Monthly State Let Construction Report For Yoakum District As Of Jul 12, 2016 Page 4 Of 4

Last Update: Tuesday, July 12, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyAUSTIN
Highway CR
From AT SANDY CREEK
To (RIPPLE LANE) STR # AA65-40-001
CSJ 0913-20-085
Proj ID BR 2012(166)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.070 442957.40 20025.50 431559.50 97.4
Work Order 07-15-15
Work Began 10-20-15
Work Completed  
Time Computed 10-13-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 34
Percent Time Used 56
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0913-20-085
CEN TEX HYDROSEED, INC.(1.23%)
JUST GROOVING, LTD.(0.28%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.63%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.61%)
WILLOW CITY SIGN & RAIL, INC.(2.96%)
MCL CONTRACTING, LLC (0.35%)
Contract # 05153054
Totals 442957.40 20025.50 431559.50 97.4

CountyMATAGORDA
Highway CR
From AT WILLOW CREEK CR 425
To (LEZAK RD) STR # AA03-15-001
CSJ 0913-21-045
Proj ID BR 2013(504)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.066 333383.92 1528.86 305448.16 91.6
Work Order 11-16-15
Work Began 02-15-16
Work Completed  
Time Computed 02-14-16
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 52
Percent Time Used 86
Contractor(s)
TCB CONSTRUCTION, INC
SUBCONTRACTOR(S) FOR CCSJ: 0913-21-045
JUST GROOVING, LTD.(0.22%)
HEMPHILL PILE DRIVING CO., A CORP. (7.19%)
LONESTAR TRAFFIC SAFETY, LLC (1.07%)
RICE ENVIRONMENTAL SERVICES(8.33%)
Contract # 07153247
Totals 333383.92 1528.86 305448.16 91.6

CountyGONZALES
Highway CR
From AT ROCKY CREEK CR 377
To (CR 360A) STR # AA05-45-001
CSJ 0913-22-043
Proj ID BR 2015(539)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.056 276692.75 0.00 265330.19 96.7
Work Order 02-18-15
Work Began 06-02-15
Work Completed  
Time Computed 06-02-15
Contract Working Days 45
Addl Days Granted 10
Working Days Charged 59
Percent Time Used 107
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-22-043
FUQUAY, INC. (3.59%)
LONESTAR TRAFFIC SAFETY, LLC (0.61%)
Contract # 01153206
Totals 276692.75 0.00 265330.19 96.7

CountyVICTORIA
Highway CR
From AT ARENOSA CREEK CR 130
To (J2 RANCH RD) STR AA01-30-006
CSJ 0913-27-065
Proj ID BR 2014(684)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.066 296070.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-11-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-27-065
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03163220
Totals 296070.60 0.00 0.00 0.0

CountyLAVACA
Highway CR
From AT SUPPLEJACK CREEK CR 402
To (CR 402) STR # AA03-78-001
CSJ 0913-29-045
Proj ID BR 2012(429)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.075 420926.25 0.00 389678.34 95.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-07-15
Work Began 06-22-15
Work Completed  
Time Computed 05-07-15
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 96
Percent Time Used 128
Contractor(s)
J. CARROLL WEAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-29-045
ENVIRONMENTAL SAFETY SERVICES, INC.(6.20%)
LONESTAR TRAFFIC SAFETY, LLC (0.48%)
HOUSTON SAWING & DRILLING(0.55%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. ( 12.16%)
MESA ROD BUSTERS, INC. (0.35%)
Contract # 11143217
Totals 420926.25 0.00 389678.34 95.5

CountyGONZALES
Highway FM 532
From US 90A
To LAVACA COUNTY LINE
CSJ 1007-02-017
Proj ID STP 2013(919)
Work Type ROADWAY WIDENING
 
