Monthly State Let Construction Report For Yoakum District As Of Jul 14, 2017 Page 4 Of 5

Last Update: Monday, July 17, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyGONZALES
HighwayIH 10
FromCALDWELL COUNTY LINE
ToSANDY FORK CREEK
CSJ0535-04-030
Proj IDNH 2017(832)
Work TypeACP OVERLAY
 
20.70514770182.690.000.0
Work Order04-24-17
Work Began00-00-00
Work Completed
Time Computed05-24-17
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0535-04-030
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03173003
Totals14770182.690.000.000.0

CountyMATAGORDA
HighwayFM 457
From0.020 MILES NORTH OF MARINA DRIVE
ToCANAL DRIVE
CSJ0605-01-060
Proj IDBR 2017(973)
Work TypeREPLACE SWING BRIDGE
 
0.60841231131.020.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days405
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0605-01-060
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173202
Totals41231131.020.000.000.0

CountyCOLORADO
HighwayFM 109
FromAT REDGATE CREEK
ToSTR # 0716-02-011
CSJ0716-02-038
Proj IDBR 1602(086)
Work TypeWIDEN BRIDGE AND APPROACHES
 
0.185533118.53530229.7599.4
Work Order06-22-16
Work Began09-16-16
Work Completed
Time Computed07-22-16
Contract Working Days50
Addl Days Granted0
Working Days Charged50
Percent Time Used100
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0716-02-038
ROADSAFE TRAFFIC SYSTEMS, INC. (0.60)
ROADWAY SPECIALTIES, INC. (5.03)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.50)
Contract #05163010
Totals533118.5377732.00530229.7599.4

CountyGONZALES
HighwayFM 443
FromAT ROCKY CREEK
ToSTR # 0839-01-002
CSJ0839-01-015
Proj IDBR 2017(259)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.3211222090.60681872.9155.7
Work Order12-28-16
Work Began04-06-17
Work Completed
Time Computed01-28-17
Contract Working Days75
Addl Days Granted0
Working Days Charged53
Percent Time Used70
Contractor(s)
HILL COUNTRY BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0839-01-015
HEMPHILL WBE PILE DRIVING CO. (5.11)
HIGHWAY BARRICADES AND SERVICES, LLC (0.43)
(USE 07366)J.R. RAMON & SONS, INC (1.43)
O & S TRAFFIC SUPPLIES (0.29)
PENHALL COMPANY (0.34)
REXCO CONSTRUCTION SERVICES, INC. (24.04)
TEXAS SHAFTS, INC. (6.73)
MCL CONTRACTING, LLC (0.32)
12-1 HIGHWAY AND ENVIRONMENTAL SERVICES, LLC (2.48)
FRANK JR REINFORCEMENT LLC (0.56)
Contract #11163209
Totals1222090.60164487.28681872.9155.7

CountyDEWITT
HighwayVA
FromVARIOUS LOCATIONS
ToIN AUSTIN, MATAGORDA, & WHARTON CO.
CSJ0913-00-088
Proj IDSTP 2012(527)
Work TypeCONSTRUCT CURB RAMPS
 
0.100475081.00577322.1799.9
Work Order06-18-12
Work Began04-05-13
Work Completed
Time Computed10-16-12
Contract Working Days165
Addl Days Granted0
Working Days Charged142
Percent Time Used86
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-00-088
PAVEMENT MARKINGS INC. (1.39)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (3.79)
SPEEDY PAVING (2.40)
Contract #05123217
Totals475081.000.00577322.1799.9

CountyDEWITT
HighwayVA
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ0913-00-092
Proj IDBR 2016(133)
Work TypeUPGRADE BRIDGE AND APPROACH RAILING
 
0.0023378506.553283198.1899.3
CountyDEWITT
HighwayVA
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ0913-00-094
Proj IDNH 2016(134)
Work TypeCONCRETE RAIL REPAIR
 
0.00190833.20155447.4299.9
Work Order11-24-15
Work Began01-18-16
Work Completed
Time Computed12-24-15
Contract Working Days203
Addl Days Granted0
Working Days Charged280
Percent Time Used137
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-00-092
WEST TEXAS RUMBLE STRIP (0.13)
D & S TEXAS ICON CONSTRUCTION, LLC. (4.10)
TINMAN ENTERPRISES (5.32)
ROADSAFE TRAFFIC SYSTEMS, INC. (6.74)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (19.38)
Contract #10153213
Totals3469339.75168197.663438645.6099.9

