Monthly State Let Construction Report For Yoakum District As Of Mar 10, 2015 Page 4 Of 5

Last Update: Wednesday, March 11, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyAUSTIN
Highway CR
From AT DRAW
To (NELIUS RD) STR # AA03-26-001
CSJ 0913-20-084
Proj ID BR 1102(474)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.071 525692.63 430.00 430.00 0.0
Work Order 01-02-15
Work Began 02-23-15
Work Completed  
Time Computed 02-23-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 1
Percent Time Used 1
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-20-084
ENVIRONMENTAL SAFETY SERVICES, INC.(3.76%)
DALLAS LITE AND BARRICADE INC. (0.32%)
Contract # 11143206
Totals 525692.63 430.00 430.00 0.0

CountyMATAGORDA
Highway CR
From AT CANEY CREEK CR 194
To (HAWKINS RD) STR # AA01-94-001
CSJ 0913-21-042
Proj ID BR 2014(299)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.171 1323586.20 164719.53 764418.70 57.7
Work Order 04-15-14
Work Began 10-21-14
Work Completed  
Time Computed 06-14-14
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 53
Percent Time Used 50
Contractor(s)
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0913-21-042
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.(2.74%)
FUQUAY, INC. (0.46%)
JMHP, INC. (1.62%)
JUST GROOVING, LTD.(0.19%)
LONESTAR TRAFFIC SAFETY, LLC (0.17%)
WEBBER-BALKE FOUNDATION COMPANY, INC.( 11.59%)
Contract # 02143019
Totals 1323586.20 164719.53 764418.70 57.7

CountyGONZALES
Highway CR
From CR 363 AT GELHORN CREEK
To STR # AA03-63-001
CSJ 0913-22-035
Proj ID BR 2011(495)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.055 236824.41 26357.60 254174.12 99.9
Work Order 05-09-14
Work Began 09-15-14
Work Completed  
Time Computed 07-08-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 54
Percent Time Used 90
Contractor(s)
HILL COUNTRY BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-22-035
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.( 16.44%)
DUSTIN ALLEN, INC. (5.68%)
FUQUAY, INC. (2.11%)
JUST GROOVING, LTD.(0.35%)
O & S TRAFFIC SUPPLIES (0.86%)
SHINN & GREGORY, INC.(7.83%)
Contract # 04143229
Totals 236824.41 26357.60 254174.12 99.9

CountyGONZALES
Highway CR
From AT BRUSHY CREEK CR 118
To (CR 118) STR # AA01-18-001
CSJ 0913-22-036
Proj ID BR 2011(596)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.066 247853.06 12823.11 246331.05 100.0
Work Order 06-02-14
Work Began 06-18-14
Work Completed 02-02-15
Time Computed 06-18-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 58
Percent Time Used 96
Contractor(s)
TMES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-22-036
SHINN & GREGORY, INC.(6.81%)
FUQUAY, INC. (4.06%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.34%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
Contract # 04143026
Totals 247853.06 12823.11 246331.05 100.0

CountyGONZALES
Highway CR
From AT ROCKY CREEK CR 377
To (CR 360A) STR # AA05-45-001
CSJ 0913-22-043
Proj ID BR 2015(539)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.056 276692.75 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-18-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-22-043
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153206
Totals 276692.75 0.00 0.00 0.0

CountyGONZALES
Highway CR
From AT FULCHUR CREEK
To CR 296 STR # AA02-96-001
CSJ 0913-22-044
Proj ID BR 2013(440)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.066 323837.00 45600.26 78449.46 24.2
Work Order 10-17-14
Work Began 00-00-00
Work Completed  
Time Computed 02-14-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-22-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143215
Totals 323837.00 45600.26 78449.46 24.2

CountyCOLORADO
Highway CR
From AT DRAW CR 153
To DIETRICH LANE STR # AA-01-53-003
CSJ 0913-26-059
Proj ID BR 2012(732)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.062 249900.02 125620.00 125620.00 50.2
Work Order 12-16-14
Work Began 02-11-15
Work Completed  
Time Computed 02-11-15
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 3
Percent Time Used 6
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-26-059
LONESTAR TRAFFIC SAFETY, LLC (0.57%)
KOSSMAN CONTRACTING CO., INC.(0.58%)
SYLVA CONSTRUCTION CO.(PORT LAVACA,TX) ( 22.96%)
Contract # 10143004
Totals 249900.02 125620.00 125620.00 50.2

