Monthly State Let Construction Report For Yoakum District As Of Aug 10, 2015 Page 4 Of 5

Last Update: Monday, August 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWHARTON
Highway CR
From AT CANEY CREEK CR 299
To (CR 263) STR. # AA02-99-001
CSJ 0913-09-061
Proj ID BR 1302(064)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.081 770327.00 183640.48 635293.70 82.4
Work Order 02-20-15
Work Began 05-28-15
Work Completed  
Time Computed 05-28-15
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 38
Percent Time Used 50
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-061
LONESTAR TRAFFIC SAFETY, LLC (0.25%)
ODUM SERVICES, L.P.(1.98%)
JUST GROOVING, LTD.(0.20%)
Contract # 01153224
Totals 770327.00 183640.48 635293.70 82.4

CountyWHARTON
Highway CR
From AT TRES PALACIOS RIVER CR 413
To (CR 405) STR # AA04-13-001
CSJ 0913-09-064
Proj ID BR 2013(439)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.062 528449.32 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-064
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153252
Totals 528449.32 0.00 0.00 0.0

CountyDEWITT
Highway CR
From AT DRAW CR 199
To (OLD GONZALES RD) # AA01-99-003
CSJ 0913-17-036
Proj ID BR 1102(585)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.063 202141.00 0.00 185041.00 94.1
Work Order 08-07-14
Work Began 12-03-14
Work Completed  
Time Computed 10-06-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 54
Percent Time Used 120
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-17-036
C. W. & A.,INC ( 10.06%)
CEN TEX HYDROSEED, INC.(1.13%)
Contract # 06143015
Totals 202141.00 0.00 185041.00 94.1

CountyDEWITT
Highway CR
From AT DRAW
To (LINCKE RD) STR # AA03-23-001
CSJ 0913-17-037
Proj ID BR 1102(586)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.066 224026.60 0.00 218497.00 100.0
Work Order 07-18-14
Work Began 10-28-14
Work Completed 08-06-15
Time Computed 09-16-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 56
Percent Time Used 93
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-17-037
CEN TEX HYDROSEED, INC.(0.67%)
HEMPHILL PILE DRIVING CO., A CORP. (3.85%)
JUST GROOVING, LTD.(0.43%)
Contract # 06143213
Totals 224026.60 0.00 218497.00 100.0

CountyJACKSON
Highway CR
From AT STEM BRANCH CR 284
To (CR 284) AA01-10-001
CSJ 0913-18-023
Proj ID BR 2011(304)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.142 696017.65 0.00 695191.64 99.8
Work Order 03-25-14
Work Began 06-03-14
Work Completed  
Time Computed 05-24-14
Contract Working Days 138
Addl Days Granted 0
Working Days Charged 136
Percent Time Used 98
Contractor(s)
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0913-18-023
LONESTAR TRAFFIC SAFETY, LLC (0.63%)
JUST GROOVING, LTD.(0.30%)
SHINN & GREGORY, INC.(7.77%)
ENVIRONMENTAL SAFETY SERVICES, INC.(4.97%)
SYLVA CONSTRUCTION CO.(PORT LAVACA,TX) ( 21.26%)
Contract # 01143021
Totals 696017.65 0.00 695191.64 99.8

CountyJACKSON
Highway CR
From AT LAVACA RIVER RELIEF CR 174
To (CR 127) STR # AA01-74-001
CSJ 0913-18-027
Proj ID BR 1102(529)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.224 1084856.00 28048.00 1100200.62 99.9
Work Order 06-16-14
Work Began 08-18-14
Work Completed  
Time Computed 08-18-14
Contract Working Days 215
Addl Days Granted 0
Working Days Charged 158
Percent Time Used 73
Contractor(s)
NBG CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-18-027
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.(4.02%)
ENVIRONMENTAL SAFETY SERVICES, INC.(4.70%)
1 PRIORITY ENVIRONMENTAL SERVICES, INC.(1.84%)
JUST GROOVING, LTD.(0.15%)
Contract # 05143017
Totals 1084856.00 28048.00 1100200.62 99.9

