Monthly State Let Construction Report For Yoakum District As Of May 15, 2013 Page 2 Of 4

Last Update: Wednesday, May 15, 2013
FTP Icon Text Version
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyGONZALES
Highway IH 10
From US 90
To FAYETTE C/L
CSJ 0535-05-035
Proj ID IM 0106(101)
Work Type ACP SURFACING
 
9.180 5947632.83 0.00 0.00 0.0
Work Order 04-10-13
Work Began 00-00-00
Work Completed  
Time Computed 04-01-13
Contract Working Days 96
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0535-05-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01133003
Totals 5947632.83 0.00 0.00 0.0

CountyMATAGORDA
Highway FM 457
From AT GIWW
To STR # 0605-01-016
CSJ 0605-01-058
Proj ID BR 2012(522)
Work Type STRINGER AND DECK REPAIR
 
0.043 185829.00 0.00 235713.49 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-21-12
Work Began 01-03-12
Work Completed  
Time Computed 10-01-12
Contract Working Days 33
Addl Days Granted 5
Working Days Charged 61
Percent Time Used 160
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0605-01-058
LONE STAR TRAFFIC SERVICE, INC.(1.04%)
Contract # 05123037
Totals 185829.00 0.00 235713.49 99.9

CountyWHARTON
Highway FM 102
From 0.27 MI. WEST OF FM 960
To 0.53 MI. WEST OF WHARTON CITY LIMIT
CSJ 0709-02-047
Proj ID STP 2013(073)
Work Type ADD SHOULDERS
 
4.109 2875006.16 459465.60 1332108.87 46.3
Work Order 11-01-12
Work Began 01-07-13
Work Completed  
Time Computed 12-31-12
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 58
Percent Time Used 55
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0709-02-047
BATTERSON,LLP(3.79%)
ENVIRONMENTAL SAFETY SERVICES, INC.(7.45%)
SEMARCK LANDSCAPE SERVICES, INC. (0.64%)
Contract # 09123247
Totals 2875006.16 459465.60 1332108.87 46.3

CountyGONZALES
Highway FM 108
From AT DRAW
To STR # 0715-01-008
CSJ 0715-01-017
Proj ID BR 2013(700)
Work Type WIDEN BRIDGE AND APPROACHES
 
0.293 1055377.51 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BEAR CREEK CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0715-01-017
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05133214
Totals 1055377.51 0.00 0.00 0.0

CountyGONZALES
Highway FM 108
From AT ELM CREEK BRANCH
To STR# 0715-02-014
CSJ 0715-02-013
Proj ID BR 2013(701)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.413 1904944.76 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 220
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HILL COUNTRY BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0715-02-013
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05133218
Totals 1904944.76 0.00 0.00 0.0

CountyMATAGORDA
Highway FM 521
From AT COLORADO RIVER WEST RELIEF
To STR # 0846-03-012
CSJ 0846-03-037
Proj ID BR 2012(523)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.316 2680479.60 403367.46 2611930.33 97.5
Work Order 06-14-12
Work Began 09-04-12
Work Completed  
Time Computed 08-13-12
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 110
Percent Time Used 104
Contractor(s)
LONE STAR ROAD CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0846-03-037
MESA ROD BUSTERS, INC. (0.72%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.77%)
ENVIRONMENTAL ALLIES, L.P. (0.03%)
DUSTROL, INC.(0.70%)
JMHP, INC. (1.74%)
HOUSTON SAWING & DRILLING(0.13%)
KOSSMAN CONTRACTING CO., INC.(0.20%)
WEBBER-BALKE FOUNDATION COMPANY, INC.( 11.00%)
S & S BRIDGE PAINTING, INC.(0.12%)
SILVA CONTRACTING COMPANY, INC.( 11.72%)
HIGHWAY TECHNOLOGIES, INC. (0.14%)
J.L. STEEL REINFORCING, LLC(0.24%)
Contract # 05123034
Totals 2680479.60 403367.46 2611930.33 97.5

