Monthly State Let Construction Report For Yoakum District As Of Mar 13, 2017 Page 4 Of 5

Last Update: Monday, March 13, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCOLORADO
HighwayFM 109
FromAT REDGATE CREEK
ToSTR # 0716-02-011
CSJ0716-02-038
Proj IDBR 1602(086)
Work TypeWIDEN BRIDGE AND APPROACHES
 
0.185533118.53393986.7473.9
Work Order06-22-16
Work Began09-16-16
Work Completed
Time Computed07-22-16
Contract Working Days50
Addl Days Granted0
Working Days Charged42
Percent Time Used84
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0716-02-038
ROADSAFE TRAFFIC SYSTEMS, INC. (0.60)
ROADWAY SPECIALTIES, INC. (5.03)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.50)
Contract #05163010
Totals533118.53125977.75393986.7473.9

CountyGONZALES
HighwayFM 443
FromAT ROCKY CREEK
ToSTR # 0839-01-002
CSJ0839-01-015
Proj IDBR 2017(259)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.3211222090.600.000.0
Work Order12-28-16
Work Began00-00-00
Work Completed
Time Computed01-28-17
Contract Working Days75
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HILL COUNTRY BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0839-01-015
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11163209
Totals1222090.600.000.000.0

CountyVICTORIA
HighwayFM 444
FromUS 77
ToUS 59
CSJ0840-05-021
Proj IDSTP 2016(966)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
17.650810634.54743867.5091.7
Work Order06-02-16
Work Began07-18-16
Work Completed
Time Computed08-31-16
Contract Working Days120
Addl Days Granted0
Working Days Charged87
Percent Time Used72
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0840-05-021
FLASHER EQUIPMENT COMPANY (1.21)
STAFF CONCRETE (63.41)
ROADWAY SPECIALTIES, INC. (14.47)
Contract #04163004
Totals810634.54206068.66743867.5091.7

CountyDEWITT
HighwayVA
FromVARIOUS LOCATIONS
ToIN AUSTIN, MATAGORDA, & WHARTON CO.
CSJ0913-00-088
Proj IDSTP 2012(527)
Work TypeCONSTRUCT CURB RAMPS
 
0.100475081.00577322.1799.9
Work Order06-18-12
Work Began04-05-13
Work Completed
Time Computed10-16-12
Contract Working Days165
Addl Days Granted0
Working Days Charged142
Percent Time Used86
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-00-088
PAVEMENT MARKINGS INC. (1.39)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (3.79)
SPEEDY PAVING (2.40)
Contract #05123217
Totals475081.000.00577322.1799.9

CountyDEWITT
HighwayVA
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ0913-00-092
Proj IDBR 2016(133)
Work TypeUPGRADE BRIDGE AND APPROACH RAILING
 
0.0023378506.552740808.2981.3
CountyDEWITT
HighwayVA
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ0913-00-094
Proj IDNH 2016(134)
Work TypeCONCRETE RAIL REPAIR
 
0.00190833.20120218.9699.9
Work Order11-24-15
Work Began01-18-16
Work Completed
Time Computed12-24-15
Contract Working Days203
Addl Days Granted0
Working Days Charged210
Percent Time Used103
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-00-092
WEST TEXAS RUMBLE STRIP (0.13)
D & S TEXAS ICON CONSTRUCTION, LLC. (4.10)
TINMAN ENTERPRISES (5.32)
ROADSAFE TRAFFIC SYSTEMS, INC. (6.74)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (19.38)
Contract #10153213
Totals3469339.75133122.722861027.2582.6

CountyWHARTON
HighwayCR
FromAT WEST MUSTANG CREEK CR 372
To(CR 372) STR # AA06-59-001
CSJ0913-09-053
Proj IDBR 2012(407)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.074629675.00597441.4098.0
Work Order07-07-15
Work Began11-11-15
Work Completed
Time Computed10-06-15
Contract Working Days75
Addl Days Granted0
Working Days Charged108
Percent Time Used144
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-053
HEMPHILL PILE DRIVING CO., A CORP. (4.74)
ODUM SERVICES, L.P. (3.89)
JUST GROOVING, LTD. (0.25)
CEN TEX HYDROSEED, INC. (0.33)
Contract #05153048
Totals629675.000.00597441.4098.0

