Tabulation of Bids for Project STP 2021(170)HES
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months.
The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.
Text version of this page | |||
County: | VAN ZANDT | Let Date: | 12/03/20 |
Type: | REPLACE GUARDRAIL | Seq No: | 3211 |
Time: | 0 X | Project ID: | STP 2021(170)HES |
Highway: | IH 20 | Contract #: | 12203211 |
Length: | 22.414 | CCSJ: | 0495-03-065 |
Limits: | |||
From: | SH 19 OVERPASS IN CANTON, E | Check: | $82,000 |
To: | CR 4517, 1.4 MI E OF FM 16 | Misc Cost: |
Estimate | $7,015,842.35 | % Over/Under | Company |
Bidder 1 | $3,660,941.00 | -47.82% | SEFBO PIPELINE BRIDGE, INCORPORATED |
Bidder 2 | $5,973,889.60 | -14.85% | TALBRAN ENTERPRISES LLC |
Bidder 3 | $6,273,793.98 | -10.58% | ALTUS CONSTRUCTION LLC |
Bidder 4 | $6,867,978.50 | -2.11% | SYNERGY SIGNS & SERVICES LLC |
Bidder 5 | $6,923,703.80 | -1.31% | HIGHWAY 19 CONSTRUCTION LLC |
Bidder 6 | $7,219,204.25 | +2.90% | SJ&J CONSTRUCTION, LLC |
Bidder 7 | $7,334,751.65 | +4.55% | EAST TEXAS BRIDGE, INC. |
Bidder 8 | $8,706,387.75 | +24.10% | FNH CONSTRUCTION, LLC |
Bidder 9 | $9,972,465.81 | +42.14% | 3LW CIVIL LLC |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
1046054 | REMOVING CONCRETE(MOW STRIP) | LF | 7,170.000 | 12.00 | 1 2 3 4 5 6 7 8 9 | 7.000 13.000 15.940 10.000 10.000 7.000 10.000 20.000 9.000 |
1326021 | EMBANKMENT (VEHICLE)(ORD COMP)(TY C) | CY | 193.000 | 22.00 | 1 2 3 4 5 6 7 8 9 | 232.000 125.000 40.940 30.000 100.000 25.000 60.000 30.000 40.000 |
1606003 | FURNISHING AND PLACING TOPSOIL (4") | SY | 4,840.000 | 1.50 | 1 2 3 4 5 6 7 8 9 | 5.000 6.000 1.590 2.500 5.000 2.000 5.000 6.000 1.000 |
1646054 | BOND FBR MTRX SEED (PERM)(RURAL)(SAND) | SY | 6,437.000 | 1.00 | 1 2 3 4 5 6 7 8 9 | 3.000 0.750 1.330 1.750 1.000 0.750 1.750 1.000 0.100 |
1646055 | BONDED FBR MTRX SEED (TEMP)(WARM) | SY | 4,840.000 | 0.75 | 1 2 3 4 5 6 7 8 9 | 2.000 0.750 1.330 1.750 1.000 0.750 1.500 1.000 0.100 |
1646056 | BONDED FBR MTRX SEED (TEMP)(COOL) | SY | 4,840.000 | 0.75 | 1 2 3 4 5 6 7 8 9 | 2.000 0.750 1.330 1.750 1.000 0.750 1.500 1.000 0.100 |
1686001 | VEGETATIVE WATERING | MG | 53,240.000 | 10.50 | 1 2 3 4 5 6 7 8 9 | 2.000 0.750 1.330 5.000 1.000 5.000 0.010 28.000 5.000 |
4326045 | RIPRAP (MOW STRIP)(4 IN) | CY | 2,394.000 | 500.00 | 1 2 3 4 5 6 7 8 9 | 420.000 415.000 531.230 475.000 578.000 700.000 500.000 450.000 750.000 |
