Tabulation of Bids for Project BPM - 635284001
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months.
The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.
Text version of this page | |||
County: | GARZA | Let Date: | 05/07/20 |
Type: | BRIDGE PREVENTIVE MAINTENANCE | Seq No: | 4018 |
Time: | 120 W | Project ID: | BPM - 635284001 |
Highway: | US0084 | Contract #: | 05204018 |
Length: | 0.001 | CCSJ: | 6352-84-001 |
Limits: | |||
From: | VARIOUS LOCATIONS | Check: | $11,000 |
To: | VARIOUS LOCATIONS | Misc Cost: |
Estimate | $530,938.80 | % Over/Under | Company |
Bidder 1 | $517,184.80 | -2.59% | BLACKSTONE CONCRETE VENTURES, LLC |
Bidder 2 | $706,810.00 | +33.12% | EARTH BUILDERS, L.P. |
Bidder 3 | $772,779.00 | +45.55% | SJ&J CONSTRUCTION, LLC |
Bidder 4 | $805,860.20 | +51.78% | SOUTHERN ROAD & BRIDGE, LLC |
Bidder 5 | $838,630.00 | +57.95% | CHAMPION INFRASTRUCTURE, LLC |
Bidder 6 | $844,648.90 | +59.09% | SCOTT TUCKER CONSTRUCTION COMPANY, LLC |
Bidder 7 | $869,887.00 | +63.84% | SCR CIVIL CONSTRUCTION, LLC |
Bidder 8 | $1,290,810.00 | +143.12% | FNH CONSTRUCTION, LLC |
Bidder 9 | $1,837,936.48 | +246.17% | SALINAS CONSTRUCTION TECHNOLOGIES, LTD. |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
1046009 | REMOVING CONC (RIPRAP) | SY | 93.000 | 50.00 | 1 2 3 4 5 6 7 8 9 | 10.000 10.000 45.000 125.000 120.000 241.000 50.000 50.000 248.370 |
4016001 | FLOWABLE BACKFILL | CY | 48.000 | 250.00 | 1 2 3 4 5 6 7 8 9 | 450.000 300.000 300.000 350.000 360.000 482.000 450.000 350.000 438.830 |
4296008 | CONC STR REPR(RAPID VERT AND OVERHEAD) | SF | 701.000 | 100.00 | 1 2 3 4 5 6 7 8 9 | 40.000 125.000 150.000 288.000 145.000 143.000 145.000 350.000 242.230 |
4296009 | CONC STR REPAIR (STANDARD) | SF | 1,128.000 | 100.00 | 1 2 3 4 5 6 7 8 9 | 55.000 100.000 90.000 188.000 110.000 114.000 145.000 325.000 283.750 |
4326008 | RIPRAP (CONC)(CL B)(RR8&RR9) | CY | 69.000 | 600.00 | 1 2 3 4 5 6 7 8 9 | 450.000 700.000 800.000 400.000 860.000 588.000 350.000 650.000 1,047.890 |
4386001 | CLEANING AND SEALING EXISTING JOINTS | LF | 573.400 | 27.00 | 1 2 3 4 5 6 7 8 9 | 70.000 50.000 50.000 100.000 75.000 54.000 60.000 100.000 176.070 |
4546004 | ARMOR JOINT (SEALED) | LF | 342.600 | 145.00 | 1 2 3 4 5 6 7 8 9 | 125.000 100.000 140.000 188.000 260.000 272.000 510.000 100.000 340.020 |
4546007 | HEADER TYPE EXPANSION JOINT | LF | 87.300 | 100.00 | 1 2 3 4 5 6 7 8 9 | 66.000 250.000 300.000 828.000 280.000 387.000 240.000 200.000 359.030 |
4806001 | CLEAN EXIST CULVERTS | EA | 3.000 | 1,000.00 | 1 2 3 4 5 6 7 8 9 | 1,000.000 15,000.000 500.000 2,500.000 6,500.000 7,962.000 5,700.000 3,000.000 6,188.060 |
5006001 | MOBILIZATION | LS | 1.000 | 50,000.00 | 1 2 3 4 5 6 7 8 9 | 100,000.000 75,000.000 100,000.000 25,000.000 60,000.000 84,544.000 67,000.000 125,000.000 490,391.280 |
5026001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 6.000 | 5,000.00 | 1 2 3 4 5 6 7 8 9 | 1,000.000 10,000.000 8,000.000 5,000.000 4,500.000 3,191.000 10,000.000 8,500.000 11,606.030 |
5126005 | PORT CTB (FUR & INST)(F-SHAPE)(TY 1) | LF | 600.000 | 80.00 | 1 2 3 4 5 6 7 8 9 | 50.000 100.000 100.000 10.000 60.000 78.000 35.000 85.000 83.850 |
5126029 | PORT CTB (MOVE)(F-SHAPE)(TY 1) | LF | 600.000 | 18.00 | 1 2 3 4 5 6 7 8 9 | 50.000 20.000 30.000 2.000 40.000 24.000 55.000 20.000 36.190 |
5126053 | PORT CTB (REMOVE)(F-SHAPE)(TY 1) | LF | 600.000 | 23.00 | 1 2 3 4 5 6 7 8 9 | 50.000 20.000 50.000 2.000 60.000 30.000 35.000 20.000 63.900 |
5456003 | CRASH CUSH ATTEN (MOVE & RESET) | EA | 3.000 | 2,000.00 | 1 2 3 4 5 6 7 8 9 | 1,000.000 2,500.000 1,000.000 50.000 8,500.000 2,777.000 5,000.000 5,000.000 2,026.000 |
5456005 | CRASH CUSH ATTEN (REMOVE) | EA | 3.000 | 1,500.00 | 1 2 3 4 5 6 7 8 9 | 1,000.000 1,500.000 1,000.000 50.000 3,500.000 2,763.000 1,000.000 2,500.000 981.000 |
5456019 | CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) | EA | 3.000 | 5,000.00 | 1 2 3 4 5 6 7 8 9 | 1,000.000 7,500.000 20,000.000 50.000 14,000.000 9,443.000 7,500.000 15,000.000 11,046.000 |
7866001 | CARBON FIBER REINF POLYMER PROTECTION | SF | 180.000 | 10.00 | 1 2 3 4 5 6 7 8 9 | 250.000 175.000 150.000 220.000 95.000 229.000 145.000 350.000 327.110 |
7886001 | CONCRETE BEAM REPAIR | EA | 2.000 | 7,600.00 | 1 2 3 4 5 6 7 8 9 | 15,000.000 5,000.000 6,000.000 15,000.000 13,000.000 24,556.000 8,000.000 25,000.000 26,713.230 |
61856002 | TMA (STATIONARY) | DAY | 180.000 | 100.00 | 1 2 3 4 5 6 7 8 9 | 10.000 100.000 150.000 5.000 250.000 165.000 125.000 350.000 774.350 |