CountyWHARTON
HighwayCR
FromAT SANDY BRANCH # 2 CR 324
To(CR 207) STR # AA03-24-001
CSJ0913-09-058
Proj IDBR 2012(411)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.068524660.50505875.5096.4
Work Order08-10-15
Work Began08-19-15
Work Completed
Time Computed08-19-15
Contract Working Days67
Addl Days Granted0
Working Days Charged62
Percent Time Used92
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-058
LONESTAR TRAFFIC SAFETY, LLC (0.42)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.43)
MESA ROD BUSTERS, INC. (0.28)
JMHP, INC. (2.77)
HOUSTON SAWING & DRILLING (0.33)
Contract #06153257
Totals524660.500.00505875.5096.4

CountyWHARTON
HighwayCR
FromAT DRAW CR 469
To(CR 315) STR # AA04-69-002
CSJ0913-09-060
Proj IDBR 1502(637)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.132902792.100.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-22-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days100
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-060
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173252
Totals902792.100.000.000.0

CountyWHARTON
HighwayCR
FromAT TRES PALACIOS RIVER CR 413
To(CR 405) STR # AA04-13-001
CSJ0913-09-064
Proj IDBR 2013(439)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.062528449.32534193.9799.9
Work Order12-04-15
Work Began01-14-16
Work Completed
Time Computed01-04-16
Contract Working Days75
Addl Days Granted0
Working Days Charged58
Percent Time Used77
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-064
LONESTAR TRAFFIC SAFETY, LLC (0.37)
FUQUAY, INC. (0.63)
W. W. FOUNDATION DRILLING, LTD. (10.89)
MESA ROD BUSTERS, INC. (0.00)
Contract #08153252
Totals528449.320.00534193.9799.9

CountyWHARTON
HighwayCR
FromAT MUD CREEK CR 419
To(CR 407) STR # AA04-19-001
CSJ0913-09-067
Proj IDBR 2014(677)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.064289824.00146786.4050.6
Work Order09-14-16
Work Began12-05-16
Work Completed
Time Computed10-14-16
Contract Working Days60
Addl Days Granted0
Working Days Charged41
Percent Time Used68
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-067
CEN TEX HYDROSEED, INC. (0.67)
HEMPHILL WBE PILE DRIVING CO. (7.59)
Contract #07163242
Totals289824.0029244.68146786.4050.6

CountyWHARTON
HighwayCR
FromAT JONES CREEK CR 648
To(CR 457) STR # AA06-48-001
CSJ0913-09-071
Proj IDBR 2014(681)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.068441100.21430081.1799.2
Work Order05-10-16
Work Began07-18-16
Work Completed
Time Computed08-08-16
Contract Working Days75
Addl Days Granted0
Working Days Charged88
Percent Time Used117
Contractor(s)
REXCO CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-071
JUST GROOVING, LTD. (0.22)
ODUM SERVICES, L.P. (2.53)
SPECIALTY DRILLING, LTD. (10.09)
CEN TEX HYDROSEED, INC. (1.78)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.13)
Contract #02163031
Totals441100.212330.94430081.1799.2

CountyWHARTON
HighwayCR
FromAT PEACH CREEK (132410AA0294001)
ToWCR 253 (AA0253)
CSJ0913-09-076
Proj IDBR 1502(198)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.130670423.18655167.8197.7
Work Order07-13-16
Work Began09-02-16
Work Completed
Time Computed10-11-16
Contract Working Days120
Addl Days Granted0
Working Days Charged85
Percent Time Used70
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-076
HEMPHILL WBE PILE DRIVING CO. (5.60)
LONESTAR TRAFFIC SAFETY, LLC (0.85)
BRANNAN PAVING CO., LTD. (4.91)
Contract #05163204
Totals670423.187097.52655167.8197.7