CountyMATAGORDA
Highway FM 521
From AT COLORADO RIVER EAST RELIEF
To STR # 0846-03-007
CSJ 0846-03-043
Proj ID BR 2012(524)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.384 3358617.20 360626.23 2295324.30 68.3
Work Order 07-25-12
Work Began 08-28-12
Work Completed  
Time Computed 08-28-12
Contract Working Days 165
Addl Days Granted 0
Working Days Charged 114
Percent Time Used 69
Contractor(s)
JASIRI CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0846-03-043
5 J"S CONSTRUCTION GROUP, LLC(4.46%)
DUSTROL, INC.(0.57%)
EE CONSTRUCTION, LLC (6.91%)
HIGHWAY TECHNOLOGIES, INC. (0.16%)
INDUSTRIAL CONSTRUCTION CO.(1.96%)
KOSSMAN CONTRACTING CO., INC.(0.17%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. ( 12.81%)
ODUM SERVICES, L.P.(3.75%)
S & S BRIDGE PAINTING, INC.(0.23%)
SILVA CONTRACTING COMPANY, INC.(9.66%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.11%)
MESA ROD BUSTERS, INC. (0.54%)
LUPE RUBIO CONSTRUCTION CO., INC.(8.33%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.76%)
Contract # 05123235
Totals 3358617.20 360626.23 2295324.30 68.3

CountyCOLORADO
Highway FM 333
From AT WEST MUSTANG CREEK
To #0897-01-001
CSJ 0897-01-011
Proj ID BR 2012(608)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.123 589199.00 0.00 618658.97 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-16-12
Work Began 10-17-12
Work Completed  
Time Computed 10-15-12
Contract Working Days 100
Addl Days Granted 3
Working Days Charged 103
Percent Time Used 100
Contractor(s)
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0897-01-011
EE CONSTRUCTION, LLC ( 23.49%)
FUQUAY, INC. (1.54%)
HEMPHILL PILE DRIVING CO., A CORP. (6.19%)
HIGHWAY TECHNOLOGIES, INC. (0.34%)
HOUSTON SAWING & DRILLING(0.20%)
ODUM SERVICES, L.P.(3.05%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.25%)
SOUTH TEXAS PAINTING COMPANY (0.23%)
PITTS CONSTRUCTION, INC. (0.27%)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.( 21.54%)
Contract # 06123207
Totals 589199.00 0.00 618658.97 99.9

CountyDEWITT
Highway VA
From VARIOUS LOCATIONS
To IN DEWITT, GONZALES & LAVACA CO.
CSJ 0913-00-085
Proj ID STP 2012(468)
Work Type CONSTRUCT CURB RAMPS
 
0.100 687193.00 2500.00 663559.00 96.5
Work Order 06-04-12
Work Began 02-04-13
Work Completed  
Time Computed 10-02-12
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 116
Percent Time Used 72
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-00-085
FAASS TRUCKING, INC. (1.93%)
GLOBE ELECTRIC SUPPLY COMPANY, INC.(3.78%)
FLASHER EQUIPMENT COMPANY(2.00%)
Contract # 04123011
Totals 687193.00 2500.00 663559.00 96.5

CountyDEWITT
Highway VA
From VARIOUS LOCATIONS
To IN FAYETTE AND COLORADO CO.
CSJ 0913-00-086
Proj ID STP 2012(526)
Work Type CONSTRUCT CURB RAMPS
 
0.100 495921.40 10646.40 332943.45 67.1
Work Order 06-18-12
Work Began 03-11-13
Work Completed  
Time Computed 10-16-12
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 103
Percent Time Used 68
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-00-086
SPEEDY PAVING(0.78%)
Contract # 05123015
Totals 495921.40 10646.40 332943.45 67.1

CountyDEWITT
Highway VA
From VARIOUS LOCATIONS
To IN AUSTIN, MATAGORDA, & WHARTON CO.
CSJ 0913-00-088
Proj ID STP 2012(527)
Work Type CONSTRUCT CURB RAMPS
 
0.100 475081.00 430230.45 430230.45 90.5
Work Order 06-18-12
Work Began 04-05-13
Work Completed  
Time Computed 10-16-12
Contract Working Days 165
Addl Days Granted 0
Working Days Charged 98
Percent Time Used 59
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-00-088
PAVEMENT MARKINGS INC. (1.39%)
Contract # 05123217
Totals 475081.00 430230.45 430230.45 90.5

CountyWHARTON
Highway CR
From AT BLUE CREEK
To EAST CALHOUN ST. #C003-45-001
CSJ 0913-09-045
Proj ID BR 1102(207)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.065 410212.89 35029.00 292864.62 74.7
Work Order 08-21-12
Work Began 11-07-12
Work Completed  
Time Computed 10-20-12
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 83
Percent Time Used 138
Contractor(s)
REXCO CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-045
ROADSAFE TRAFFIC SYSTEMS, INC. (0.58%)
SPECIALTY DRILLING, LTD. (5.68%)
HOUSTON SAWING & DRILLING(0.29%)
Contract # 07123016
Totals 410212.89 35029.00 292864.62 74.7

