Monthly Local Let Maintenance Report For Yoakum District As Of Mar 13, 2017 Page 2 Of 2

Last Update: Monday, March 13, 2017
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyFAYETTE
HighwayUS0077
FromFAYETTE COUNTY PICNIC AREAS
To.
CSJ6300-61-001
Proj IDSUP - 630061001
Work TypePICNIC AREA MAINTENANCE FAYETTE COUNTY
 
0.001190203.4875137.9939.5
Work Order00-00-00
Work Began04-01-16
Work Completed
Time Computed04-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged331
Percent Time Used45
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6300-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03161302
Totals190203.484855.3775137.9939.5

CountyCOLORADO
HighwayIH0010
FromDISTRICT WIDE
To.
CSJ6301-61-001
Proj IDRMC - 630161001
Work TypeSPECIALTY MARKINGS
 
0.00171774.850.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6301-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171307
Totals71774.850.000.000.0

CountyWHARTON
HighwayUS0059
FromDISTRICT WIDE
To.
CSJ6301-62-001
Proj IDRMC - 630162001
Work TypeRAISED PAVEMENT MARKINGS
 
0.00175836.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171308
Totals75836.000.000.000.0

CountyCOLORADO
HighwayIH0010
FromGONZALES, COLORADO, FAYETTE, AND
ToAUSTIN COUNTIES
CSJ6302-41-001
Proj IDSUP - 630241001
Work TypeRUBBER LITTER REMOVAL ON IH 10 & SH 71
 
0.001710882.48256361.9336.0
Work Order00-00-00
Work Began06-01-16
Work Completed
Time Computed06-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged270
Percent Time Used36
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6302-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05161301
Totals710882.4819894.84256361.9336.0

CountyVICTORIA
HighwayUS0059
FromVICTORIA AREA OFFICE
To.
CSJ6304-90-001
Proj IDRMC - 630490001
Work TypeJANITORIAL SERVICES VICTORIA AREA OFFICE
 
0.00112999.967312.4856.2
Work Order00-00-00
Work Began08-12-16
Work Completed
Time Computed08-12-16
Contract Working Days365
Addl Days Granted0
Working Days Charged198
Percent Time Used54
Contractor(s)
FLORES CONTRACTS
SUBCONTRACTOR(S) FOR CCSJ: 6304-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161301
Totals12999.961083.337312.4856.2

CountyDEWITT
HighwayBU0077Q
FromYOAKUM DISTRICT OFFICE COMPLEX
To.
CSJ6304-91-001
Proj IDRMC - 630491001
Work TypeJANITORIAL SERVICES YOAKUM DO COMPLEX
 
0.00130000.0016000.0053.3
Work Order00-00-00
Work Began08-12-16
Work Completed
Time Computed08-12-16
Contract Working Days365
Addl Days Granted0
Working Days Charged197
Percent Time Used53
Contractor(s)
FLORES CONTRACTS
SUBCONTRACTOR(S) FOR CCSJ: 6304-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161302
Totals30000.002000.0016000.0053.3

CountyVICTORIA
HighwayUS0059
FromVICTORIA, JACKSON, AND
ToCALHOUN COUNTIES
CSJ6305-84-001
Proj IDSUP - 630584001
Work TypePICNIC AREA AND CAR POOL MAINTENANCE
 
0.00159883.4614764.4624.6
Work Order00-00-00
Work Began08-01-16
Work Completed
Time Computed08-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged209
Percent Time Used28
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6305-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161303
Totals59883.462224.7614764.4624.6

CountyDEWITT
HighwayUS0183
FromDEWITT AND
ToLAVACA COUNTIES
CSJ6305-85-001
Proj IDSUP - 630585001
Work TypePICNIC AREA AND LANDSCAPE MAINTENANCE
 
0.00166494.8818114.7927.2
Work Order00-00-00
Work Began08-01-16
Work Completed
Time Computed08-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged213
Percent Time Used29
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6305-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161304
Totals66494.882463.0018114.7927.2

CountyVICTORIA
HighwayUS0059
FromVICTORIA, JACKSON, AND
ToWHARTON COUNTIES
CSJ6307-72-001
Proj IDSUP - 630772001
Work TypeRUBBER LITTER PICKUP & DISPOSAL US 59
 
0.001424875.32105319.6124.7
Work Order00-00-00
Work Began08-01-16
Work Completed
Time Computed07-26-16
Contract Working Days730
Addl Days Granted0
Working Days Charged209
Percent Time Used28
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6307-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161305
Totals424875.3210553.33105319.6124.7

CountyMATAGORDA
HighwaySH0035
FromAUSTIN, DEWITT, JACKSON, MATAGORDA, AND
ToVICTORIA COUNTIES
CSJ6310-63-001
Proj IDRMC - 631063001
Work TypeCRACK SEALING
 
0.001180704.0032916.9018.2
Work Order00-00-00
Work Began02-23-17
Work Completed
Time Computed03-02-17
Contract Working Days35
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6310-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161301
Totals180704.0032916.9032916.9018.2

CountyCALHOUN
HighwayUS0087
FromCALHOUN COUNTY
To.
CSJ6312-17-001
Proj IDRMC - 631217001
Work TypeFULL-WIDTH MOWING
 
0.001145926.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HAMMOND LAND DEVELOPMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6312-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171301
Totals145926.000.000.000.0

CountyCOLORADO
HighwaySH0071
FromCOLORADO COUNTY
To.
CSJ6312-18-001
Proj IDRMC - 631218001
Work TypeFULL-WIDTH MOWING
 
0.001214273.520.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days65
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6312-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171302
Totals214273.520.000.000.0

CountyDEWITT
HighwayUS0087
FromDEWITT COUNTY
To.
CSJ6312-19-001
Proj IDRMC - 631219001
Work TypeFULL-WIDTH MOWING
 
0.001287000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days85
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AZTECA DESIGNS, INC
SUBCONTRACTOR(S) FOR CCSJ: 6312-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171303
Totals287000.000.000.000.0

CountyGONZALES
HighwayIH0010
FromFAYETTE, GONZALES, COLORADO, AND
ToAUSTIN COUNTIES
CSJ6312-20-001
Proj IDRMC - 631220001
Work TypeFULL-WIDTH MOWING
 
0.001263731.200.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6312-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171304
Totals263731.200.000.000.0

CountyJACKSON
HighwayUS0059
FromJACKSON COUNTY
To.
CSJ6312-21-001
Proj IDRMC - 631221001
Work TypeFULL-WIDTH MOWING
 
0.001284092.800.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days85
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6312-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171305
Totals284092.800.000.000.0

CountyLAVACA
HighwayUS0077
FromLAVACA COUNTY
To.
CSJ6312-22-001
Proj IDRMC - 631222001
Work TypeFULL-WIDTH MOWING
 
0.001269282.160.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days85
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6312-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171306
Totals269282.160.000.000.0