Monthly State Let Maintenance Report For Wichita Falls District As Of Apr 12, 2024 Page 1 Of 2

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyARCHER
HighwaySH0079
FromVARIOUS LOCATIONS IN
ToARCHER, COOKE, AND WILBARGER COUNTIES
CSJ6377-32-001
Proj IDBPM - 637732001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010758085.691378703.17100.0
Work Order00-00-00
Work Began10-04-21
Work Completed08-31-23
Time Computed10-04-21
Contract Working Days137
Addl Days Granted72
Working Days Charged273
Percent Time Used130
Contractor(s)
SCOTT TUCKER CONSTRUCTION COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6377-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07214016
Totals758085.690.001378703.17100.0

CountyCLAY
HighwayUS0082
FromBPM AT VARIOUS PLACES
ToTHROUGHOUT THE DISTRICT
CSJ6401-97-001
Proj IDBPM - 640197001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.0101243840.001169078.1296.7
Work Order00-00-00
Work Began10-24-22
Work Completed
Time Computed10-24-22
Contract Working Days182
Addl Days Granted0
Working Days Charged232
Percent Time Used127
Contractor(s)
TALBRAN ENTERPRISES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6401-97-001
GARRET SHIELDS INFRASTRUCTURE (0.00)
Contract #06224618
Totals1243840.006892.401169078.1296.7

CountyMONTAGUE
HighwayUS0287
FromVARIOUS ROADWAYS IN
ToCOOKE AND MONTAGUE COUNTIES
CSJ6421-35-001
Proj IDRMC - 642135001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010841926.640.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days106
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
3LW CIVIL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6421-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02244202
Totals841926.640.000.000.0

CountyWICHITA
HighwayUS0287
FromVARIOUS ROADWAYS THROUGHOUT
ToTHE WICHITA FALLS DISTRICT
CSJ6428-40-001
Proj IDRMC - 642840001
Work TypePAVEMENT MARKINGS
 
0.0101342430.501000226.5574.5
Work Order00-00-00
Work Began09-27-23
Work Completed
Time Computed09-27-23
Contract Working Days366
Addl Days Granted0
Working Days Charged187
Percent Time Used51
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6428-40-001
STRIPING TECHNOLOGY, L.P. (93.37)
SURFACE PREPARATION TECHNOLOGIES, LLC (8.80)
Contract #08234047
Totals1342430.50276148.281000226.5574.5

CountyWICHITA
HighwayUS0287
FromVARIOUS ROADWAYS
ToTHROUGHOUT WFS DISTRICT
CSJ6428-44-001
Proj IDRMC - 642844001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.0101681104.00571366.9033.9
Work Order09-01-23
Work Began09-01-23
Work Completed
Time Computed09-01-23
Contract Working Days366
Addl Days Granted0
Working Days Charged213
Percent Time Used58
Contractor(s)
ROSS SA ENTERPRISE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6428-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234627
Totals1681104.0064946.90571366.9033.9

CountyARCHER
HighwayFM0368
FromVARIOUS BRIDGES
ToDISTRICTWIDE
CSJ6436-53-001
Proj IDBPM - 643653001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.0101834460.001182525.5564.4
Work Order00-00-00
Work Began11-06-23
Work Completed
Time Computed11-06-23
Contract Working Days187
Addl Days Granted0
Working Days Charged66
Percent Time Used35
Contractor(s)
PATHFIELD INVESTMENTS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6436-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234048
Totals1834460.00568691.801182525.5564.4

CountyWICHITA
HighwayUS0287
FromVARIOUS COUNTIES
ToWICHITA FALLS DISTRICT
CSJ6436-78-001
Proj IDMMC - 643678001
Work TypeAGGREGATE
 
0.010674333.30738310.7999.9
Work Order00-00-00
Work Began05-23-23
Work Completed
Time Computed05-23-23
Contract Working Days180
Addl Days Granted180
Working Days Charged314
Percent Time Used87
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 6436-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04234022
Totals674333.3029602.27738310.7999.9

CountyWICHITA
HighwayUS0287
FromVARIOUS COUNTIES
ToWICHITA FALLS DISTRICT
CSJ6437-93-001
Proj IDMMC - 643793001
Work TypeEMULSION
 
0.010886650.00610335.6268.8
Work Order00-00-00
Work Began05-12-23
Work Completed
Time Computed05-12-23
Contract Working Days180
Addl Days Granted180
Working Days Charged325
Percent Time Used90
Contractor(s)
ERGON ASPHALT & EMULSIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6437-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04234023
Totals886650.0013295.24610335.6268.8

CountyCLAY
HighwayUS0287
FromVARIOUS LOCATIONS
ToCLAY COUNTY
CSJ6437-99-001
Proj IDMMC - 643799001
Work TypeHOT MIX
 
0.010910150.00801976.3388.1
Work Order00-00-00
Work Began05-30-23
Work Completed
Time Computed05-30-23
Contract Working Days180
Addl Days Granted180
Working Days Charged307
Percent Time Used85
Contractor(s)
EUROVIA ATLANTIC COAST LLC
SUBCONTRACTOR(S) FOR CCSJ: 6437-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04234024
Totals910150.0072877.04801976.3388.1

CountyCOOKE
HighwayUS0082
FromVARIOUS LOCATIONS
ToCOOKE COUNTY
CSJ6438-03-001
Proj IDMMC - 643803001
Work TypeHOT MIX
 
