Monthly Local Let Maintenance Report For Yoakum District As Of Aug 10, 2015 Page 2 Of 4

Last Update: Monday, August 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyFAYETTE
Highway IH0010
From FAYETTE, COLORADO, DEWITT, GONZALES,
To LAVACA
CSJ 6269-78-001
Proj ID RMC - 626978001
Work Type CALL OUT GUARDRAIL REPAIR
 
0.001 250800.00 64885.00 539059.80 99.9
Work Order 04-15-14
Work Began 04-14-14
Work Completed  
Time Computed 04-18-14
Contract Working Days 365
Addl Days Granted 378
Working Days Charged 386
Percent Time Used 51
Contractor(s)
SHORT-LINE CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6269-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03141311
Totals 250800.00 64885.00 539059.80 99.9

CountyCOLORADO
Highway IH0010
From COLORADO, AUSTIN, GONZALES
To FAYETTE
CSJ 6270-88-001
Proj ID SUP - 627088001
Work Type RUBBER LITTER REMOVAL
 
0.001 735835.98 31334.68 353525.84 48.0
Work Order 06-01-14
Work Began 06-01-14
Work Completed  
Time Computed 06-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 420
Percent Time Used 57
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6270-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141312
Totals 735835.98 31334.68 353525.84 48.0

CountyDEWITT
Highway US0183
From DEWITT COUNTY
To LAVACA COUNTY
CSJ 6270-89-001
Proj ID SUP - 627089001
Work Type PICNIC AREA MAINTENANCE
 
0.001 66494.88 0.00 28726.58 43.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 08-01-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 359
Percent Time Used 49
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6270-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07141313
Totals 66494.88 0.00 28726.58 43.2

CountyFAYETTE
Highway US0077
From VARIOUS
To .
CSJ 6270-93-001
Proj ID SUP - 627093001
Work Type PICNIC AREA MAINTENANCE
 
0.001 190203.48 12222.83 107478.07 56.5
Work Order 03-14-14
Work Began 04-01-14
Work Completed  
Time Computed 04-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 481
Percent Time Used 65
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6270-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03141315
Totals 190203.48 12222.83 107478.07 56.5

CountyVICTORIA
Highway US0059
From VICTORIA, JACKSON, AND
To CALHOUN COUNTIES
CSJ 6270-94-001
Proj ID SUP - 627094001
Work Type PICNIC AREA AND CARPOOL MAINTENANCE
 
0.001 59883.46 0.00 25253.03 42.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 08-01-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 359
Percent Time Used 49
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6270-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07141316
Totals 59883.46 0.00 25253.03 42.1

CountyDEWITT
Highway BU0077Q
From 403 HUCK STREET YOAKUM
To 403 HUCK STREET YOAKUM
CSJ 6270-98-001
Proj ID SUP - 627098001
Work Type JANITORIAL SERVICES FOR YOAKUM COMPLEX
 
0.001 87840.00 0.00 27308.00 31.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 07-01-14
Work Completed  
Time Computed 07-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 360
Percent Time Used 49
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6270-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141317
Totals 87840.00 0.00 27308.00 31.0

CountyMATAGORDA
Highway FM0457
From MATAGORDA
To .
CSJ 6274-43-001
Proj ID EMC - 627443001
Work Type EMERGENCY SWINGBRIDGE REPAIR
 
0.001 361860.00 0.00 390062.08 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 06-13-14
Work Completed  
Time Computed 06-04-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 55
Percent Time Used 91
Contractor(s)
J & S CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06141301
Totals 361860.00 0.00 390062.08 99.9

CountyDEWITT
Highway SH0111
From DEWITT, GONZALES, LAVACA, AND
To FAYETTE COUNTIES
CSJ 6274-85-001
Proj ID RMC - 627485001
Work Type ON - CALL FLAGGING OPERATIONS
 
0.001 154200.00 0.00 144254.40 93.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 10-01-14
Work Completed  
Time Computed 10-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 268
Percent Time Used 73
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6274-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08141303
Totals 154200.00 0.00 144254.40 93.5

CountyWHARTON
Highway SH0071
From WHARTON, MATAGORDA, AUSTIN, AND
To COLORADO COUNTIES
CSJ 6274-86-001
Proj ID RMC - 627486001
Work Type ON - CALL FLAGGING OPERATIONS
 
0.001 195600.00 0.00 157935.00 80.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 10-01-14
Work Completed  
Time Computed 10-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 253
Percent Time Used 69
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6274-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08141304
Totals 195600.00 0.00 157935.00 80.7

CountyVICTORIA
Highway US0077
From VICTORIA, JACKSON, AND
To CALHOUN COUNTIES
CSJ 6274-87-001
Proj ID RMC - 627487001
Work Type ON - CALL FLAGGING OPERATIONS
 
0.001 115812.00 0.00 47779.50 41.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 10-01-14
Work Completed  
Time Computed 10-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 211
Percent Time Used 57
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6274-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08141305
Totals 115812.00 0.00 47779.50 41.2