4516019 | RETROFIT RAIL (TY T631) | LF | 1,086.200 | 101.50 | 1 2 3 4 5 6 7 8 9 | 70.000 78.000 199.210 100.000 159.000 100.000 60.000 165.000 260.000 |
4966099 | REMOVE STR (RAIL) | LF | 1,061.000 | 30.00 | 1 2 3 4 5 6 7 8 9 | 90.000 18.000 9.300 10.000 84.000 10.000 10.000 50.000 50.000 |
5006001 | MOBILIZATION | LS | 1.000 | 91,521.55 | 1 2 3 4 5 6 7 8 9 | 250,000.000 100,000.000 464,825.410 500,000.000 450,000.000 300,000.000 420,000.000 550,000.000 715,000.000 |
5026001008 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 11.000 | 7,000.00 | 1 2 3 4 5 6 7 8 9 | 3,000.000 3,000.000 13,280.730 15,000.000 25,000.000 5,000.000 60,000.000 8,500.000 100,000.000 |
5066038002 | TEMP SEDMT CONT FENCE (INSTALL) | LF | 1,100.000 | 3.00 | 1 2 3 4 5 6 7 8 9 | 3.000 4.000 2.660 5.000 4.000 3.000 4.000 4.000 0.500 |
5066039002 | TEMP SEDMT CONT FENCE (REMOVE) | LF | 1,100.000 | 0.75 | 1 2 3 4 5 6 7 8 9 | 2.000 2.000 0.850 2.000 1.000 1.000 0.500 2.000 0.500 |
5126005 | PORT CTB (FUR & INST)(F-SHAPE)(TY 1) | LF | 1,260.000 | 60.00 | 1 2 3 4 5 6 7 8 9 | 95.000 53.000 26.560 25.000 75.000 50.000 75.000 70.000 90.000 |
5126029 | PORT CTB (MOVE)(F-SHAPE)(TY 1) | LF | 2,410.000 | 10.00 | 1 2 3 4 5 6 7 8 9 | 15.000 26.000 6.640 20.000 25.000 25.000 10.000 20.000 20.000 |
5126053 | PORT CTB (REMOVE)(F-SHAPE)(TY 1) | LF | 1,260.000 | 14.00 | 1 2 3 4 5 6 7 8 9 | 9.000 31.000 19.920 20.000 25.000 25.000 5.000 20.000 30.000 |
5406001001 | MTL W-BEAM GD FEN (TIM POST) | LF | 33,332.500 | 25.00 | 1 2 3 4 5 6 7 8 9 | 17.000 20.000 37.190 20.500 19.000 30.000 18.000 19.500 22.000 |
5406002001 | MTL W-BEAM GD FEN (STEEL POST) | LF | 212.500 | 30.00 | 1 2 3 4 5 6 7 8 9 | 47.000 45.000 33.200 60.000 23.000 29.000 50.000 50.000 35.000 |
5406006001 | MTL BEAM GD FEN TRANS (THRIE-BEAM) | EA | 71.000 | 1,700.00 | 1 2 3 4 5 6 7 8 9 | 1,270.000 1,625.000 1,799.540 1,350.000 1,355.000 1,800.000 1,800.000 1,500.000 1,600.000 |
5406016001 | DOWNSTREAM ANCHOR TERMINAL SECTION | EA | 73.000 | 1,150.00 | 1 2 3 4 5 6 7 8 9 | 950.000 875.000 1,626.890 1,300.000 1,250.000 1,250.000 1,000.000 1,500.000 1,300.000 |
5406018001 | MTL BM GD FEN TRANS (NON - SYM) | EA | 54.000 | 1,200.00 | 1 2 3 4 5 6 7 8 9 | 520.000 850.000 1,189.290 800.000 896.000 700.000 600.000 1,200.000 900.000 |
5426001 | REMOVE METAL BEAM GUARD FENCE | LF | 31,813.000 | 5.00 | 1 2 3 4 5 6 7 8 9 | 4.000 1.750 2.460 3.500 2.000 4.000 2.500 3.000 7.000 |
