Monthly State Let Construction Report For Yoakum District As Of Apr 11, 2016 Page 4 Of 4

Last Update: Monday, April 11, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyAUSTIN
Highway CR
From AT SANDY CREEK
To (RIPPLE LANE) STR # AA65-40-001
CSJ 0913-20-085
Proj ID BR 2012(166)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.070 442957.40 0.00 371076.00 83.7
Work Order 07-15-15
Work Began 10-20-15
Work Completed  
Time Computed 10-13-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 24
Percent Time Used 40
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0913-20-085
CEN TEX HYDROSEED, INC.(1.23%)
JUST GROOVING, LTD.(0.28%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.63%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.61%)
WILLOW CITY SIGN & RAIL, INC.(2.96%)
MCL CONTRACTING, LLC (0.35%)
Contract # 05153054
Totals 442957.40 0.00 371076.00 83.7

CountyMATAGORDA
Highway CR
From AT WILLOW CREEK CR 425
To (LEZAK RD) STR # AA03-15-001
CSJ 0913-21-045
Proj ID BR 2013(504)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.066 333383.92 91617.86 208281.51 62.4
Work Order 11-16-15
Work Began 02-15-16
Work Completed  
Time Computed 02-14-16
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 23
Percent Time Used 38
Contractor(s)
TCB CONSTRUCTION, INC
SUBCONTRACTOR(S) FOR CCSJ: 0913-21-045
JUST GROOVING, LTD.(0.22%)
HEMPHILL PILE DRIVING CO., A CORP. (7.19%)
LONESTAR TRAFFIC SAFETY, LLC (1.07%)
RICE ENVIRONMENTAL SERVICES(8.33%)
Contract # 07153247
Totals 333383.92 91617.86 208281.51 62.4

CountyGONZALES
Highway CR
From AT ROCKY CREEK CR 377
To (CR 360A) STR # AA05-45-001
CSJ 0913-22-043
Proj ID BR 2015(539)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.056 276692.75 1491.44 265330.19 96.7
Work Order 02-18-15
Work Began 06-02-15
Work Completed  
Time Computed 06-02-15
Contract Working Days 45
Addl Days Granted 10
Working Days Charged 59
Percent Time Used 107
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-22-043
FUQUAY, INC. (3.59%)
LONESTAR TRAFFIC SAFETY, LLC (0.61%)
Contract # 01153206
Totals 276692.75 1491.44 265330.19 96.7

CountyVICTORIA
Highway CR
From AT ARENOSA CREEK CR 130
To (J2 RANCH RD) STR AA01-30-006
CSJ 0913-27-065
Proj ID BR 2014(684)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.066 296070.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-27-065
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03163220
Totals 296070.60 0.00 0.00 0.0

CountyLAVACA
Highway CR
From AT SUPPLEJACK CREEK CR 402
To (CR 402) STR # AA03-78-001
CSJ 0913-29-045
Proj ID BR 2012(429)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.075 420926.25 0.00 389678.34 95.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-07-15
Work Began 06-22-15
Work Completed  
Time Computed 05-07-15
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 96
Percent Time Used 128
Contractor(s)
J. CARROLL WEAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-29-045
ENVIRONMENTAL SAFETY SERVICES, INC.(6.20%)
LONESTAR TRAFFIC SAFETY, LLC (0.48%)
HOUSTON SAWING & DRILLING(0.55%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. ( 12.16%)
MESA ROD BUSTERS, INC. (0.35%)
Contract # 11143217
Totals 420926.25 0.00 389678.34 95.5

CountyLAVACA
Highway CR
From AT NAVIDAD RIVER CR 124
To (CR 214) STR # AA04-95-001
CSJ 0913-29-046
Proj ID BR 2012(430)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.116 639216.42 6451.01 716937.60 99.9
Work Order 07-22-14
Work Began 11-11-14
Work Completed  
Time Computed 11-11-14
Contract Working Days 105
Addl Days Granted 6
Working Days Charged 111
Percent Time Used 100
Contractor(s)
J. CARROLL WEAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-29-046
ENVIRONMENTAL SAFETY SERVICES, INC.(3.18%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.88%)
JUST GROOVING, LTD.(0.26%)
WEBBER-BALKE FOUNDATION COMPANY, INC.( 10.30%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
HOUSTON SAWING & DRILLING(0.46%)
Contract # 05143024
Totals 639216.42 6451.01 716937.60 99.9

