Monthly State Let Construction Report For Yoakum District As Of Mar 13, 2017 Page 2 Of 5

Last Update: Monday, March 13, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyGONZALES
HighwayUS 183
FromBU 183 NORTH
ToCONE STREET IN GONZALES
CSJ0153-02-039
Proj IDNH 2013(591)
Work TypeACP OVERLAY
 
3.3351398785.731388701.2999.9
Work Order05-04-15
Work Began04-11-16
Work Completed
Time Computed06-01-15
Contract Working Days30
Addl Days Granted0
Working Days Charged43
Percent Time Used143
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0153-02-039
FLASHER EQUIPMENT COMPANY (4.44)
CHEROKEE SERVICES (2.64)
Contract #03153015
Totals1398785.730.001388701.2999.9

CountyDEWITT
HighwayUS 183
FromFM 2718
ToGOLIAD C/L
CSJ0155-01-038
Proj IDNH 1502(123)
Work TypePAVEMENT REPAIR AND RESURFACING
 
11.3364639995.064508400.8797.7
Work Order06-18-15
Work Began12-18-15
Work Completed
Time Computed10-17-15
Contract Working Days60
Addl Days Granted0
Working Days Charged88
Percent Time Used146
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0155-01-038
CHEROKEE SERVICES (0.66)
COWBELL TRAFFIC SERVICES, INC. (0.87)
D&S TEXAS ICON CONSTRUCTION (0.08)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.77)
INTERSTATE BARRICADES & MARKINGS, INC. (1.71)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.17)
ROADWAY SPECIALTIES, INC. (0.08)
EGGEMEYER LAND CLEARING, LLC (0.31)
Contract #05153017
Totals4639995.060.004508400.8797.7

CountyMATAGORDA
HighwaySH 35
From0.75 MI. N. OF CHANNEL INDUSTRY RD.
ToSH 71
CSJ0179-06-042
Proj IDSTP 1402(090)HESG
Work TypeSAFETY TREAT FIXED OBJECTS
 
12.803494554.71519315.7099.9
CountyMATAGORDA
HighwaySH 71
FromSH 111
ToSH 35
CSJ0266-07-020
Proj IDSTP 1402(091)HESG
Work TypeSAFETY TREAT FIXED OBJECTS
 
3.981155355.94148368.6495.5
Work Order10-17-14
Work Began09-08-15
Work Completed
Time Computed02-14-15
Contract Working Days60
Addl Days Granted27
Working Days Charged87
Percent Time Used100
Contractor(s)
ACE ASPHALT OF ARIZONA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0179-06-042
RICE ENVIRONMENTAL SERVICES (2.08)
JMHP, INC. (13.55)
BEAR CREEK CONSTRUCTION, LLC (20.56)
Contract #08143232
Totals649910.650.00667684.3499.9

CountyCALHOUN
HighwaySH 35
FromLAVACA BAY CAUSEWAY
ToNBI# 13-029-0-0179-10-061
CSJ0179-10-105
Proj IDBR 1502(288)
Work TypeREHABILITATE BRIDGE
 
2.25416253957.064169390.2425.6
Work Order03-29-16
Work Began05-25-16
Work Completed
Time Computed06-27-16
Contract Working Days500
Addl Days Granted0
Working Days Charged147
Percent Time Used29
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0179-10-105
HIGHWAY BARRICADES AND SERVICES, LLC (0.17)
MARINE TECH SERVICES, LLC (12.85)
SALT WATER SALVAGE (11.38)
Contract #12153209
Totals16253957.06435375.604169390.2425.6

CountyAUSTIN
HighwaySH 36
FromORANGE HILL RD.
ToCR 380 (MIXVILLE ROAD)
CSJ0187-03-064
Proj IDNH 1502(127)
Work TypeCONSTRUCT AUXILLARY LANES
 
8.82110535006.212869656.4527.2
Work Order12-01-15
Work Began04-04-16
Work Completed
Time Computed03-30-16
Contract Working Days339
Addl Days Granted0
Working Days Charged155
Percent Time Used45
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0187-03-064
ROADWAY SPECIALTIES, INC. (0.54)
WILLOW CITY SIGN & RAIL, INC. (1.30)
WEST TEXAS RUMBLE STRIP (0.12)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.20)
INTERSTATE BARRICADES & MARKINGS, INC. (1.27)
SCMU (9.41)
M.V. HENKE ENTERPRISES, INC. (1.84)
Contract #05153207
Totals10535006.21333821.772869656.4527.2

CountyCOLORADO
HighwayFM 155
FromFM 2434
To1 MI S OF FM 532
CSJ0211-10-042
Proj IDSTP 2017(484)HES
Work TypeINCREASE SUPERELEVATION
 
