Tabulation of Bids for Project NH 1802(605)
Text version of this page | |||
County: | HARRIS | Let Date: | 08/08/18 |
Type: | LANDSCAPE ENHANCEMENTS | Seq No: | 3239 |
Time: | 45 WORKING DAYS | Project ID: | NH 1802(605) |
Highway: | IH 610 | Contract #: | 08183239 |
Length: | 12.663 | CCSJ: | 0271-14-236 |
Limits: | |||
From: | US 290 | Check: | $11,000 |
To: | IH 10 | Misc Cost: | $5,000.00 |
Estimate | $572,928.00 | % Over/Under | Company |
Bidder 1 | $566,852.65 | -1.06% | CROSBY RD CONSTRUCTION INC |
Bidder 2 | $575,532.95 | +0.45% | BOYER, INC. |
Bidder 3 | $702,075.35 | +22.54% | CENTRAL NORTH CONSTRUCTION, LLC |
Bidder 4 | $761,442.50 | +32.90% | CHAMPION INFRASTRUCTURE, LLC |
Bidder 5 | $814,847.41 | +42.23% | YELLOWSTONE LANDSCAPE - CENTRAL, INC. |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
1006008 | PREPARING ROW (TREE) (0" TO 6" DIA) | EA | 14.000 | 75.00 | 1 2 3 4 5 | 800.000 476.000 1,500.000 150.000 375.940 |
1006013 | PREP ROW (TREE) (2" TO 12" DIA) | EA | 5.000 | 100.00 | 1 2 3 4 5 | 400.000 2,031.000 600.000 150.000 652.632 |
1616009 | EROSION CONTROL COMPOST | CY | 3,777.000 | 28.00 | 1 2 3 4 5 | 19.000 28.500 18.000 22.000 39.482 |
1616012 | GENERAL USE COMPOST | CY | 1,881.000 | 30.00 | 1 2 3 4 5 | 26.000 29.500 18.000 20.000 45.308 |
1926021001 | PLANT MATERIAL (5 GAL) (TREE) | EA | 3,785.000 | 20.00 | 1 2 3 4 5 | 19.000 15.700 18.000 15.000 16.792 |
1926023001 | PLANT MATERIAL (15 GAL) (TREE) | EA | 665.000 | 105.00 | 1 2 3 4 5 | 90.000 78.000 62.000 45.000 106.700 |
1926065001 | PLANT BED PREP (TYPE III) | SY | 33,991.000 | 1.00 | 1 2 3 4 5 | 0.750 0.150 1.300 0.500 0.619 |
1936001 | PLANT MAINTENANCE | MO | 18.000 | 1,800.00 | 1 2 3 4 5 | 5,000.000 3,503.000 1,500.000 8,000.000 4,385.965 |
1936002 | PLANT MAINTENANCE | CYC | 9.000 | 9,000.00 | 1 2 3 4 5 | 4,000.000 9,430.000 5,000.000 18,000.000 12,670.565 |
5006001 | MOBILIZATION | LS | 1.000 | 27,500.00 | 1 2 3 4 5 | 42,000.000 57,250.000 150,333.750 50,000.000 78,947.368 |
5026001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 3.000 | 1,500.00 | 1 2 3 4 5 | 4,000.000 540.000 1,250.000 4,200.000 2,706.433 |
5066041004 | BIODEG EROSN CONT LOGS (INSTL) (12") | LF | 2.000 | 6.00 | 1 2 3 4 5 | 20.000 5.000 25.000 1.000 117.895 |
5066043004 | BIODEG EROSN CONT LOGS (REMOVE) | LF | 2.000 | 1.00 | 1 2 3 4 5 | 3.000 3.000 25.000 1.000 30.175 |
7516011 | PRUNING | CYC | 1.000 | 25,000.00 | 1 2 3 4 5 | 14,000.000 10,001.000 50,000.000 48,000.000 49,122.807 |
10006006 | PRUNING AND TRIMMING TREES AND SHRUBS | CYC | 1.000 | 12,000.00 | 1 2 3 4 5 | 14,000.000 10,400.000 35,000.000 60,000.000 50,008.772 |
10066001 | LANDSCAPE SOIL AMENDMENT (TYPE I) | SY | 33,991.000 | 0.25 | 1 2 3 4 5 | 0.400 0.450 0.650 0.500 0.280 |
10066002 | LANDSCAPE SOIL AMENDMENT (TYPE II) | SY | 33,991.000 | 0.25 | 1 2 3 4 5 | 0.600 0.350 0.650 0.500 0.291 |
10066003 | LANDSCAPE SOIL AMENDMENT (TYPE III) | SY | 4,819.000 | 3.00 | 1 2 3 4 5 | 1.800 1.400 2.000 1.500 1.278 |
10066004 | LANDSCAPE SOIL AMENDMENT (TYPE IV) | SY | 23,900.000 | 0.50 | 1 2 3 4 5 | 0.600 0.550 0.650 0.500 0.251 |
10066005 | LANDSCAPE SOIL AMENDMENT (TYPE V) | SY | 4,819.000 | 0.50 | 1 2 3 4 5 | 1.800 0.600 2.000 0.500 0.624 |
61856002 | TMA (STATIONARY) | DAY | 5.000 | 290.00 | 1 2 3 4 5 | 400.000 400.000 6,500.000 400.000 473.860 |