Monthly State Let Construction Report For Wichita Falls District As Of Feb 10, 2017 Page 2 Of 2

Last Update: Friday, February 10, 2017
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWICHITA ETC
HighwayUS 281 ETC
From0.1 MI W OF WINDTHORST RD
ToUS 281 CONNECTOR
CSJ0249-01-045
Proj IDNH 2016(381)
Work TypeOVERLAY
 
10.4802947967.381440544.0050.3
Work Order03-02-16
Work Began10-24-16
Work Completed
Time Computed04-01-16
Contract Working Days59
Addl Days Granted8
Working Days Charged115
Percent Time Used171
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0249-01-045
COTHRAN TRUCKING, LLC (1.52)
COWBELL TRAFFIC SERVICES, INC. (0.22)
ALTUS TRAFFIC MANAGEMENT LLC (0.55)
TEX OP CONSTRUCTION, LP (1.11)
PAVEMENT MARKINGS INC. (2.97)
Contract #01163008
Totals2947967.38292606.861440544.0050.3

CountyARCHER
HighwayUS 281
FromSH 25
ToJACK COUNTY LINE
CSJ0249-04-039
Proj IDSTP 2013(624)
Work TypeREHABLIITAITION OF EXISTING ROAD
 
8.73710168493.229343610.0691.8
Work Order05-08-15
Work Began07-13-15
Work Completed
Time Computed05-24-15
Contract Working Days345
Addl Days Granted1
Working Days Charged257
Percent Time Used74
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0249-04-039
W.S. CONSTRUCTION COMPANY (6.30)
CROSSROADS, L.P. (0.23)
STRIPING TECHNOLOGY, L.P. (1.55)
DUSTROL, INC. (2.47)
WOLFE CONSTRUCTION GROUP, INC. (0.85)
MARCOM"S MOWING SERVICE, LLC (0.35)
WEST TEXAS RUMBLE STRIP (0.08)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.30)
TRP CONSTRUCTION GROUP, LLC (0.73)
Contract #03153034
Totals10168493.221236453.159343610.0691.8

CountyYOUNG
HighwayFM 61
FromUS 380
ToFM 3003
CSJ0529-01-023
Proj IDSTP 1602(001)
Work TypeOVERLAY
 
8.7974288948.681473692.9334.3
Work Order06-24-16
Work Began08-03-16
Work Completed
Time Computed07-24-16
Contract Working Days186
Addl Days Granted19
Working Days Charged86
Percent Time Used41
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0529-01-023
W.S. CONSTRUCTION COMPANY (10.39)
DALLAS LITE AND BARRICADE INC. (0.41)
BARRICADES UNLIMITED (2.30)
HJC FARMS, INC. (1.63)
ZACK BURKETT CO. (29.82)
Contract #04163003
Totals4288948.68451489.681473692.9334.3

CountyWICHITA
HighwaySH 258
From0.2 MILES WEST OF FM 2226
ToUS 82
CSJ0544-01-020
Proj IDSTP 2013(903)HES
Work TypeREHABILITATION OF EXISTING ROAD
 
7.0003882193.043910414.6699.9
CountyWICHITA
HighwaySH 258
FromSH 25
To0.2 MILES WEST OF FM 2226
CSJ0544-01-021
Proj IDSTP 2013(904)
Work TypeREHABILITATION OF EXISTING ROAD
 
3.3531941339.061995338.2599.9
Work Order12-19-13
Work Began03-06-14
Work Completed
Time Computed02-17-14
Contract Working Days150
Addl Days Granted23
Working Days Charged360
Percent Time Used208
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0544-01-020
ALTUS TRAFFIC MANAGEMENT LLC (0.48)
ZACK BURKETT CO. (42.92)
FLAT LINE, INC. (0.83)
J.V. CONCRETE CONSTRUCTION (15.86)
MARCOM"S MOWING SERVICE, LLC (2.95)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00)
W.S. CONSTRUCTION COMPANY (4.69)
Contract #09133206
Totals5823532.100.005905752.9199.9

CountyWICHITA
HighwayFM 171
FromFM 890
ToCLAY COUNTY LINE
CSJ0681-01-021
Proj IDSTP 2015(875)HES
Work TypeREHABILITATION OF EXISTING ROADWAY
 
6.5774534926.903958145.9888.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-01-15
Work Began07-07-15
Work Completed
Time Computed07-02-15
Contract Working Days170
Addl Days Granted18
Working Days Charged224
Percent Time Used119
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0681-01-021
ALTUS TRAFFIC MANAGEMENT LLC (0.22)
W.S. CONSTRUCTION COMPANY (28.48)
BARRICADES UNLIMITED (1.45)
MARCOM"S MOWING SERVICE, LLC (0.40)
JE CASEY, LLC (2.03)
ZACK BURKETT CO. (27.96)
LONE STAR BARRIER SERVICES, LLC (0.57)
Contract #04153244
Totals4534926.900.003958145.9888.2

CountyWILBARGER
HighwayFM 91
FromFM 91 AT WANDERERS CREEK
To.
CSJ0702-01-014
Proj IDBR 2016(928)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.7672458571.50915563.5437.2
Work Order06-02-16
Work Began09-13-16
Work Completed
Time Computed07-02-16
Contract Working Days187
Addl Days Granted0
Working Days Charged81
Percent Time Used43
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0702-01-014
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.47)
DALLAS LITE AND BARRICADE INC. (0.76)
BARRICADES UNLIMITED (1.40)
HOUSTON SAWING & DRILLING (0.30)
LANCO TURF & SEEDING, INC. (2.01)
MCL CONTRACTING, LLC (0.57)
Contract #04163019
Totals2458571.5063975.00915563.5437.2

