Tabulation of Bids for Project BR 2017(117)
Text version of this page | |||
County: | LAVACA | Let Date: | 08/09/17 |
Type: | REPLACE BRIDGE AND APPROACHES | Seq No: | 3238 |
Time: | 90 WORKING DAYS | Project ID: | BR 2017(117) |
Highway: | CR | Contract #: | 08173238 |
Length: | 0.101 | CCSJ: | 0913-29-050 |
Limits: | |||
From: | AT CAMPBELL BRANCH_____CR 198 | Check: | $9,000 |
To: | STR# 13-143-0-AA01-02-001 | Misc Cost: | $1,500.00 |
Estimate | $461,364.30 | % Over/Under | Company |
Bidder 1 | $451,306.00 | -2.18% | CONSTAR CONSTRUCTION |
Bidder 2 | $453,672.66 | -1.67% | TREVWAY, INC. |
Bidder 3 | $456,618.92 | -1.03% | ACME BRIDGE COMPANY, INC. |
Bidder 4 | $485,606.79 | +5.25% | CAPITAL EXCAVATION COMPANY |
Bidder 5 | $490,797.71 | +6.38% | HILL COUNTRY BRIDGE, INC. |
Bidder 6 | $517,838.26 | +12.24% | SB CONTRACTORS LLC |
Bidder 7 | $543,534.53 | +17.81% | A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C. |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
1006002 | PREPARING ROW | STA | 2.850 | 3,000.00 | 1 2 3 4 5 6 7 | 2,300.000 1,000.000 4,500.000 6,000.000 5,735.000 4,500.000 2,500.000 |
1106001 | EXCAVATION (ROADWAY) | CY | 104.000 | 25.00 | 1 2 3 4 5 6 7 | 19.000 36.410 33.000 33.000 38.350 15.000 44.000 |
1326005 | EMBANKMENT (FINAL)(ORD COMP)(TY C) | CY | 450.000 | 30.00 | 1 2 3 4 5 6 7 | 35.000 26.000 33.000 20.000 30.550 35.000 55.000 |
1506002 | BLADING | HR | 25.000 | 100.00 | 1 2 3 4 5 6 7 | 100.000 50.480 150.000 75.000 113.000 50.000 180.000 |
1646023 | CELL FBR MLCH SEED(PERM)(RURAL)(CLAY) | SY | 1,055.000 | 1.00 | 1 2 3 4 5 6 7 | 2.000 2.000 1.300 1.250 1.100 1.200 1.300 |
1646029 | CELL FBR MLCH SEED(TEMP)(WARM) | SY | 264.000 | 1.00 | 1 2 3 4 5 6 7 | 2.000 1.000 0.210 0.200 4.100 4.000 0.210 |
1646031 | CELL FBR MLCH SEED(TEMP)(COOL) | SY | 264.000 | 1.00 | 1 2 3 4 5 6 7 | 2.000 1.000 0.210 0.200 4.100 4.000 0.210 |
1686001 | VEGETATIVE WATERING | MG | 8.900 | 100.00 | 1 2 3 4 5 6 7 | 150.000 100.000 41.200 100.000 95.000 60.000 110.000 |
2476366 | FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS) | CY | 315.000 | 100.00 | 1 2 3 4 5 6 7 | 120.000 75.360 100.000 95.000 111.400 100.000 125.000 |
3106009 | PRIME COAT (MC-30) | GAL | 263.500 | 5.00 | 1 2 3 4 5 6 7 | 20.000 12.000 10.100 10.000 6.450 16.000 6.400 |
3166246 | AGGR(TY-PE GR-3 SAC-B) | CY | 15.300 | 100.00 | 1 2 3 4 5 6 7 | 800.000 505.260 210.000 210.000 134.000 550.000 130.000 |
3166249 | AGGR(TY-PE GR-4 SAC-B) | CY | 10.200 | 100.00 | 1 2 3 4 5 6 7 | 800.000 505.260 210.000 210.000 134.000 550.000 130.000 |
3166400 | ASPH (AC-15P OR AC-10-2TR OR CRS-2P) | GAL | 976.200 | 4.00 | 1 2 3 4 5 6 7 | 20.000 14.000 16.800 17.000 10.700 16.000 10.500 |
4006005 | CEM STABIL BKFL | CY | 49.000 | 100.00 | 1 2 3 4 5 6 7 | 100.000 100.000 218.000 180.000 176.000 175.000 210.000 |
4166003 | DRILL SHAFT (30 IN) | LF | 282.000 | 175.00 | 1 2 3 4 5 6 7 | 210.000 277.000 169.000 270.000 197.000 240.000 184.000 |
