Monthly State Let Construction Report For Yoakum District As Of Aug 10, 2015 Page 3 Of 5

Last Update: Monday, August 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyDEWITT
Highway SH 119
From FM 108
To SH 72
CSJ 0359-03-025
Proj ID STP 1502(051)
Work Type RESTORE ROADWAY
 
3.718 4573832.63 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-13-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0359-03-025
COWBELL TRAFFIC SERVICE, INC.(0.36%)
FLASHER EQUIPMENT COMPANY(0.24%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.65%)
LONE STAR EROSION CONTROL(0.92%)
MURRAY CONSTRUCTION(0.33%)
Contract # 03153233
Totals 4573832.63 0.00 0.00 0.0

CountyDEWITT
Highway SH 119
From KARNES C/L
To FM 108
CSJ 0359-03-026
Proj ID STP 1502(477)HES
Work Type SAFETY TREAT FIXED OBJECTS, WIDEN
 
7.907 5170038.51 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0359-03-026
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07153025
Totals 5170038.51 0.00 0.00 0.0

CountyAUSTIN
Highway SH 159
From FM 109
To SH 36
CSJ 0408-02-045
Proj ID STP 2015(428)
Work Type ADD SHOULDERS
 
14.079 11278713.11 0.00 108282.33 0.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-10-15
Work Began 07-13-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 417
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 2
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0408-02-045
ROADWAY SPECIALTIES, INC.(2.18%)
WEST TEXAS RUMBLE STRIP(0.16%)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.57%)
Contract # 12143204
Totals 11278713.11 0.00 108282.33 0.9

CountyLAVACA
Highway US 90A
From @ BRUSHY CREEK
To STR # 0446-01-016
CSJ 0446-01-047
Proj ID BR 2015(245)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.606 3321678.02 844444.45 1079259.60 32.4
Work Order 12-11-14
Work Began 00-00-00
Work Completed  
Time Computed 04-10-15
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 18
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0446-01-047
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10143213
Totals 3321678.02 844444.45 1079259.60 32.4

CountyCOLORADO
Highway US 90A
From AT EAST SANDY CREEK
To STR # 0446-02-027
CSJ 0446-02-030
Proj ID BR 2014(212)
Work Type REPLACE BRIDGE AND APPROACHES
 
1.060 3488667.34 516294.09 3289946.18 97.5
Work Order 02-06-14
Work Began 03-21-14
Work Completed  
Time Computed 03-21-14
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 267
Percent Time Used 178
Contractor(s)
FUQUA CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0446-02-030
SHINN & GREGORY, INC.(6.49%)
ROADWAY SPECIALTIES, INC.(3.12%)
JUST GROOVING, LTD.(0.13%)
JAMES CONSTRUCTION GROUP, L.L.C. ( 19.79%)
UNITED PAVEMENT & MARKINGS, LLC(0.52%)
LONESTAR TRAFFIC SAFETY, LLC (0.16%)
CD TRUCKING, INC (4.14%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.12%)
REPUBLIC TRAFFIC SAFETY, INC.(0.60%)
Contract # 11133206
Totals 3488667.34 516294.09 3289946.18 97.5

CountyCOLORADO
Highway US 90A
From LAVACA COUNTY LINE
To 2.5 MI. WEST OF SH 71
CSJ 0446-02-035
Proj ID STP 1502(010)
Work Type ACP OVERLAY
 
13.157 3589079.85 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-21-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
REXCO CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0446-02-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153211
Totals 3589079.85 0.00 0.00 0.0

CountyCOLORADO
Highway US 90A
From SH 71
To EAST A STREET IN EAGLE LAKE
CSJ 0446-03-049
Proj ID STP 1502(050)
Work Type CONSTRUCT SUPER 2 LANES
 
7.929 6297396.25 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-19-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 183
Addl Days Granted 0
Working Days Charged 2
Percent Time Used 1
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0446-03-049
WEST TEXAS RUMBLE STRIP(0.20%)
LONE STAR TRAFFIC SERVICE, INC.(0.19%)
M.V. HENKE ENTERPRISES, INC. (0.59%)
RICE ENVIRONMENTAL SERVICES(0.69%)
DUSTROL, INC.(0.37%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.26%)
SCMU (3.28%)
Contract # 03153232
Totals 6297396.25 0.00 0.00 0.0

CountyFAYETTE
Highway IH 10
From US 77
To COLORADO C/L (EASTBOUND LANES)
CSJ 0535-07-048
Proj ID IM 0106(102)
Work Type ASPHALTIC CONCRETE PAVEMENT
 
