Monthly State Let Construction Report For Yoakum District As Of Aug 16, 2016 Page 4 Of 4

Last Update: Tuesday, August 16, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyAUSTIN
Highway CR
From AT CANEY CREEK CR 310
To (KRAMER RD) STR AA03-10-005
CSJ 0913-20-087
Proj ID BR 1502(358)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.059 314926.26 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SB CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-20-087
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163021
Totals 314926.26 0.00 0.00 0.0

CountyMATAGORDA
Highway CR
From AT WILLOW CREEK CR 425
To (LEZAK RD) STR # AA03-15-001
CSJ 0913-21-045
Proj ID BR 2013(504)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.066 333383.92 270.00 305718.16 91.7
Work Order 11-16-15
Work Began 02-15-16
Work Completed  
Time Computed 02-14-16
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 52
Percent Time Used 86
Contractor(s)
TCB CONSTRUCTION, INC
SUBCONTRACTOR(S) FOR CCSJ: 0913-21-045
JUST GROOVING, LTD.(0.22%)
HEMPHILL PILE DRIVING CO., A CORP. (7.19%)
LONESTAR TRAFFIC SAFETY, LLC (1.07%)
RICE ENVIRONMENTAL SERVICES(8.33%)
Contract # 07153247
Totals 333383.92 270.00 305718.16 91.7

CountyVICTORIA
Highway CR
From AT ARENOSA CREEK CR 130
To (J2 RANCH RD) STR AA01-30-006
CSJ 0913-27-065
Proj ID BR 2014(684)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.066 296070.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-11-16
Work Began 08-11-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-27-065
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03163220
Totals 296070.60 0.00 0.00 0.0

CountyLAVACA
Highway CR
From AT SUPPLEJACK CREEK CR 402
To (CR 402) STR # AA03-78-001
CSJ 0913-29-045
Proj ID BR 2012(429)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.075 420926.25 0.00 389678.34 95.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-07-15
Work Began 06-22-15
Work Completed  
Time Computed 05-07-15
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 96
Percent Time Used 128
Contractor(s)
J. CARROLL WEAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-29-045
ENVIRONMENTAL SAFETY SERVICES, INC.(6.20%)
LONESTAR TRAFFIC SAFETY, LLC (0.48%)
HOUSTON SAWING & DRILLING(0.55%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. ( 12.16%)
MESA ROD BUSTERS, INC. (0.35%)
Contract # 11143217
Totals 420926.25 0.00 389678.34 95.5

CountyGONZALES
Highway FM 532
From US 90A
To LAVACA COUNTY LINE
CSJ 1007-02-017
Proj ID STP 2013(919)
Work Type ROADWAY WIDENING
 
13.775 8097588.87 0.00 8232746.41 99.9
Work Order 10-10-13
Work Began 12-03-13
Work Completed  
Time Computed 12-03-13
Contract Working Days 285
Addl Days Granted 13
Working Days Charged 369
Percent Time Used 123
Contractor(s)
SMC CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1007-02-017
FOX QUALITY CONCRETE, L.L.C. (3.01%)
M.V. HENKE ENTERPRISES, INC. (0.46%)
F. N. PLOCH CONSTRUCTION COMPANY, INC. ( 12.05%)
C-3 ENVIRONMENTAL SPECIALTIES, LP(1.07%)
LAND STABILIZER, LTD (7.21%)
ROADWAY SPECIALTIES, INC.(0.21%)
FLASHER EQUIPMENT COMPANY(1.71%)
ZAMCO TRUCKING, LLC(1.29%)
RELMCO, INC. (3.69%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.08%)
ARIAS & ASSOCIATES, INC. (0.12%)
LONE STAR PAVING ( 24.35%)
FUTURE CONCRETE STRUCTURES (1.28%)
A BROTHERS MILLING, LLC(0.45%)
BR CARTAGE COMPANY (0.00%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.15%)
PENHALL COMPANY(0.05%)
Contract # 07133251
Totals 8097588.87 0.00 8232746.41 99.9

