIN 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 11081905 MGR.NO. 058 PAGE 001 CONT 6183 SEC 82 JOB 001 RES ENGR JONES, TOMMIE PROJ RMC - 618382001 HWY FM0251 689 SH 8 LINDEN CNTY CASS DIST 19 CONTRACT PRICE $ 112,511.70 REPORT DATE 11/06/2009 16.46.20 CONTRACTOR BRADFORD MOWING CO. 8680 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 006 DIST. 19 COUNTY CASS CONTROL 6183-82-001 PROJECT RMC - 618382001 HIGHWAY FM0251 0LIMITS- VARIOUS . 0TYPE OF WORK- MOWING RIGHT OF WAY TRACT 5 0 0005 ROBERT H. RATCLIFF, P.E. 0 0055 MOWING RIGHT OF WAY TRACT 5 NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 FULL-WIDTH MOWING - TRACT (5) AC 5,953.000 4,968.000 18.900 93,895.20 0 SUBTOTAL BID ITEMS $ 93,895.20 0 TOTAL AMOUNT WORK DONE MOWING RIGHT OF WAY TRACT 5 $ 93,895.20 0 TOTAL AMOUNT WORK DONE CONTROL 6183-82-001 $ 93,895.20 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 11081905 MGR.NO. 058 PAGE 001 CONT 6183 SEC 82 JOB 001 RES ENGR JONES, TOMMIE PROJ RMC - 618382001 HWY FM0251 689 SH 8 LINDEN CNTY CASS DIST 19 CONTRACT PRICE $ 112,511.70 REPORT DATE 11/06/2009 16.46.20 CONTRACTOR BRADFORD MOWING CO. 8680 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 006 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 . DATE WORK BEGAN MAY 20, 2009 WORKING DAYS USED 32 PERCENT COMPLETE 83.45 PERCENT TIME USED 52.40 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6183-82-001 RMC - 618382001 19 FM0251 CASS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING - TRACT (5) AC 5,953.000 4,968.000 18.900 93,895.20 0 SUBTOTAL BID ITEMS $ 93,895.20 0 CONTRACT TOTAL ALL ITEMS $ 93,895.20 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 11081905 MGR.NO. 058 PAGE 001 CONT 6183 SEC 82 JOB 001 RES ENGR JONES, TOMMIE PROJ RMC - 618382001 HWY FM0251 689 SH 8 LINDEN CNTY CASS DIST 19 CONTRACT PRICE $ 112,511.70 REPORT DATE 11/06/2009 16.46.20 CONTRACTOR BRADFORD MOWING CO. 8680 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 006 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 34 RMC - 618382001 6183-82-001 93,895.20 .00 93,895.20 .00 .00 93,895.20 85,257.90 8,637.30 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 93,895.20 .00 93,895.20 .00 .00 93,895.20 85,257.90 8,637.30 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 11081905 MGR.NO. 058 PAGE 001 CONT 6183 SEC 82 JOB 001 RES ENGR JONES, TOMMIE PROJ RMC - 618382001 HWY FM0251 689 SH 8 LINDEN CNTY CASS DIST 19 CONTRACT PRICE $ 112,511.70 REPORT DATE 11/06/2009 16.46.20 CONTRACTOR BRADFORD MOWING CO. 8680 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 006 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6183-82-001 RMC - 618382001 19 FM0251 CASS -LIMITS - VARIOUS . LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0730 FULL-WIDTH MOWING - TRACT AC 5,953.000 457.000 18.900 8,637.30 (5) --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 8,637.30 0 TOTAL AMOUNT WORK DONE TO DATE - $ 93,895.20