Monthly State Let Construction Report For Yoakum District As Of Aug 11, 2017 Page 2 Of 6

Last Update: Friday, September 22, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyDEWITT
HighwayUS 87
FromGUADALUPE RIVER RELIEF BRIDGE
ToSH 72
CSJ0143-08-097
Proj IDNH 2017(700)
Work TypeWIDEN ROADWAY
 
1.7293015734.98949859.0831.4
Work Order03-16-17
Work Began05-24-17
Work Completed
Time Computed06-14-17
Contract Working Days148
Addl Days Granted0
Working Days Charged35
Percent Time Used23
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0143-08-097
FLASHER EQUIPMENT COMPANY (2.37)
HILL COUNTRY BRIDGE, INC (18.97)
ROADWAY SPECIALTIES, INC. (2.94)
EGGEMEYER LAND CLEARING, LLC (2.27)
Contract #02173212
Totals3015734.98409485.43949859.0831.4

CountyDEWITT
HighwayUS 87
From2.27 MILES SOUTH OF US 183
ToIRISH CREEK BRIDGE
CSJ0143-09-069
Proj IDNH 2017(831)
Work TypeACP OVERLAY
 
4.2411812578.620.000.0
Work Order04-24-17
Work Began00-00-00
Work Completed
Time Computed05-24-17
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0143-09-069
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03173215
Totals1812578.620.000.000.0

CountyVICTORIA
HighwayUS 87
From0.62 MI. NORTH OF FM 447
To0.65 MI. SOUTH OF FM 447
CSJ0143-10-050
Proj IDNH 1602(277)
Work TypeCONSTRCT GRADE SEPARATED INTERCHNGE
 
1.26810878661.264042640.9937.1
Work Order08-22-16
Work Began12-14-16
Work Completed
Time Computed11-20-16
Contract Working Days240
Addl Days Granted2
Working Days Charged119
Percent Time Used49
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0143-10-050
CHEROKEE SERVICES (0.07)
COWBELL TRAFFIC SERVICES, INC. (0.08)
THE LEVY COMPANY, L.P. (3.38)
MCL CONTRACTING, LLC (0.24)
MURRAY CONSTRUCTION (0.14)
PRIMATE CONSTRUCTION, INC. (0.05)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.54)
ROADWAY SPECIALTIES, INC. (1.42)
W. W. FOUNDATION DRILLING, LTD. (0.59)
STRIPE-A-ZONE, INC. (0.08)
FLASHER EQUIPMENT COMPANY (0.02)
Contract #07163005
Totals10878661.26411741.614042640.9937.1

CountyGONZALES
HighwayUS 183
FromBU 183 NORTH
ToCONE STREET IN GONZALES
CSJ0153-02-039
Proj IDNH 2013(591)
Work TypeACP OVERLAY
 
3.3351398785.731388701.2999.9
Work Order05-04-15
Work Began04-11-16
Work Completed
Time Computed06-01-15
Contract Working Days30
Addl Days Granted0
Working Days Charged43
Percent Time Used143
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0153-02-039
FLASHER EQUIPMENT COMPANY (4.44)
CHEROKEE SERVICES (2.64)
Contract #03153015
Totals1398785.730.001388701.2999.9

CountyDEWITT
HighwayUS 183
FromFM 2718
ToGOLIAD C/L
CSJ0155-01-038
Proj IDNH 1502(123)
Work TypePAVEMENT REPAIR AND RESURFACING
 
11.3364639995.064595666.3199.6
Work Order06-18-15
Work Began12-18-15
Work Completed
Time Computed10-17-15
Contract Working Days60
Addl Days Granted0
Working Days Charged88
Percent Time Used146
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0155-01-038
CHEROKEE SERVICES (0.66)
COWBELL TRAFFIC SERVICES, INC. (0.87)
D&S TEXAS ICON CONSTRUCTION (0.08)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.77)
INTERSTATE BARRICADES & MARKINGS, INC. (1.71)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.17)
ROADWAY SPECIALTIES, INC. (0.08)
EGGEMEYER LAND CLEARING, LLC (0.31)
Contract #05153017
Totals4639995.06525.694595666.3199.6

CountyMATAGORDA
HighwaySH 35
From0.75 MI. N. OF CHANNEL INDUSTRY RD.
ToSH 71
CSJ0179-06-042
Proj IDSTP 1402(090)HESG
Work TypeSAFETY TREAT FIXED OBJECTS
 
12.803494554.71519315.7099.9
CountyMATAGORDA
HighwaySH 71
FromSH 111
ToSH 35
CSJ0266-07-020
Proj IDSTP 1402(091)HESG
Work TypeSAFETY TREAT FIXED OBJECTS
 
