1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 4130834 MGR.NO. PAGE 001 CONT 6258 SEC 78 JOB 001 RES ENGR BOLIN, SENDY PROJ SUP - 625878001 HWY US0083 4250 NORTH CLACK ABILENE CNTY TAYLOR DIST 08 CONTRACT PRICE $ 149,176.24 REPORT DATE 02/21/2014 13.30.53 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD MAY 01,2013 TO JAN 31,2014 EST NO 009 & FINAL WORK SERVICES CORPORATION 11541 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN MAY 01, 2013 TIME COMPUTED FROM MAY 01, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 245 245 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JAN 14 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 01/31/14 3 1 DAYS CHARGED TO DATE = 276 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 31 1 ----- ----- ----- 276 276 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 4130834 MGR.NO. PAGE 001 CONT 6258 SEC 78 JOB 001 RES ENGR BOLIN, SENDY PROJ SUP - 625878001 HWY US0083 4250 NORTH CLACK ABILENE CNTY TAYLOR DIST 08 CONTRACT PRICE $ 149,176.24 REPORT DATE 02/21/2014 13.30.54 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD MAY 01,2013 TO JAN 31,2014 EST NO 009 & FINAL WORK SERVICES CORPORATION 11541 DIST. 08 COUNTY TAYLOR CONTROL 6258-78-001 PROJECT SUP - 625878001 HIGHWAY US0083 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- LITTER REMOVAL 0 0005 PREPARED BY SENDY BOLIN 0 0055 ALL ITEMS NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0734 LITTER REMOVAL(SPOT) AC 596.000 500.000 12.000 6,000.00 0065 0734 LITTER REMOVAL - TRACT (1) CYC 24.000 14.000 1,280.000 17,920.00 0070 0734 LITTER REMOVAL - TRACT (2) CYC 24.000 15.000 1,024.100 15,361.50 0075 0734 LITTER REMOVAL - TRACT (3) CYC 4.000 2.000 4,521.410 9,042.82 0080 0734 LITTER REMOVAL - TRACT (4) CYC 6.000 4.000 3,099.850 12,399.40 0085 0734 LITTER REMOVAL - TRACT (5) CYC 4.000 3.000 2,321.800 6,965.40 0090 0734 LITTER REMOVAL - TRACT (6) CYC 6.000 5.000 2,712.960 13,564.80 0095 0734 LITTER REMOVAL - TRACT (7) CYC 12.000 9.000 50.520 454.68 0100 0734 LITTER REMOVAL - TRACT (8) CYC 10.000 6.000 502.830 3,016.98 0105 0734 LITTER REMOVAL - TRACT (9) CYC 8.000 4.000 2,355.200 9,420.80 0 SUBTOTAL BID ITEMS $ 94,146.38 0 TOTAL AMOUNT WORK DONE ALL ITEMS $ 94,146.38 0 TOTAL AMOUNT WORK DONE CONTROL 6258-78-001 $ 94,146.38 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 4130834 MGR.NO. PAGE 001 CONT 6258 SEC 78 JOB 001 RES ENGR BOLIN, SENDY PROJ SUP - 625878001 HWY US0083 4250 NORTH CLACK ABILENE CNTY TAYLOR DIST 08 CONTRACT PRICE $ 149,176.24 REPORT DATE 02/21/2014 13.30.54 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD MAY 01,2013 TO JAN 31,2014 EST NO 009 & FINAL WORK SERVICES CORPORATION 11541 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN MAY 1 , 2013 WORKING DAYS USED 276 PERCENT COMPLETE 100.00 PERCENT TIME USED 75.60 DATE COMPLETED JAN 31 2014 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6258-78-001 SUP - 625878001 08 US0083 TAYLOR - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0734 LITTER REMOVAL(SPOT) AC 596.000 500.000 12.000 6,000.00 0734 LITTER REMOVAL - TRACT (1) CYC 24.000 14.000 1,280.000 17,920.00 0734 LITTER REMOVAL - TRACT (2) CYC 24.000 15.000 1,024.100 15,361.50 0734 LITTER REMOVAL - TRACT (3) CYC 4.000 2.000 4,521.410 9,042.82 0734 LITTER REMOVAL - TRACT (4) CYC 6.000 4.000 3,099.850 12,399.40 0734 LITTER REMOVAL - TRACT (5) CYC 4.000 3.000 2,321.800 6,965.40 0734 LITTER REMOVAL - TRACT (6) CYC 6.000 5.000 2,712.960 13,564.80 0734 LITTER REMOVAL - TRACT (7) CYC 12.000 9.000 50.520 454.68 0734 LITTER REMOVAL - TRACT (8) CYC 10.000 6.000 502.830 3,016.98 0734 LITTER REMOVAL - TRACT (9) CYC 8.000 4.000 2,355.200 9,420.80 0 SUBTOTAL BID ITEMS $ 94,146.38 0 CONTRACT TOTAL ALL ITEMS $ 94,146.38 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 4130834 MGR.NO. PAGE 001 CONT 6258 SEC 78 JOB 001 RES ENGR BOLIN, SENDY PROJ SUP - 625878001 HWY US0083 4250 NORTH CLACK ABILENE CNTY TAYLOR DIST 08 CONTRACT PRICE $ 149,176.24 REPORT DATE 02/21/2014 13.30.54 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD MAY 01,2013 TO JAN 31,2014 EST NO 009 & FINAL WORK SERVICES CORPORATION 11541 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 221 SUP - 625878001 6258-78-001 94,146.38 .00 94,146.38 .00 .00 94,146.38 81,207.98 12,938.40 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 94,146.38 .00 94,146.38 .00 .00 94,146.38 81,207.98 12,938.40 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 4130834 MGR.NO. PAGE 001 CONT 6258 SEC 78 JOB 001 RES ENGR BOLIN, SENDY PROJ SUP - 625878001 HWY US0083 4250 NORTH CLACK ABILENE CNTY TAYLOR DIST 08 CONTRACT PRICE $ 149,176.24 REPORT DATE 02/21/2014 13.30.55 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD MAY 01,2013 TO JAN 31,2014 EST NO 009 & FINAL WORK SERVICES CORPORATION 11541 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6258-78-001 SUP - 625878001 08 US0083 TAYLOR -LIMITS - VARIOUS VARIOUS LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 65 0734 LITTER REMOVAL - TRACT (1) CYC 24.000 2.000 1,280.000 2,560.00 70 0734 LITTER REMOVAL - TRACT (2) CYC 24.000 2.000 1,024.100 2,048.20 80 0734 LITTER REMOVAL - TRACT (4) CYC 6.000 1.000 3,099.850 3,099.85 85 0734 LITTER REMOVAL - TRACT (5) CYC 4.000 1.000 2,321.800 2,321.80 95 0734 LITTER REMOVAL - TRACT (7) CYC 12.000 1.000 50.520 50.52 100 0734 LITTER REMOVAL - TRACT (8) CYC 10.000 1.000 502.830 502.83 105 0734 LITTER REMOVAL - TRACT (9) CYC 8.000 1.000 2,355.200 2,355.20 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 12,938.40 0 TOTAL AMOUNT WORK DONE TO DATE - $ 94,146.38