CountyVICTORIA
Highway CR
From AT DRY CREEK CR 114
To (WEBER ROAD) STR # AA01-14-001
CSJ 0913-27-054
Proj ID BR 2011(496)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.097 338315.31 0.00 309638.06 91.5
Work Order 06-20-14
Work Began 08-21-14
Work Completed  
Time Computed 08-19-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 52
Percent Time Used 86
Contractor(s)
REXCO CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-27-054
RICE ENVIRONMENTAL SERVICES(5.16%)
SPECIALTY DRILLING, LTD. ( 14.84%)
LONE STAR TRAFFIC SERVICE, INC.(0.63%)
HOLES INCORPORATED (0.73%)
MESA ROD BUSTERS, INC. (0.48%)
JUST GROOVING, LTD.(0.30%)
BRANNAN PAVING CO., LTD. (0.23%)
Contract # 05143034
Totals 338315.31 0.00 309638.06 91.5

CountyFAYETTE
Highway CR
From AT DRAW CR 282
To (DUBINA-WEIMAR RD) AA02-84-001
CSJ 0913-28-056
Proj ID BR 2008(549)
Work Type REPLACE BRIDGE
 
0.077 414242.66 0.00 33558.15 8.1
Work Order 08-27-14
Work Began 00-00-00
Work Completed  
Time Computed 09-12-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HILL COUNTRY BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-28-056
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143020
Totals 414242.66 0.00 33558.15 8.1

CountyFAYETTE
Highway CR
From AT OWL CREEK CR 190
To (OWL CREEK RD) STR # AA03-79-002
CSJ 0913-28-057
Proj ID BR 2008(550)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.071 404024.62 68235.22 358797.72 88.8
Work Order 08-27-14
Work Began 10-28-14
Work Completed  
Time Computed 10-26-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 53
Percent Time Used 88
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0913-28-057
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.21%)
ODUM SERVICES, L.P.(3.16%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.81%)
CEN TEX HYDROSEED, INC.(1.19%)
MESA ROD BUSTERS, INC. (1.10%)
Contract # 07143220
Totals 404024.62 68235.22 358797.72 88.8

CountyLAVACA
Highway CR
From AT LAVACA RIVER CR 12
To (CR 12) STR # AA03-47-001
CSJ 0913-29-044
Proj ID BR 2014(595)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.094 588575.12 247428.64 492497.16 83.6
Work Order 06-20-14
Work Began 11-11-14
Work Completed  
Time Computed 08-19-14
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 62
Percent Time Used 68
Contractor(s)
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0913-29-044
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.( 10.01%)
ENVIRONMENTAL SAFETY SERVICES, INC.(6.53%)
HEMPHILL PILE DRIVING CO., A CORP. (8.93%)
JUST GROOVING, LTD.(0.21%)
LONESTAR TRAFFIC SAFETY, LLC (0.35%)
C-3 ENVIRONMENTAL SPECIALTIES, LP(3.59%)
Contract # 04143013
Totals 588575.12 247428.64 492497.16 83.6

CountyLAVACA
Highway CR
From AT SUPPLEJACK CREEK CR 402
To (CR 402) STR # AA03-78-001
CSJ 0913-29-045
Proj ID BR 2012(429)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.075 420926.25 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-07-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. CARROLL WEAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-29-045
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11143217
Totals 420926.25 0.00 0.00 0.0

CountyLAVACA
Highway CR
From AT NAVIDAD RIVER CR 124
To (CR 214) STR # AA04-95-001
CSJ 0913-29-046
Proj ID BR 2012(430)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.116 639216.42 86827.81 424735.94 66.4
Work Order 07-22-14
Work Began 11-11-14
Work Completed  
Time Computed 11-11-14
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 52
Percent Time Used 49
Contractor(s)
J. CARROLL WEAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-29-046
ENVIRONMENTAL SAFETY SERVICES, INC.(3.18%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.88%)
JUST GROOVING, LTD.(0.26%)
WEBBER-BALKE FOUNDATION COMPANY, INC.( 10.30%)
Contract # 05143024
Totals 639216.42 86827.81 424735.94 66.4

CountyGONZALES
Highway FM 532
From US 90A
To LAVACA COUNTY LINE
CSJ 1007-02-017
Proj ID STP 2013(919)
Work Type ROADWAY WIDENING
 