CountyCOLORADO
Highway US0090
From COLORADO, FAYETTE, WHARTON, AUSTIN,
To AND MATAGORDA COUNTIES
CSJ 6275-35-001
Proj ID RMC - 627535001
Work Type CRACK SEALING
 
0.001 161587.34 0.00 167507.28 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 03-31-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 35
Contractor(s)
FYL ENTERPRISES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6275-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01151301
Totals 161587.34 0.00 167507.28 99.9

CountyCALHOUN
Highway US0087
From CALHOUN COUNTY
To .
CSJ 6277-11-001
Proj ID RMC - 627711001
Work Type MOWING
 
0.001 182833.20 0.00 43629.30 23.8
Work Order 00-00-00
Work Began 06-08-15
Work Completed  
Time Computed 06-15-15
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 5
Percent Time Used 11
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6277-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01151304
Totals 182833.20 0.00 43629.30 23.8

CountyCOLORADO
Highway SH0071
From COLORADO COUNTY
To .
CSJ 6277-12-001
Proj ID RMC - 627712001
Work Type MOWING
 
0.001 271185.60 67796.40 67796.40 25.0
Work Order 00-00-00
Work Began 06-17-15
Work Completed  
Time Computed 06-17-15
Contract Working Days 65
Addl Days Granted 0
Working Days Charged 16
Percent Time Used 24
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6277-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01151305
Totals 271185.60 67796.40 67796.40 25.0

CountyDEWITT
Highway US0087
From DEWITT COUNTY
To .
CSJ 6277-13-001
Proj ID RMC - 627713001
Work Type MOWING
 
0.001 342104.00 85526.00 85526.00 25.0
Work Order 00-00-00
Work Began 07-01-15
Work Completed  
Time Computed 07-08-15
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 17
Percent Time Used 20
Contractor(s)
COASTAL MAINTENANCE
SUBCONTRACTOR(S) FOR CCSJ: 6277-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01151306
Totals 342104.00 85526.00 85526.00 25.0

CountyGONZALES
Highway IH0010
From GONZALES, FAYETTE, COLORADO, AND
To AUSTIN COUNTIES
CSJ 6277-14-001
Proj ID RMC - 627714001
Work Type MOWING
 
0.001 325203.20 69314.91 81300.80 25.0
Work Order 00-00-00
Work Began 06-15-15
Work Completed  
Time Computed 06-22-15
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 17
Percent Time Used 21
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6277-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01151307
Totals 325203.20 69314.91 81300.80 25.0

CountyJACKSON
Highway US0059
From JACKSON COUNTY
To .
CSJ 6277-15-001
Proj ID RMC - 627715001
Work Type MOWING
 
0.001 342224.00 85556.00 85556.00 25.0
Work Order 00-00-00
Work Began 06-29-15
Work Completed  
Time Computed 07-06-15
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 17
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6277-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01151308
Totals 342224.00 85556.00 85556.00 25.0

CountyLAVACA
Highway US0077
From LAVACA COUNTY
To .
CSJ 6277-16-001
Proj ID RMC - 627716001
Work Type MOWING
 
0.001 343702.80 85925.70 85925.70 25.0
Work Order 00-00-00
Work Began 06-04-15
Work Completed  
Time Computed 06-12-15
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 8
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6277-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01151309
Totals 343702.80 85925.70 85925.70 25.0

CountyWHARTON
Highway US0059
From WHARTON COUNTY
To .
CSJ 6278-96-001
Proj ID RMC - 627896001
Work Type INSTALLATION OF SMALL SIGNS
 
0.001 227747.05 3695.75 165241.95 72.5
Work Order 00-00-00
Work Began 03-25-15
Work Completed  
Time Computed 04-01-15
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 37
Percent Time Used 82
Contractor(s)
LONESTAR TRAFFIC SAFETY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6278-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10141301
Totals 227747.05 3695.75 165241.95 72.5

CountyWHARTON
Highway UA0090
From WHARTON, GONZALES, JACKSON, DEWITT,
To AND MATAGORDA_COUNTIES
CSJ 6279-42-001
Proj ID RMC - 627942001
Work Type INTERSECTION AND DRAINAGE IMPROVEMENTS
 
0.001 333531.80 60732.24 210120.58 62.9
Work Order 00-00-00
Work Began 04-28-15
Work Completed  
Time Computed 05-05-15
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 41
Percent Time Used 91
Contractor(s)
ACE ASPHALT OF ARIZONA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6279-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11141301
Totals 333531.80 60732.24 210120.58 62.9

CountyWHARTON
Highway US0059
From DISTRICTWIDE
To .
CSJ 6280-47-001
Proj ID RMC - 628047001
Work Type RAISED PAVEMENT MARKERS
 
0.001 133948.82 0.00 144280.26 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 05-04-15
Work Completed  
Time Computed 05-04-15
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 19
Percent Time Used 42
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6280-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12141301
Totals 133948.82 0.00 144280.26 99.9

page 1 | page 2 | page 3 | page 4