CountyWHARTON
HighwayCR
FromAT WEST MUSTANG CREEK CR 372
To(CR 372) STR # AA06-59-001
CSJ0913-09-053
Proj IDBR 2012(407)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.074629675.00597441.4098.0
Work Order07-07-15
Work Began11-11-15
Work Completed
Time Computed10-06-15
Contract Working Days75
Addl Days Granted0
Working Days Charged108
Percent Time Used144
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-053
HEMPHILL PILE DRIVING CO., A CORP. (4.74)
ODUM SERVICES, L.P. (3.89)
JUST GROOVING, LTD. (0.25)
CEN TEX HYDROSEED, INC. (0.33)
Contract #05153048
Totals629675.000.00597441.4098.0

CountyWHARTON
HighwayCR
FromAT EAST CARANCAHUA CREEK CR 458
To(CR 322) STR # AA04-58-001
CSJ0913-09-056
Proj IDBR 2012(409)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.061552981.250.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-14-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days73
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HILL COUNTRY BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-056
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05173236
Totals552981.250.000.000.0

CountyWHARTON
HighwayCR
FromAT GUM TREE BRANCH # 2
To(CR 252) STR # AA03-17-003
CSJ0913-09-059
Proj IDBR 2012(412)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.164746501.3010966.801.4
Work Order05-11-17
Work Began00-00-00
Work Completed
Time Computed06-12-17
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-059
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04173029
Totals746501.304112.5510966.801.4

CountyWHARTON
HighwayCR
FromAT DRAW CR 469
To(CR 315) STR # AA04-69-002
CSJ0913-09-060
Proj IDBR 1502(637)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.132902792.10257033.8628.4
Work Order02-22-17
Work Began00-00-00
Work Completed
Time Computed05-23-17
Contract Working Days100
Addl Days Granted0
Working Days Charged9
Percent Time Used9
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-060
LONESTAR TRAFFIC SAFETY, LLC (0.56)
JMHP, INC. (1.99)
Contract #01173252
Totals902792.10233636.74257033.8628.4

CountyWHARTON
HighwayCR
FromAT TRES PALACIOS RIVER CR 413
To(CR 405) STR # AA04-13-001
CSJ0913-09-064
Proj IDBR 2013(439)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.062528449.32534193.9799.9
Work Order12-04-15
Work Began01-14-16
Work Completed
Time Computed01-04-16
Contract Working Days75
Addl Days Granted0
Working Days Charged58
Percent Time Used77
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-064
LONESTAR TRAFFIC SAFETY, LLC (0.37)
FUQUAY, INC. (0.63)
W. W. FOUNDATION DRILLING, LTD. (10.89)
MESA ROD BUSTERS, INC. (0.00)
Contract #08153252
Totals528449.320.00534193.9799.9

CountyWHARTON
HighwayCR
FromAT MUD CREEK CR 419
To(CR 407) STR # AA04-19-001
CSJ0913-09-067
Proj IDBR 2014(677)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.064289824.00276172.2097.1
Work Order09-14-16
Work Began12-05-16
Work Completed
Time Computed10-14-16
Contract Working Days60
Addl Days Granted0
Working Days Charged69
Percent Time Used115
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-067
CEN TEX HYDROSEED, INC. (0.67)
HEMPHILL WBE PILE DRIVING CO. (7.59)
Contract #07163242
Totals289824.000.00276172.2097.1

CountyWHARTON
HighwayCR
FromAT JONES CREEK CR 648
To(CR 457) STR # AA06-48-001
CSJ0913-09-071
Proj IDBR 2014(681)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.068441100.21437751.1799.2
Work Order05-10-16
Work Began07-18-16
Work Completed
Time Computed08-08-16
Contract Working Days75
Addl Days Granted0
Working Days Charged75
Percent Time Used100
Contractor(s)
REXCO CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-071
JUST GROOVING, LTD. (0.22)
ODUM SERVICES, L.P. (2.53)
SPECIALTY DRILLING, LTD. (10.09)
CEN TEX HYDROSEED, INC. (1.78)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.13)
Contract #02163031
Totals441100.210.00437751.1799.2

