Tabulation of Bids for Project BPM - 631987001
Text version of this page | |||
County: | GILLESPIE | Let Date: | 08/15/17 |
Type: | REP MOD EXP JTS, REP SPALLS, INS CONC RR | Seq No: | 1405 |
Time: | 34 W | Project ID: | BPM - 631987001 |
Highway: | US0087 | Contract #: | 08171405 |
Length: | 0.000 | CCSJ: | 6319-87-001 |
Limits: | |||
From: | BARONS CR-1408700720132, LLANO RV-1 | Check: | $2,000 |
To: | 29001023, N ROCKY CR-14027119802012 | Misc Cost: |
Estimate | $101,274.00 | % Over/Under | Company |
Bidder 1 | $138,394.50 | +36.65% | 3LW CIVIL LLC |
Bidder 2 | $149,556.50 | +47.68% | BECK-REIT & SONS, LTD. |
Bidder 3 | $161,462.50 | +59.43% | L.C. JORDAN & SON |
Bidder 4 | $196,412.50 | +93.94% | FNH CONSTRUCTION, LLC |
Bidder 5 | $242,202.50 | +139.16% | CHAMPION INFRASTRUCTURE, LLC |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
4326036 | RIPRAP (STONE PROTECTION)(30 IN) | CY | 379.000 | 90.00 | 1 2 3 4 5 | 190.000 211.000 200.000 300.000 340.000 |
4386002 | CLEANING AND SEALING EXIST JOINTS(CL3) | LF | 582.500 | 40.00 | 1 2 3 4 5 | 29.000 75.000 45.000 45.000 65.000 |
5006001 | MOBILIZATION | LS | 1.000 | 8,389.00 | 1 2 3 4 5 | 13,840.000 10,000.000 20,000.000 19,000.000 6,000.000 |
5026001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 3.000 | 3,000.00 | 1 2 3 4 5 | 4,600.000 1,500.000 100.000 8,500.000 3,800.000 |
5066038002 | TEMP SEDMT CONT FENCE (INSTALL) | LF | 300.000 | 2.50 | 1 2 3 4 5 | 3.000 3.000 2.000 4.000 8.000 |
5066039002 | TEMP SEDMT CONT FENCE (REMOVE) | LF | 300.000 | 0.75 | 1 2 3 4 5 | 1.500 1.000 1.000 2.000 2.000 |
7856008 | BRIDGE JOINT REPAIR (FULL DEPTH) | LF | 102.000 | 250.00 | 1 2 3 4 5 | 201.000 100.000 375.000 100.000 540.000 |