CountyWHARTON
HighwayCS
FromVARIOUS LOC. ALONG AVE I& NORRIS ST
ToIN THE CITY OF EL CAMPO
CSJ0913-09-081
Proj IDSTP 1602(475)TAPS
Work TypeCONSTRUCT SIDEWALKS
 
1.202311986.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-09-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-081
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173226
Totals311986.000.000.000.0

CountyDEWITT
HighwayCR
FromAT CABEZA CREEK CR 271
To(BACHLE RD) STR AA02-71-003
CSJ0913-17-040
Proj IDBR 1502(215)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.069449866.900.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-13-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TMES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-17-040
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173015
Totals449866.900.000.000.0

CountyDEWITT
HighwayCR
FromAT DRAW CHARCO RD
ToSTR # AA01-16-001
CSJ0913-17-041
Proj IDBR 1502(365)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.067323694.00275060.0088.2
Work Order08-25-16
Work Began10-31-16
Work Completed
Time Computed10-23-16
Contract Working Days45
Addl Days Granted0
Working Days Charged63
Percent Time Used140
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-17-041
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07163213
Totals323694.006660.00275060.0088.2

CountyJACKSON
HighwayCR
FromAT ARENOSA CREEK_ CR 325
ToSTR AA01-60-001
CSJ0913-18-028
Proj IDBR 2016(433)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.084925264.60439263.8147.4
Work Order08-01-16
Work Began11-29-16
Work Completed
Time Computed10-27-16
Contract Working Days75
Addl Days Granted0
Working Days Charged34
Percent Time Used45
Contractor(s)
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0913-18-028
ENVIRONMENTAL SAFETY SERVICES, INC. (4.75)
LONE STAR TRAFFIC SERVICE, INC. (0.24)
SHINN & GREGORY, INC. (8.34)
JIMMY EVANS COMPANY, LTD (16.83)
Contract #06163020
Totals925264.6049425.58439263.8147.4

CountyCALHOUN
HighwayCR
FromAT DRAW CR 206
To(GIN ROAD) STR # AA02-06-001
CSJ0913-19-028
Proj IDBR 2012(730)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100416186.670.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-22-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
REXCO CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-19-028
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173020
Totals416186.670.000.000.0

CountyAUSTIN
HighwayCR
FromAT POST OAK POINT CREEK CR 5198
To(NEW BREMAN RD) STR # AA01-92-006
CSJ0913-20-073
Proj IDBR 2008(610)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.072538926.26390955.6672.5
Work Order09-15-16
Work Began11-07-16
Work Completed
Time Computed10-15-16
Contract Working Days75
Addl Days Granted0
Working Days Charged37
Percent Time Used49
Contractor(s)
SB CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-20-073
ODUM SERVICES, L.P. (4.51)
FUQUAY, INC. (1.54)
SHINN & GREGORY, INC. (11.69)
Contract #08163222
Totals538926.2692171.39390955.6672.5

CountyAUSTIN
HighwayCR
FromAT DRAW
To(NELIUS RD) STR # AA03-26-001
CSJ0913-20-084
Proj IDBR 1102(474)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.071525692.63460588.8388.8
Work Order01-02-15
Work Began02-23-15
Work Completed
Time Computed02-23-15
Contract Working Days60
Addl Days Granted0
Working Days Charged71
Percent Time Used118
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-20-084
ENVIRONMENTAL SAFETY SERVICES, INC. (3.76)
DALLAS LITE AND BARRICADE INC. (0.32)
Contract #11143206
Totals525692.630.00460588.8388.8

CountyAUSTIN
HighwayCR
FromAT CANEY CREEK CR 310
To(KRAMER RD) STR AA03-10-005
CSJ0913-20-087
Proj IDBR 1502(358)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.059314926.26234421.1874.4
Work Order09-16-16
Work Began11-14-16
Work Completed
Time Computed10-16-16
Contract Working Days60
Addl Days Granted0
Working Days Charged16
Percent Time Used26
Contractor(s)
SB CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-20-087
DIIBS SPECIALISTS (5.31)
SHINN & GREGORY, INC. (8.12)
Contract #08163021
Totals314926.26111622.40234421.1874.4

page 1 | page 2 | page 3 | page 4 | page 5