3.981155355.94148368.6495.5
Work Order10-17-14
Work Began09-08-15
Work Completed
Time Computed02-14-15
Contract Working Days60
Addl Days Granted27
Working Days Charged87
Percent Time Used100
Contractor(s)
ACE ASPHALT OF ARIZONA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0179-06-042
RICE ENVIRONMENTAL SERVICES (2.08)
JMHP, INC. (13.55)
BEAR CREEK CONSTRUCTION, LLC (20.56)
Contract #08143232
Totals649910.650.00667684.3499.9

CountyCALHOUN
HighwaySH 35
FromLAVACA BAY CAUSEWAY
ToNBI# 13-029-0-0179-10-061
CSJ0179-10-105
Proj IDBR 1502(288)
Work TypeREHABILITATE BRIDGE
 
2.25416253957.066407085.3739.4
Work Order03-29-16
Work Began05-25-16
Work Completed
Time Computed06-27-16
Contract Working Days500
Addl Days Granted0
Working Days Charged234
Percent Time Used46
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0179-10-105
HIGHWAY BARRICADES AND SERVICES, LLC (0.17)
MARINE TECH SERVICES, LLC (12.85)
SALT WATER SALVAGE (11.38)
M&J OF PINELLAS COUNTY, INC. (12.85)
Contract #12153209
Totals16253957.06595747.196407085.3739.4

CountyMATAGORDA
HighwayBS 35-H
FromSH 35
ToSH 35 WEST OF PALACIOS
CSJ0179-14-008
Proj IDSTP 2017(204)
Work TypeACP OVERLAY AND SHOULDER WIDENING
 
3.6171611272.540.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0179-14-008
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173034
Totals1611272.540.000.000.0

CountyAUSTIN
HighwaySH 36
FromORANGE HILL RD.
ToCR 380 (MIXVILLE ROAD)
CSJ0187-03-064
Proj IDNH 1502(127)
Work TypeCONSTRUCT AUXILLARY LANES
 
8.82110535006.214935863.5446.8
Work Order12-01-15
Work Began04-04-16
Work Completed
Time Computed03-30-16
Contract Working Days339
Addl Days Granted62
Working Days Charged256
Percent Time Used63
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0187-03-064
ROADWAY SPECIALTIES, INC. (0.54)
WILLOW CITY SIGN & RAIL, INC. (1.30)
WEST TEXAS RUMBLE STRIP (0.12)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.20)
INTERSTATE BARRICADES & MARKINGS, INC. (1.27)
SCMU (9.41)
M.V. HENKE ENTERPRISES, INC. (1.84)
Contract #05153207
Totals10535006.21574487.504935863.5446.8

CountyCOLORADO
HighwayFM 155
FromFM 2434
To1 MI S OF FM 532
CSJ0211-10-042
Proj IDSTP 2017(484)HES
Work TypeINCREASE SUPERELEVATION
 
8.540714920.82213905.8329.9
Work Order03-01-17
Work Began06-12-17
Work Completed
Time Computed05-30-17
Contract Working Days40
Addl Days Granted0
Working Days Charged28
Percent Time Used70
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0211-10-042
D. I. J. CONSTRUCTION, INC. (2.63)
DELGADO"S CONSTRUCTION (18.91)
EGGEMEYER LAND CLEARING, LLC (2.73)
ROADWAY SPECIALTIES, INC. (4.16)
AREA WIDE PROTECTIVE, INC. (0.81)
Contract #01173205
Totals714920.82148154.41213905.8329.9

CountyWHARTON
HighwaySH 60
FromFM 2919
To0.2 MI N OF BU 59-R(W. BERNARD RD)
CSJ0240-03-036
Proj IDSTP 1702(486)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
20.7861947826.260.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-08-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days179
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SB CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 0240-03-036
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173042
Totals1947826.260.000.000.0

CountyMATAGORDA
HighwaySH 60
From@ GRACE ST
ToIN BAY CITY
CSJ0241-02-053
Proj IDSTP 2017(319)HES
Work TypeIMPROVE TRAFFIC SIGNAL
 
0.002306857.4550506.7116.4
Work Order02-13-17
Work Began00-00-00
Work Completed
Time Computed05-14-17
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0241-02-053
STRIPE LINES, INC. (2.02)
SOUTH RANGER CONSTRUCTION, INC. (6.44)
Contract #12163011
Totals306857.453230.0150506.7116.4

CountyMATAGORDA ETC
HighwaySH 60 ETC
From0.1 MI S OF FM 2668
To2.867 MI S OF FM 2668
CSJ0241-03-025
Proj IDSTP 2017(165)HESG
Work TypeMILLED CENTERLINE RUMBLE STRIPS
 
