Monthly Local Let Maintenance Report For Yoakum District As Of Aug 12, 2014 Page 2 Of 3

Last Update: Tuesday, August 12, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyLAVACA
Highway UA0090
From HALLETTSVILLE
To LAVACA COUNTY
CSJ 6258-06-001
Proj ID SUP - 625806001
Work Type JANITOR SERVICES FOR TXDOT OFFICE
 
0.001 36384.32 998.49 17394.12 47.8
Work Order 04-30-13
Work Began 07-01-13
Work Completed  
Time Computed 07-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 396
Percent Time Used 54
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6258-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04131339
Totals 36384.32 998.49 17394.12 47.8

CountyMATAGORDA
Highway SH0035
From BAY CITY
To MATAGORDA COUNTY
CSJ 6258-07-001
Proj ID SUP - 625807001
Work Type JANITOR SERVICES FOR TXDOT OFFICE
 
0.001 21692.74 610.72 8919.50 41.1
Work Order 04-30-13
Work Began 07-01-13
Work Completed  
Time Computed 07-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 396
Percent Time Used 54
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6258-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04131340
Totals 21692.74 610.72 8919.50 41.1

CountyWHARTON
Highway FM0102
From WHARTON
To WHARTON COUNTY
CSJ 6258-08-001
Proj ID SUP - 625808001
Work Type JANITOR SERVICES AT TXDOT OFFICE
 
0.001 37712.98 985.21 17254.73 45.7
Work Order 04-30-13
Work Began 07-01-13
Work Completed  
Time Computed 07-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 396
Percent Time Used 54
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6258-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04131341
Totals 37712.98 985.21 17254.73 45.7

CountyVICTORIA
Highway US0077
From VICTORIA, JACKSON,
To & CALHOUN COUNTIES
CSJ 6258-45-001
Proj ID RMC - 625845001
Work Type ON - CALL FLAGGING OPERATIONS
 
0.001 190000.00 14990.00 84357.50 44.3
Work Order 09-26-13
Work Began 10-01-13
Work Completed  
Time Computed 10-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 304
Percent Time Used 83
Contractor(s)
DELTA PRIME SPECIALTY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6258-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07131301
Totals 190000.00 14990.00 84357.50 44.3

CountyWHARTON
Highway SH0071
From WHARTON, MATAGORDA
To AND AUSTIN COUNTIES
CSJ 6258-46-001
Proj ID RMC - 625846001
Work Type ON - CALL FLAGGING OPERATIONS
 
0.001 183700.00 8625.00 110946.10 60.3
Work Order 09-25-13
Work Began 10-01-13
Work Completed  
Time Computed 10-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 304
Percent Time Used 83
Contractor(s)
NIXON ENGINEERING
SUBCONTRACTOR(S) FOR CCSJ: 6258-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07131302
Totals 183700.00 8625.00 110946.10 60.3

CountyDEWITT
Highway SH0111
From DEWITT, GONZALES, LAVACA
To FAYETTE & COLORADO COUNTIES
CSJ 6258-47-001
Proj ID RMC - 625847001
Work Type ON - CALL FLAGGING OPERATIONS
 
0.001 207900.00 17385.00 179707.00 86.4
Work Order 09-18-13
Work Began 10-01-13
Work Completed  
Time Computed 10-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 304
Percent Time Used 83
Contractor(s)
NIXON ENGINEERING
SUBCONTRACTOR(S) FOR CCSJ: 6258-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07131303
Totals 207900.00 17385.00 179707.00 86.4

CountyAUSTIN
Highway IH0010
From AUSTIN COUNTY
To COLORADO COUNTY
CSJ 6258-59-001
Proj ID SUP - 625859001
Work Type LITTER PICKUP AND DISPOSAL
 
0.001 55440.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6258-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04131342
Totals 55440.00 0.00 0.00 0.0

CountyFAYETTE
Highway US0077
From FAYETTE, LAVACA, GONZALES, DEWITT,
To COLORADO, AUSTIN, MATAGORDA, WHARTON
CSJ 6259-44-001
Proj ID RMC - 625944001
Work Type TREE REMOVAL & BRUSH TRIMMING
 
0.001 241735.00 0.00 247468.50 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-11-13
Work Began 11-11-13
Work Completed 07-01-14
Time Computed 11-18-13
Contract Working Days 75
Addl Days Granted 47
Working Days Charged 117
Percent Time Used 95
Contractor(s)
T.F.R. ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09131301
Totals 241735.00 0.00 247468.50 100.0

CountyVICTORIA
Highway US0059
From VICTORIA, JACKSON
To AND CALHOUN COUNTIES
CSJ 6259-58-001
Proj ID RMC - 625958001
Work Type METAL BEAM GUARDFENCE REPAIR (AS NEED)
 
0.001 113923.25 8628.10 64809.45 56.8
Work Order 11-01-13
Work Began 11-05-13
Work Completed  
Time Computed 11-05-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 269
Percent Time Used 73
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07131305
Totals 113923.25 8628.10 64809.45 56.8

CountyWHARTON
Highway US0059
From WHARTON, MATAGORDA
To AND AUSTIN COUNTIES
CSJ 6259-59-001
Proj ID RMC - 625959001
Work Type METAL BEAM GUARDFENCE REPAIR (AS NEED)
 