CountyLAVACA
Highway FM 532
From GONZALES C/L
To SH 95
CSJ 1007-03-021
Proj ID STP 2016(509)
Work Type RESTORE ROADWAY
 
4.608 2721588.22 0.00 0.00 0.0
CountyLAVACA
Highway FM 1680
From 0.5 MI N OF FM 532
To FM 532
CSJ 1442-04-010
Proj ID STP 2016(509)
Work Type RESTORE ROADWAY
 
0.460 122619.12 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-17-16
Work Began 08-15-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1007-03-021
BEAVER CONTRACTORS, LLC(6.89%)
COWBELL TRAFFIC SERVICES, INC. (0.33%)
FLASHER EQUIPMENT COMPANY(0.27%)
INTERSTATE BARRICADES & MARKINGS, INC. (2.27%)
LONE STAR EROSION CONTROL(0.67%)
MURRAY CONSTRUCTION(0.55%)
ROADWAY SPECIALTIES, INC.(0.77%)
Contract # 02163245
Totals 2844207.34 0.00 0.00 0.0

CountyLAVACA
Highway FM 958
From FM 966
To SH 95
CSJ 1008-02-018
Proj ID C 1008-2-18
Work Type SUBGRADE WIDEN, BASE, RESURFACING
 
5.012 3498600.69 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 135
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1008-02-018
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06163219
Totals 3498600.69 0.00 0.00 0.0

CountyCOLORADO
Highway FM 949
From 2.5 MI S OF IH 10
To 0.9 MI S OF IH 10
CSJ 1106-04-006
Proj ID STP 2016(432)HES
Work Type INCREASE SUPERELEVATION
 
1.642 217162.30 19519.25 255790.86 99.9
Work Order 01-21-16
Work Began 03-14-16
Work Completed  
Time Computed 04-21-16
Contract Working Days 15
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 93
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1106-04-006
ROADSAFE TRAFFIC SYSTEMS, INC. (3.76%)
Contract # 12153020
Totals 217162.30 19519.25 255790.86 99.9

CountyDEWITT
Highway FM 766
From END OF STATE MAINTENANCE
To 3.922 MI. NORTH OF FM 953
CSJ 1113-01-026
Proj ID C 1113-1-26
Work Type RESTORE ROADWAY
 
8.139 4871848.95 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 165
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1113-01-026
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07163014
Totals 4871848.95 0.00 0.00 0.0

CountyFAYETTE
Highway FM 1115
From 0.8 MI W OF FM 2762
To GONZALES C/L
CSJ 1262-01-014
Proj ID STP 1602(482)
Work Type RESTORE ROADWAY
 
5.614 3558330.17 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1262-01-014
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163224
Totals 3558330.17 0.00 0.00 0.0

CountyCALHOUN
Highway FM 1289
From AT COLOMA CREEK
To STR # 1438-01-002
CSJ 1438-01-021
Proj ID BR 2015(164)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.599 4870061.86 311999.42 4592911.80 94.3
Work Order 02-05-15
Work Began 07-23-15
Work Completed  
Time Computed 06-05-15
Contract Working Days 130
Addl Days Granted 26
Working Days Charged 132
Percent Time Used 84
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1438-01-021
REBAR MASTER"S LLC (0.41%)
JMHP, INC. (0.55%)
WEBER-BALKE FOUNDATION COMPANY, INC(7.34%)
DS TEXAS ICON CONSTRUCTION (0.67%)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.( 34.82%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.47%)
Contract # 10143230
Totals 4870061.86 311999.42 4592911.80 94.3

