Jobs Delayed From The May 2017 Letting

 
 
Last Update: Tuesday, May 01, 2017

Jan |Feb |Mar |Apr |May |Jun |Jul |Aug |Sep |Oct |Nov |Dec

Seq No County Project ID CCSJ Highway Reason for change
006 VICTORIA C 2350-1-54 2350-01-054 SL 463 S.T.I.P. Revision Required
015 KAUFMAN STP 2017(888) 1016-06-011 FM 1392 accelerated to April 2017
016 ECTOR DMO 2010(951) 3570-01-009 FM 3503 due to unclear ROW
020 POLK BR 2008(917) 0911-04-046 CR due to waiting for NEPA processes to be completed
033 BRAZORIA NH 1702(112) 0598-02-047 SH 288 S.T.I.P. Revision Required
034 WICHITA NH 1702(125) 0903-00-074 VA per district request. Project is replaced with 0044-04-060
043 PECOS STP 1702(194)HES 0076-01-030 US 67 became subordinate to 0075-02-027
044 PECOS STP 1702(235)HES 0292-06-031 SH 18 became subordinate to 0075-02-027
204 MC CULLOCH STP 2017(458) 0128-04-035 US 190 due to unclear utilities and outstanding railroad agreement
210 VAN ZANDT BR 2013(723) 0910-12-066 CR due to unclear utilities
210 PARKER STP 1602(435)MM 0314-07-052 IH 20 S.T.I.P. Revision Required
217 TRAVIS STP 2015(603)HES 0914-04-291 CS due to the estimate being higher than available HES funds
222 KAUFMAN BR 1602(004) 0918-11-091 CR accelerated to April 2017
227 ORANGE BR 2014(324) 0920-30-079 CS due to late P.S.&E.
237 PARKER NH 1702(087) 0008-03-089 IH 20 due to late P.S.&E.
241 WARD STP 1702(207)HES 0292-04-062 SH 18 became subordinate to 0075-02-027

 