CountyCALHOUN
Highway CR
From AT SIXMILE CREEK
To (ROYAL RD) STR # AA01-97-001
CSJ 0913-19-026
Proj ID BR 2012(404)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.056 219241.82 15112.63 159482.63 73.8
Work Order 10-17-14
Work Began 03-16-15
Work Completed  
Time Computed 02-14-15
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 49
Percent Time Used 108
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-19-026
HIGHWAY BARRICADES AND SERVICES, LLC (1.14%)
SYLVA CONSTRUCTION CO.(PORT LAVACA,TX) ( 21.94%)
Contract # 09143210
Totals 219241.82 15112.63 159482.63 73.8

CountyCALHOUN
Highway CR
From AT LITTLE CHOCOLATE BAYOU
To WESTERLUND GRADE RD STR#AA02-06-002
CSJ 0913-19-027
Proj ID BR 2012(405)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.058 318903.60 200047.60 253439.60 79.4
Work Order 12-10-14
Work Began 03-02-15
Work Completed  
Time Computed 03-02-15
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 5
Percent Time Used 16
Contractor(s)
LESTER CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-19-027
ENVIRONMENTAL SAFETY SERVICES, INC.(1.05%)
SYLVA CONSTRUCTION CO.(PORT LAVACA,TX) ( 21.77%)
GONZALEZ CONTRACTING ( 13.54%)
Contract # 10143018
Totals 318903.60 200047.60 253439.60 79.4

CountyCALHOUN
Highway PW
From BUFFALO LAKE ROAD
To GUADALUPE DELTA WMA
CSJ 0913-19-029
Proj ID C 913-19-29
Work Type ADD BASE & DRAINAGE CULVERTS
 
2.297 318306.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-23-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LESTER CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-19-029
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153005
Totals 318306.00 0.00 0.00 0.0

CountyAUSTIN
Highway CR
From AT DRAW
To (NELIUS RD) STR # AA03-26-001
CSJ 0913-20-084
Proj ID BR 1102(474)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.071 525692.63 62679.00 436243.13 82.9
Work Order 01-02-15
Work Began 02-23-15
Work Completed  
Time Computed 02-23-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 55
Percent Time Used 91
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-20-084
ENVIRONMENTAL SAFETY SERVICES, INC.(3.76%)
DALLAS LITE AND BARRICADE INC. (0.32%)
Contract # 11143206
Totals 525692.63 62679.00 436243.13 82.9

CountyAUSTIN
Highway CR
From AT SANDY CREEK
To (RIPPLE LANE) STR # AA65-40-001
CSJ 0913-20-085
Proj ID BR 2012(166)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.070 442957.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-15-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0913-20-085
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153054
Totals 442957.40 0.00 0.00 0.0

CountyMATAGORDA
Highway CR
From AT CANEY CREEK CR 194
To (HAWKINS RD) STR # AA01-94-001
CSJ 0913-21-042
Proj ID BR 2014(299)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.171 1323586.20 2636.64 1315935.08 99.4
Work Order 04-15-14
Work Began 10-21-14
Work Completed  
Time Computed 06-14-14
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 95
Percent Time Used 90
Contractor(s)
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0913-21-042
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.(2.74%)
FUQUAY, INC. (0.46%)
JMHP, INC. (1.62%)
JUST GROOVING, LTD.(0.19%)
LONESTAR TRAFFIC SAFETY, LLC (0.17%)
WEBBER-BALKE FOUNDATION COMPANY, INC.( 11.59%)
Contract # 02143019
Totals 1323586.20 2636.64 1315935.08 99.4

CountyMATAGORDA
Highway CR
From AT WILLOW CREEK CR 425
To (LEZAK RD) STR # AA03-15-001
CSJ 0913-21-045
Proj ID BR 2013(504)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.066 333383.92 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TCB CONSTRUCTION, INC
SUBCONTRACTOR(S) FOR CCSJ: 0913-21-045
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07153247
Totals 333383.92 0.00 0.00 0.0