8.540714920.820.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0211-10-042
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173205
Totals714920.820.000.000.0

CountyMATAGORDA
HighwaySH 60
From@ GRACE ST
ToIN BAY CITY
CSJ0241-02-053
Proj IDSTP 2017(319)HES
Work TypeIMPROVE TRAFFIC SIGNAL
 
0.002306857.450.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-13-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0241-02-053
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12163011
Totals306857.450.000.000.0

CountyMATAGORDA ETC
HighwaySH 60 ETC
From0.1 MI S OF FM 2668
To2.867 MI S OF FM 2668
CSJ0241-03-025
Proj IDSTP 2017(165)HESG
Work TypeMILLED CENTERLINE RUMBLE STRIPS
 
44.406100967.030.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-29-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0241-03-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10163223
Totals100967.030.000.000.0

CountyFAYETTE
HighwaySH 71
From0.051 MI W OF PRAIRIE VLY RD(CR 516
To0.698 MI WEST OF BU 71-E
CSJ0265-08-065
Proj IDNH 1602(186)
Work TypeACP OVERLAY
 
5.3341780622.901905843.8599.9
Work Order06-22-16
Work Began08-05-16
Work Completed
Time Computed07-07-16
Contract Working Days30
Addl Days Granted3
Working Days Charged38
Percent Time Used115
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0265-08-065
ROADSAFE TRAFFIC SYSTEMS, INC. (2.91)
WEST TEXAS RUMBLE STRIP (0.50)
Contract #05163035
Totals1780622.900.001905843.8599.9

CountyFAYETTE
HighwaySH 71
FromSH 159
ToCOLORADO C/L
CSJ0266-01-074
Proj IDSTP 2017(256)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
24.367276120.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-07-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0266-01-074
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11163007
Totals276120.000.000.000.0

CountyFAYETTE ETC
HighwaySH 71 ETC
FromAT FM 955
To.
CSJ0266-01-075
Proj IDSTP 2017(486)HES
Work TypeSAFETY LIGHTING AT INTERSECTION
 
2.801681093.200.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-15-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
F & W ELECTRICAL CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0266-01-075
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173251
Totals681093.200.000.000.0

CountyCOLORADO
HighwaySH 71
FromSOUTH OF RATLIFF CREEK
To0.2 MILES N. OF US 90A
CSJ0266-03-029
Proj IDSTP 2016(621)
Work TypeCONSTRUCT SUPER 2 LANES
 
9.8059120997.861185316.8412.9
Work Order03-15-16
Work Began08-25-16
Work Completed
Time Computed06-13-16
Contract Working Days226
Addl Days Granted0
Working Days Charged90
Percent Time Used39
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0266-03-029
ROADSAFE TRAFFIC SYSTEMS, INC. (2.13)
WEST TEXAS RUMBLE STRIP (0.11)
MV HENKE COMPANY, LLC (0.83)
SCMU (5.97)
Contract #01163042
Totals9120997.86645056.081185316.8412.9

CountyMATAGORDA
HighwaySH 71
FromWHARTON COUNTY LINE
ToTO 0.1 MI. NORTH OF SH 35
CSJ0266-07-021
Proj IDSTP 2017(173)
Work TypeADD SHOULDERS
 
9.3083097496.790.000.0
Work Order11-22-16
Work Began00-00-00
Work Completed
Time Computed02-17-17
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0266-07-021
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10163020
Totals3097496.790.000.000.0

CountyFAYETTE
HighwayUS 77
From0.33 MI NORTH OF LAVACA CO. LINE
ToSL 222 IN SCHULENBURG
CSJ0269-01-029
Proj IDSTP 1502(135)
Work TypeADD SHOULDERS
 
2.4602609953.182613897.1299.9
Work Order11-13-15
Work Began03-28-16
Work Completed
Time Computed03-09-16
Contract Working Days75
Addl Days Granted0
Working Days Charged102
Percent Time Used136
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0269-01-029
COWBELL TRAFFIC SERVICES, INC. (0.44)
D&S TEXAS ICON CONSTRUCTION (3.13)
ROADSAFE TRAFFIC SYSTEMS, INC. (1.97)
MURRAY CONSTRUCTION (0.55)
BILL HALL JR. TRUCKING, LTD. (0.00)
JUAN DEANDA TRUCKING, LLC DBA JUAN DEANDA TRUCKING (0.00)
RAMI MATERIALS TRANSPORT, LLC (0.00)
EGGEMEYER LAND CLEARING, LLC (1.38)
Contract #09153015
Totals2609953.181383.752613897.1299.9