CountyFAYETTE
Highway FM 1457
From AT ROCKY CREEK
To STR # 1441-01-001
CSJ 1441-01-012
Proj ID BR 2016(062)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.204 1089950.26 147427.25 667275.32 61.2
Work Order 11-16-15
Work Began 01-14-16
Work Completed  
Time Computed 12-16-15
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 56
Percent Time Used 46
Contractor(s)
SB CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 1441-01-012
JJ KOONS, LLC. ( 17.29%)
RICE ENVIRONMENTAL SERVICES(5.36%)
N-LINE TRAFFIC MAINTENANCE, L.P. (9.62%)
BEAIRD DRILLING(2.11%)
LONE STAR PAVING ( 10.85%)
ENVIRONMENTAL SAFETY SERVICES, INC.(8.10%)
Contract # 09153210
Totals 1089950.26 147427.25 667275.32 61.2

CountyAUSTIN
Highway FM 1094
From 7.2 MI WEST OF SH 36(SCHLUENS RD)
To 0.4 MI WEST OF SH 36(HOWARD ST)
CSJ 1721-02-012
Proj ID STP 1502(478)HES
Work Type SAFETY TREAT FIXED OBJECTS, WIDEN SH
 
6.749 3954433.25 649412.96 1136533.17 28.7
Work Order 01-29-16
Work Began 03-23-16
Work Completed  
Time Computed 05-29-16
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 63
Percent Time Used 42
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1721-02-012
CEN TEX HYDROSEED, INC.(2.77%)
J & M CONTRACTING, COMPANY ( 11.03%)
D.I.J. CONSTRUCTION, INC (3.33%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.27%)
Contract # 11153009
Totals 3954433.25 649412.96 1136533.17 28.7

CountyVICTORIA
Highway US 77
From 0.52 MI. EAST OF FM 1685
To 1.04 MI. WEST OF US 87
CSJ 2350-01-041
Proj ID C 2350-1-41
Work Type CONSTRUCTING TWO ADDITIONAL LANES
 
2.493 21361349.82 1005162.73 10110860.61 47.3
Work Order 11-24-15
Work Began 01-18-16
Work Completed  
Time Computed 12-24-15
Contract Working Days 450
Addl Days Granted 0
Working Days Charged 98
Percent Time Used 21
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2350-01-041
CAT SKINNER, LLC.(0.78%)
ROADWAY SPECIALTIES, INC.(1.33%)
FLASHER EQUIPMENT COMPANY(0.48%)
MCL CONTRACTING, LLC (0.50%)
W. W. FOUNDATION DRILLING, LTD.(3.01%)
WEBBER, LLC( 12.42%)
THE LEVY COMPANY, L.P. (0.23%)
PRIMATE CONSTRUCTION, INC. (0.19%)
ANDERSON COLUMBIA CO., INC.( 22.71%)
VALCO CONSTRUCTION (0.22%)
PRIMATE CONSTRUCTION, INC. (0.05%)
AARON CONCRETE CONTRACTORS, L.P. (0.62%)
W. W. FOUNDATION DRILLING, LTD.(2.01%)
SCOTT DERR PAINTING CO (0.02%)
Contract # 09153036
Totals 21361349.82 1005162.73 10110860.61 47.3

CountyVICTORIA
Highway FM 1432
From SH 185
To END OF STATE MAINTENANCE
CSJ 3063-01-011
Proj ID STP 2016(280)
Work Type RESTORE ROADWAY
 
1.929 2639774.35 8136.80 3031028.14 99.9
Work Order 12-21-15
Work Began 02-17-16
Work Completed  
Time Computed 03-20-16
Contract Working Days 50
Addl Days Granted 19
Working Days Charged 49
Percent Time Used 71
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 3063-01-011
D.& S. CONSTRUCTION(0.41%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.07%)
HUNTER INDUSTRIES, LTD.( 31.37%)
D. I. J. CONSTRUCTION, INC.(0.38%)
ALTUS TRAFFIC MANAGEMENT LLC (0.19%)
Contract # 11153226
Totals 2639774.35 8136.80 3031028.14 99.9

page 1 | page 2 | page 3 | page 4