0.010828900.00678041.4081.8
Work Order00-00-00
Work Began05-30-23
Work Completed
Time Computed05-30-23
Contract Working Days180
Addl Days Granted180
Working Days Charged307
Percent Time Used85
Contractor(s)
EUROVIA ATLANTIC COAST LLC
SUBCONTRACTOR(S) FOR CCSJ: 6438-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04234025
Totals828900.0077285.63678041.4081.8

CountyMONTAGUE
HighwayUS0082
FromVARIOUS LOCATIONS
ToMONTAGUE COUNTY
CSJ6438-06-001
Proj IDMMC - 643806001
Work TypeHOT MIX
 
0.0101119757.50830372.4274.1
Work Order00-00-00
Work Began05-30-23
Work Completed
Time Computed05-30-23
Contract Working Days180
Addl Days Granted180
Working Days Charged307
Percent Time Used85
Contractor(s)
EUROVIA ATLANTIC COAST LLC
SUBCONTRACTOR(S) FOR CCSJ: 6438-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04234220
Totals1119757.5038100.07830372.4274.1

CountyTHROCKMORTON
HighwayUS0183
FromVARIOUS LOCATIONS
ToTHROCKMORTON COUNTY
CSJ6438-07-001
Proj IDMMC - 643807001
Work TypeHOT MIX
 
0.010429148.50726179.3699.9
Work Order00-00-00
Work Began05-23-23
Work Completed
Time Computed05-23-23
Contract Working Days180
Addl Days Granted180
Working Days Charged314
Percent Time Used87
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 6438-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04234221
Totals429148.500.00726179.3699.9

CountyYOUNG
HighwayUS0380
FromVARIOUS LOCATIONS
ToYOUNG COUNTY
CSJ6438-09-001
Proj IDMMC - 643809001
Work TypeHOT MIX
 
0.010464125.001260534.2299.9
Work Order00-00-00
Work Began05-23-23
Work Completed
Time Computed05-23-23
Contract Working Days180
Addl Days Granted180
Working Days Charged314
Percent Time Used87
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 6438-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04234222
Totals464125.000.001260534.2299.9

CountyWICHITA
HighwayUS0287
FromVARIOUS LOCATIONS
ToWICHITA COUNTY
CSJ6441-55-001
Proj IDMMC - 644155001
Work TypeHOT MIX
 
0.010851094.00100082.7511.7
Work Order00-00-00
Work Began06-15-23
Work Completed
Time Computed06-15-23
Contract Working Days180
Addl Days Granted180
Working Days Charged291
Percent Time Used80
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 6441-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05234028
Totals851094.0037201.62100082.7511.7

CountyWILBARGER
HighwayUS0287
FromVARIOUS LOCATIONS
ToWILBARGER COUNTY
CSJ6441-58-001
Proj IDMMC - 644158001
Work TypeHOT MIX
 
0.010677120.00571179.5184.3
Work Order00-00-00
Work Began06-15-23
Work Completed
Time Computed06-15-23
Contract Working Days180
Addl Days Granted180
Working Days Charged291
Percent Time Used80
Contractor(s)
OVERLAND MATERIALS & MANUFACTURING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6441-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05234221
Totals677120.00330567.06571179.5184.3

CountyWICHITA
HighwayUS0082
FromDISTRICT-WIDE LOCATIONS
ToTHROUGHOUT THE WICHITA FALLS DISTRICT
CSJ6445-74-001
Proj IDRMC - 644574001
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.0101942000.001368760.9770.4
Work Order09-26-23
Work Began09-26-23
Work Completed
Time Computed09-26-23
Contract Working Days366
Addl Days Granted0
Working Days Charged188
Percent Time Used51
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6445-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234231
Totals1942000.00185454.781368760.9770.4

CountyWICHITA
HighwayUS0287
FromVARIOUS TXDOT MAINTENANCE FACILITIES
ToWICHITA FALLS DISTRICT
CSJ6449-27-001
Proj IDMMC - 644927001
Work TypeWINTER WEATHER MATERIAL
 
0.010459641.3279959.4117.3
Work Order00-00-00
Work Began11-17-23
Work Completed
Time Computed11-17-23
Contract Working Days180
Addl Days Granted0
Working Days Charged136
Percent Time Used75
Contractor(s)
UNITED SALT CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6449-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09234035
Totals459641.320.0079959.4117.3

CountyWICHITA
HighwayIH0044
FromVARIOUS LOCATIONS
ToTHROUGHOUT THE WFS DISTRICT
CSJ6462-27-001
Proj IDRMC - 646227001
Work TypePAVEMENT MARKINGS
 
0.0101459912.300.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPE-A-ZONE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6462-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03244226
Totals1459912.300.000.000.0

CountyCLAY
HighwayUS0287
FromHENRIETTA MAINTENANCE SECTION
ToVARIOUS ROADWAYS
CSJ6462-45-001
Proj IDRMC - 646245001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010292671.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days84
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BIG STATE MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6462-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04244016
Totals292671.000.000.000.0

CountyCOOKE
HighwayIH0035
FromGAINESVILLE MAINTENANCE SECTION
ToVARIOUS ROADWAYS
CSJ6462-46-001
Proj IDRMC - 646246001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010286568.320.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days88
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANTHONY SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6462-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03244027
Totals286568.320.000.000.0

page 1 | page 2