Tabulation of Bids for Project STP 2014(714)HES

Last Update: Thursday, June 12, 2014
Text version of this page
County: CALDWELL Let Date: 06/12/14
Type: INSTALL CONTINUOUS TURN LANE Seq No: 3018
Time: 71 WORKING DAYS Project ID: STP 2014(714)HES
Highway: SH 80 Contract #: 06143018
Length: 0.378 CCSJ: 0286-02-030
Limits:  
From: 0.235 MILES WEST OF FM 20 Check: $9,000.00
To: FM 20 Misc Cost: $12,000.00
Estimate $442,165.07 % Over/Under Company
Bidder 1 $499,490.10 +12.96% ANGEL BROTHERS ENTERPRISES, LTD.
Bidder 2 $505,196.40 +14.26% AARON CONCRETE CONTRACTORS, L.P.
Bidder 3 $577,987.45 +30.72% ACE ASPHALT OF ARIZONA, INC.
Item Code Description Unit Quantity Unit Est. Bidder Unit Bid
1002002002 PREPARING ROW STA 18.300 1000.00 1
2
3
850.000
1700.000
2000.000
1042009 REMOVING CONC (RIPRAP) SY 105.000 25.00 1
2
3
20.000
33.000
25.000
1102001 EXCAVATION (ROADWAY) CY 664.000 10.00 1
2
3
18.000
35.000
25.000
1322003 EMBANKMENT (FINAL) (ORD COMP) (TY B) CY 259.000 14.00 1
2
3
22.000
30.000
12.000
1322019 EMBANKMENT (VEHICLE) (ORD COMP) (TY B) CY 200.000 18.00 1
2
3
58.000
38.000
25.000
1602003 FURNISHING AND PLACING TOPSOIL (4") SY 4173.000 1.50 1
2
3
1.400
1.100
3.000
1642023002 CELL FBR MLCH SEED (PERM) (RURAL) (CLAY) SY 4173.000 0.30 1
2
3
0.320
0.400
0.400
1642031002 CELL FBR MLCH SEED (TEMP) (COOL) SY 2087.000 0.15 1
2
3
0.320
0.400
0.390
1682001 VEGETATIVE WATERING MG 94.000 20.00 1
2
3
24.000
40.000
35.000
1692002002 SOIL RETENTION BLANKETS (CL 1) (TY B) SY 1044.000 1.20 1
2
3
1.350
1.500
1.650
2472392033 FL BS (CMP IN PLC) (TY D GR 5) (FNAL POS CY 789.000 50.00 1
2
3
55.000
34.000
55.000
3102016 PRIME COAT (RC - 250) GAL 442.000 4.50 1
2
3
11.000
5.000
10.000
3162672016 AGGR (TY - B GR - 5 OR TY - L GR - 5) CY 13.000 130.00 1
2
3
540.000
250.000
450.000
3342064 HMCL ACP TY - C AES - 300 TON 10.000 110.00 1
2
3
150.000
270.000
250.000
4292008008 CNC STR REP (VERTICAL OR OVERHEAD) SF 20.000 150.00 1
2
3
100.000
170.000
400.000
4322002 RIPRAP (CONC) (5 IN) CY 8.400 420.00 1
2
3
580.000
450.000
450.000
4322039 RIPRAP (MOW STRIP) (4 IN) CY 3.800 450.00 1
2
3
580.000
730.000
450.000
4602004 CMP (GAL STL 24 IN) LF 10.000 60.00 1
2
3
106.000
130.000
85.000
4602014 CMP AR (GAL STL DES 2) LF 20.000 90.00 1
2
3
108.000
120.000
78.000
4622010015 CONC BOX CULV (6 FT X 3 FT) LF 80.000 450.00 1
2
3
600.000
500.000
450.000
4662020 WINGWALL (FW - 0) (HW=4 FT) EA 2.000 4000.00 1
2
3
4000.000
5500.000
15500.000
4672375 SET (TY II) (DES 2) (CMP) (8: 1) (P) EA 2.000 1500.00 1
2
3
1200.000
630.000
1500.000
4672635 SET (TY II) (15 IN) (RCP) (8: 1) (P) EA 2.000 1500.00 1
2
3
1500.000
1300.000
1500.000
4722002 REMOV & RE - LAY PIPE (15 IN) LF 8.000 50.00 1
2
3
140.000
130.000
50.000
