Tabulation of Bids for Project STP 1802(382)
Text version of this page | |||
County: | JOHNSON | Let Date: | 07/10/18 |
Type: | BS REPR, MILL, OV, PAV MK, MBGF | Seq No: | 3010 |
Time: | 64 WORKING DAYS | Project ID: | STP 1802(382) |
Highway: | FM 2331 | Contract #: | 07183010 |
Length: | 8.244 | CCSJ: | 2417-02-016 |
Limits: | |||
From: | TARRANT C/L | Check: | $33,000 |
To: | SH 171 | Misc Cost: | $85,500.00 |
Estimate | $1,640,814.92 | % Over/Under | Company |
Bidder 1 | $1,839,667.79 | +12.12% | PEACHTREE CONSTRUCTION, LTD. |
Bidder 2 | $1,937,190.11 | +18.06% | OLDCASTLE MATERIALS TEXAS, INC. |
Bidder 3 | $2,074,023.28 | +26.40% | BICK'S CONSTRUCTION, INC. |
Bidder 4 | $2,833,260.30 | +72.67% | NORTHEASTERN PAVERS, INC. |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
1346001 | BACKFILL (TY A) | STA | 20.000 | 200.00 | 1 2 3 4 | 380.000 530.000 200.000 350.000 |
3056002 | SALV, HAUL & STKPL RCL APH PV (0 TO 2") | SY | 110.000 | 5.00 | 1 2 3 4 | 40.000 41.000 7.250 60.000 |
3406246 | D-GR HMA (SQ) TY-D PG64_22(LEVEL-UP) | TON | 2,050.000 | 100.00 | 1 2 3 4 | 94.000 96.000 111.000 160.000 |
3476001 | TOM (ASPHALT) PG 76-22 | TON | 420.000 | 200.00 | 1 2 3 4 | 135.000 135.000 143.370 185.000 |
3476002 | TOM-C (AGGREGATE) SAC-A | TON | 6,150.000 | 100.00 | 1 2 3 4 | 135.000 135.000 143.370 185.000 |
3516008 | FLEXIBLE PAVEMENT STRUCTURE REPAIR(12") | SY | 7,200.000 | 55.00 | 1 2 3 4 | 67.000 70.000 86.400 100.000 |
5006001 | MOBILIZATION | LS | 1.000 | 105,380.42 | 1 2 3 4 | 100,000.000 132,800.000 131,925.000 300,000.000 |
5026001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 3.000 | 10,000.00 | 1 2 3 4 | 5,000.000 23,000.000 615.000 2,500.000 |
5066042002 | BIODEG EROSN CONT LOGS (INSTL) (18") | LF | 500.000 | 6.75 | 1 2 3 4 | 10.000 5.000 5.000 0.010 |
5066043002 | BIODEG EROSN CONT LOGS (REMOVE) | LF | 500.000 | 1.00 | 1 2 3 4 | 5.000 1.000 5.000 0.010 |
5406001 | MTL W-BEAM GD FEN (TIM POST) | LF | 600.000 | 20.00 | 1 2 3 4 | 21.000 26.550 22.750 35.000 |
5406006 | MTL BEAM GD FEN TRANS (THRIE-BEAM) | EA | 7.000 | 1,450.00 | 1 2 3 4 | 1,600.000 1,785.000 1,886.000 3,000.000 |
5406014 | SHORT RADIUS | LF | 50.000 | 110.00 | 1 2 3 4 | 40.000 47.250 40.500 62.000 |
5406015 | DRIVEWAY TERMINAL ANCHOR SECTION | EA | 1.000 | 750.00 | 1 2 3 4 | 1,000.000 1,035.000 942.000 1,450.000 |
5426001 | REMOVE METAL BEAM GUARD FENCE | LF | 600.000 | 8.00 | 1 2 3 4 | 4.400 5.750 3.000 5.000 |
5426004 | RM MTL BM GD FENCE TRANS (THRIE-BEAM) | EA | 7.000 | 200.00 | 1 2 3 4 | 380.000 253.000 200.000 310.000 |
5446001 | GUARDRAIL END TREATMENT (INSTALL) | EA | 8.000 | 2,250.00 | 1 2 3 4 | 2,800.000 2,805.000 2,750.000 4,200.000 |
5446003 | GUARDRAIL END TREATMENT (REMOVE) | EA | 9.000 | 250.00 | 1 2 3 4 | 380.000 253.000 200.000 300.000 |
6626111 | WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | EA | 8,706.000 | 1.00 | 1 2 3 4 | 1.500 1.060 1.500 1.000 |
6666041007 | REFL PAV MRK TY I (W)12"(SLD)(090MIL) | LF | 140.000 | 2.50 | 1 2 3 4 | 3.100 2.800 2.780 8.000 |
6666302007 | RE PM W/RET REQ TY I (W)4"(SLD)(090MIL) | LF | 85,223.000 | 0.50 | 1 2 3 4 | 0.320 0.300 0.290 0.350 |
6666311007 | RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL) | LF | 7,440.000 | 0.50 | 1 2 3 4 | 0.390 0.360 0.350 0.590 |
6666314007 | RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL) | LF | 41,169.000 | 0.50 | 1 2 3 4 | 0.320 0.300 0.290 0.350 |
6686031 | PREFAB PAV MRK TY B (W)(RR XING) | EA | 2.000 | 950.00 | 1 2 3 4 | 1,050.000 955.000 950.000 675.000 |
6726009 | REFL PAV MRKR TY II-A-A | EA | 965.000 | 2.50 | 1 2 3 4 | 3.350 3.050 3.000 3.500 |
61856002 | TMA (STATIONARY) | DAY | 100.000 | 600.00 | 1 2 3 4 | 225.000 112.000 238.150 750.000 |
61856003 | TMA (MOBILE OPERATION) | HR | 15.000 | 125.00 | 1 2 3 4 | 35.000 100.000 50.000 1,500.000 |