13.775 8097588.87 107825.34 3316259.99 40.9
Work Order 10-10-13
Work Began 12-03-13
Work Completed  
Time Computed 12-03-13
Contract Working Days 285
Addl Days Granted 0
Working Days Charged 233
Percent Time Used 81
Contractor(s)
SMC CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1007-02-017
FOX QUALITY CONCRETE, L.L.C. (3.01%)
M.V. HENKE ENTERPRISES, INC. (0.46%)
F. N. PLOCH CONSTRUCTION COMPANY, INC. ( 12.05%)
C-3 ENVIRONMENTAL SPECIALTIES, LP(1.07%)
LAND STABILIZER, LTD (7.21%)
ROADWAY SPECIALTIES, INC.(0.21%)
FLASHER EQUIPMENT COMPANY(1.71%)
ZAMCO TRUCKING, LLC(1.29%)
RELMCO, INC. (3.69%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.08%)
ARIAS & ASSOCIATES, INC. (0.12%)
Contract # 07133251
Totals 8097588.87 107825.34 3316259.99 40.9

CountyAUSTIN
Highway FM 949
From 0.4 MI. NORTH OF FM 1094
To SH 36
CSJ 1106-02-020
Proj ID STP 2013(595)HES
Work Type WIDEN ROADWAY
 
8.259 3120993.47 0.00 3310765.29 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-23-13
Work Began 07-31-13
Work Completed 11-06-14
Time Computed 08-08-13
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 169
Percent Time Used 112
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 1106-02-020
MURRAY CONSTRUCTION(1.25%)
CEN TEX HYDROSEED, INC.(2.12%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.98%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
JEFFERY BAILEY TRUCKING, INC.(0.00%)
Contract # 04133204
Totals 3120993.47 0.00 3310765.29 100.0

CountyWHARTON
Highway FM 1161
From FM 102
To SH 60
CSJ 1303-01-017
Proj ID STP 2013(486)HES
Work Type WIDEN ROADWAY
 
10.413 2257894.57 0.00 2107468.02 100.0
Work Order 05-23-13
Work Began 06-27-13
Work Completed 03-09-15
Time Computed 06-08-13
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 155
Percent Time Used 129
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 1303-01-017
FLASHER EQUIPMENT COMPANY(2.56%)
KOSSMAN CONTRACTING CO., INC.(2.33%)
MURRAY CONSTRUCTION(1.63%)
STAFF CONCRETE (5.76%)
A.J.J.A . TRUCKING, INC. (2.37%)
Contract # 03133033
Totals 2257894.57 0.00 2107468.02 100.0

CountyCALHOUN
Highway FM 1289
From AT COLOMA CREEK
To STR # 1438-01-002
CSJ 1438-01-021
Proj ID BR 2015(164)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.599 4870061.86 0.00 47000.00 0.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-05-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 130
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1438-01-021
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10143230
Totals 4870061.86 0.00 47000.00 0.9

CountyFAYETTE
Highway FM 1579
From AT EAST NAVIDAD RIVER
To STR # 1498-01-002
CSJ 1498-01-012
Proj ID BR 2015(347)
Work Type REHABILITATE BRIDGE AND APPROACHES
 
0.144 185135.00 72552.72 139020.00 75.0
Work Order 11-14-14
Work Began 01-12-15
Work Completed  
Time Computed 11-30-14
Contract Working Days 48
Addl Days Granted 0
Working Days Charged 34
Percent Time Used 70
Contractor(s)
3LW MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1498-01-012
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10143227
Totals 185135.00 72552.72 139020.00 75.0

CountyFAYETTE
Highway FM 615
From AT MIDDLE CREEK
To STR # 1692-01-001
CSJ 1692-01-007
Proj ID BR 2014(932)
Work Type BASE, STURCTURAL, SURFACING
 
0.125 742839.91 130557.69 638704.61 85.9
Work Order 09-30-14
Work Began 11-17-14
Work Completed  
Time Computed 11-17-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 53
Percent Time Used 88
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1692-01-007
WEBBER-BALKE FOUNDATION COMPANY, INC.(5.82%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (3.86%)
D. I. J. CONSTRUCTION, INC.(0.78%)
JUST GROOVING, LTD.(0.18%)
FUQUAY, INC. (0.67%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.55%)
Contract # 07143228
Totals 742839.91 130557.69 638704.61 85.9

CountyJACKSON
Highway FM 1822
From LP 521 IN EDNA
To FM 3131
CSJ 1945-01-020
Proj ID STP 2015(629)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
7.598 618946.48 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
3LW MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1945-01-020
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153011
Totals 618946.48 0.00 0.00 0.0