Tabulation of Bids for Project NH 1702(678)
Text version of this page | |||
County: | BEXAR | Let Date: | 08/08/17 |
Type: | LANDSCAPE DEVELOPEMENT | Seq No: | 3010 |
Time: | 95 WORKING DAYS | Project ID: | NH 1702(678) |
Highway: | VA | Contract #: | 08173010 |
Length: | 0.001 | CCSJ: | 0915-12-591 |
Limits: | |||
From: | VARIOUS LOCATIONS IN BEXAR COUNTY | Check: | $11,000 |
To: | . | Misc Cost: | $1,500.00 |
Estimate | $527,386.32 | % Over/Under | Company |
Bidder 1 | $510,193.00 | -3.26% | ENCINO LANDSCAPE, INC. |
Bidder 2 | $706,793.87 | +34.02% | YELLOWSTONE LANDSCAPE - CENTRAL, INC. |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
1006008 | PREPARING ROW (TREE) (0" TO 6" DIA) | EA | 29.000 | 350.00 | 1 2 | 400.000 57.919 |
1706001 | IRRIGATION SYSTEM | LS | 1.000 | 120,000.00 | 1 2 | 50,000.000 163,842.145 |
1926004 | PLANT MATERIAL (5-GAL) | EA | 4,196.000 | 27.00 | 1 2 | 25.000 15.327 |
1926005 | PLANT MATERIAL (15-GAL) | EA | 400.000 | 120.00 | 1 2 | 110.000 68.548 |
1926013 | MULCH | SY | 13,181.000 | 2.00 | 1 2 | 3.000 5.139 |
1926049 | PLANT MATERIAL (MIN 4' TRNK HT) (PALM) | EA | 12.000 | 450.00 | 1 2 | 500.000 662.177 |
1936001 | PLANT MAINTENANCE | MO | 30.000 | 2,000.00 | 1 2 | 2,000.000 3,294.908 |
1936002 | PLANT MAINTENANCE | CYC | 11.000 | 2,500.00 | 1 2 | 5,000.000 13,225.489 |
1936005 | PLANT REPLACEMENT (5-GAL) | EA | 5.000 | 30.00 | 1 2 | 30.000 27.419 |
1936007 | IRRIGATION SYSTEM OPER AND MAINT | MO | 30.000 | 2,000.00 | 1 2 | 2,000.000 901.290 |
1936009 | PLANT REPLACEMENT (15 GAL) | EA | 5.000 | 160.00 | 1 2 | 200.000 122.251 |
5006001 | MOBILIZATION | LS | 1.000 | 37,732.32 | 1 2 | 60,000.000 69,354.839 |
5026001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 6.000 | 3,000.00 | 1 2 | 3,000.000 5,398.008 |