CountyWHARTON
Highway CR
From AT BLUE CREEK # 1 CR 421
To (CR 421) STR # AA04-00-001
CSJ 0913-09-047
Proj ID BR 2011(926)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.213 1070386.80 298207.83 618800.03 57.8
Work Order 01-29-13
Work Began 02-25-13
Work Completed  
Time Computed 03-04-13
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 34
Percent Time Used 22
Contractor(s)
JOHN REED AND COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0913-09-047
KOSSMAN CONTRACTING CO., INC.(0.19%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.41%)
ODUM SERVICES, L.P.(3.01%)
HIGHWAY TECHNOLOGIES, INC. (0.32%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.92%)
MESA ROD BUSTERS, INC. (0.06%)
Contract # 12123233
Totals 1070386.80 298207.83 618800.03 57.8

CountyDEWITT
Highway CR
From AT MANAHUILLA CREEK CR 294
To (YKT SLICKFIELD ROAD) #AA0293003
CSJ 0913-17-032
Proj ID BR 2010(290)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.066 276156.23 0.00 257359.22 97.2
Work Order 03-12-12
Work Began 06-05-12
Work Completed  
Time Computed 05-10-12
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 94
Percent Time Used 125
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-17-032
LONE STAR TRAFFIC SERVICE, INC.(0.81%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (4.51%)
FUQUAY, INC. (1.50%)
HEMPHILL PILE DRIVING CO., A CORP. (6.11%)
Contract # 01123012
Totals 276156.23 0.00 257359.22 97.2

CountyDEWITT
Highway CR
From AT DRAW CR 264
To (CABEZA RD) STR # AA03-05-001
CSJ 0913-17-033
Proj ID BR 2011(921)
Work Type STRUCTURE, BASE, SURFACING
 
0.066 487910.26 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-08-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-17-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03133214
Totals 487910.26 0.00 0.00 0.0

CountyJACKSON
Highway CR
From AT DRY CREEK CR 721
To (CR 317A) STR # AA02-77-001
CSJ 0913-18-022
Proj ID BR 2011(303)
Work Type STRUCTURAL, GR, SURFACING
 
0.085 322931.00 0.00 303911.80 98.1
Work Order 03-16-12
Work Began 06-15-12
Work Completed  
Time Computed 05-15-12
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 97
Percent Time Used 129
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-18-022
HEMPHILL PILE DRIVING CO., A CORP. (7.14%)
Contract # 02123015
Totals 322931.00 0.00 303911.80 98.1

CountyCALHOUN
Highway CS
From ALONG HALF LEAGUE RD./SEADRIFT ST
To IN CITY OF PORT LAVACA
CSJ 0913-19-023
Proj ID STP 1102(151)SRS
Work Type CONSTRUCT SIDEWALKS
 
1.062 259105.30 0.00 259834.64 99.9
Work Order 08-30-11
Work Began 10-31-11
Work Completed  
Time Computed 10-30-11
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 80
Percent Time Used 106
Contractor(s)
L.L. & F. CONSTRUCTION MANAGEMENT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-19-023
LONE STAR TRAFFIC SERVICE, INC.(1.25%)
CROSS TEX CURBS(2.74%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. (5.71%)
HIGHWAY TECHNOLOGIES, INC. (4.79%)
Contract # 07113212
Totals 259105.30 0.00 259834.64 99.9

CountyCALHOUN
Highway CR
From AT AGUA DULCE BRANCH CR 508
To (SWEETWATER RD) STR# AA02-04-001
CSJ 0913-19-024
Proj ID BR 1102(131)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.072 352620.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-03-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CONSTAR CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0913-19-024
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01133006
Totals 352620.00 0.00 0.00 0.0

CountyCALHOUN
Highway PW
From AT HOG BAYOU
To GUADALUPE DELTA WMA PROJECT
CSJ 0913-19-025
Proj ID C 913-19-25
Work Type ROAD IMPROVEMENTS
 
2.710 397123.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-10-13
Work Began 00-00-00
Work Completed  
Time Computed 04-26-13
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LESTER CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0913-19-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01133211
Totals 397123.00 0.00 0.00 0.0

CountyAUSTIN
Highway CR
From AT DRAW CR 5175
To (WAGNER RD) STR # AA02-41-001
CSJ 0913-20-076
Proj ID BR 2007(533)
Work Type REPLACE BRIDGE
 
0.055 273616.44 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0913-20-076
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03133003
Totals 273616.44 0.00 0.00 0.0

page 1 | page 2 | page 3 | page 4