Monthly State Let Construction Report For Yoakum District As Of Nov 9, 2016 Page 3 Of 4

Last Update: Wednesday, November 9, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyDEWITT
Highway SH 119
From FM 108
To SH 72
CSJ 0359-03-025
Proj ID STP 1502(051)
Work Type RESTORE ROADWAY
 
3.718 4573832.63 0.00 4584957.51 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-13-15
Work Began 08-10-15
Work Completed  
Time Computed 08-10-15
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 134
Percent Time Used 148
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0359-03-025
COWBELL TRAFFIC SERVICE, INC.(0.36%)
FLASHER EQUIPMENT COMPANY(0.24%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.65%)
LONE STAR EROSION CONTROL(0.92%)
MURRAY CONSTRUCTION(0.33%)
BILL HALL JR. TRUCKING, LTD. (0.00%)
RAMI MATERIALS TRANSPORT, LLC(0.00%)
JUAN DEANDA TRUCKING, LLC DBA JUAN DEANDA TRUCKING (0.00%)
Contract # 03153233
Totals 4573832.63 0.00 4584957.51 99.9

CountyDEWITT
Highway SH 119
From KARNES C/L
To FM 108
CSJ 0359-03-026
Proj ID STP 1502(477)HES
Work Type SAFETY TREAT FIXED OBJECTS, WIDEN
 
7.907 5170038.51 290393.71 2781430.39 53.7
Work Order 10-20-15
Work Began 03-04-16
Work Completed  
Time Computed 02-17-16
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 129
Percent Time Used 86
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0359-03-026
COWBELL TRAFFIC SERVICES, INC. (0.37%)
D&S TEXAS ICON CONSTRUCTION, LLC (1.87%)
MURRAY CONSTRUCTION(0.33%)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.25%)
ROADWAY SPECIALTIES, INC.(2.22%)
Contract # 07153025
Totals 5170038.51 290393.71 2781430.39 53.7

CountyAUSTIN
Highway SH 159
From FM 109
To SH 36
CSJ 0408-02-045
Proj ID STP 2015(428)
Work Type ADD SHOULDERS
 
14.079 11278713.11 179591.33 5148687.70 45.6
Work Order 02-10-15
Work Began 07-13-15
Work Completed  
Time Computed 06-10-15
Contract Working Days 417
Addl Days Granted 0
Working Days Charged 167
Percent Time Used 40
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0408-02-045
ROADWAY SPECIALTIES, INC.(2.18%)
WEST TEXAS RUMBLE STRIP(0.16%)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.57%)
Contract # 12143204
Totals 11278713.11 179591.33 5148687.70 45.6

CountyVICTORIA
Highway SH 185
From AT FM 1432
To .
CSJ 0432-02-088
Proj ID STP 1602(278)HESG
Work Type INSTALL TRAFFIC SIGNAL
 
0.001 193412.35 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-18-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0432-02-088
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07163210
Totals 193412.35 0.00 0.00 0.0

CountyLAVACA
Highway US 90A
From @ BRUSHY CREEK
To STR # 0446-01-016
CSJ 0446-01-047
Proj ID BR 2015(245)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.606 3321678.02 138279.03 2945531.62 91.8
Work Order 12-11-14
Work Began 06-08-15
Work Completed  
Time Computed 04-10-15
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 258
Percent Time Used 172
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0446-01-047
ANGEL BROTHERS ENTERPRISES, LTD. (9.33%)
ROADWAY SPECIALTIES, INC.(1.29%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.52%)
HEMPHILL PILE DRIVING CO., A CORP. (3.49%)
FLASHER EQUIPMENT COMPANY(0.29%)
Contract # 10143213
Totals 3321678.02 138279.03 2945531.62 91.8

CountyCOLORADO
Highway US 90A
From AT EAST SANDY CREEK
To STR # 0446-02-027
CSJ 0446-02-030
Proj ID BR 2014(212)
Work Type REPLACE BRIDGE AND APPROACHES
 
1.060 3488667.34 0.00 3343192.71 99.2
Work Order 02-06-14
Work Began 03-21-14
Work Completed  
Time Computed 03-21-14
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 273
Percent Time Used 182
Contractor(s)
FUQUA CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0446-02-030
SHINN & GREGORY, INC.(6.49%)
ROADWAY SPECIALTIES, INC.(3.12%)
JUST GROOVING, LTD.(0.13%)
JAMES CONSTRUCTION GROUP, L.L.C. ( 19.79%)
UNITED PAVEMENT & MARKINGS, LLC(0.52%)
LONESTAR TRAFFIC SAFETY, LLC (0.16%)
CD TRUCKING, INC (4.14%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.12%)
REPUBLIC TRAFFIC SAFETY, INC.(0.60%)
Contract # 11133206
Totals 3488667.34 0.00 3343192.71 99.2

CountyCOLORADO
Highway US 90A
From SH 71
To EAST A STREET IN EAGLE LAKE
CSJ 0446-03-049
Proj ID STP 1502(050)
Work Type CONSTRUCT SUPER 2 LANES
 