44.406100967.0399024.1598.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-29-16
Work Began05-11-17
Work Completed
Time Computed02-26-17
Contract Working Days30
Addl Days Granted0
Working Days Charged14
Percent Time Used46
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0241-03-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10163223
Totals100967.030.0099024.1598.0

CountyFAYETTE
HighwaySH 71
FromBASTROP C/L
To0.051 MI. WEST OF PRAIRIE VALLEY RD
CSJ0265-07-049
Proj IDNH 1702(642)
Work TypeACP OVERLAY
 
7.5762399994.550.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0265-07-049
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173034
Totals2399994.550.000.000.0

CountyFAYETTE
HighwaySH 71
From0.051 MI W OF PRAIRIE VLY RD(CR 516
To0.698 MI WEST OF BU 71-E
CSJ0265-08-065
Proj IDNH 1602(186)
Work TypeACP OVERLAY
 
5.3341780622.901963703.9799.9
Work Order06-22-16
Work Began08-05-16
Work Completed
Time Computed07-07-16
Contract Working Days30
Addl Days Granted11
Working Days Charged38
Percent Time Used92
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0265-08-065
ROADSAFE TRAFFIC SYSTEMS, INC. (2.91)
WEST TEXAS RUMBLE STRIP (0.50)
Contract #05163035
Totals1780622.900.001963703.9799.9

CountyFAYETTE
HighwaySH 71
FromSH 159
ToCOLORADO C/L
CSJ0266-01-074
Proj IDSTP 2017(256)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
24.367276120.00265875.2696.2
Work Order12-07-16
Work Began03-27-17
Work Completed
Time Computed03-07-17
Contract Working Days30
Addl Days Granted12
Working Days Charged42
Percent Time Used100
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0266-01-074
LONESTAR TRAFFIC SAFETY, LLC (3.20)
ENVIRONMENTAL SAFETY SERVICES, INC. (38.41)
Contract #11163007
Totals276120.000.00265875.2696.2

CountyFAYETTE ETC
HighwaySH 71 ETC
FromAT FM 955
To.
CSJ0266-01-075
Proj IDSTP 2017(486)HES
Work TypeSAFETY LIGHTING AT INTERSECTION
 
2.801681093.20167238.0024.5
Work Order02-15-17
Work Began00-00-00
Work Completed
Time Computed05-16-17
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
F & W ELECTRICAL CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0266-01-075
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173251
Totals681093.20167238.00167238.0024.5

CountyCOLORADO
HighwaySH 71
FromSOUTH OF RATLIFF CREEK
To0.2 MILES N. OF US 90A
CSJ0266-03-029
Proj IDSTP 2016(621)
Work TypeCONSTRUCT SUPER 2 LANES
 
9.8059120997.862549811.4727.9
Work Order03-15-16
Work Began08-25-16
Work Completed
Time Computed06-13-16
Contract Working Days226
Addl Days Granted0
Working Days Charged164
Percent Time Used72
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0266-03-029
ROADSAFE TRAFFIC SYSTEMS, INC. (2.13)
WEST TEXAS RUMBLE STRIP (0.11)
MV HENKE COMPANY, LLC (0.83)
SCMU (5.97)
Contract #01163042
Totals9120997.8648816.902549811.4727.9

CountyWHARTON
HighwaySH 71
From0.021 MI. S OF FM 2674
To0.019 MI. N OF CR 405
CSJ0266-06-047
Proj IDSTP 2017(972)
Work TypePAVEMENT REPAIR AND SURFACING
 
3.2841713209.170.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-18-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0266-06-047
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04173228
Totals1713209.170.000.000.0

CountyMATAGORDA
HighwaySH 71
FromWHARTON COUNTY LINE
ToTO 0.1 MI. NORTH OF SH 35
CSJ0266-07-021
Proj IDSTP 2017(173)
Work TypeADD SHOULDERS
 
9.3083097496.792035273.0165.7
Work Order11-22-16
Work Began03-30-17
Work Completed
Time Computed02-17-17
Contract Working Days120
Addl Days Granted0
Working Days Charged65
Percent Time Used54
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0266-07-021
HIGHWAY BARRICADES AND SERVICES, LLC (1.20)
STRIPE LINES, INC. (1.95)
CEN TEX HYDROSEED, INC. (3.06)
WEST TX RUMBLE STRIP (0.14)
Contract #10163020
Totals3097496.79573387.292035273.0165.7

page 1 | page 2 | page 3 | page 4 | page 5 | page 6