1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 2094004 MGR.NO. PAGE 001 CONT 6032 SEC 49 JOB 001 RES ENGR WRIGHT, ROY PROJ RMC - 603249001 HWY FM0382 4250 N CLACK ABILENE CNTY TAYLOR DIST 08 CONTRACT PRICE $ 873,031.27 REPORT DATE 08/26/2009 16.42.09 CONTRACTOR DOUBLE A CONTRACTING, L.P. 12178 EST PERIOD APR 07,2009 TO AUG 10,2009 EST NO 005 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN APR 07, 2009 TIME COMPUTED FROM APR 08, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 60 116 72 44 BROUGHT FORWARD ADDL DAYS GRANTED = 18 AUG 09 1 1 SATURDAY TOTAL DAYS ALLOWED = 78 2 1 SUNDAY DATE WORK COMPLETED 08/10/09 3 1 DAYS CHARGED TO DATE = 75 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 500 6 1 WORK COMPLETED 7 1 AWAITING FINAL INSPECTION LIQUIDATED DAMAGES 8 1 SATURDAY 0 DAYS AT $ 500 PER DAY 9 1 SUNDAY TOTAL = $ .00 10 1 WORK ACCEPTED CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 126 75 51 2 SATURDAY 2 SUNDAY 0 HOLIDAY 1 WORK COMPLETED 1 AWAITING FINAL INSPECTION 1 WORK ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 2094004 MGR.NO. PAGE 001 CONT 6032 SEC 49 JOB 001 RES ENGR WRIGHT, ROY PROJ RMC - 603249001 HWY FM0382 4250 N CLACK ABILENE CNTY TAYLOR DIST 08 CONTRACT PRICE $ 873,031.27 REPORT DATE 08/26/2009 16.42.10 CONTRACTOR DOUBLE A CONTRACTING, L.P. 12178 EST PERIOD APR 07,2009 TO AUG 10,2009 EST NO 005 & FINAL DIST. 08 COUNTY TAYLOR CONTROL 6032-49-001 PROJECT RMC - 603249001 HIGHWAY FM0382 0LIMITS- VARIOUS LOCATIONS IN THE ABILENE DISTRICT 0TYPE OF WORK- THERMOPLASTIC PAVEMENT MARKINGS 0 0005 ESTIMATE PREPARED BY PAT MCKENNON 0 0055 THERMOPLASTIC PAVEMENT MARKINGS NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0500 MOBILIZATION LS 1.000 1.000 1.000 1.00 0065 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 4.000 1.000 4.00 0065 0502 ADJ EST QUANTITY TO DATE 4.000 0070 0668 PREFAB PAV MRK TY C (W) (ARROW) EA 1.000 27.000 200.000 5,400.00 0070 0668 ADJ EST QUANTITY TO DATE 17.000 0075 0668 PREFAB PAV MRK TY C (W) (RR XING) EA 6.000 12.000 360.000 4,320.00 0075 0668 ADJ EST QUANTITY TO DATE 15.000 0080 0668 PREFAB PAV MRK TY C (W) (WORD) EA 1.000 15.000 200.000 3,000.00 0080 0668 ADJ EST QUANTITY TO DATE 8.000 0085 0668 PREFAB PAV MRK TY C (W) (36")(YLD TRI) EA 280.000 331.000 25.000 8,275.00 0090 6110 REF PAV MRK TY I (W)(4")(SLD)(100 MIL) LF 1,897,526.000 2,295,875.000 .180 413,257.50 0090 6110 ADJ EST QUANTITY TO DATE 2,418,902.000 0095 6110 REF PAV MRK TY I (Y)(4")(BRK)(100 MIL) LF 373,680.000 378,365.000 .190 71,889.35 0095 6110 ADJ EST QUANTITY TO DATE 419,500.000 0100 6110 REF PAV MRK TY I (W)(4")(BRK)(100 MIL) LF 14,540.000 42,957.000 .190 8,161.83 0100 6110 ADJ EST QUANTITY TO DATE 41,347.000 0105 6110 REF PAV MRK TY I (W)(6")(BRK)(100 MIL) LF 16,590.000 16,898.000 .290 