7.929 6297396.25 541167.61 6693818.14 99.9
Work Order 05-19-15
Work Began 08-26-15
Work Completed  
Time Computed 08-26-15
Contract Working Days 183
Addl Days Granted 0
Working Days Charged 214
Percent Time Used 116
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0446-03-049
WEST TEXAS RUMBLE STRIP(0.20%)
M.V. HENKE ENTERPRISES, INC. (0.59%)
RICE ENVIRONMENTAL SERVICES(0.69%)
DUSTROL, INC.(0.37%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.26%)
SCMU (3.28%)
LONESTAR TRAFFIC SAFETY, LLC (0.19%)
ROADWAY SPECIALTIES, INC.(0.84%)
Contract # 03153232
Totals 6297396.25 541167.61 6693818.14 99.9

CountyCALHOUN
Highway FM 1090
From 0.3 MI N OF FM 3084
To 0.3 MI S OF FM 3084
CSJ 0515-03-049
Proj ID STP 2016(430)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
0.600 170325.18 32460.76 134976.78 79.9
CountyCALHOUN
Highway FM 2433
From US 87
To SH 35
CSJ 0580-02-012
Proj ID STP 2016(431)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
2.685 174465.49 0.00 143333.87 82.1
Work Order 03-01-16
Work Began 05-05-16
Work Completed  
Time Computed 05-31-16
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 62
Percent Time Used 103
Contractor(s)
REXCO CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0515-03-049
FUQUAY, INC. (2.85%)
HIGHWAY BARRICADES AND SERVICES, LLC (3.78%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (3.31%)
Contract # 12153011
Totals 344790.67 32460.76 278310.65 81.0

CountyMATAGORDA
Highway FM 457
From CANEY DRIVE IN SARGENT
To 0.1 MI. NORTH OF GIWW
CSJ 0605-01-061
Proj ID STP 2016(279)
Work Type ADD SHOULDERS
 
3.111 814911.00 273892.09 450996.27 56.2
Work Order 12-21-15
Work Began 07-20-16
Work Completed  
Time Computed 03-20-16
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 57
Percent Time Used 126
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0605-01-061
WIMMS ENVIRONMENTAL, INC.(9.75%)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.16%)
MURRAY CONSTRUCTION(1.68%)
SCMU (6.30%)
Contract # 11153217
Totals 814911.00 273892.09 450996.27 56.2

CountyAUSTIN
Highway FM 109
From 1.5 MI S OF FM 2502_(WITTNER RD)
To 3.7 MI S OF FM 2502_(MERTZ LN)
CSJ 0716-01-045
Proj ID STP 1602(469)HES
Work Type INCREASE SUPERELEVATION
 
2.205 605947.89 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-20-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 20
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0716-01-045
INTERSTATE BARRICADES & MARKINGS, INC. (0.80%)
BATTERSON,LLP(3.09%)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.( 10.88%)
WEST TEXAS RUMBLE STRIP(0.69%)
Contract # 08163027
Totals 605947.89 0.00 0.00 0.0

CountyCOLORADO
Highway FM 109
From AT REDGATE CREEK
To STR # 0716-02-011
CSJ 0716-02-038
Proj ID BR 1602(086)
Work Type WIDEN BRIDGE AND APPROACHES
 
0.185 533118.53 117077.00 220909.75 41.4
Work Order 06-22-16
Work Began 09-16-16
Work Completed  
Time Computed 07-22-16
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 21
Percent Time Used 42
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0716-02-038
ROADSAFE TRAFFIC SYSTEMS, INC. (0.60%)
ROADWAY SPECIALTIES, INC.(5.03%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.50%)
Contract # 05163010
Totals 533118.53 117077.00 220909.75 41.4

CountyGONZALES
Highway FM 443
From AT ROCKY CREEK
To STR # 0839-01-002
CSJ 0839-01-015
Proj ID BR 2017(259)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.321 1222090.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HILL COUNTRY BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0839-01-015
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11163209
Totals 1222090.60 0.00 0.00 0.0

CountyVICTORIA
Highway FM 444
From US 77
To US 59
CSJ 0840-05-021
Proj ID STP 2016(966)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
17.650 810634.54 104176.30 314682.44 38.8
Work Order 06-02-16
Work Began 07-18-16
Work Completed  
Time Computed 08-31-16
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 50
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0840-05-021
FLASHER EQUIPMENT COMPANY(1.21%)
STAFF CONCRETE ( 63.41%)
ROADWAY SPECIALTIES, INC.( 14.47%)
Contract # 04163004
Totals 810634.54 104176.30 314682.44 38.8

CountyDEWITT
Highway VA
From VARIOUS LOCATIONS
To IN AUSTIN, MATAGORDA, & WHARTON CO.
CSJ 0913-00-088
Proj ID STP 2012(527)
Work Type CONSTRUCT CURB RAMPS
 