0.001 129693.30 6196.50 75637.70 64.6
Work Order 12-11-13
Work Began 12-16-13
Work Completed  
Time Computed 12-16-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 228
Percent Time Used 62
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07131306
Totals 129693.30 6196.50 75637.70 64.6

CountyVICTORIA
Highway US0059
From VICTORIA, JACKSON,
To CALHOUN
CSJ 6265-41-001
Proj ID RMC - 626541001
Work Type THERMOPLASTIC PAVEMENT MARKINGS ON - CALL
 
0.001 267690.00 0.00 162834.20 60.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-06-14
Work Began 01-06-14
Work Completed  
Time Computed 01-13-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 43
Percent Time Used 11
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6265-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131301
Totals 267690.00 0.00 162834.20 60.8

CountyJACKSON
Highway US0059
From DEWITT, JACKSON,
To GONZALES, CALHOUN
CSJ 6268-43-001
Proj ID RMC - 626843001
Work Type CRACK SEAL - - WEST
 
408.060 163224.00 0.00 159944.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-01-14
Work Began 04-07-14
Work Completed 07-01-14
Time Computed 04-07-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 26
Percent Time Used 57
Contractor(s)
DELTA PRIME SPECIALTY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6268-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02141301
Totals 163224.00 0.00 159944.00 100.0

CountyCOLORADO
Highway US0090
From COLORADO, LAVACA, FAYETTE, WHARTON,
To MATAGORDA, AUSTIN
CSJ 6268-44-001
Proj ID RMC - 626844001
Work Type CRACK SEAL - - EAST
 
405.900 162360.00 0.00 162360.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-01-14
Work Began 04-07-14
Work Completed 07-01-14
Time Computed 04-07-14
Contract Working Days 47
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 68
Contractor(s)
DELTA PRIME SPECIALTY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6268-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02141302
Totals 162360.00 0.00 162360.00 100.0

CountyCOLORADO
Highway US0090
From DISTRICTWIDE
To .
CSJ 6268-97-001
Proj ID RMC - 626897001
Work Type RAISED PAVEMENT MARKERS
 
0.001 99889.44 24741.68 81316.80 87.6
Work Order 04-28-14
Work Began 04-28-14
Work Completed  
Time Computed 05-05-14
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 41
Percent Time Used 136
Contractor(s)
FLASHER EQUIPMENT COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6268-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03141309
Totals 99889.44 24741.68 81316.80 87.6

CountyVICTORIA
Highway US0059
From VICTORIA
To VICTORIA_COUNTY
CSJ 6268-99-001
Proj ID SUP - 626899001
Work Type JANITORIAL SERVICES FOR VICTORIA TXDOT
 
0.001 42233.10 0.00 12121.85 28.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-25-13
Work Began 01-01-14
Work Completed  
Time Computed 01-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 96
Percent Time Used 13
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL INDUSTRIES OF SOUTH TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6268-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01141301
Totals 42233.10 0.00 12121.85 28.7

CountyFAYETTE
Highway IH0010
From FAYETTE, COLORADO, DEWITT, GONZALES,
To LAVACA
CSJ 6269-78-001
Proj ID RMC - 626978001
Work Type CALL OUT GUARDRAIL REPAIR
 
0.001 250800.00 39799.00 179157.00 71.4
Work Order 04-15-14
Work Began 04-14-14
Work Completed  
Time Computed 04-18-14
Contract Working Days 365
Addl Days Granted 2
Working Days Charged 59
Percent Time Used 16
Contractor(s)
SHORT-LINE CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6269-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03141311
Totals 250800.00 39799.00 179157.00 71.4

CountyCOLORADO
Highway IH0010
From COLORADO, AUSTIN, GONZALES
To FAYETTE
CSJ 6270-88-001
Proj ID SUP - 627088001
Work Type RUBBER LITTER REMOVAL
 
0.001 735835.98 23746.38 41608.12 5.6
Work Order 06-01-14
Work Began 06-01-14
Work Completed  
Time Computed 06-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 55
Percent Time Used 7
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6270-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141312
Totals 735835.98 23746.38 41608.12 5.6

CountyDEWITT
Highway US0183
From DEWITT COUNTY
To LAVACA COUNTY
CSJ 6270-89-001
Proj ID SUP - 627089001
Work Type PICNIC AREA MAINTENANCE
 
0.001 66494.88 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6270-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07141313
Totals 66494.88 0.00 0.00 0.0

CountyVICTORIA
Highway US0059
From VICTORIA, JACKSON
To WHARTON
CSJ 6270-90-001
Proj ID SUP - 627090001
Work Type RUBBER LITTER PICKUP (STATE USE PROGRAM)
 
0.001 219984.86 5898.48 11330.69 5.1
Work Order 06-01-14
Work Began 06-01-14
Work Completed  
Time Computed 06-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 55
Percent Time Used 7
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6270-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141314
Totals 219984.86 5898.48 11330.69 5.1

CountyFAYETTE
Highway US0077
From VARIOUS
To .
CSJ 6270-93-001
Proj ID SUP - 627093001
Work Type PICNIC AREA MAINTENANCE
 
0.001 190203.48 0.00 29352.20 15.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-14-14
Work Began 04-01-14
Work Completed  
Time Computed 04-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 116
Percent Time Used 15
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6270-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03141315
Totals 190203.48 0.00 29352.20 15.4

page 1 | page 2 | page 3