5426002 | REMOVE TERMINAL ANCHOR SECTION | EA | 82.000 | 225.00 | 1 2 3 4 5 6 7 8 9 | 200.000 200.000 332.020 150.000 165.000 168.000 110.000 500.000 200.000 |
5446001 | GUARDRAIL END TREATMENT (INSTALL) | EA | 142.000 | 2,600.00 | 1 2 3 4 5 6 7 8 9 | 2,100.000 2,585.000 3,320.180 2,500.000 2,150.000 2,700.000 2,500.000 2,500.000 7,100.000 |
5446003 | GUARDRAIL END TREATMENT (REMOVE) | EA | 131.000 | 270.00 | 1 2 3 4 5 6 7 8 9 | 250.000 200.000 205.850 250.000 155.000 325.000 220.000 500.000 4,000.000 |
5456003 | CRASH CUSH ATTEN (MOVE & RESET) | EA | 3.000 | 2,196.00 | 1 2 3 4 5 6 7 8 9 | 1,100.000 2,500.000 1,394.480 1,500.000 1,000.000 1,000.000 1,400.000 5,000.000 1,900.000 |
5456005 | CRASH CUSH ATTEN (REMOVE) | EA | 1.000 | 936.00 | 1 2 3 4 5 6 7 8 9 | 800.000 2,500.000 1,055.820 1,000.000 1,000.000 1,000.000 800.000 2,500.000 800.000 |
5456019 | CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) | EA | 1.000 | 10,000.00 | 1 2 3 4 5 6 7 8 9 | 9,800.000 8,000.000 19,921.090 9,500.000 10,000.000 12,000.000 9,000.000 12,500.000 9,000.000 |
6586015 | INSTL DEL ASSM (D-SW)SZ (BRF)GF1 | EA | 475.000 | 25.00 | 1 2 3 4 5 6 7 8 9 | 20.000 20.000 37.850 12.000 35.000 25.000 30.000 50.000 30.370 |
6586028 | INSTL DEL ASSM (D-SY)SZ (BRF)GF1 | EA | 146.000 | 24.00 | 1 2 3 4 5 6 7 8 9 | 20.000 20.000 37.850 12.000 35.000 20.000 30.000 50.000 24.190 |
6586061 | INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2 | EA | 105.000 | 28.00 | 1 2 3 4 5 6 7 8 9 | 24.000 20.000 37.850 20.000 35.000 40.000 30.000 50.000 32.270 |
6586064 | INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2 | EA | 39.000 | 30.00 | 1 2 3 4 5 6 7 8 9 | 24.000 20.000 41.830 20.000 35.000 30.000 30.000 50.000 31.000 |
6586068 | INSTL DEL ASSM (D-DY)SZ 1(BRF)GF2 | EA | 13.000 | 26.00 | 1 2 3 4 5 6 7 8 9 | 24.000 20.000 45.820 20.000 35.000 22.000 30.000 50.000 22.090 |
7786002 | CONCRETE RAIL REPAIR (MISC) | LF | 20.000 | 550.00 | 1 2 3 4 5 6 7 8 9 | 500.000 650.000 996.050 500.000 500.000 550.000 300.000 500.000 400.830 |
60016002 | PORTABLE CHANGEABLE MESSAGE SIGN | EA | 24.000 | 110.00 | 1 2 3 4 5 6 7 8 9 | 15,500.000 8,250.000 3,984.220 150.000 5,000.000 5,000.000 15,000.000 13,500.000 4,000.000 |
61856002002 | TMA (STATIONARY) | DAY | 196.000 | 175.00 | 1 2 3 4 5 6 7 8 9 | 500.000 300.000 166.010 150.000 300.000 100.000 300.000 300.000 100.000 |
8006001 | NO. OF WORKING DAYS | $/D | 15,000.000 | 196.00 | 1 2 3 4 5 6 7 8 9 | 1.000 180.000 100.000 196.000 178.000 170.000 196.000 196.000 170.000 |