0.100 475081.00 0.00 577322.17 99.9
Work Order 06-18-12
Work Began 04-05-13
Work Completed  
Time Computed 10-16-12
Contract Working Days 165
Addl Days Granted 0
Working Days Charged 142
Percent Time Used 86
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-00-088
PAVEMENT MARKINGS INC. (1.39%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (3.79%)
SPEEDY PAVING(2.40%)
Contract # 05123217
Totals 475081.00 0.00 577322.17 99.9

CountyDEWITT
Highway VA
From DISTRICTWIDE
To DISTRICTWIDE
CSJ 0913-00-092
Proj ID BR 2016(133)
Work Type UPGRADE BRIDGE AND APPROACH RAILING
 
0.002 3378506.55 56178.88 2075684.92 61.4
CountyDEWITT
Highway VA
From DISTRICTWIDE
To DISTRICTWIDE
CSJ 0913-00-094
Proj ID NH 2016(134)
Work Type CONCRETE RAIL REPAIR
 
0.001 90833.20 0.00 84990.50 93.5
Work Order 11-24-15
Work Began 01-18-16
Work Completed  
Time Computed 12-24-15
Contract Working Days 203
Addl Days Granted 0
Working Days Charged 150
Percent Time Used 73
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-00-092
WEST TEXAS RUMBLE STRIP(0.13%)
D & S TEXAS ICON CONSTRUCTION, LLC.(4.10%)
TINMAN ENTERPRISES (5.32%)
ROADSAFE TRAFFIC SYSTEMS, INC. (6.74%)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.( 19.38%)
Contract # 10153213
Totals 3469339.75 56178.88 2160675.42 62.2

CountyWHARTON
Highway CR
From AT WEST MUSTANG CREEK CR 372
To (CR 372) STR # AA06-59-001
CSJ 0913-09-053
Proj ID BR 2012(407)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.074 629675.00 0.00 597441.40 98.0
Work Order 07-07-15
Work Began 11-11-15
Work Completed  
Time Computed 10-06-15
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 108
Percent Time Used 144
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-053
HEMPHILL PILE DRIVING CO., A CORP. (4.74%)
ODUM SERVICES, L.P.(3.89%)
JUST GROOVING, LTD.(0.25%)
CEN TEX HYDROSEED, INC.(0.33%)
Contract # 05153048
Totals 629675.00 0.00 597441.40 98.0

CountyWHARTON
Highway CR
From AT BAUGHMAN SLOUGH CR 231
To (WILKE RD) STR # AA02-66-001
CSJ 0913-09-057
Proj ID BR 2012(410)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.093 465982.00 0.00 461397.73 99.0
Work Order 01-22-15
Work Began 05-05-15
Work Completed  
Time Computed 05-22-15
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 68
Percent Time Used 90
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-057
LONESTAR TRAFFIC SAFETY, LLC (0.41%)
ODUM SERVICES, L.P.(3.84%)
JUST GROOVING, LTD.(0.28%)
CEN TEX HYDROSEED, INC.(0.28%)
CRAIG & HEIDT, INC.(7.29%)
CPAVE, INC.(0.12%)
Contract # 12143028
Totals 465982.00 0.00 461397.73 99.0

CountyWHARTON
Highway CR
From AT SANDY BRANCH # 2 CR 324
To (CR 207) STR # AA03-24-001
CSJ 0913-09-058
Proj ID BR 2012(411)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.068 524660.50 0.00 495515.50 94.4
Work Order 08-10-15
Work Began 08-19-15
Work Completed  
Time Computed 08-19-15
Contract Working Days 67
Addl Days Granted 0
Working Days Charged 62
Percent Time Used 92
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-058
LONESTAR TRAFFIC SAFETY, LLC (0.42%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.43%)
MESA ROD BUSTERS, INC. (0.28%)
JMHP, INC. (2.77%)
HOUSTON SAWING & DRILLING(0.33%)
Contract # 06153257
Totals 524660.50 0.00 495515.50 94.4

CountyWHARTON
Highway CR
From AT TRES PALACIOS RIVER CR 413
To (CR 405) STR # AA04-13-001
CSJ 0913-09-064
Proj ID BR 2013(439)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.062 528449.32 0.00 534193.97 99.9
Work Order 12-04-15
Work Began 01-14-16
Work Completed  
Time Computed 01-04-16
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 58
Percent Time Used 77
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-064
LONESTAR TRAFFIC SAFETY, LLC (0.37%)
FUQUAY, INC. (0.63%)
W. W. FOUNDATION DRILLING, LTD.( 10.89%)
MESA ROD BUSTERS, INC. (0.00%)
Contract # 08153252
Totals 528449.32 0.00 534193.97 99.9

CountyWHARTON
Highway CR
From AT MUD CREEK CR 419
To (CR 407) STR # AA04-19-001
CSJ 0913-09-067
Proj ID BR 2014(677)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.064 289824.00 0.00 0.00 0.0
Work Order 09-14-16
Work Began 00-00-00
Work Completed  
Time Computed 10-14-16
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-067
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07163242
Totals 289824.00 0.00 0.00 0.0