1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 7081931 MGR.NO. 054 PAGE 001 CONT 6182 SEC 15 JOB 001 RES ENGR THOMAS, SAMMY PROJ SUP - 618215001 HWY US0259 2210 W. FERGUSON MT. PLEA CNTY UPSHUR DIST 19 CONTRACT PRICE $ 20,146.00 REPORT DATE 09/15/2009 08.10.19 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD SEP 01,2008 TO AUG 31,2009 EST NO 013 & FINAL CAMP COUNTY SERVICE INDUSTRIES 10865 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN SEP 01, 2008 TIME COMPUTED FROM SEP 01, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 334 334 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 AUG 09 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 08/31/09 3 1 DAYS CHARGED TO DATE = 365 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 31 1 ----- ----- ----- 365 365 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 7081931 MGR.NO. 054 PAGE 001 CONT 6182 SEC 15 JOB 001 RES ENGR THOMAS, SAMMY PROJ SUP - 618215001 HWY US0259 2210 W. FERGUSON MT. PLEA CNTY UPSHUR DIST 19 CONTRACT PRICE $ 20,146.00 REPORT DATE 09/15/2009 08.10.20 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD SEP 01,2008 TO AUG 31,2009 EST NO 013 & FINAL CAMP COUNTY SERVICE INDUSTRIES 10865 DIST. 19 COUNTY UPSHUR CONTROL 6182-15-001 PROJECT SUP - 618215001 HIGHWAY US0259 0LIMITS- VARIOUS . 0TYPE OF WORK- PICNIC MAINTENANCE FY 2009 0 0005 PREPARED BY ROBERT H. RATCLIFF, P.E. 0 0055 PICNIC AREA MAINTENANCE NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0745 JANITORIAL MAINT (PICNIC AREAS) CYC 104.000 105.000 138.500 14,542.50 0065 0745 GROUNDS MAINT (MOWING/TRIMMING) CYC 10.000 10.000 404.200 4,042.00 0070 0745 GROUNDS MAINT (TREE PRUN/LEAF REMOVAL) CYC 2.000 1.000 850.000 850.00 0 SUBTOTAL BID ITEMS $ 19,434.50 0 TOTAL AMOUNT WORK DONE PICNIC AREA MAINTENANCE $ 19,434.50 0 TOTAL AMOUNT WORK DONE CONTROL 6182-15-001 $ 19,434.50 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 7081931 MGR.NO. 054 PAGE 001 CONT 6182 SEC 15 JOB 001 RES ENGR THOMAS, SAMMY PROJ SUP - 618215001 HWY US0259 2210 W. FERGUSON MT. PLEA CNTY UPSHUR DIST 19 CONTRACT PRICE $ 20,146.00 REPORT DATE 09/15/2009 08.10.20 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD SEP 01,2008 TO AUG 31,2009 EST NO 013 & FINAL CAMP COUNTY SERVICE INDUSTRIES 10865 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 . DATE WORK BEGAN SEP 1 , 2008 WORKING DAYS USED 365 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED AUG 31 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6182-15-001 SUP - 618215001 19 US0259 UPSHUR - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0745 JANITORIAL MAINT (PICNIC AREAS) CYC 104.000 105.000 138.500 14,542.50 0745 GROUNDS MAINT (MOWING/TRIMMING) CYC 10.000 10.000 404.200 4,042.00 0745 GROUNDS MAINT (TREE PRUN/LEAF REMOVAL) CYC 2.000 1.000 850.000 850.00 0 SUBTOTAL BID ITEMS $ 19,434.50 0 CONTRACT TOTAL ALL ITEMS $ 19,434.50 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 7081931 MGR.NO. 054 PAGE 001 CONT 6182 SEC 15 JOB 001 RES ENGR THOMAS, SAMMY PROJ SUP - 618215001 HWY US0259 2210 W. FERGUSON MT. PLEA CNTY UPSHUR DIST 19 CONTRACT PRICE $ 20,146.00 REPORT DATE 09/15/2009 08.10.20 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD SEP 01,2008 TO AUG 31,2009 EST NO 013 & FINAL CAMP COUNTY SERVICE INDUSTRIES 10865 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 230 SUP - 618215001 6182-15-001 19,434.50 .00 19,434.50 .00 .00 19,434.50 19,434.50 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 19,434.50 .00 19,434.50 .00 .00 19,434.50 19,434.50 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 7081931 MGR.NO. 054 PAGE 001 CONT 6182 SEC 15 JOB 001 RES ENGR THOMAS, SAMMY PROJ SUP - 618215001 HWY US0259 2210 W. FERGUSON MT. PLEA CNTY UPSHUR DIST 19 CONTRACT PRICE $ 20,146.00 REPORT DATE 09/15/2009 08.10.20 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD SEP 01,2008 TO AUG 31,2009 EST NO 013 & FINAL CAMP COUNTY SERVICE INDUSTRIES 10865 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6182-15-001 SUP - 618215001 19 US0259 UPSHUR -LIMITS - VARIOUS . - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 19,434.50