CountyGONZALES
Highway CR
From CR 363 AT GELHORN CREEK
To STR # AA03-63-001
CSJ 0913-22-035
Proj ID BR 2011(495)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.055 236824.41 0.00 256474.12 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-09-14
Work Began 09-15-14
Work Completed 04-23-15
Time Computed 07-08-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 54
Percent Time Used 90
Contractor(s)
HILL COUNTRY BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-22-035
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.( 16.44%)
DUSTIN ALLEN, INC. (5.68%)
FUQUAY, INC. (2.11%)
JUST GROOVING, LTD.(0.35%)
O & S TRAFFIC SUPPLIES (0.86%)
SHINN & GREGORY, INC.(7.83%)
Contract # 04143229
Totals 236824.41 0.00 256474.12 100.0

CountyGONZALES
Highway CR
From AT BRUSHY CREEK CR 118
To (CR 118) STR # AA01-18-001
CSJ 0913-22-036
Proj ID BR 2011(596)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.066 247853.06 0.00 247493.27 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-02-14
Work Began 06-18-14
Work Completed 02-02-15
Time Computed 06-18-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 58
Percent Time Used 96
Contractor(s)
TMES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-22-036
SHINN & GREGORY, INC.(6.81%)
FUQUAY, INC. (4.06%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.34%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
Contract # 04143026
Totals 247853.06 0.00 247493.27 100.0

CountyGONZALES
Highway CR
From AT ROCKY CREEK CR 377
To (CR 360A) STR # AA05-45-001
CSJ 0913-22-043
Proj ID BR 2015(539)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.056 276692.75 0.00 209546.00 75.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-18-15
Work Began 06-02-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 21
Percent Time Used 46
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-22-043
FUQUAY, INC. (3.59%)
LONESTAR TRAFFIC SAFETY, LLC (0.61%)
Contract # 01153206
Totals 276692.75 0.00 209546.00 75.7

CountyGONZALES
Highway CR
From AT FULCHUR CREEK
To CR 296 STR # AA02-96-001
CSJ 0913-22-044
Proj ID BR 2013(440)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.066 323837.00 0.00 78449.46 24.2
Work Order 10-17-14
Work Began 00-00-00
Work Completed  
Time Computed 02-14-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-22-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143215
Totals 323837.00 0.00 78449.46 24.2

CountyCOLORADO
Highway CR
From AT DRAW CR 153
To DIETRICH LANE STR # AA-01-53-003
CSJ 0913-26-059
Proj ID BR 2012(732)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.062 249900.02 15456.39 143476.39 57.4
Work Order 12-16-14
Work Began 02-11-15
Work Completed  
Time Computed 02-11-15
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 5
Percent Time Used 11
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-26-059
LONESTAR TRAFFIC SAFETY, LLC (0.57%)
KOSSMAN CONTRACTING CO., INC.(0.58%)
SYLVA CONSTRUCTION CO.(PORT LAVACA,TX) ( 22.96%)
Contract # 10143004
Totals 249900.02 15456.39 143476.39 57.4

CountyVICTORIA
Highway CR
From AT DRY CREEK CR 114
To (WEBER ROAD) STR # AA01-14-001
CSJ 0913-27-054
Proj ID BR 2011(496)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.097 338315.31 1185.00 334578.23 100.0
Work Order 06-20-14
Work Began 08-21-14
Work Completed 06-22-15
Time Computed 08-19-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 52
Percent Time Used 86
Contractor(s)
REXCO CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-27-054
RICE ENVIRONMENTAL SERVICES(5.16%)
SPECIALTY DRILLING, LTD. ( 14.84%)
LONE STAR TRAFFIC SERVICE, INC.(0.63%)
HOLES INCORPORATED (0.73%)
MESA ROD BUSTERS, INC. (0.48%)
JUST GROOVING, LTD.(0.30%)
BRANNAN PAVING CO., LTD. (0.23%)
Contract # 05143034
Totals 338315.31 1185.00 334578.23 100.0

CountyVICTORIA
Highway CR
From AT DRAW CR 169
To (KOHUTEK RD) STR AA01-69-001
CSJ 0913-27-064
Proj ID BR 2014(977)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.063 254387.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-08-15
Work Began 00-00-00
Work Completed  
Time Computed 07-09-15
Contract Working Days 35
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CONSTRUCTION COMPANIES GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-27-064
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153047
Totals 254387.00 0.00 0.00 0.0

page 1 | page 2 | page 3 | page 4 | page 5