Monthly State Let Construction Report For Yoakum District As Of Jan 10, 2018 Page 1 Of 6

Last Update: Wednesday, January 10, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyGONZALES ETC
HighwayUS 90A ETC
FromGUADALUPE C/L
To0.1 MI EAST OF SH 80
CSJ0025-05-022
Proj IDSTP 2017(255)
Work TypeSEAL COAT
 
335.25111550371.7412059755.0299.9
Work Order01-25-17
Work Began06-14-17
Work Completed
Time Computed04-27-17
Contract Working Days75
Addl Days Granted3
Working Days Charged101
Percent Time Used129
Contractor(s)
F. N. PLOCH CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0025-05-022
STRIPE-A-ZONE, INC. (0.14)
BATTERSON,LLP (16.37)
BRYDL CONTRACTING, INC. (1.22)
Contract #11163206
Totals11550371.7420392.1012059755.0299.9

CountyGONZALES ETC
HighwaySH 97 ETC
FromSH 304
ToSANDY FORK SOUTH RELIEF
CSJ0025-07-064
Proj IDSTP 2018(255)
Work TypeSEAL COAT
 
186.2305889198.080.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-14-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
F. N. PLOCH CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0025-07-064
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11173207
Totals5889198.080.000.000.0

CountyFAYETTE
HighwayUS 90
FromAT MIDDLE CREEK
ToSTR # 0026-03-028
CSJ0026-03-042
Proj IDBR 2017(318)
Work TypeWIDEN BRIDGE AND APPROACHES
 
0.288831842.19574897.6072.4
Work Order01-10-17
Work Began03-03-17
Work Completed
Time Computed04-10-17
Contract Working Days60
Addl Days Granted0
Working Days Charged106
Percent Time Used176
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0026-03-042
DELGADO"S CONSTRUCTION (60.07)
EGGEMEYER LAND CLEARING, LLC (2.87)
ROADWAY SPECIALTIES, INC. (3.88)
FLASHER EQUIPMENT COMPANY (0.39)
PAVEMENT MARKINGS INC. (0.94)
Contract #12163022
Totals831842.1997033.15574897.6072.4

CountyFAYETTE
HighwayUS 90
FromUS 77
ToIH 10
CSJ0026-03-043
Proj IDSTP 2016(506)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
3.326958370.00920233.4797.5
Work Order05-09-16
Work Began10-05-16
Work Completed
Time Computed08-08-16
Contract Working Days75
Addl Days Granted0
Working Days Charged99
Percent Time Used132
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0026-03-043
F. N. PLOCH CONSTRUCTION COMPANY, INC. (2.12)
Contract #01163220
Totals958370.000.00920233.4797.5

CountyCOLORADO
HighwayUS 90
FromAT COLORADO RIVER
ToSTR # 0027-01-001
CSJ0027-01-040
Proj IDBR 2016(507)
Work TypeCONSTRUCT ONE WAY BRIDGE AND APPR
 
0.3647142388.4023100.000.3
Work Order06-21-17
Work Began00-00-00
Work Completed
Time Computed09-19-17
Contract Working Days350
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0027-01-040
HIGHWAY 1, LLC (0.60)
LONESTAR TRAFFIC SAFETY, LLC (0.25)
HOUSTON SAWING & DRILLING (0.11)
W. W. FOUNDATION DRILLING, LTD. (6.76)
CHOCTAW ERECTORS, INC. (7.10)
Contract #05173011
Totals7142388.4023100.0023100.000.3

CountyCOLORADO
HighwayUS 90A
FromFM 102 IN EAGLE LAKE
ToWHARTON COUNTY LINE
CSJ0027-03-071
Proj IDSTP 1702(426)
Work TypeCONSTRUCT SUPER 2 LANES
 
5.0284487326.99518414.0011.5
Work Order08-11-17
Work Began10-25-17
Work Completed
Time Computed11-09-17
Contract Working Days160
Addl Days Granted0
Working Days Charged24
Percent Time Used15
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0027-03-071
AREA WIDE PROTECTIVE, INC. (0.26)
D. I. J. CONSTRUCTION, INC. (1.88)
D&S TEXAS ICON CONSTRUCTION (0.35)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.27)
RIOS TRUCKING CO. (1.40)
STRIPE-A-ZONE, INC. (0.27)
Contract #06173243
Totals4487326.99138020.00518414.0011.5

CountyVICTORIA
HighwayUS 59
From1.26 MI NORTH OF US 87
To1.73 MI NORTH OF US 87
CSJ0088-05-092
Proj IDC 88-5-92
Work TypeCONSTRUCT 4-LANE OVERPASS
 