4792008 ADJUST INLET (SPL) EA 1.000 1500.00 1
2
3
1600.000
2500.000
3500.000
4962007 REMOV STR (PIPE) LF 110.000 40.00 1
2
3
18.000
40.000
25.000
5002001011 MOBILIZATION LS 1.000 40000.00 1
2
3
49000.000
48000.000
32716.000
5022001033 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 5.000 3000.00 1
2
3
4000.000
900.000
4500.000
5402011031 MTL BEAM GD FEN TRANS (THRIE - BEAM) EA 12.000 1400.00 1
2
3
1800.000
1500.000
1250.000
5402030031 MTL BEAM GD FEN (MOVE AND RESET) LF 1625.000 9.00 1
2
3
11.000
16.000
11.000
5422002 REMOVING TERMINAL ANCHOR SECTION EA 14.000 150.00 1
2
3
110.000
140.000
150.000
5442006001 GDRAIL END TRT (INST) (WOOD POST) (TY II EA 14.000 2200.00 1
2
3
2300.000
2500.000
2500.000
5442009001 GDRAIL END TRT (MOV & RST) (WOOD PST) TY EA 2.000 1200.00 1
2
3
600.000
1200.000
350.000
6442004 IN SM RD SN SUP & AM TY10BWG (1) SA (T) EA 2.000 550.00 1
2
3
440.000
610.000
485.000
6442056 RELOCATE SM RD SN SUP & AM TY 10BWG EA 11.000 260.00 1
2
3
305.000
450.000
400.000
6442060 REMOVE SM RD SN SUP & AM EA 10.000 70.00 1
2
3
50.000
73.000
85.000
6442081 IN SM RD SN SUP & AM TYTWT (1) WS (P) EA 6.000 350.00 1
2
3
260.000
320.000
1850.000
6582259 INSTL DEL ASSM (D - SW) SZ (TYC) CTB (BI EA 16.000 22.00 1
2
3
18.000
12.000
14.000
6582261 INSTL DEL ASSM (D - SW) SZ (TYC) GF1 (BI EA 48.000 20.00 1
2
3
18.000
12.000
15.000
6582314 INSTL OM ASSM (OM - 2X) (WC) GND EA 2.000 90.00 1
2
3
42.000
46.000
54.000
6622115 WK ZN PAV MRK SHT TERM (TAB) TY Y - 2 EA 1066.000 1.50 1
2
3
1.000
2.000
1.850
6662012 REFL PAV MRK TY I (W) 4" (SLD) (100MIL) LF 3856.000 0.38 1
2
3
0.380
0.500
0.600
6662036 REFL PAV MRK TY I (W) 8" (SLD) (100MIL) LF 715.000 2.00 1
2
3
1.000
1.200
1.350
6662048 REFL PAV MRK TY I (W) 24" (SLD) (100MIL) LF 84.000 6.00 1
2
3
8.000
9.000
9.450
6662054 REFL PAV MRK TY I (W) (ARROW) (100MIL) EA 3.000 200.00 1
2
3
85.000
96.000
135.000
6662069 REFL PAV MRK TY I (W) (DBL ARROW) (100MI EA 2.000 170.00 1
2
3
188.000
210.000
185.000
6662096 REFL PAV MRK TY I (W) (WORD) (100MIL) EA 3.000 200.00 1
2
3
91.000
102.000
142.000
6662105 REFL PAV MRK TY I (Y) 4" (BRK) (100MIL) LF 7895.000 0.40 1
2
3
0.360
0.400
0.650
6662111 REFL PAV MRK TY I (Y) 4" (SLD) (100MIL) LF 43503.000 0.38 1
2
3
0.320
0.400
0.740
6722012034 REFL PAV MRKR TY I - C EA 36.000 4.50 1
2
3
8.000
9.000
5.250
6722015034 REFL PAV MRKR TY II - A - A EA 1088.000 4.50 1
2
3
3.220
3.600
7.000
11222037001 TEMPORARY SEDIMENT CONTROL FENCE INSTLL LF 687.000 2.50 1
2
3
3.000
2.300
2.000
11222057001 TEMPORARY SEDIMENT CONTROL FENCE REMOVE LF 687.000 0.50 1
2
3
0.500
0.600
1.000
32682042 D - GR HMA TY - D SAC - B PG70 - 22 TON 1334.000 80.00 1
2
3
89.000
93.000
95.000
53692001 CENTERLINE TEXTURING STA 422.400 36.00 1
2
3
20.000
12.000
40.000