CountyGONZALES
Highway FM 532
From US 90A
To LAVACA COUNTY LINE
CSJ 1007-02-017
Proj ID STP 2013(919)
Work Type ROADWAY WIDENING
 
13.775 8097588.87 15068.95 8147125.08 99.9
Work Order 10-10-13
Work Began 12-03-13
Work Completed  
Time Computed 12-03-13
Contract Working Days 285
Addl Days Granted 13
Working Days Charged 369
Percent Time Used 123
Contractor(s)
SMC CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1007-02-017
FOX QUALITY CONCRETE, L.L.C. (3.01%)
M.V. HENKE ENTERPRISES, INC. (0.46%)
F. N. PLOCH CONSTRUCTION COMPANY, INC. ( 12.05%)
C-3 ENVIRONMENTAL SPECIALTIES, LP(1.07%)
LAND STABILIZER, LTD (7.21%)
ROADWAY SPECIALTIES, INC.(0.21%)
FLASHER EQUIPMENT COMPANY(1.71%)
ZAMCO TRUCKING, LLC(1.29%)
RELMCO, INC. (3.69%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.08%)
ARIAS & ASSOCIATES, INC. (0.12%)
LONE STAR PAVING ( 24.35%)
FUTURE CONCRETE STRUCTURES (1.28%)
A BROTHERS MILLING, LLC(0.45%)
BR CARTAGE COMPANY (0.00%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.15%)
Contract # 07133251
Totals 8097588.87 15068.95 8147125.08 99.9

CountyLAVACA
Highway FM 532
From GONZALES C/L
To SH 95
CSJ 1007-03-021
Proj ID STP 2016(509)
Work Type RESTORE ROADWAY
 
4.608 2721588.22 0.00 0.00 0.0
CountyLAVACA
Highway FM 1680
From 0.5 MI N OF FM 532
To FM 532
CSJ 1442-04-010
Proj ID STP 2016(509)
Work Type RESTORE ROADWAY
 
0.460 122619.12 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1007-03-021
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163245
Totals 2844207.34 0.00 0.00 0.0

CountyCOLORADO
Highway FM 949
From 2.5 MI S OF IH 10
To 0.9 MI S OF IH 10
CSJ 1106-04-006
Proj ID STP 2016(432)HES
Work Type INCREASE SUPERELEVATION
 
1.642 217162.30 227627.41 227627.41 99.9
Work Order 01-21-16
Work Began 03-14-16
Work Completed  
Time Computed 04-21-16
Contract Working Days 15
Addl Days Granted 0
Working Days Charged 9
Percent Time Used 60
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1106-04-006
ROADSAFE TRAFFIC SYSTEMS, INC. (3.76%)
Contract # 12153020
Totals 217162.30 227627.41 227627.41 99.9

CountyWHARTON
Highway FM 1160
From FM 1300
To US 59
CSJ 1302-01-022
Proj ID STP 1502(203)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
7.919 636444.30 28359.53 607911.33 95.5
Work Order 08-10-15
Work Began 09-16-15
Work Completed  
Time Computed 09-14-15
Contract Working Days 90
Addl Days Granted 5
Working Days Charged 94
Percent Time Used 98
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1302-01-022
WILLOW CITY SIGN & RAIL, INC.( 10.52%)
N-LINE TRAFFIC MAINTENANCE, L.P. (2.60%)
Contract # 06153264
Totals 636444.30 28359.53 607911.33 95.5

CountyCALHOUN
Highway FM 1289
From AT COLOMA CREEK
To STR # 1438-01-002
CSJ 1438-01-021
Proj ID BR 2015(164)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.599 4870061.86 0.00 3828201.89 78.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-05-15
Work Began 07-23-15
Work Completed  
Time Computed 06-05-15
Contract Working Days 130
Addl Days Granted 10
Working Days Charged 108
Percent Time Used 77
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1438-01-021
REBAR MASTER"S LLC (0.41%)
JMHP, INC. (0.55%)
WEBER-BALKE FOUNDATION COMPANY, INC(7.34%)
DS TEXAS ICON CONSTRUCTION (0.67%)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.( 34.82%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.47%)
Contract # 10143230
Totals 4870061.86 0.00 3828201.89 78.6