0.4908914435.173997731.4544.8
Work Order11-23-16
Work Began07-06-17
Work Completed
Time Computed02-21-17
Contract Working Days165
Addl Days Granted0
Working Days Charged78
Percent Time Used47
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-092
HOUSTON SAWING & DRILLING (0.04)
LONE STAR EROSION CONTROL (0.18)
MCL CONTRACTING, LLC (0.34)
ROADWAY SPECIALTIES, INC. (0.96)
STRIPE LINES, INC. (0.74)
V.C. HUFF, L.L.C. (2.16)
WEST TEXAS RUMBLE STRIP (0.05)
W. W. FOUNDATION DRILLING, LTD. (2.31)
Contract #10163032
Totals8914435.17724866.923997731.4544.8

CountyVICTORIA ETC
HighwayUS 59 ETC
From2.00 MI N OF SP 91
ToSP 91
CSJ0088-05-094
Proj IDSTP 1702(483)HES
Work TypeINSTALL MEDIAN BARRIER
 
16.4791983066.57472499.0823.8
Work Order08-08-17
Work Began11-13-17
Work Completed
Time Computed11-06-17
Contract Working Days90
Addl Days Granted0
Working Days Charged14
Percent Time Used15
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-094
(USE 25816)D & S TEXAS ICON CONSTRUCTION, LLC. (6.00)
LONESTAR TRAFFIC SAFETY, LLC (0.69)
Contract #07173008
Totals1983066.57255077.82472499.0823.8

CountyVICTORIA
HighwayUS 59
From0.4 MI. EAST OF FM 1686
ToJACKSON C/L
CSJ0089-01-090
Proj IDNH 2016(965)
Work TypeACP OVERLAY
 
8.0107280415.334030993.0155.6
Work Order00-00-00
Work Began03-06-17
Work Completed
Time Computed05-31-16
Contract Working Days105
Addl Days Granted10
Working Days Charged136
Percent Time Used118
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0089-01-090
CHEROKEE SERVICES (2.45)
DIAMOND K SERVICES, INC. (0.24)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.45)
Contract #04163208
Totals7280415.33209316.634030993.0155.6

CountyJACKSON
HighwayUS 59
FromFROM 0.5 MI. NORTH OF LAVACA RIVER
ToVICTORIA COUNTY LINE
CSJ0089-03-088
Proj IDNH 2016(508)
Work TypeACP OVERLAY
 
6.5646620873.224158013.4063.4
Work Order03-01-16
Work Began03-06-17
Work Completed
Time Computed03-16-16
Contract Working Days90
Addl Days Granted0
Working Days Charged130
Percent Time Used144
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0089-03-088
MPB, INC. (8.62)
DIAMOND SURFACE, INC. (0.24)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.37)
Contract #01163029
Totals6620873.22205529.664158013.4063.4

CountyWHARTON
HighwayUS 59
FromFM 647 (NORTHBOUND ONLY)
ToJACKSON COUNTY LINE
CSJ0089-06-079
Proj IDNH 2016(700)
Work TypePAVEMENT REPAIR & ACP OVERLAY
 
8.9743681313.693491955.7095.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-07-16
Work Began08-23-16
Work Completed
Time Computed03-19-16
Contract Working Days60
Addl Days Granted0
Working Days Charged95
Percent Time Used158
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0089-06-079
FLASHER EQUIPMENT COMPANY (2.62)
WEST TEXAS RUMBLE STRIP (0.18)
MPB, INC. (5.42)
Contract #02163029
Totals3681313.690.003491955.7095.4

CountyWHARTON
HighwayUS 59
FromBU 59 SOUTH OF EL CAMPO
ToFM 1163
CSJ0089-06-081
Proj IDNH 1502(476)
Work TypeCONSTRUCT FRONTAGE RO025809111
 
2.60218889263.0314192490.4575.1
Work Order04-07-16
Work Began06-14-16
Work Completed
Time Computed10-04-16
Contract Working Days324
Addl Days Granted0
Working Days Charged241
Percent Time Used74
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0089-06-081
ROADSAFE TRAFFIC SYSTEMS, INC. (0.64)
WILLOW CITY SIGN & RAIL, INC. (1.38)
MBN ENTERPRISES LLC (2.93)
SEMARCK LANDSCAPE SERVICES, INC. (0.69)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (4.23)
J & M CONTRACTING, COMPANY (6.90)
Contract #11153007
Totals18889263.0393390.9314192490.4575.1

CountyWHARTON
HighwayUS 59
FromLP 524 N. OF HILLJE (NB LANES ONLY)
To0.130 MI.N.OF FM 647(NB LANES ONLY)
CSJ0089-06-088
Proj IDNH 1702(485)
Work TypeACP OVERLAY
 
17.2038161719.843000.000.0
Work Order08-16-17
Work Began00-00-00
Work Completed
Time Computed11-14-17
Contract Working Days84
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0089-06-088
BATTERSON,LLP (3.59)
DEVTEX INC. (2.18)
A BROTHERS MILLING, LLC (1.99)
WEST TEXAS RUMBLE STRIP (0.17)
Contract #07173210
Totals8161719.843000.003000.000.0