15.334 7464747.06 2168562.51 5330359.53 71.4
Work Order 03-10-15
Work Began 05-03-15
Work Completed  
Time Computed 05-01-15
Contract Working Days 92
Addl Days Granted 0
Working Days Charged 50
Percent Time Used 54
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0535-07-048
ROADSAFE TRAFFIC SYSTEMS, INC. (2.33%)
CPAVE, INC.(1.99%)
Contract # 01153228
Totals 7464747.06 2168562.51 5330359.53 71.4

CountyCOLORADO
Highway FM 102
From SENIOR BRIDGE ROAD
To WHARTON COUNTY LINE
CSJ 0709-01-024
Proj ID STP 2013(918)
Work Type PAVEMENT REPAIR & SHOULDER WIDENING
 
5.655 3248432.42 0.00 3140019.95 99.2
Work Order 10-17-13
Work Began 02-19-14
Work Completed  
Time Computed 12-16-13
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 190
Percent Time Used 180
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0709-01-024
KOSSMAN CONTRACTING CO., INC.(0.60%)
MURRAY CONSTRUCTION(0.32%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.86%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.16%)
M.V. HENKE ENTERPRISES, INC. (0.43%)
WEST TEXAS RUMBLE STRIP(0.11%)
DUSTROL, INC.(2.69%)
Contract # 07133048
Totals 3248432.42 0.00 3140019.95 99.2

CountyWHARTON
Highway FM 102
From 0.27 MI. WEST OF FM 960
To 0.53 MI. WEST OF WHARTON CITY LIMIT
CSJ 0709-02-047
Proj ID STP 2013(073)
Work Type ADD SHOULDERS
 
4.109 2875006.16 0.00 2874765.70 99.9
Work Order 11-01-12
Work Began 01-07-13
Work Completed  
Time Computed 12-31-12
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 126
Percent Time Used 120
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0709-02-047
BATTERSON,LLP(3.79%)
ENVIRONMENTAL SAFETY SERVICES, INC.(7.45%)
SEMARCK LANDSCAPE SERVICES, INC. (0.64%)
Contract # 09123247
Totals 2875006.16 0.00 2874765.70 99.9

CountyGONZALES
Highway FM 108
From AT DRAW
To STR # 0715-01-008
CSJ 0715-01-017
Proj ID BR 2013(700)
Work Type WIDEN BRIDGE AND APPROACHES
 
0.293 1055377.51 0.00 1126538.75 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-09-13
Work Began 10-28-13
Work Completed 02-02-15
Time Computed 09-25-13
Contract Working Days 90
Addl Days Granted 10
Working Days Charged 100
Percent Time Used 100
Contractor(s)
BEAR CREEK CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0715-01-017
ROADWAY SPECIALTIES, INC.(3.62%)
D. I. J. CONSTRUCTION, INC.(1.13%)
N-LINE TRAFFIC MAINTENANCE, L.P. (2.70%)
LONE STAR HIGHWAY PRODUCTS, INC. (1.04%)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.( 22.67%)
Contract # 05133214
Totals 1055377.51 0.00 1126538.75 100.0

CountyGONZALES
Highway FM 108
From AT ELM CREEK BRANCH
To STR# 0715-02-014
CSJ 0715-02-013
Proj ID BR 2013(701)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.413 1904944.76 110201.38 1828738.54 96.7
Work Order 09-06-13
Work Began 11-25-13
Work Completed  
Time Computed 09-22-13
Contract Working Days 220
Addl Days Granted 1
Working Days Charged 240
Percent Time Used 108
Contractor(s)
HILL COUNTRY BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0715-02-013
AVAILABLE CONSTRUCTION AND TRANSPORT SERVICES, INC.( 27.69%)
FLASHER EQUIPMENT COMPANY(0.92%)
JUST GROOVING, LTD.(0.29%)
O & S TRAFFIC SUPPLIES (0.57%)
J R RAMON, INC.(2.28%)
ROADWAY SPECIALTIES, INC.(3.66%)
VOGES DRILLING CO. (5.25%)
PIPE WHOLESALERS OF TEXAS, INC.(0.07%)
DOUBLE S PAVING, INC.(5.93%)
Contract # 05133218
Totals 1904944.76 110201.38 1828738.54 96.7

CountyFAYETTE
Highway FM 153
From BASTROP COUNTY LINE
To US 77
CSJ 0807-03-032
Proj ID STP 2015(429)HRR
Work Type SAFETY TREAT FIXED OBJECTS
 
