1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 5050406 MGR.NO. 015 PAGE 001 CONT 6122 SEC 15 JOB 001 RES ENGR DAVIS, DAVID PROJ RMC - 612215001 HWY US0287 PO BOX 1125 STRATFORD CNTY SHERMAN DIST 04 CONTRACT PRICE $ 127,282.08 REPORT DATE 11/15/2010 09.55.40 CONTRACTOR BERT WHITAKER 11255 EST PERIOD OCT 12,2005 TO AUG 01,2010 EST NO 059 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN OCT 12, 2005 TIME COMPUTED FROM OCT 12, 2005 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 75 1,723 44 1,679 BROUGHT FORWARD ADDL DAYS GRANTED = 75 AUG 10 1 1 WORK COMPLETED AND ACCEPTED TOTAL DAYS ALLOWED = 150 DATE WORK COMPLETED 08/01/10 DAYS CHARGED TO DATE = 48 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 400 0 LIQUIDATED DAMAGES 0 DAYS AT $ 400 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 1,724 44 1,680 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 5050406 MGR.NO. 015 PAGE 001 CONT 6122 SEC 15 JOB 001 RES ENGR DAVIS, DAVID PROJ RMC - 612215001 HWY US0287 PO BOX 1125 STRATFORD CNTY SHERMAN DIST 04 CONTRACT PRICE $ 127,282.08 REPORT DATE 11/15/2010 09.55.40 CONTRACTOR BERT WHITAKER 11255 EST PERIOD OCT 12,2005 TO AUG 01,2010 EST NO 059 & FINAL DIST. 04 COUNTY SHERMAN CONTROL 6122-15-001 PROJECT RMC - 612215001 HIGHWAY US0287 0LIMITS- SEE PLAN SHEETS SEE PLAN SHEETS 0TYPE OF WORK- MOWING HIGHWAY RIGHT OF WAY 0 0005 PREPARED BY BRAD BUCHANAN 3-10-2005 0 0055 MOWING HIGHWAY RIGHT OF WAY NET LENGTH 1.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 STRIP MOWING AC 3,884.000 6,437.000 16.980 109,300.26 0060 0730 ADJ EST QUANTITY TO DATE 6,526.000 0065 0730 FULL-WIDTH MOWING AC 3,412.000 8,066.000 16.980 136,960.68 0065 0730 ADJ EST QUANTITY TO DATE 8,066.000 0070 0730 SPOT MOWING AC 200.000 0.000 16.980 .00 0070 0730 ADJ EST QUANTITY TO DATE 400.000 0 SUBTOTAL BID ITEMS $ 246,260.94 0 TOTAL AMOUNT WORK DONE MOWING HIGHWAY RIGHT OF WAY $ 246,260.94 0 TOTAL AMOUNT WORK DONE CONTROL 6122-15-001 $ 246,260.94 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 5050406 MGR.NO. 015 PAGE 001 CONT 6122 SEC 15 JOB 001 RES ENGR DAVIS, DAVID PROJ RMC - 612215001 HWY US0287 PO BOX 1125 STRATFORD CNTY SHERMAN DIST 04 CONTRACT PRICE $ 127,282.08 REPORT DATE 11/15/2010 09.55.40 CONTRACTOR BERT WHITAKER 11255 EST PERIOD OCT 12,2005 TO AUG 01,2010 EST NO 059 & FINAL 0*********************************************************************************************************************************** -LIMITS - SEE PLAN SHEETS 0 SEE PLAN SHEETS DATE WORK BEGAN OCT 12, 2005 WORKING DAYS USED 48 PERCENT COMPLETE 100.00 PERCENT TIME USED 32.00 DATE COMPLETED AUG 1 2010 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6122-15-001 RMC - 612215001 04 US0287 SHERMAN - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 STRIP MOWING AC 3,884.000 6,437.000 16.980 109,300.26 0730 ADJ EST QUANTITY TO DATE 6,526.000 0730 FULL-WIDTH MOWING AC 3,412.000 8,066.000 16.980 136,960.68 0730 ADJ EST QUANTITY TO DATE 8,066.000 0 SUBTOTAL BID ITEMS $ 246,260.94 0 CONTRACT TOTAL ALL ITEMS $ 246,260.94 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 5050406 MGR.NO. 015 PAGE 001 CONT 6122 SEC 15 JOB 001 RES ENGR DAVIS, DAVID PROJ RMC - 612215001 HWY US0287 PO BOX 1125 STRATFORD CNTY SHERMAN DIST 04 CONTRACT PRICE $ 127,282.08 REPORT DATE 11/15/2010 09.55.40 CONTRACTOR BERT WHITAKER 11255 EST PERIOD OCT 12,2005 TO AUG 01,2010 EST NO 059 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 211 RMC - 612215001 6122-15-001 246,260.94 .00 246,260.94 .00 .00 246,260.94 246,260.94 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 246,260.94 .00 246,260.94 .00 .00 246,260.94 246,260.94 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 5050406 MGR.NO. 015 PAGE 001 CONT 6122 SEC 15 JOB 001 RES ENGR DAVIS, DAVID PROJ RMC - 612215001 HWY US0287 PO BOX 1125 STRATFORD CNTY SHERMAN DIST 04 CONTRACT PRICE $ 127,282.08 REPORT DATE 11/15/2010 09.55.41 CONTRACTOR BERT WHITAKER 11255 EST PERIOD OCT 12,2005 TO AUG 01,2010 EST NO 059 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6122-15-001 RMC - 612215001 04 US0287 SHERMAN -LIMITS - SEE PLAN SHEETS SEE PLAN SHEETS - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 246,260.94