CountyWHARTON
HighwayBU 59-R
From0.9 MI. SOUTH OF SH 60
ToSH 60 IN WHARTON
CSJ0089-10-022
Proj IDBR 1602(449)
Work TypeREHABILITATE EXISTING BRIDGE
 
0.9194875271.505517830.6299.9
Work Order01-17-17
Work Began02-15-17
Work Completed
Time Computed02-15-17
Contract Working Days170
Addl Days Granted188
Working Days Charged201
Percent Time Used56
Contractor(s)
CEKRA INC.
SUBCONTRACTOR(S) FOR CCSJ: 0089-10-022
HAYWARD BAKER, INC. (4.92)
Contract #11163222
Totals4875271.5098892.995517830.6299.9

CountyJACKSON
HighwaySL 522
From0.2 MI W OF SH 172
ToUS 59
CSJ0089-12-004
Proj IDSTP 2018(355)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
1.373679501.160.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0089-12-004
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12173022
Totals679501.160.000.000.0

CountyGONZALES
HighwayUS 87
FromFM 2922
To0.067 MI S. OF GCR 181(RAMSEY ST)
CSJ0143-06-027
Proj IDNH 2018(032)
Work TypeCONSTRUCT SUPER 2 LANE
 
16.78716127476.450.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-19-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days329
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0143-06-027
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09173002
Totals16127476.450.000.000.0

CountyGONZALES
HighwayUS 87
FromWILSON COUNTY LINE
ToFM 77
CSJ0143-06-029
Proj IDNH 2015(532)
Work TypePAVEMENT REPAIR AND SURFACING
 
3.2545409576.714856262.8994.5
Work Order02-26-15
Work Began07-20-15
Work Completed
Time Computed06-26-15
Contract Working Days150
Addl Days Granted47
Working Days Charged427
Percent Time Used216
Contractor(s)
ZURICH AMERICAN INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0143-06-029
FLASHER EQUIPMENT COMPANY (1.77)
ALTUS TRAFFIC MANAGEMENT LLC (0.46)
Contract #01153207
Totals5409576.71118756.604856262.8994.5

CountyDEWITT
HighwayUS 87
FromUS 183 IN CUERO
ToTO SH 72
CSJ0143-08-087
Proj IDNH 1502(122)
Work TypeUPGRADE TRAFFIC SIGNALS
 
0.002930045.00858378.9396.5
Work Order07-01-15
Work Began12-03-15
Work Completed
Time Computed10-30-15
Contract Working Days149
Addl Days Granted0
Working Days Charged214
Percent Time Used143
Contractor(s)
MIDASCO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0143-08-087
SOUTH RANGER CONSTRUCTION, INC. (17.12)
BAY CITY TRAFFIC (10.19)
M & M STRIPING & POWER WASHING, LLC (4.62)
GREEN LIGHT IN THE GROUND (1.58)
UNION ELECTRICAL CONTRACTOR, INC. (0.87)
Contract #05153216
Totals930045.000.00858378.9396.5

CountyDEWITT
HighwayUS 87
FromGONZALES COUNTY LINE
ToSH 72
CSJ0143-08-091
Proj IDNH 2017(480)
Work TypeCONSTRUCTING AUXILIARY LANES
 
12.13710180818.703933967.9438.6
Work Order02-22-17
Work Began05-23-17
Work Completed
Time Computed05-23-17
Contract Working Days246
Addl Days Granted0
Working Days Charged117
Percent Time Used47
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0143-08-091
CHEROKEE SERVICES (0.44)
DELGADO"S CONSTRUCTION (5.38)
FLASHER EQUIPMENT COMPANY (0.87)
FUQUAY, INC. (0.10)
LONE STAR EROSION CONTROL (0.73)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.34)
ROADWAY SPECIALTIES, INC. (4.15)
STRIPE-A-ZONE, INC. (0.27)
Contract #01173202
Totals10180818.7071336.053933967.9438.6

CountyDEWITT
HighwayUS 87
FromGUADALUPE RIVER RELIEF BRIDGE
ToSH 72
CSJ0143-08-097
Proj IDNH 2017(700)
Work TypeWIDEN ROADWAY
 
1.7293015734.982117073.3270.2
Work Order03-16-17
Work Began05-24-17
Work Completed
Time Computed06-14-17
Contract Working Days148
Addl Days Granted0
Working Days Charged102
Percent Time Used68
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0143-08-097
FLASHER EQUIPMENT COMPANY (2.37)
HILL COUNTRY BRIDGE, INC (18.97)
ROADWAY SPECIALTIES, INC. (2.94)
EGGEMEYER LAND CLEARING, LLC (2.27)
Contract #02173212
Totals3015734.9848736.572117073.3270.2

page 1 | page 2 | page 3 | page 4 | page 5 | page 6