Tabulation of Bids for Project RMC - 636957001
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months.
The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.
Text version of this page | |||
County: | GONZALES | Let Date: | 04/08/21 |
Type: | ON CALL SPOT REPAIRS | Seq No: | 4218 |
Time: | 365 CALENDAR DAYS | Project ID: | RMC - 636957001 |
Highway: | UA0090 | Contract #: | 04214218 |
Length: | 0.010 | CCSJ: | 6369-57-001 |
Limits: | |||
From: | . | Check: | $20,000 |
To: | . | Misc Cost: |
Estimate | $1,007,000.00 | % Over/Under | Company |
Bidder 1 | $756,100.00 | -24.92% | CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. |
Bidder 2 | $813,500.00 | -19.22% | ANGEL BROTHERS HOLDINGS CORP. |
Bidder 3 | $865,709.55 | -14.03% | HUNTER INDUSTRIES, LTD. |
Bidder 4 | $933,000.00 | -7.35% | LONE STAR PAVING COMPANY |
Bidder 5 | $1,009,700.00 | +0.27% | TEXAS MATERIALS GROUP, INC. |
Bidder 6 | $1,218,550.00 | +21.01% | AUSTIN MATERIALS, LLC |
Bidder 7 | $1,512,650.00 | +50.21% | FORDE CONSTRUCTION COMPANY, INC. |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
3516002 | FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") | SY | 3,000.000 | 60.00 | 1 2 3 4 5 6 7 | 54.000 45.000 47.510 53.000 80.000 62.000 101.000 |
3516004 | FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | SY | 4,000.000 | 70.00 | 1 2 3 4 5 6 7 | 65.000 59.000 62.780 71.000 85.000 71.000 114.000 |
3516008 | FLEXIBLE PAVEMENT STRUCTURE REPAIR(12") | SY | 4,000.000 | 90.00 | 1 2 3 4 5 6 7 | 82.000 86.000 86.270 107.000 90.000 92.000 136.000 |
5006033 | MOBILIZATION (CALLOUT) | EA | 3.000 | 25,000.00 | 1 2 3 4 5 6 7 | 300.000 28,000.000 10,159.850 1,000.000 20,000.000 30,200.000 20,000.000 |
61856002002 | TMA (STATIONARY) | DAY | 60.000 | 200.00 | 1 2 3 4 5 6 7 | 50.000 150.000 225.000 250.000 125.000 650.000 330.000 |
70226001 | 1 LANE CLOSURE-2 LANE ROAD, NO SHLDR | EA | 35.000 | 1,000.00 | 1 2 3 4 5 6 7 | 20.000 50.000 900.000 400.000 20.000 2,385.000 1,400.000 |
70226002 | 1 LANE CLOSURE-2 LANE ROAD, PAVED SHLDR | EA | 35.000 | 1,000.00 | 1 2 3 4 5 6 7 | 20.000 50.000 900.000 400.000 20.000 2,385.000 1,350.000 |
70226003 | 1 LANE CLOSURE-4 LANE ROAD | EA | 10.000 | 1,500.00 | 1 2 3 4 5 6 7 | 20.000 50.000 500.000 400.000 20.000 2,385.000 1,350.000 |
70226016 | WORK AREA ON SHOULDER | EA | 30.000 | 500.00 | 1 2 3 4 5 6 7 | 20.000 50.000 500.000 400.000 20.000 2,005.000 670.000 |