Monthly State Let Construction Report For Yoakum District As Of Nov 22, 2017 Page 4 Of 6

Last Update: Wednesday, November 22, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyJACKSON
HighwayFM 616
FromSH 172
To3.2 MI E OF SH 172(W. CARANCAHUA CR
CSJ0497-03-009
Proj IDSTP 2017(702)
Work TypeRESTORE ROADWAY
 
3.3002063461.48888213.7043.0
Work Order03-08-17
Work Began00-00-00
Work Completed
Time Computed06-06-17
Contract Working Days105
Addl Days Granted0
Working Days Charged69
Percent Time Used65
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0497-03-009
ROADSAFE TRAFFIC SYSTEMS, INC. (1.46)
ROADWAY SPECIALTIES, INC. (4.71)
Contract #02173214
Totals2063461.48289860.00888213.7043.0

CountyAUSTIN
HighwayFM 1458
From3.4 MI S OF IH 10 (WARD BEND RD)
ToFM 1093
CSJ0527-03-024
Proj IDSTP 2017(493)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
7.9281002148.60391300.0039.0
Work Order03-30-17
Work Began09-08-17
Work Completed
Time Computed06-18-17
Contract Working Days90
Addl Days Granted0
Working Days Charged32
Percent Time Used35
Contractor(s)
SJ&J CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0527-03-024
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173243
Totals1002148.60239700.00391300.0039.0

CountyGONZALES
HighwayIH 10
FromCALDWELL COUNTY LINE
ToSANDY FORK CREEK
CSJ0535-04-030
Proj IDNH 2017(832)
Work TypeACP OVERLAY
 
20.70514770182.692684345.7718.1
Work Order04-24-17
Work Began07-17-17
Work Completed
Time Computed05-24-17
Contract Working Days180
Addl Days Granted0
Working Days Charged36
Percent Time Used20
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0535-04-030
AWP, INC. (0.16)
DIAMOND SURFACE, INC. (0.22)
DUSTROL, INC. (2.82)
PRIMATE CONSTRUCTION, INC. (2.81)
INTERSTATE BARRICADES & MARKINGS, INC. (4.22)
Contract #03173003
Totals14770182.691108761.552684345.7718.1

CountyGONZALES
HighwayFM 1116
FromSH 97
To7.2 MI S OF SH 97
CSJ0573-04-015
Proj IDSTP 1702(643)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
14.4004044139.160.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-21-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0573-04-015
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173228
Totals4044139.160.000.000.0

CountyMATAGORDA
HighwayFM 457
From0.020 MILES NORTH OF MARINA DRIVE
ToCANAL DRIVE
CSJ0605-01-060
Proj IDBR 2017(973)
Work TypeREPLACE SWING BRIDGE
 
0.60841231131.02228000.000.5
Work Order08-16-17
Work Began00-00-00
Work Completed
Time Computed02-12-18
Contract Working Days405
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0605-01-060
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173202
Totals41231131.020.00228000.000.5

CountyCOLORADO
HighwayFM 109
FromAT REDGATE CREEK
ToSTR # 0716-02-011
CSJ0716-02-038
Proj IDBR 1602(086)
Work TypeWIDEN BRIDGE AND APPROACHES
 
0.185533118.53580331.0799.9
Work Order06-22-16
Work Began09-16-16
Work Completed
Time Computed07-22-16
Contract Working Days50
Addl Days Granted0
Working Days Charged50
Percent Time Used100
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0716-02-038
ROADSAFE TRAFFIC SYSTEMS, INC. (0.60)
ROADWAY SPECIALTIES, INC. (5.03)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.50)
Contract #05163010
Totals533118.5350101.32580331.0799.9