4206013 | CL C CONC (ABUT) | CY | 31.400 | 1,000.00 | 1 2 3 4 5 6 7 | 950.000 450.000 1,000.000 870.000 845.000 1,200.000 1,000.000 |
4226005 | REINF CONC SLAB (BOX BEAM) | SF | 1,962.000 | 22.00 | 1 2 3 4 5 6 7 | 15.000 24.000 17.000 18.870 21.550 18.000 20.500 |
4226023 | SHEAR KEY | CY | 20.000 | 375.00 | 1 2 3 4 5 6 7 | 300.000 200.000 522.000 600.690 430.000 275.000 410.000 |
4256003 | PRESTR CONC BOX BEAM (4B28) | LF | 298.000 | 220.00 | 1 2 3 4 5 6 7 | 180.000 200.000 210.000 174.000 221.250 180.000 190.000 |
4256004 | PRESTR CONC BOX BEAM (5B28) | LF | 149.000 | 220.00 | 1 2 3 4 5 6 7 | 200.000 200.000 229.000 174.000 221.250 180.000 190.000 |
4326026 | RIPRAP (STONE COMMON)(DRY)(18 IN) | CY | 111.000 | 200.00 | 1 2 3 4 5 6 7 | 190.000 115.210 173.000 140.000 148.000 200.000 220.000 |
4506006 | RAIL (TY T223) | LF | 190.000 | 125.00 | 1 2 3 4 5 6 7 | 140.000 64.700 100.000 85.520 105.000 115.000 180.000 |
4546004 | ARMOR JOINT (SEALED) | LF | 45.000 | 80.00 | 1 2 3 4 5 6 7 | 80.000 86.840 92.400 86.230 75.000 65.000 150.000 |
4606004 | CMP (GAL STL 30 IN) | LF | 60.000 | 80.00 | 1 2 3 4 5 6 7 | 60.000 49.460 46.000 78.440 58.000 75.000 220.000 |
4676410 | SET (TY II) (30 IN) (CMP) (6: 1) (P) | EA | 1.000 | 3,000.00 | 1 2 3 4 5 6 7 | 1,700.000 2,019.990 2,200.000 2,038.250 2,500.000 1,200.000 3,500.000 |
4966009 | REMOV STR (BRIDGE 0 - 99 FT LENGTH) | EA | 1.000 | 15,000.00 | 1 2 3 4 5 6 7 | 16,000.000 27,000.000 20,000.000 35,000.000 25,950.000 20,000.000 19,000.000 |
5006001 | MOBILIZATION | LS | 1.000 | 40,000.00 | 1 2 3 4 5 6 7 | 20,000.000 46,000.000 32,000.000 48,000.000 48,300.000 50,616.560 57,000.000 |
5026001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 7.000 | 3,000.00 | 1 2 3 4 5 6 7 | 800.000 600.000 1,000.000 1,000.000 1,725.000 4,500.000 4,500.000 |
5066001002 | ROCK FILTER DAMS (INSTALL) (TY 1) | LF | 70.000 | 50.00 | 1 2 3 4 5 6 7 | 25.000 10.000 31.800 30.000 26.000 45.000 32.000 |
5066011002 | ROCK FILTER DAMS (REMOVE) | LF | 70.000 | 8.00 | 1 2 3 4 5 6 7 | 10.000 2.000 15.900 15.000 5.000 12.000 16.000 |
5066038002 | TEMP SEDMT CONT FENCE (INSTALL) | LF | 415.000 | 3.00 | 1 2 3 4 5 6 7 | 5.000 3.000 4.250 4.000 2.000 5.000 4.300 |
5066039002 | TEMP SEDMT CONT FENCE (REMOVE) | LF | 415.000 | 1.00 | 1 2 3 4 5 6 7 | 2.000 1.000 1.600 1.500 1.000 0.500 1.610 |
5406006 | MTL BEAM GD FEN TRANS (THRIE-BEAM) | EA | 4.000 | 1,500.00 | 1 2 3 4 5 6 7 | 1,300.000 2,477.000 2,010.000 1,896.000 2,300.000 1,896.000 2,000.000 |
5446001 | GUARDRAIL END TREATMENT (INSTALL) | EA | 4.000 | 2,200.00 | 1 2 3 4 5 6 7 | 2,700.000 3,347.000 2,730.000 2,573.000 2,035.000 2,573.000 2,800.000 |
5526001 | WIRE FENCE (TY A) | LF | 235.000 | 15.00 | 1 2 3 4 5 6 7 | 17.000 10.000 10.600 10.000 23.500 12.000 16.000 |
6586014 | INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) | EA | 6.000 | 30.00 | 1 2 3 4 5 6 7 | 45.000 10.000 15.900 15.000 15.000 15.000 16.000 |
6586062 | INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) | EA | 8.000 | 30.00 | 1 2 3 4 5 6 7 | 50.000 10.000 15.900 15.000 19.000 15.000 16.000 |