13.775 8097588.87 0.00 8232746.41 99.9
Work Order 10-10-13
Work Began 12-03-13
Work Completed  
Time Computed 12-03-13
Contract Working Days 285
Addl Days Granted 13
Working Days Charged 369
Percent Time Used 123
Contractor(s)
SMC CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1007-02-017
FOX QUALITY CONCRETE, L.L.C. (3.01%)
M.V. HENKE ENTERPRISES, INC. (0.46%)
F. N. PLOCH CONSTRUCTION COMPANY, INC. ( 12.05%)
C-3 ENVIRONMENTAL SPECIALTIES, LP(1.07%)
LAND STABILIZER, LTD (7.21%)
ROADWAY SPECIALTIES, INC.(0.21%)
FLASHER EQUIPMENT COMPANY(1.71%)
ZAMCO TRUCKING, LLC(1.29%)
RELMCO, INC. (3.69%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.08%)
ARIAS & ASSOCIATES, INC. (0.12%)
LONE STAR PAVING ( 24.35%)
FUTURE CONCRETE STRUCTURES (1.28%)
A BROTHERS MILLING, LLC(0.45%)
BR CARTAGE COMPANY (0.00%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.15%)
PENHALL COMPANY(0.05%)
Contract # 07133251
Totals 8097588.87 0.00 8232746.41 99.9

CountyLAVACA
Highway FM 532
From GONZALES C/L
To SH 95
CSJ 1007-03-021
Proj ID STP 2016(509)
Work Type RESTORE ROADWAY
 
4.608 2721588.22 0.00 0.00 0.0
CountyLAVACA
Highway FM 1680
From 0.5 MI N OF FM 532
To FM 532
CSJ 1442-04-010
Proj ID STP 2016(509)
Work Type RESTORE ROADWAY
 
0.460 122619.12 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-17-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1007-03-021
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163245
Totals 2844207.34 0.00 0.00 0.0

CountyLAVACA
Highway FM 958
From FM 966
To SH 95
CSJ 1008-02-018
Proj ID C 1008-2-18
Work Type SUBGRADE WIDEN, BASE, RESURFACING
 
5.012 3498600.69 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 135
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1008-02-018
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06163219
Totals 3498600.69 0.00 0.00 0.0

CountyCOLORADO
Highway FM 949
From 2.5 MI S OF IH 10
To 0.9 MI S OF IH 10
CSJ 1106-04-006
Proj ID STP 2016(432)HES
Work Type INCREASE SUPERELEVATION
 
1.642 217162.30 0.00 236271.61 99.9
Work Order 01-21-16
Work Began 03-14-16
Work Completed  
Time Computed 04-21-16
Contract Working Days 15
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 93
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1106-04-006
ROADSAFE TRAFFIC SYSTEMS, INC. (3.76%)
Contract # 12153020
Totals 217162.30 0.00 236271.61 99.9

CountyDEWITT
Highway FM 766
From END OF STATE MAINTENANCE
To 3.922 MI. NORTH OF FM 953
CSJ 1113-01-026
Proj ID C 1113-1-26
Work Type RESTORE ROADWAY
 
8.139 4871848.95 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 165
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1113-01-026
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07163014
Totals 4871848.95 0.00 0.00 0.0

CountyWHARTON
Highway FM 1160
From FM 1300
To US 59
CSJ 1302-01-022
Proj ID STP 1502(203)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
7.919 636444.30 0.00 608471.33 95.6
Work Order 08-10-15
Work Began 09-16-15
Work Completed  
Time Computed 09-14-15
Contract Working Days 90
Addl Days Granted 5
Working Days Charged 94
Percent Time Used 98
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1302-01-022
WILLOW CITY SIGN & RAIL, INC.( 10.52%)
N-LINE TRAFFIC MAINTENANCE, L.P. (2.60%)
Contract # 06153264
Totals 636444.30 0.00 608471.33 95.6

CountyCALHOUN
Highway FM 1289
From AT COLOMA CREEK
To STR # 1438-01-002
CSJ 1438-01-021
Proj ID BR 2015(164)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.599 4870061.86 77390.00 4280912.38 87.9
Work Order 02-05-15
Work Began 07-23-15
Work Completed  
Time Computed 06-05-15
Contract Working Days 130
Addl Days Granted 24
Working Days Charged 126
Percent Time Used 81
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1438-01-021
REBAR MASTER"S LLC (0.41%)
JMHP, INC. (0.55%)
WEBER-BALKE FOUNDATION COMPANY, INC(7.34%)
DS TEXAS ICON CONSTRUCTION (0.67%)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.( 34.82%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.47%)
Contract # 10143230
Totals 4870061.86 77390.00 4280912.38 87.9