CountyGONZALES
HighwayFM 443
FromAT ROCKY CREEK
ToSTR # 0839-01-002
CSJ0839-01-015
Proj IDBR 2017(259)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.3211222090.601176893.0597.5
Work Order12-28-16
Work Began04-06-17
Work Completed
Time Computed01-28-17
Contract Working Days75
Addl Days Granted0
Working Days Charged98
Percent Time Used130
Contractor(s)
HILL COUNTRY BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0839-01-015
HEMPHILL WBE PILE DRIVING CO. (5.11)
HIGHWAY BARRICADES AND SERVICES, LLC (0.43)
(USE 07366)J.R. RAMON & SONS, INC (1.43)
O & S TRAFFIC SUPPLIES (0.29)
PENHALL COMPANY (0.34)
REXCO CONSTRUCTION SERVICES, INC. (24.04)
TEXAS SHAFTS, INC. (6.73)
MCL CONTRACTING, LLC (0.32)
12-1 HIGHWAY AND ENVIRONMENTAL SERVICES, LLC (2.48)
FRANK JR REINFORCEMENT LLC (0.56)
Contract #11163209
Totals1222090.6045109.351176893.0597.5

CountyDEWITT
HighwayVA
FromVARIOUS LOCATIONS
ToIN AUSTIN, MATAGORDA, & WHARTON CO.
CSJ0913-00-088
Proj IDSTP 2012(527)
Work TypeCONSTRUCT CURB RAMPS
 
0.100475081.00577322.1799.9
Work Order06-18-12
Work Began04-05-13
Work Completed
Time Computed10-16-12
Contract Working Days165
Addl Days Granted0
Working Days Charged142
Percent Time Used86
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-00-088
PAVEMENT MARKINGS INC. (1.39)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (3.79)
SPEEDY PAVING (2.40)
Contract #05123217
Totals475081.000.00577322.1799.9

CountyDEWITT
HighwayVA
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ0913-00-092
Proj IDBR 2016(133)
Work TypeUPGRADE BRIDGE AND APPROACH RAILING
 
0.0023378506.553353625.0199.9
CountyDEWITT
HighwayVA
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ0913-00-094
Proj IDNH 2016(134)
Work TypeCONCRETE RAIL REPAIR
 
0.00190833.20156947.4299.9
Work Order11-24-15
Work Began01-18-16
Work Completed
Time Computed12-24-15
Contract Working Days203
Addl Days Granted0
Working Days Charged305
Percent Time Used150
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-00-092
WEST TEXAS RUMBLE STRIP (0.13)
D & S TEXAS ICON CONSTRUCTION, LLC. (4.10)
TINMAN ENTERPRISES (5.32)
ROADSAFE TRAFFIC SYSTEMS, INC. (6.74)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (19.38)
Contract #10153213
Totals3469339.750.003510572.4399.9

CountyWHARTON
HighwayCR
FromAT WEST MUSTANG CREEK CR 372
To(CR 372) STR # AA06-59-001
CSJ0913-09-053
Proj IDBR 2012(407)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.074629675.00597441.4098.0
Work Order07-07-15
Work Began11-11-15
Work Completed
Time Computed10-06-15
Contract Working Days75
Addl Days Granted0
Working Days Charged108
Percent Time Used144
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-053
HEMPHILL PILE DRIVING CO., A CORP. (4.74)
ODUM SERVICES, L.P. (3.89)
JUST GROOVING, LTD. (0.25)
CEN TEX HYDROSEED, INC. (0.33)
Contract #05153048
Totals629675.000.00597441.4098.0

CountyWHARTON
HighwayCR
FromAT EAST CARANCAHUA CREEK CR 458
To(CR 322) STR # AA04-58-001
CSJ0913-09-056
Proj IDBR 2012(409)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.061552981.25150532.0027.2
Work Order06-14-17
Work Began10-25-17
Work Completed
Time Computed09-12-17
Contract Working Days73
Addl Days Granted0
Working Days Charged2
Percent Time Used2
Contractor(s)
HILL COUNTRY BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-056
TRIPLE J-SA CONSTRUCTION (15.34)
HEMPHILL WBE PILE DRIVING CO. (11.34)
LONESTAR TRAFFIC SAFETY, LLC (0.52)
HOUSTON SAWING & DRILLING (0.29)
ZENITH SITE SERVICES (11.00)
Contract #05173236
Totals552981.25150532.00150532.0027.2

CountyWHARTON
HighwayCR
FromAT GUM TREE BRANCH # 2
To(CR 252) STR # AA03-17-003
CSJ0913-09-059
Proj IDBR 2012(412)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.164746501.3066762.148.9
Work Order05-11-17
Work Began00-00-00
Work Completed
Time Computed06-12-17
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-059
LONESTAR TRAFFIC SAFETY, LLC (0.62)
JMHP, INC. (5.97)
Contract #04173029
Totals746501.300.0066762.148.9

