1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 11120806 MGR.NO. PAGE 001 CONT 6249 SEC 31 JOB 001 RES ENGR PAYLOR, DEBBIE PROJ RMC - 624931001 HWY US0380 4250 N. CLACK ABILENE CNTY KENT DIST 08 CONTRACT PRICE $ 172,854.00 REPORT DATE 07/02/2014 16.22.47 CONTRACTOR KENNETH THOMASON 11017 EST PERIOD JUN 01,2014 TO JUN 30,2014 EST NO 012 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 24, 2013 TIME COMPUTED FROM JUL 08, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 64 328 64 264 BROUGHT FORWARD ADDL DAYS GRANTED = 64 JUN 14 1 1 SUNDAY TOTAL DAYS ALLOWED = 128 2 1 CYCLE NOT STARTED DATE WORK COMPLETED 3 1 CYCLE NOT STARTED DAYS CHARGED TO DATE = 68 4 1 CYCLE NOT STARTED ASSESSED LIQ DAMAGES = 0 5 1 CYCLE NOT STARTED LIQ DAMAGE RATE $ 590 6 1 CYCLE NOT STARTED 7 1 SATURDAY LIQUIDATED DAMAGES 8 1 SUNDAY 0 DAYS AT $ 590 PER DAY 9 1 CYCLE NOT STARTED TOTAL = $ .00 10 1 CYCLE NOT STARTED 11 1 CYCLE NOT STARTED CERTIFIED AS CORRECT AND 12 1 CYCLE NOT STARTED ONE COPY HAS BEEN GIVEN 13 1 CYCLE NOT STARTED TO THE CONTRACTOR 14 1 SATURDAY 15 1 SUNDAY 16 1 CYCLE NOT STARTED ---------------------------- 17 1 CYCLE NOT STARTED AREA/PROJECT ENGINEER 18 1 CYCLE NOT STARTED 19 1 CYCLE NOT STARTED 20 1 CYCLE NOT STARTED 21 1 SATURDAY 22 1 SUNDAY 23 1 CYCLE NOT STARTED 24 1 CYCLE NOT STARTED 25 1 TIME STARTED NO WORK PERFORMED 26 1 TIME STARTED NO WORK PERFORMED 27 1 TIME STARTED NO WORK PERFORMED 28 1 SATURDAY 29 1 SUNDAY 30 1 TIME STARTED NO WORK PERFORMED 0 ----- ----- ----- 358 68 290 4 SATURDAY 5 SUNDAY 0 HOLIDAY 17 CYCLE NOT STARTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 11120806 MGR.NO. PAGE 001 CONT 6249 SEC 31 JOB 001 RES ENGR PAYLOR, DEBBIE PROJ RMC - 624931001 HWY US0380 4250 N. CLACK ABILENE CNTY KENT DIST 08 CONTRACT PRICE $ 172,854.00 REPORT DATE 07/02/2014 16.22.47 CONTRACTOR KENNETH THOMASON 11017 EST PERIOD JUN 01,2014 TO JUN 30,2014 EST NO 012 DIST. 08 COUNTY KENT CONTROL 6249-31-001 PROJECT RMC - 624931001 HIGHWAY US0380 0LIMITS- VARIOUS LOCATIONS IN KENT CO. VARIOUS LOCATIONS IN SCURRY CO. 0TYPE OF WORK- MOWING HIGHWAY RIGHT OF WAY 0 0005 PREPARED BY DEBBIE PAYLOR 0 0055 ALL ITEMS NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 FULL-WIDTH MOWING AC 7,857.000 7,857.000 22.000 172,854.00 0060 0730 ADJ EST QUANTITY TO DATE 15,714.000 0 SUBTOTAL BID ITEMS $ 172,854.00 0 TOTAL AMOUNT WORK DONE ALL ITEMS $ 172,854.00 0 TOTAL AMOUNT WORK DONE CONTROL 6249-31-001 $ 172,854.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 11120806 MGR.NO. PAGE 001 CONT 6249 SEC 31 JOB 001 RES ENGR PAYLOR, DEBBIE PROJ RMC - 624931001 HWY US0380 4250 N. CLACK ABILENE CNTY KENT DIST 08 CONTRACT PRICE $ 172,854.00 REPORT DATE 07/02/2014 16.22.48 CONTRACTOR KENNETH THOMASON 11017 EST PERIOD JUN 01,2014 TO JUN 30,2014 EST NO 012 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATIONS IN KENT CO. 0 VARIOUS LOCATIONS IN SCURRY CO. DATE WORK BEGAN JUL 24, 2013 WORKING DAYS USED 68 PERCENT COMPLETE 99.99 PERCENT TIME USED 53.10 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6249-31-001 RMC - 624931001 08 US0380 KENT - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING AC 7,857.000 7,857.000 22.000 172,854.00 0730 ADJ EST QUANTITY TO DATE 15,714.000 0 SUBTOTAL BID ITEMS $ 172,854.00 0 CONTRACT TOTAL ALL ITEMS $ 172,854.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 11120806 MGR.NO. PAGE 001 CONT 6249 SEC 31 JOB 001 RES ENGR PAYLOR, DEBBIE PROJ RMC - 624931001 HWY US0380 4250 N. CLACK ABILENE CNTY KENT DIST 08 CONTRACT PRICE $ 172,854.00 REPORT DATE 07/02/2014 16.22.48 CONTRACTOR KENNETH THOMASON 11017 EST PERIOD JUN 01,2014 TO JUN 30,2014 EST NO 012 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 132 RMC - 624931001 6249-31-001 172,854.00 .00 172,854.00 .00 .00 172,854.00 172,854.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 172,854.00 .00 172,854.00 .00 .00 172,854.00 172,854.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 11120806 MGR.NO. PAGE 001 CONT 6249 SEC 31 JOB 001 RES ENGR PAYLOR, DEBBIE PROJ RMC - 624931001 HWY US0380 4250 N. CLACK ABILENE CNTY KENT DIST 08 CONTRACT PRICE $ 172,854.00 REPORT DATE 07/02/2014 16.22.48 CONTRACTOR KENNETH THOMASON 11017 EST PERIOD JUN 01,2014 TO JUN 30,2014 EST NO 012 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6249-31-001 RMC - 624931001 08 US0380 KENT -LIMITS - VARIOUS LOCATIONS IN KENT CO. VARIOUS LOCATIONS IN SCURRY CO. - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 172,854.00