1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 4090802 MGR.NO. PAGE 001 CONT 6032 SEC 89 JOB 001 RES ENGR PAYLOR, DEBBIE PROJ RMC - 603289001 HWY US0083 4250 N. CLACK ABILENE CNTY JONES DIST 08 CONTRACT PRICE $ 125,526.64 REPORT DATE 01/13/2010 08.24.32 CONTRACTOR 3JB CONTRACTING 12538 EST PERIOD JUL 06,2009 TO DEC 23,2009 EST NO 006 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 07, 2009 TIME COMPUTED FROM JUL 06, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 92 148 59 89 BROUGHT FORWARD ADDL DAYS GRANTED = 0 DEC 09 1 1 RAIN TOTAL DAYS ALLOWED = 92 2 1 RAIN DATE WORK COMPLETED 12/23/09 3 1 TOO WET DAYS CHARGED TO DATE = 71 4 1 TOO WET ASSESSED LIQ DAMAGES = 0 5 1 SATURDAY LIQ DAMAGE RATE $ 400 6 1 SUNDAY 7 1 LIQUIDATED DAMAGES 8 1 TOO WET 0 DAYS AT $ 400 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 SATURDAY ONE COPY HAS BEEN GIVEN 13 1 SUNDAY TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 SATURDAY 20 1 SUNDAY 21 1 22 1 23 1 CYCLE COMPLETED AND WORK ACCEPTED - - - ----- ----- ----- 171 71 100 3 SATURDAY 3 SUNDAY 0 HOLIDAY 2 RAIN 3 TOO WET 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 4090802 MGR.NO. PAGE 001 CONT 6032 SEC 89 JOB 001 RES ENGR PAYLOR, DEBBIE PROJ RMC - 603289001 HWY US0083 4250 N. CLACK ABILENE CNTY JONES DIST 08 CONTRACT PRICE $ 125,526.64 REPORT DATE 01/13/2010 08.24.33 CONTRACTOR 3JB CONTRACTING 12538 EST PERIOD JUL 06,2009 TO DEC 23,2009 EST NO 006 & FINAL DIST. 08 COUNTY JONES CONTROL 6032-89-001 PROJECT RMC - 603289001 HIGHWAY US0083 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- MOWING HIGHWAY RIGHT OF WAY 0 0005 PREPARED BY DEBBIE PAYLOR 0 0055 ALL ITEMS NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 STRIP MOWING AC 4,233.000 4,140.000 15.640 64,749.60 0065 0730 FULL-WIDTH MOWING AC 3,743.000 3,667.000 15.640 57,351.88 0070 0730 SPOT MOWING AC 50.000 0.000 15.640 .00 0 SUBTOTAL BID ITEMS $ 122,101.48 0 TOTAL AMOUNT WORK DONE ALL ITEMS $ 122,101.48 0 TOTAL AMOUNT WORK DONE CONTROL 6032-89-001 $ 122,101.48 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 4090802 MGR.NO. PAGE 001 CONT 6032 SEC 89 JOB 001 RES ENGR PAYLOR, DEBBIE PROJ RMC - 603289001 HWY US0083 4250 N. CLACK ABILENE CNTY JONES DIST 08 CONTRACT PRICE $ 125,526.64 REPORT DATE 01/13/2010 08.24.33 CONTRACTOR 3JB CONTRACTING 12538 EST PERIOD JUL 06,2009 TO DEC 23,2009 EST NO 006 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN JUL 7 , 2009 WORKING DAYS USED 71 PERCENT COMPLETE 100.00 PERCENT TIME USED 77.10 DATE COMPLETED DEC 23 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6032-89-001 RMC - 603289001 08 US0083 JONES - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 STRIP MOWING AC 4,233.000 4,140.000 15.640 64,749.60 0730 FULL-WIDTH MOWING AC 3,743.000 3,667.000 15.640 57,351.88 0 SUBTOTAL BID ITEMS $ 122,101.48 0 CONTRACT TOTAL ALL ITEMS $ 122,101.48 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 4090802 MGR.NO. PAGE 001 CONT 6032 SEC 89 JOB 001 RES ENGR PAYLOR, DEBBIE PROJ RMC - 603289001 HWY US0083 4250 N. CLACK ABILENE CNTY JONES DIST 08 CONTRACT PRICE $ 125,526.64 REPORT DATE 01/13/2010 08.24.33 CONTRACTOR 3JB CONTRACTING 12538 EST PERIOD JUL 06,2009 TO DEC 23,2009 EST NO 006 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 128 RMC - 603289001 6032-89-001 122,101.48 .00 122,101.48 .00 .00 122,101.48 64,749.60 57,351.88 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 122,101.48 .00 122,101.48 .00 .00 122,101.48 64,749.60 57,351.88 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 4090802 MGR.NO. PAGE 001 CONT 6032 SEC 89 JOB 001 RES ENGR PAYLOR, DEBBIE PROJ RMC - 603289001 HWY US0083 4250 N. CLACK ABILENE CNTY JONES DIST 08 CONTRACT PRICE $ 125,526.64 REPORT DATE 01/13/2010 08.24.33 CONTRACTOR 3JB CONTRACTING 12538 EST PERIOD JUL 06,2009 TO DEC 23,2009 EST NO 006 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6032-89-001 RMC - 603289001 08 US0083 JONES -LIMITS - VARIOUS VARIOUS LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 65 0730 FULL-WIDTH MOWING AC 3,743.000 3,667.000 15.640 57,351.88 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 57,351.88 0 TOTAL AMOUNT WORK DONE TO DATE - $ 122,101.48