1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 10090801 MGR.NO. PAGE 001 CONT 6073 SEC 22 JOB 001 RES ENGR PAYLOR, DEBBIE PROJ RMC - 607322001 HWY US0083 4250 N. CLACK ABILENE CNTY JONES DIST 08 CONTRACT PRICE $ 23,331.31 REPORT DATE 12/08/2010 14.25.23 CONTRACTOR WYATT FARMS 13461 EST PERIOD DEC 08,2009 TO NOV 04,2010 EST NO 012 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN DEC 21, 2009 TIME COMPUTED FROM DEC 08, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 104 328 78 250 BROUGHT FORWARD ADDL DAYS GRANTED = 0 NOV 10 1 1 CYCLE COMPLETE TOTAL DAYS ALLOWED = 104 2 1 CYCLE COMPLETE DATE WORK COMPLETED 11/04/10 3 1 CYCLE COMPLETE DAYS CHARGED TO DATE = 78 4 1 CONTRACT TERMINATED ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 425 0 LIQUIDATED DAMAGES 0 DAYS AT $ 425 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 332 78 254 0 SATURDAY 0 SUNDAY 0 HOLIDAY 3 CYCLE COMPLETE 1 CONTRACT TERMINATED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 10090801 MGR.NO. PAGE 001 CONT 6073 SEC 22 JOB 001 RES ENGR PAYLOR, DEBBIE PROJ RMC - 607322001 HWY US0083 4250 N. CLACK ABILENE CNTY JONES DIST 08 CONTRACT PRICE $ 23,331.31 REPORT DATE 12/08/2010 14.25.23 CONTRACTOR WYATT FARMS 13461 EST PERIOD DEC 08,2009 TO NOV 04,2010 EST NO 012 & FINAL DIST. 08 COUNTY JONES CONTROL 6073-22-001 PROJECT RMC - 607322001 HIGHWAY US0083 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- LANDSCAPE MAINTENANCE 0 0005 PREPARED BY DEBBIE PAYLOR 0 0055 ALL ITEMS NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0751 LITTER PICKUP AC 719.880 539.910 14.910 8,050.06 0065 0751 MOWING, TRIMMING, AND EDGING AC 719.880 539.910 17.500 9,448.43 0 SUBTOTAL BID ITEMS $ 17,498.49 0 SPECIAL DEDUCTIONS - 0 LINE MATRL. NO MATERIAL DESCRIPTION UNIT QUANTITY UNIT AMOUNT NO. PRICE($) ($) - 0070 00000000775 DAMAGES LS 1.000 3,520.140 -3,520.14 0 TOTAL SPECIAL DEDUCTIONS - $ -3,520.14 0 0100 DAMAGES - LANDSCAPE PROJECT AT "Y" NORTH OF ANSON 0 TOTAL AMOUNT WORK DONE ALL ITEMS $ 17,498.49 TOTAL SPECIAL DEDUCTIONS ALL ITEMS $ -3,520.14 0 TOTAL AMOUNT WORK DONE CONTROL 6073-22-001 $ 17,498.49 0 TOTAL SPECIAL DEDUCTIONS CONTROL 6073-22-001 $ -3,520.14 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 10090801 MGR.NO. PAGE 001 CONT 6073 SEC 22 JOB 001 RES ENGR PAYLOR, DEBBIE PROJ RMC - 607322001 HWY US0083 4250 N. CLACK ABILENE CNTY JONES DIST 08 CONTRACT PRICE $ 23,331.31 REPORT DATE 12/08/2010 14.25.23 CONTRACTOR WYATT FARMS 13461 EST PERIOD DEC 08,2009 TO NOV 04,2010 EST NO 012 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN DEC 21, 2009 WORKING DAYS USED 78 PERCENT COMPLETE 100.00 PERCENT TIME USED 75.00 DATE COMPLETED NOV 4 2010 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6073-22-001 RMC - 607322001 08 US0083 JONES - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0751 LITTER PICKUP AC 719.880 539.910 14.910 8,050.06 0751 MOWING, TRIMMING, AND EDGING AC 719.880 539.910 17.500 9,448.43 0 SUBTOTAL BID ITEMS $ 17,498.49 0 CONTRACT TOTAL ALL ITEMS $ 17,498.49 SPECIAL DEDUCTIONS 0 UNIT AMOUNT MATRL. NO. MATERIAL DESCRIPTION UNIT QUANTITY PRICE ($) ($) 0 00000000775 DAMAGES LS 1.000 3,520.140 -3,520.14 0 TOTAL SPECIAL DEDUCTIONS $ -3,520.14 0 CONTRACT TOTAL SPECIAL DEDUCTIONS $ -3,520.14 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 10090801 MGR.NO. PAGE 001 CONT 6073 SEC 22 JOB 001 RES ENGR PAYLOR, DEBBIE PROJ RMC - 607322001 HWY US0083 4250 N. CLACK ABILENE CNTY JONES DIST 08 CONTRACT PRICE $ 23,331.31 REPORT DATE 12/08/2010 14.25.23 CONTRACTOR WYATT FARMS 13461 EST PERIOD DEC 08,2009 TO NOV 04,2010 EST NO 012 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 128 RMC - 607322001 6073-22-001 17,498.49 .00 17,498.49 3,520.14 .00 13,978.35 13,431.93 546.42 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 17,498.49 .00 17,498.49 3,520.14 .00 13,978.35 13,431.93 546.42 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 10090801 MGR.NO. PAGE 001 CONT 6073 SEC 22 JOB 001 RES ENGR PAYLOR, DEBBIE PROJ RMC - 607322001 HWY US0083 4250 N. CLACK ABILENE CNTY JONES DIST 08 CONTRACT PRICE $ 23,331.31 REPORT DATE 12/08/2010 14.25.24 CONTRACTOR WYATT FARMS 13461 EST PERIOD DEC 08,2009 TO NOV 04,2010 EST NO 012 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6073-22-001 RMC - 607322001 08 US0083 JONES -LIMITS - VARIOUS VARIOUS - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 17,498.49