CountyWHARTON
HighwayCR
FromAT PEACH CREEK (132410AA0294001)
ToWCR 253 (AA0253)
CSJ0913-09-076
Proj IDBR 1502(198)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.130670423.18656767.8197.9
Work Order07-13-16
Work Began09-02-16
Work Completed
Time Computed10-11-16
Contract Working Days120
Addl Days Granted0
Working Days Charged85
Percent Time Used70
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-076
HEMPHILL WBE PILE DRIVING CO. (5.60)
LONESTAR TRAFFIC SAFETY, LLC (0.85)
BRANNAN PAVING CO., LTD. (4.91)
Contract #05163204
Totals670423.180.00656767.8197.9

CountyWHARTON
HighwayCS
FromVARIOUS LOC. ALONG AVE I& NORRIS ST
ToIN THE CITY OF EL CAMPO
CSJ0913-09-081
Proj IDSTP 1602(475)TAPS
Work TypeCONSTRUCT SIDEWALKS
 
1.202311986.00214826.0068.8
Work Order02-09-17
Work Began04-28-17
Work Completed
Time Computed05-10-17
Contract Working Days45
Addl Days Granted0
Working Days Charged26
Percent Time Used57
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-081
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173226
Totals311986.0094808.00214826.0068.8

CountyDEWITT
HighwayCR
FromAT CABEZA CREEK CR 271
To(BACHLE RD) STR AA02-71-003
CSJ0913-17-040
Proj IDBR 1502(215)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.069449866.90340858.8975.7
Work Order02-13-17
Work Began04-14-17
Work Completed
Time Computed05-14-17
Contract Working Days60
Addl Days Granted0
Working Days Charged44
Percent Time Used73
Contractor(s)
TMES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-17-040
HEMPHILL WBE PILE DRIVING CO. (12.88)
Contract #01173015
Totals449866.9049201.79340858.8975.7

CountyDEWITT
HighwayCR
FromAT DRAW CHARCO RD
ToSTR # AA01-16-001
CSJ0913-17-041
Proj IDBR 1502(365)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.067323694.00297070.0095.7
Work Order08-25-16
Work Began10-31-16
Work Completed
Time Computed10-23-16
Contract Working Days45
Addl Days Granted0
Working Days Charged67
Percent Time Used148
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-17-041
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07163213
Totals323694.000.00297070.0095.7

CountyJACKSON
HighwayCR
FromAT ARENOSA CREEK_ CR 325
ToSTR AA01-60-001
CSJ0913-18-028
Proj IDBR 2016(433)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.084925264.60923971.3799.8
Work Order08-01-16
Work Began11-29-16
Work Completed
Time Computed10-27-16
Contract Working Days75
Addl Days Granted6
Working Days Charged78
Percent Time Used96
Contractor(s)
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0913-18-028
ENVIRONMENTAL SAFETY SERVICES, INC. (4.75)
LONE STAR TRAFFIC SERVICE, INC. (0.24)
SHINN & GREGORY, INC. (8.34)
JIMMY EVANS COMPANY, LTD (16.83)
HOUSTON SAWING & DRILLING (0.22)
LONE STAR PAVING (1.93)
GLENN FUQUA, INC. (0.53)
Contract #06163020
Totals925264.60166166.07923971.3799.8

CountyJACKSON
HighwayCR
FromAT LUNIS CREEK CR 443
ToSTR AA02-21-001
CSJ0913-18-029
Proj IDBR 1602(012)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.068462863.850.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-18-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-18-029
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04173016
Totals462863.850.000.000.0

CountyCALHOUN
HighwayCR
FromAT DRAW CR 206
To(GIN ROAD) STR # AA02-06-001
CSJ0913-19-028
Proj IDBR 2012(730)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100416186.67235117.9656.4
Work Order02-22-17
Work Began04-17-17
Work Completed
Time Computed05-23-17
Contract Working Days60
Addl Days Granted0
Working Days Charged35
Percent Time Used58
Contractor(s)
REXCO CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-19-028
HIGHWAY BARRICADES AND SERVICES, LLC (0.78)
D&S TEXAS ICON CONSTRUCTION (4.32)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (10.71)
Contract #01173020
Totals416186.6739210.83235117.9656.4

page 1 | page 2 | page 3 | page 4 | page 5