CountyLAVACA
HighwayFM 531
FromAT YELLOW BANK CREEK
ToSTR # 0269-10-027
CSJ0269-10-023
Proj IDBR 1502(585)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.1641574475.261543610.0999.2
Work Order11-10-15
Work Began02-25-16
Work Completed
Time Computed02-07-16
Contract Working Days120
Addl Days Granted0
Working Days Charged145
Percent Time Used120
Contractor(s)
SB CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 0269-10-023
ALTUS TRAFFIC MANAGEMENT LLC (0.51)
BEAIRD DRILLING (3.78)
ENVIRONMENTAL SAFETY SERVICES, INC. (4.76)
LONE STAR EROSION CONTROL (0.59)
WEBER-BALKE FOUNDATION COMPANY, INC (2.37)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00)
Contract #08153039
Totals1574475.260.001543610.0999.2

CountyAUSTIN
HighwayIH 10
FromREXVILLE ROAD
ToSH 36
CSJ0271-02-058
Proj IDIM 0106(103)
Work TypeRECONSTRUCT RAMPS & ADD FRONTAGE RD
 
1.1644099769.803694180.3690.1
Work Order12-21-15
Work Began04-28-16
Work Completed
Time Computed04-19-16
Contract Working Days120
Addl Days Granted0
Working Days Charged120
Percent Time Used100
Contractor(s)
LONE STAR ROAD CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0271-02-058
LONE STAR TRAFFIC SERVICE, INC. (0.17)
MESA ROD BUSTERS, INC. (0.44)
PROFESSIONAL TRAFFIC CONTROL, LLC (0.88)
SPECIALTY DRILLING, LTD. (1.17)
THIRD COAST SERVICES LLC (1.35)
JAMES CONSTRUCTION GROUP, L.L.C. (17.63)
WEBER-BALKE FOUNDATION COMPANY, INC (1.07)
WILLOW CITY SIGN & RAIL, INC. (1.81)
GEORGE MEEKS LANDPRO, INC. (0.94)
ANGEL BROTHERS ENTERPRISES, LTD. (17.63)
DUSTROL, INC. (0.57)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.30)
Contract #08153058
Totals4099769.80555535.303694180.3690.1

CountyAUSTIN
HighwayUS 90
FromAT SH 36 & BNSF RR
ToSTR # 0271-08-419 & 025
CSJ0271-08-012
Proj IDBR 2017(052)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.7359013434.63555931.006.1
Work Order01-17-17
Work Began02-20-17
Work Completed
Time Computed02-17-17
Contract Working Days190
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0271-08-012
AREA WIDE PROTECTIVE, INC. (0.13)
FLASHER EQUIPMENT COMPANY (0.35)
JASSO"S SAWING & SEALING (0.02)
J. T. B. SERVICES, INC. (1.15)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.93)
MCL CONTRACTING, LLC (0.98)
PFEIFFER & SON LTD. (0.78)
ROADWAY SPECIALTIES, INC. (0.65)
HOUSTON SAWING & DRILLING (0.05)
D&S TEXAS ICON CONSTRUCTION (0.42)
Contract #09163211
Totals9013434.63555931.00555931.006.1

CountyGONZALES
HighwaySH 80
From2.1 MI NORTH OF SH 97
To0.06 MI NORTH OF US 87
CSJ0287-04-037
Proj IDSTP 2017(321)
Work TypePAVEMENT REPAIR AND RESURFACING
 
10.3363460417.810.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-17-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0287-04-037
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12163019
Totals3460417.810.000.000.0

CountyFAYETTE
HighwaySH 95
FromUS 90 IN FLATONIA
To0.6 MI SOUTH OF US 90
CSJ0324-01-026
Proj IDSTP 2016(131)
Work TypePAVEMENT REPAIR AND SURFACING
 
0.5891046229.461019553.1098.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-13-16
Work Began07-14-16
Work Completed
Time Computed07-12-16
Contract Working Days30
Addl Days Granted0
Working Days Charged44
Percent Time Used146
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0324-01-026
A BROTHERS MILLING, LLC (6.74)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.26)
FLASHER EQUIPMENT COMPANY (1.56)
Contract #10153224
Totals1046229.460.001019553.1098.3

CountyLAVACA
HighwaySH 95
FromFM 532 IN MOULTON
ToLCR 298
CSJ0324-02-022
Proj IDSTP 2015(535)
Work TypeRESTORE ROADWAY
 
9.9922310815.092284712.7598.8
Work Order06-18-15
Work Began12-11-15
Work Completed
Time Computed10-08-15
Contract Working Days60
Addl Days Granted0
Working Days Charged50
Percent Time Used83
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0324-02-022
CHEROKEE SERVICES (0.33)
INTERSTATE BARRICADES & MARKINGS, INC. (2.65)
Contract #05153254
Totals2310815.090.002284712.7598.8

page 1 | page 2 | page 3 | page 4 | page 5