11.432 488019.50 93402.92 327905.42 67.1
Work Order 01-28-15
Work Began 04-29-15
Work Completed  
Time Computed 04-29-15
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 50
Percent Time Used 66
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0807-03-032
AUSTEX TREE SERVICE, INC.(4.39%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.83%)
Contract # 12143011
Totals 488019.50 93402.92 327905.42 67.1

CountyVICTORIA
Highway FM 447
From US 87
To FM 236
CSJ 0842-02-021
Proj ID STP 1302(043)
Work Type REPAIR & WIDEN ROADWAY
 
5.401 2015294.58 77961.96 2121880.24 99.9
Work Order 12-03-13
Work Began 01-16-14
Work Completed  
Time Computed 01-16-14
Contract Working Days 165
Addl Days Granted 4
Working Days Charged 174
Percent Time Used 102
Contractor(s)
REXCO CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0842-02-021
ROADSAFE TRAFFIC SYSTEMS, INC. (5.83%)
ROADWAY SPECIALTIES, INC.(6.05%)
LHOIST NORTH AMERICA (0.00%)
INGRAM READY MIX (0.00%)
ALAMO CONCRETE (0.00%)
BRANNAN PAVING CO., LTD. (0.00%)
Contract # 09133234
Totals 2015294.58 77961.96 2121880.24 99.9

CountyDEWITT
Highway VA
From VARIOUS LOCATIONS
To IN AUSTIN, MATAGORDA, & WHARTON CO.
CSJ 0913-00-088
Proj ID STP 2012(527)
Work Type CONSTRUCT CURB RAMPS
 
0.100 475081.00 0.00 577322.17 99.9
Work Order 06-18-12
Work Began 04-05-13
Work Completed  
Time Computed 10-16-12
Contract Working Days 165
Addl Days Granted 0
Working Days Charged 142
Percent Time Used 86
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-00-088
PAVEMENT MARKINGS INC. (1.39%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (3.79%)
SPEEDY PAVING(2.40%)
Contract # 05123217
Totals 475081.00 0.00 577322.17 99.9

CountyWHARTON
Highway CR
From AT MUD CREEK CR 423
To (CR 409) STR # AA04-23-001
CSJ 0913-09-050
Proj ID BR 1102(036)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.066 348651.60 0.00 43484.34 12.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-10-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-050
ODUM SERVICES, L.P.(3.96%)
CEN TEX HYDROSEED, INC.(0.63%)
SPECIALTY DRILLING, LTD. (8.05%)
Contract # 12143228
Totals 348651.60 0.00 43484.34 12.4

CountyWHARTON
Highway CR
From AT WILLOW CREEK CR 411
To (CR 424) STR # AA04-11-002
CSJ 0913-09-051
Proj ID BR 1102(038)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.071 448631.00 22940.00 385305.00 85.8
Work Order 02-10-15
Work Began 03-09-15
Work Completed  
Time Computed 03-09-15
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 73
Percent Time Used 97
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-051
HEMPHILL PILE DRIVING CO., A CORP. (9.69%)
C. W. & A.,INC (5.20%)
CEN TEX HYDROSEED, INC.(0.69%)
ODUM SERVICES, L.P.(3.10%)
Contract # 12143220
Totals 448631.00 22940.00 385305.00 85.8

CountyWHARTON
Highway CR
From AT WEST MUSTANG CREEK CR 372
To (CR 372) STR # AA06-59-001
CSJ 0913-09-053
Proj ID BR 2012(407)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.074 629675.00 8076.73 8076.73 1.2
Work Order 07-07-15
Work Began 00-00-00
Work Completed  
Time Computed 10-06-15
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-053
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153048
Totals 629675.00 8076.73 8076.73 1.2

CountyWHARTON
Highway CR
From AT BAUGHMAN SLOUGH CR 231
To (WILKE RD) STR # AA02-66-001
CSJ 0913-09-057
Proj ID BR 2012(410)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.093 465982.00 27034.00 357739.83 76.7
Work Order 01-22-15
Work Began 05-05-15
Work Completed  
Time Computed 05-05-15
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 36
Percent Time Used 48
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-057
LONESTAR TRAFFIC SAFETY, LLC (0.41%)
ODUM SERVICES, L.P.(3.84%)
JUST GROOVING, LTD.(0.28%)
Contract # 12143028
Totals 465982.00 27034.00 357739.83 76.7

CountyWHARTON
Highway CR
From AT SANDY BRANCH # 2 CR 324
To (CR 207) STR # AA03-24-001
CSJ 0913-09-058
Proj ID BR 2012(411)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.068 524660.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 67
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-058
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153257
Totals 524660.50 0.00 0.00 0.0

page 1 | page 2 | page 3 | page 4 | page 5