CountyFAYETTE
Highway FM 1457
From AT ROCKY CREEK
To STR # 1441-01-001
CSJ 1441-01-012
Proj ID BR 2016(062)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.204 1089950.26 23933.20 337839.16 30.9
Work Order 11-16-15
Work Began 01-14-16
Work Completed  
Time Computed 12-16-15
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 5
Percent Time Used 4
Contractor(s)
SB CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 1441-01-012
JJ KOONS, LLC. ( 17.29%)
RICE ENVIRONMENTAL SERVICES(5.36%)
N-LINE TRAFFIC MAINTENANCE, L.P. (9.62%)
BEAIRD DRILLING(2.11%)
LONE STAR PAVING ( 10.85%)
Contract # 09153210
Totals 1089950.26 23933.20 337839.16 30.9

CountyAUSTIN
Highway FM 1094
From 7.2 MI WEST OF SH 36(SCHLUENS RD)
To 0.4 MI WEST OF SH 36(HOWARD ST)
CSJ 1721-02-012
Proj ID STP 1502(478)HES
Work Type SAFETY TREAT FIXED OBJECTS, WIDEN SH
 
6.749 3954433.25 5175.00 5175.00 0.1
Work Order 01-29-16
Work Began 03-23-16
Work Completed  
Time Computed 05-29-16
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 1
Percent Time Used 0
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1721-02-012
CEN TEX HYDROSEED, INC.(2.77%)
J & M CONTRACTING, COMPANY ( 11.03%)
D.I.J. CONSTRUCTION, INC (3.33%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.27%)
Contract # 11153009
Totals 3954433.25 5175.00 5175.00 0.1

CountyVICTORIA
Highway US 77
From 0.52 MI. EAST OF FM 1685
To 1.04 MI. WEST OF US 87
CSJ 2350-01-041
Proj ID C 2350-1-41
Work Type CONSTRUCTING TWO ADDITIONAL LANES
 
2.493 21361349.82 507381.97 4991509.76 23.3
Work Order 11-24-15
Work Began 01-18-16
Work Completed  
Time Computed 12-24-15
Contract Working Days 450
Addl Days Granted 0
Working Days Charged 39
Percent Time Used 8
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2350-01-041
CAT SKINNER, LLC.(0.78%)
ROADWAY SPECIALTIES, INC.(1.33%)
FLASHER EQUIPMENT COMPANY(0.48%)
MCL CONTRACTING, LLC (0.50%)
W. W. FOUNDATION DRILLING, LTD.(3.01%)
WEBBER, LLC( 12.42%)
THE LEVY COMPANY, L.P. (0.23%)
PRIMATE CONSTRUCTION, INC. (0.19%)
ANDERSON COLUMBIA CO., INC.( 22.71%)
VALCO CONSTRUCTION (0.22%)
PRIMATE CONSTRUCTION, INC. (0.05%)
AARON CONCRETE CONTRACTORS, L.P. (0.62%)
W. W. FOUNDATION DRILLING, LTD.(2.01%)
SCOTT DERR PAINTING CO (0.02%)
Contract # 09153036
Totals 21361349.82 507381.97 4991509.76 23.3

CountyVICTORIA
Highway FM 1432
From SH 185
To END OF STATE MAINTENANCE
CSJ 3063-01-011
Proj ID STP 2016(280)
Work Type RESTORE ROADWAY
 
1.929 2639774.35 620053.33 1350640.90 51.1
Work Order 12-21-15
Work Began 02-17-16
Work Completed  
Time Computed 03-20-16
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 24
Percent Time Used 48
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 3063-01-011
D.& S. CONSTRUCTION(0.41%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.07%)
HUNTER INDUSTRIES, LTD.( 31.37%)
D. I. J. CONSTRUCTION, INC.(0.38%)
ALTUS TRAFFIC MANAGEMENT LLC (0.19%)
Contract # 11153226
Totals 2639774.35 620053.33 1350640.90 51.1

CountyCOLORADO
Highway FM 3013
From AUSTIN COUNTY LINE
To 0.03 MI. SOUTH OF US 90A
CSJ 3205-02-019
Proj ID STP 2015(319)HESG
Work Type SAFETY TREAT FIXED OBJECTS
 
8.137 478431.08 3009.93 462959.83 96.7
Work Order 01-30-15
Work Began 05-14-15
Work Completed  
Time Computed 05-14-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 47
Percent Time Used 78
Contractor(s)
BEAR CREEK CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 3205-02-019
N-LINE TRAFFIC MAINTENANCE, L.P. ( 10.73%)
RICE ENVIRONMENTAL SERVICES( 14.06%)
ROADWAY SPECIALTIES, INC.(2.70%)
Contract # 11143013
Totals 478431.08 3009.93 462959.83 96.7

page 1 | page 2 | page 3 | page 4