1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 4090804 MGR.NO. PAGE 001 CONT 6032 SEC 91 JOB 001 RES ENGR PAYLOR, DEBBIE PROJ RMC - 603291001 HWY US0083 4250 N. CLACK ABILENE CNTY TAYLOR DIST 08 CONTRACT PRICE $ 90,496.16 REPORT DATE 11/03/2009 10.45.43 CONTRACTOR KENNETH THOMASON 11017 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 005 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 02, 2009 TIME COMPUTED FROM JUN 08, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 59 121 33 88 BROUGHT FORWARD ADDL DAYS GRANTED = 0 OCT 09 1 1 NO TIME CHARGED NO WORK ORDER ISSUED TOTAL DAYS ALLOWED = 59 2 1 NO TIME CHARGED NO WORK ORDER ISSUED DATE WORK COMPLETED 3 1 SATURDAY DAYS CHARGED TO DATE = 33 4 1 SUNDAY ASSESSED LIQ DAMAGES = 0 5 1 NO TIME CHARGED NO WORK ORDER ISSUED LIQ DAMAGE RATE $ 400 6 1 NO TIME CHARGED NO WORK ORDER ISSUED 7 1 NO TIME CHARGED NO WORK ORDER ISSUED LIQUIDATED DAMAGES 8 1 NO TIME CHARGED NO WORK ORDER ISSUED 0 DAYS AT $ 400 PER DAY 9 1 NO TIME CHARGED NO WORK ORDER ISSUED TOTAL = $ .00 10 1 SATURDAY 11 1 SUNDAY CERTIFIED AS CORRECT AND 12 1 NO TIME CHARGED NO WORK ORDER ISSUED ONE COPY HAS BEEN GIVEN 13 1 NO TIME CHARGED NO WORK ORDER ISSUED TO THE CONTRACTOR 14 1 NO TIME CHARGED NO WORK ORDER ISSUED 15 1 NO TIME CHARGED NO WORK ORDER ISSUED 16 1 NO TIME CHARGED NO WORK ORDER ISSUED ---------------------------- 17 1 SATURDAY AREA/PROJECT ENGINEER 18 1 SUNDAY 19 1 NO TIME CHARGED NO WORK ORDER ISSUED 20 1 NO TIME CHARGED NO WORK ORDER ISSUED 21 1 NO TIME CHARGED NO WORK ORDER ISSUED 22 1 NO TIME CHARGED NO WORK ORDER ISSUED 23 1 NO TIME CHARGED NO WORK ORDER ISSUED 24 1 SATURDAY 25 1 SUNDAY 26 1 NO TIME CHARGED NO WORK ORDER ISSUED 27 1 NO TIME CHARGED NO WORK ORDER ISSUED 28 1 NO TIME CHARGED NO WORK ORDER ISSUED 29 1 NO TIME CHARGED NO WORK ORDER ISSUED 30 1 NO TIME CHARGED NO WORK ORDER ISSUED 31 1 SATURDAY ----- ----- ----- 152 33 119 5 SATURDAY 4 SUNDAY 0 HOLIDAY 22 NO TIME CHARGED NO WORK ORDER ISSUED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 4090804 MGR.NO. PAGE 001 CONT 6032 SEC 91 JOB 001 RES ENGR PAYLOR, DEBBIE PROJ RMC - 603291001 HWY US0083 4250 N. CLACK ABILENE CNTY TAYLOR DIST 08 CONTRACT PRICE $ 90,496.16 REPORT DATE 11/03/2009 10.45.44 CONTRACTOR KENNETH THOMASON 11017 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 005 DIST. 08 COUNTY TAYLOR CONTROL 6032-91-001 PROJECT RMC - 603291001 HIGHWAY US0083 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- MOWING HIGHWAY RIGHT OF WAY 0 0005 PREPARED BY DEBBIE PAYLOR 0 0055 ALL ITEMS NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 STRIP MOWING AC 2,766.000 1,383.000 18.490 25,571.67 0065 0730 FULL-WIDTH MOWING AC 2,078.330 2,078.330 18.490 38,428.32 0070 0730 SPOT MOWING AC 50.000 0.000 18.490 .00 0 SUBTOTAL BID ITEMS $ 63,999.99 0 TOTAL AMOUNT WORK DONE ALL ITEMS $ 63,999.99 0 TOTAL AMOUNT WORK DONE CONTROL 6032-91-001 $ 63,999.99 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 4090804 MGR.NO. PAGE 001 CONT 6032 SEC 91 JOB 001 RES ENGR PAYLOR, DEBBIE PROJ RMC - 603291001 HWY US0083 4250 N. CLACK ABILENE CNTY TAYLOR DIST 08 CONTRACT PRICE $ 90,496.16 REPORT DATE 11/03/2009 10.45.44 CONTRACTOR KENNETH THOMASON 11017 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 005 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN JUN 2 , 2009 WORKING DAYS USED 33 PERCENT COMPLETE 70.72 PERCENT TIME USED 55.90 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6032-91-001 RMC - 603291001 08 US0083 TAYLOR - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 STRIP MOWING AC 2,766.000 1,383.000 18.490 25,571.67 0730 FULL-WIDTH MOWING AC 2,078.330 2,078.330 18.490 38,428.32 0 SUBTOTAL BID ITEMS $ 63,999.99 0 CONTRACT TOTAL ALL ITEMS $ 63,999.99 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 4090804 MGR.NO. PAGE 001 CONT 6032 SEC 91 JOB 001 RES ENGR PAYLOR, DEBBIE PROJ RMC - 603291001 HWY US0083 4250 N. CLACK ABILENE CNTY TAYLOR DIST 08 CONTRACT PRICE $ 90,496.16 REPORT DATE 11/03/2009 10.45.44 CONTRACTOR KENNETH THOMASON 11017 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 005 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 221 RMC - 603291001 6032-91-001 63,999.99 .00 63,999.99 .00 .00 63,999.99 63,999.99 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 63,999.99 .00 63,999.99 .00 .00 63,999.99 63,999.99 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 4090804 MGR.NO. PAGE 001 CONT 6032 SEC 91 JOB 001 RES ENGR PAYLOR, DEBBIE PROJ RMC - 603291001 HWY US0083 4250 N. CLACK ABILENE CNTY TAYLOR DIST 08 CONTRACT PRICE $ 90,496.16 REPORT DATE 11/03/2009 10.45.44 CONTRACTOR KENNETH THOMASON 11017 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 005 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6032-91-001 RMC - 603291001 08 US0083 TAYLOR -LIMITS - VARIOUS VARIOUS - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 63,999.99