500 2001 - 560 2009
Item No Description Units March 31, 2014 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
500 2001 MOBILIZATION LS 2.000 182,646.56000 34.000 225,004.62735 34
502 2001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 8.000 1,404.80000 224.000 2,716.84116 34
508 2001 CONSTRUCTING DETOURS STA     54.800 5,005.02190 2
508 2003 CONSTRUCTING DETOURS EA     2.000 83,558.50000 2
512 2001 PORT CTB (FUR & INST) (SAFETY SH) (TY 1) LF     330.000 40.00000 1
512 2008 PORT CTB (FUR & INST) (LOW PROF) (TY 1) LF     80.000 40.00000 1
512 2009 PORT CTB (FUR & INST) (LOW PROF) (TY 2) LF     20.000 40.00000 1
512 2010 PORT CTB (DES SOURCE) (SAFETY SH) (TY 1) LF     480.000 25.16750 2
512 2019 PORT CTB (MOVE) (SAFETY SH) (TY 1) LF     330.000 5.00000 1
512 2026 PORT CTB (MOVE) (LOW PROF) (TY 1) LF     80.000 5.00000 1
512 2027 PORT CTB (MOVE) (LOW PROF) (TY 2) LF     20.000 5.00000 1
512 2028 PORT CTB (STKPL) (SAFETY SH) (TY 1) LF     480.000 21.73313 2
512 2037 PORT CTB (REMOVE) (SAFETY SH) (TY 1) LF     330.000 10.00000 1
512 2044 PORT CTB (REMOVE) (LOW PROF) (TY 1) LF     80.000 10.00000 1
512 2045 PORT CTB (REMOVE) (LOW PROF) (TY 2) LF     20.000 10.00000 1
512 2048 PORT CTB (FUR & INST) (F - SHAPE) (TY 1) LF     8,950.000 26.92641 4
512 2050 PORT CTB (MOVE) (F - SHAPE) (TY 1) LF     13,720.000 8.74979 4
512 2052 PORT CTB (REMOVE) (F - SHAPE) (TY 1) LF     8,950.000 10.35041 4
514 2004 PERM CONC TRF BARR (SGL SLP) (TY 1) (42" LF     12,000.000 67.22083 2
514 2015 PERM CONC TRF BARR (F - SHAPE) (TY 1) LF     60.000 78.00000 1
514 2017 PERM CONC TRF BARR (F - SHAPE) (TY 3) LF     167.000 150.00000 1
514 2022 PERM CONC TRF BARR (SGL SLP) (TY 4) (42" LF     470.000 153.19149 2
528 2006 COLORED TEXTURED CONC (5") SY     1,414.000 70.00000 1
529 2003 CONC CURB & GUTTER (TY I) LF     1,888.000 14.00000 1
529 2004 CONC CURB & GUTTER (TY II) LF     2,078.000 15.00000 1
529 2006 CONC CURB (MONO) (TY II) LF     241.000 15.24000 1
530 2002 INTERSECTIONS (ACP) EA     7.000 4,016.47143 3
530 2003 INTERSECTIONS (SURF TREAT) EA     1.000 3,300.00000 1
530 2006 INTERSECTIONS (SURF TREAT) SY     410.000 12.99000 1
530 2007 DRIVEWAYS (CONC) EA     7.000 3,700.00000 1
530 2008 DRIVEWAYS (ACP) EA     6.000 1,801.83333 2
530 2009 DRIVEWAYS (SURF TREAT) EA     296.000 907.18547 6
530 2010 DRIVEWAYS (CONC) SY     3,332.000 60.47471 4
530 2011 DRIVEWAYS (ACP) SY     5,720.000 31.16942 4
530 2012 DRIVEWAYS (SURF TREAT) SY     4,698.000 21.28613 4
530 2015 TURNOUTS (SURF TREAT) EA     5.000 1,075.00000 1
530 2028 DRIVEWAYS AND TURNOUTS (SURF TREAT) EA     12.000 1,450.00000 1
530 2075 DRIVEWAYS (GRAVEL) SY     666.000 5.50000 1
530 2090 DRIVEWAYS (FL BS) SY     237.000 28.50000 1
