Monthly State Let Maintenance Report For Yoakum District As Of Aug 12, 2014 Page 2 Of 2

Last Update: Tuesday, August 12, 2014
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyCOLORADO
Highway US0090
From DISTRICTWIDE
To .
CSJ 6268-95-001
Proj ID RMC - 626895001
Work Type THERMOPLASTIC PAVEMENT MARKINGS
 
0.001 634038.36 73011.98 320941.68 50.6
Work Order 05-20-14
Work Began 05-20-14
Work Completed  
Time Computed 05-27-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 29
Percent Time Used 64
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6268-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03144007
Totals 634038.36 73011.98 320941.68 50.6

CountyDEWITT
Highway US0077
From DEWITT, GONZALES,
To LAVACA, FAYETTE
CSJ 6273-65-001
Proj ID RMC - 627365001
Work Type SPOT REPAIR
 
0.001 1142315.12 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6273-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08144004
Totals 1142315.12 0.00 0.00 0.0

page 1 | page 2