CountyFAYETTE
Highway FM 1457
From AT ROCKY CREEK
To STR # 1441-01-001
CSJ 1441-01-012
Proj ID BR 2016(062)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.204 1089950.26 60513.57 519848.07 47.6
Work Order 11-16-15
Work Began 01-14-16
Work Completed  
Time Computed 12-16-15
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 35
Percent Time Used 29
Contractor(s)
SB CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 1441-01-012
JJ KOONS, LLC. ( 17.29%)
RICE ENVIRONMENTAL SERVICES(5.36%)
N-LINE TRAFFIC MAINTENANCE, L.P. (9.62%)
BEAIRD DRILLING(2.11%)
LONE STAR PAVING ( 10.85%)
Contract # 09153210
Totals 1089950.26 60513.57 519848.07 47.6

CountyAUSTIN
Highway FM 1094
From 7.2 MI WEST OF SH 36(SCHLUENS RD)
To 0.4 MI WEST OF SH 36(HOWARD ST)
CSJ 1721-02-012
Proj ID STP 1502(478)HES
Work Type SAFETY TREAT FIXED OBJECTS, WIDEN SH
 
6.749 3954433.25 456399.21 487120.21 12.3
Work Order 01-29-16
Work Began 03-23-16
Work Completed  
Time Computed 05-29-16
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 43
Percent Time Used 28
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1721-02-012
CEN TEX HYDROSEED, INC.(2.77%)
J & M CONTRACTING, COMPANY ( 11.03%)
D.I.J. CONSTRUCTION, INC (3.33%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.27%)
Contract # 11153009
Totals 3954433.25 456399.21 487120.21 12.3

CountyVICTORIA
Highway US 77
From 0.52 MI. EAST OF FM 1685
To 1.04 MI. WEST OF US 87
CSJ 2350-01-041
Proj ID C 2350-1-41
Work Type CONSTRUCTING TWO ADDITIONAL LANES
 
2.493 21361349.82 384880.62 9105697.88 42.6
Work Order 11-24-15
Work Began 01-18-16
Work Completed  
Time Computed 12-24-15
Contract Working Days 450
Addl Days Granted 0
Working Days Charged 78
Percent Time Used 17
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2350-01-041
CAT SKINNER, LLC.(0.78%)
ROADWAY SPECIALTIES, INC.(1.33%)
FLASHER EQUIPMENT COMPANY(0.48%)
MCL CONTRACTING, LLC (0.50%)
W. W. FOUNDATION DRILLING, LTD.(3.01%)
WEBBER, LLC( 12.42%)
THE LEVY COMPANY, L.P. (0.23%)
PRIMATE CONSTRUCTION, INC. (0.19%)
ANDERSON COLUMBIA CO., INC.( 22.71%)
VALCO CONSTRUCTION (0.22%)
PRIMATE CONSTRUCTION, INC. (0.05%)
AARON CONCRETE CONTRACTORS, L.P. (0.62%)
W. W. FOUNDATION DRILLING, LTD.(2.01%)
SCOTT DERR PAINTING CO (0.02%)
Contract # 09153036
Totals 21361349.82 384880.62 9105697.88 42.6

CountyVICTORIA
Highway FM 1432
From SH 185
To END OF STATE MAINTENANCE
CSJ 3063-01-011
Proj ID STP 2016(280)
Work Type RESTORE ROADWAY
 
1.929 2639774.35 558415.29 3022891.34 99.9
Work Order 12-21-15
Work Began 02-17-16
Work Completed  
Time Computed 03-20-16
Contract Working Days 50
Addl Days Granted 19
Working Days Charged 48
Percent Time Used 69
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 3063-01-011
D.& S. CONSTRUCTION(0.41%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.07%)
HUNTER INDUSTRIES, LTD.( 31.37%)
D. I. J. CONSTRUCTION, INC.(0.38%)
ALTUS TRAFFIC MANAGEMENT LLC (0.19%)
Contract # 11153226
Totals 2639774.35 558415.29 3022891.34 99.9

page 1 | page 2 | page 3 | page 4