531 2003 CONC SIDEWALKS (5') (6") LF     241.000 21.84000 1
531 2068 CURB RAMPS (TY 2) SY     8.000 194.01000 1
533 2006 SHOULDER TEXTURING (MILLED) (ASPHALT) LF 69,958.000 .10486 455,352.000 .18318 9
536 2002 CONC MEDIAN SY     720.000 50.00000 1
540 2001 MTL W - BEAM GD FEN (TIM POST) LF 275.000 18.80000 7,348.000 19.22547 15
540 2002 MTL W - BEAM GD FEN (STEEL POST) LF     152.000 29.80000 1
540 2011 MTL BEAM GD FEN TRANS (THRIE - BEAM) EA     67.000 1,355.03164 10
540 2012 MTL BEAM GD FEN TRANS (TL2) EA     24.000 1,087.50000 5
540 2013 MTL BEAM GD FEN TRANS (T101) EA     8.000 965.66000 1
540 2015 MTL W - BEAM GD FEN (TIM POST) RADIUS RAIL LF     12.500 41.00000 1
540 2036 DRIVEWAY TERMINAL ANCHOR SECTION EA     1.000 1,200.00000 1
540 2044 DOWNSTREAM ANCHOR TERMINAL (DAT) SECTION EA     6.000 964.00000 2
540 2045 MTL BM GD FEN (LONG SPAN SYSTEM) LF     100.000 21.00000 1
542 2001 REMOVING METAL BEAM GUARD FENCE LF 1,225.000 2.00000 13,325.000 1.71749 8
542 2002 REMOVING TERMINAL ANCHOR SECTION EA 8.000 175.00000 56.000 146.97786 6
542 2003 RM MTL BM GD FEN TRANS (THRIE - BEAM) EA     4.000 116.07000 1
544 2001 GUARDRAIL END TREATMENT (INSTALL) EA     1.000 2,286.90000 1
544 2003 GUARDRAIL END TREATMENT (REMOVE) EA     16.000 250.00000 3
544 2004 GDRAIL END TRT (INST) (WOOD POST) (TY I) EA 2.000 2,025.00000 101.000 2,131.53149 17
544 2007 GDRAIL END TRT (MV & RST) (WOOD PST) (TY I) EA     1.000 1,129.30000 1
545 2001 CRASH CUSH ATTEN (INSTL) EA     18.000 10,192.31778 6
545 2002 CRASH CUSH ATTEN (MOVE & RESET) EA     9.000 1,201.80444 4
545 2003 CRASH CUSH ATTEN (REMOVE) EA     13.000 553.04308 5
545 2049 CRASH CUSH ATTEN (INSTL) (WORK ZONE) EA     10.000 8,750.00000 1
545 2050 CRASH CUSH ATTEN (MOV & RESET) (WORK ZONE) EA     7.000 850.00000 1
545 2051 CRASH CUSH ATTEN (REMOVE) (WORK ZONE) EA     10.000 500.00000 1
550 2001 CHAIN LINK FENCE (INSTALL) (6') LF     76.000 15.00000 1
550 2003 CHAIN LINK FENCE (REMOVE) LF     80.000 3.00000 1
550 2006 GATE (REMOVE) EA     2.000 225.00000 1
550 2014 GATE (INSTALL) (DOUBLE) (6'X20') EA     1.000 3,000.00000 1
552 2001 WIRE FENCE (TY A) LF     945.000 9.05262 3
552 2002 WIRE FENCE (TY B) LF     227.000 11.50000 1
552 2005 GATE (TY 1) EA     2.000 700.00000 2
552 2006 GATE (TY 2) EA     1.000 1,100.00000 1
556 2006 PIPE UNDERDRAINS (TY 6) (6") LF     85.000 25.00000 1
560 2004 MAILBOX INSTALL - S (WC - POST) TY 3 FND EA     125.000 123.04640 10
560 2005 MAILBOX INSTALL - D (WC - POST) TY 3 FND EA     23.000 148.29783 2
560 2008 MAILBOX INSTALL - M (TWW - POST) TY 4 FND - T EA     4.000 475.00000 1
560 2009 MAILBOX INSTALL - M (TWG - POST) TY 1 FND EA     4.000 533.35000 2