CountyWHARTON
HighwayCR
FromAT DRAW CR 469
To(CR 315) STR # AA04-69-002
CSJ0913-09-060
Proj IDBR 1502(637)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.132902792.10827006.7191.2
Work Order02-22-17
Work Began00-00-00
Work Completed
Time Computed05-23-17
Contract Working Days100
Addl Days Granted0
Working Days Charged80
Percent Time Used80
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-060
LONESTAR TRAFFIC SAFETY, LLC (0.56)
JMHP, INC. (1.99)
Contract #01173252
Totals902792.10232113.39827006.7191.2

CountyWHARTON
HighwayCR
FromAT EAST FORK JONES CREEK CR 461
To(CR 461) STR # AA06-47-002
CSJ0913-09-065
Proj IDBR 2014(682)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100320804.300.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-18-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
3LW CIVIL LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-065
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173027
Totals320804.300.000.000.0

CountyWHARTON
HighwayCR
FromAT MUD CREEK CR 419
To(CR 407) STR # AA04-19-001
CSJ0913-09-067
Proj IDBR 2014(677)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.064289824.00276172.2097.1
Work Order09-14-16
Work Began12-05-16
Work Completed
Time Computed10-14-16
Contract Working Days60
Addl Days Granted0
Working Days Charged69
Percent Time Used115
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-067
HEMPHILL WBE PILE DRIVING CO. (7.59)
Contract #07163242
Totals289824.000.00276172.2097.1

CountyWHARTON
HighwayCR
FromAT BEE TREE BAYOU CR 103
To(CR 103) STR # AA01-95-002
CSJ0913-09-069
Proj IDBR 2014(679)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.068425246.700.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-25-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-069
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09173012
Totals425246.700.000.000.0

CountyWHARTON
HighwayCR
FromAT JONES CREEK CR 648
To(CR 457) STR # AA06-48-001
CSJ0913-09-071
Proj IDBR 2014(681)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.068441100.21437751.1799.2
Work Order05-10-16
Work Began07-18-16
Work Completed
Time Computed08-08-16
Contract Working Days75
Addl Days Granted0
Working Days Charged75
Percent Time Used100
Contractor(s)
REXCO CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-071
JUST GROOVING, LTD. (0.22)
ODUM SERVICES, L.P. (2.53)
SPECIALTY DRILLING, LTD. (10.09)
CEN TEX HYDROSEED, INC. (1.78)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.13)
Contract #02163031
Totals441100.210.00437751.1799.2

CountyWHARTON
HighwayCR
FromAT PEACH CREEK (132410AA0294001)
ToWCR 253 (AA0253)
CSJ0913-09-076
Proj IDBR 1502(198)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.130670423.18656767.8197.9
Work Order07-13-16
Work Began09-02-16
Work Completed
Time Computed10-11-16
Contract Working Days120
Addl Days Granted0
Working Days Charged85
Percent Time Used70
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-076
HEMPHILL WBE PILE DRIVING CO. (5.60)
LONESTAR TRAFFIC SAFETY, LLC (0.85)
BRANNAN PAVING CO., LTD. (4.91)
Contract #05163204
Totals670423.180.00656767.8197.9

CountyWHARTON
HighwayCS
FromVARIOUS LOC. ALONG AVE I& NORRIS ST
ToIN THE CITY OF EL CAMPO
CSJ0913-09-081
Proj IDSTP 1602(475)TAPS
Work TypeCONSTRUCT SIDEWALKS
 
1.202311986.00316064.6099.9
Work Order02-09-17
Work Began04-28-17
Work Completed
Time Computed05-10-17
Contract Working Days45
Addl Days Granted0
Working Days Charged45
Percent Time Used100
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-081
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173226
Totals311986.000.00316064.6099.9

CountyWHARTON
HighwayCR
FromAT DRAW CR 303
ToSTR AA04-62-001
CSJ0913-09-083
Proj IDBR 1602(017)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.2591499626.260.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-16-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days225
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SB CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-083
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10173211
Totals1499626.260.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6