4,900.42 0110 6110 REF PAV MRK TY I (W)(6")(SLD)(100 MIL) LF 66,360.000 64,960.000 .290 18,838.40 0115 6110 REF PAV MRK TY I 1 (W)(8")(SLD)(100 MIL) LF 4,554.000 8,124.000 .400 3,249.60 0115 6110 ADJ EST QUANTITY TO DATE 8,130.000 0120 6110 REF PAV MRK TY I (W)(24")(SLD)(100 MIL) LF 3,296.000 5,024.000 4.000 20,096.00 0120 6110 ADJ EST QUANTITY TO DATE 5,140.000 0125 6110 REF PAV MRK TY I (Y)(4")(SLD)(100 MIL) LF 2,014,371.000 2,399,014.000 .190 455,812.66 0125 6110 ADJ EST QUANTITY TO DATE 2,387,594.000 0130 6110 REF PAV MRK TY I (Y)(6")(SLD)(100 MIL) LF 66,360.000 65,442.000 .300 19,632.60 0135 6110 REF PAV MRK TY I (Y)(8")(SLD)(100 MIL) LF 2,128.000 7,065.000 .400 2,826.00 0135 6110 ADJ EST QUANTITY TO DATE 7,128.000 0140 6110 REF PAV MRK TY I (Y)(24")(SLD)(100 MIL) LF 1,400.000 2,012.000 4.000 8,048.00 0140 6110 ADJ EST QUANTITY TO DATE 1,955.000 0 SUBTOTAL BID ITEMS $ 1,047,712.36 0 TOTAL AMOUNT WORK DONE THERMOPLASTIC PAVEMENT MARKINGS $ 1,047,712.36 0 TOTAL AMOUNT WORK DONE CONTROL 6032-49-001 $ 1,047,712.36 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 2094004 MGR.NO. PAGE 001 CONT 6032 SEC 49 JOB 001 RES ENGR WRIGHT, ROY PROJ RMC - 603249001 HWY FM0382 4250 N CLACK ABILENE CNTY TAYLOR DIST 08 CONTRACT PRICE $ 873,031.27 REPORT DATE 08/26/2009 16.42.10 CONTRACTOR DOUBLE A CONTRACTING, L.P. 12178 EST PERIOD APR 07,2009 TO AUG 10,2009 EST NO 005 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATIONS IN 0 THE ABILENE DISTRICT DATE WORK BEGAN APR 7 , 2009 WORKING DAYS USED 75 PERCENT COMPLETE 100.00 PERCENT TIME USED 96.10 DATE COMPLETED AUG 10 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6032-49-001 RMC - 603249001 08 FM0382 TAYLOR - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0500 MOBILIZATION LS 1.000 1.000 1.000 1.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 4.000 1.000 4.00 0502 ADJ EST QUANTITY TO DATE 4.000 0668 PREFAB PAV MRK TY C (W) (ARROW) EA 1.000 27.000 200.000 5,400.00 0668 ADJ EST QUANTITY TO DATE 17.000 0668 PREFAB PAV MRK TY C (W) (RR XING) EA 6.000 12.000 360.000 4,320.00 0668 ADJ EST QUANTITY TO DATE 15.000 0668 PREFAB PAV MRK TY C (W) (WORD) EA 1.000 15.000 200.000 3,000.00 0668 ADJ EST QUANTITY TO DATE 8.000 0668 PREFAB PAV MRK TY C (W) (36")(YLD TRI) EA 280.000 331.000 25.000 8,275.00 6110 REF PAV MRK TY I (W)(4")(SLD)(100 MIL) LF 1,897,526.000 2,295,875.000 .180 413,257.50 6110 ADJ EST QUANTITY TO DATE 2,418,902.000 6110 REF PAV MRK TY I (Y)(4")(BRK)(100 MIL) LF 373,680.000 378,365.000 .190 71,889.35 6110 ADJ EST QUANTITY TO DATE 419,500.000 6110 REF PAV MRK TY I (W)(4")(BRK)(100 MIL) LF 14,540.000 42,957.000 .190 8,161.83 6110 ADJ EST QUANTITY TO DATE 41,347.000 6110 REF PAV MRK TY I 1 (W)(6")(BRK)(100 MIL) LF 16,590.000 16,898.000 .290 4,900.42 6110 REF PAV MRK TY I (W)(6")(SLD)(100 MIL) LF 66,360.000 64,960.000 .290 18,838.40 6110 REF PAV MRK TY I (W)(8")(SLD)(100 MIL) LF 4,554.000 8,124.000 .400 3,249.60 6110 ADJ EST QUANTITY TO DATE 8,130.000 6110 REF PAV MRK TY I (W)(24")(SLD)(100 MIL) LF 3,296.000 5,024.000 4.000 20,096.00 6110 ADJ EST QUANTITY TO DATE 5,140.000 6110 REF PAV MRK TY I (Y)(4")(SLD)(100 MIL) LF 2,014,371.000 2,399,014.000 .190 455,812.66 6110 ADJ EST QUANTITY TO DATE 2,387,594.000 6110 REF PAV MRK TY I (Y)(6")(SLD)(100 MIL) LF 66,360.000 65,442.000 .300 19,632.60 6110 REF PAV MRK TY I (Y)(8")(SLD)(100 MIL) LF 2,128.000 7,065.000 .400 2,826.00 6110 ADJ EST QUANTITY TO DATE 7,128.000 6110 REF PAV MRK TY I (Y)(24")(SLD)(100 MIL) LF 1,400.000 2,012.000 4.000 8,048.00 6110 ADJ EST QUANTITY TO DATE 1,955.000 0 SUBTOTAL BID ITEMS $ 1,047,712.36 0 CONTRACT TOTAL ALL ITEMS $ 1,047,712.36 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 2094004 MGR.NO. PAGE 001 CONT 6032 SEC 49 JOB 001 RES ENGR WRIGHT, ROY PROJ RMC - 603249001 HWY FM0382 4250 N CLACK ABILENE CNTY TAYLOR DIST 08 CONTRACT PRICE $ 873,031.27 REPORT DATE 08/26/2009 16.42.10 CONTRACTOR DOUBLE A CONTRACTING, L.P. 12178 EST PERIOD APR 07,2009 TO AUG 10,2009 EST NO 005 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 221 RMC - 603249001 6032-49-001 1,047,712.36 .00 1,047,712.36 .00 .00 1,047,712.36 1,018,341.56 29,370.80 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 1,047,712.36 .00 1,047,712.36 .00 .00 1,047,712.36 1,018,341.56 29,370.80 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 2094004 MGR.NO. PAGE 001 CONT 6032 SEC 49 JOB 001 RES ENGR WRIGHT, ROY PROJ RMC - 603249001 HWY FM0382 4250 N CLACK ABILENE CNTY TAYLOR DIST 08 CONTRACT PRICE $ 873,031.27 REPORT DATE 08/26/2009 16.42.10 CONTRACTOR DOUBLE A CONTRACTING, L.P. 12178 EST PERIOD APR 07,2009 TO AUG 10,2009 EST NO 005 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6032-49-001 RMC - 603249001 08 FM0382 TAYLOR -LIMITS - VARIOUS LOCATIONS IN THE ABILENE DISTRICT LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 65 0502 BARRICADES, SIGNS AND MO 3.000 1.000 1.000 1.00 TRAFFIC HANDLING 70 0668 PREFAB PAV MRK TY C (W) EA 1.000 18.000 200.000 3,600.00 (ARROW) 75 0668 PREFAB PAV MRK TY C (W) (RR EA 6.000 8.000 360.000 2,880.00 XING) 80 0668 PREFAB PAV MRK TY C (W) EA 1.000 7.000 200.000 1,400.00 (WORD) 85 0668 PREFAB PAV MRK TY C (W) EA 280.000 188.000 25.000 4,700.00 (36")(YLD TRI) 95 6110 REF PAV MRK TY I LF 373,680.000 -180.000 0.190 -34.20 (Y)(4")(BRK)(100 MIL) 120 6110 REF PAV MRK TY I LF 3,296.000 2,309.000 4.000 9,236.00 (W)(24")(SLD)(100 MIL) 140 6110 REF PAV MRK TY I LF 1,400.000 1,897.000 4.000 7,588.00 (Y)(24")(SLD)(100 MIL) --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 29,370.80 0 TOTAL AMOUNT WORK DONE TO DATE - $ 1,047,712.36