CountyCOOKE
HighwayFM 678
FromFM 3092
ToFM 3164
CSJ0782-01-033
Proj IDSTP 1502(097)
Work TypeREHABILITATION OF EXISTING ROADWAY
 
9.5863375961.863597944.3999.9
Work Order07-06-15
Work Began01-25-16
Work Completed
Time Computed08-06-15
Contract Working Days162
Addl Days Granted0
Working Days Charged130
Percent Time Used80
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0782-01-033
TOTAL HIGHWAY MAINTENANCE, LLC (1.13)
VENUS CONSTRUCTION (24.18)
ALTUS TRAFFIC MANAGEMENT LLC (0.26)
HJC FARMS, INC. (0.88)
RAMBO CONTRACTING, INC. (4.48)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.59)
HAYWARD BAKER, INC. (2.17)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (6.91)
WITHERS CONSTRUCTION, LLC (0.49)
Contract #05153014
Totals3375961.861837.503597944.3999.9

CountyWICHITA
HighwayFM 369
FromAT FAIRWAY INT, NEAR HUGHES ST
ToNEAR MCNIEL AVE
CSJ0802-02-052
Proj IDSTP 2013(622)
Work TypeMISCELLANEOUS WORK
 
0.3311792483.501550920.4586.5
Work Order07-24-15
Work Began03-14-16
Work Completed
Time Computed08-23-15
Contract Working Days202
Addl Days Granted17
Working Days Charged187
Percent Time Used85
Contractor(s)
NORTH TEXAS CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0802-02-052
ALTUS TRAFFIC MANAGEMENT LLC (0.41)
OSCAR ORDUNO, INC. (2.96)
PEACHTREE CONSTRUCTION, LTD. (4.50)
J. E. GUZMAN CONSTRUCTION, INC. (3.90)
WOLFE CONSTRUCTION GROUP, INC. (0.29)
KLP COMMERCIAL, LLC (22.26)
Contract #05153250
Totals1792483.5032154.751550920.4586.5

CountyWICHITA
HighwayFM 369
FromNEAR US 82/277
ToLP 473/ SH 79 INTERCHANGE
CSJ0802-02-066
Proj IDNH 1602(002)
Work TypeREHABILITATION OF EXISTING ROAD
 
6.9412496814.42391532.9215.6
Work Order09-20-16
Work Began12-06-16
Work Completed
Time Computed10-20-16
Contract Working Days268
Addl Days Granted0
Working Days Charged29
Percent Time Used10
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0802-02-066
ALTUS TRAFFIC MANAGEMENT LLC (0.95)
W.O.E. CONSTRUCTION (0.38)
TRP CONSTRUCTION GROUP, LLC (11.76)
PEACHTREE CONSTRUCTION, LTD. (7.19)
LANCO TURF & SEEDING, INC. (1.23)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (25.12)
Contract #07163033
Totals2496814.42174845.72391532.9215.6

CountyCOOKE
HighwayFM 922
FromMONTAGUE COUNTY LINE
ToFM 373
CSJ0845-03-056
Proj IDSTP 2014(357)
Work TypeRESTORATION
 
13.0824230047.494571497.4899.9
Work Order04-15-14
Work Began10-21-14
Work Completed
Time Computed06-14-14
Contract Working Days213
Addl Days Granted31
Working Days Charged244
Percent Time Used100
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0845-03-056
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.84)
ALTUS TRAFFIC MANAGEMENT LLC (0.33)
J.V. CONCRETE CONSTRUCTION (6.52)
LONE STAR BARRIER SERVICES, LLC (3.84)
MARCOM"S MOWING SERVICE, LLC (1.06)
TOTAL HIGHWAY MAINTENANCE, LLC (2.42)
STORM WATER MANAGEMENT, INC. (0.96)
MIKE ALBERT, INC. (3.19)
DUSTIN ALLEN, INC. (4.80)
TRANSPORT TRUST (2.83)
Contract #02143007
Totals4230047.49151749.974571497.4899.9

CountyWICHITA
HighwayVA
FromAT VARIOUS LOCATIONS IN WICHITA
ToFALLS DISTRICT
CSJ0903-00-075
Proj IDNH 2015(078)
Work TypeCONSTRUCT ADA CURB RAMPS
 
0.0013132333.322952857.2195.5
Work Order11-03-14
Work Began01-07-15
Work Completed
Time Computed11-19-14
Contract Working Days223
Addl Days Granted0
Working Days Charged264
Percent Time Used118
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-00-075
W.S. CONSTRUCTION COMPANY (7.60)
MELS ELECTRIC, L.P. (5.66)
STRIPING TECHNOLOGY, L.P. (0.74)
BTA SERVICES, LTD. (1.00)
SHAW BROS. WELDING (0.64)
Contract #09143037
Totals3132333.320.002952857.2195.5

CountyCOOKE
HighwayCR
FromCR 145 (CR 411) AT SOUTH FISH CREEK
To.
CSJ0903-15-082
Proj IDBR 2006(653)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.200837893.660.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-25-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days107
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-15-082
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12163034
Totals837893.660.000.000.0

CountyMONTAGUE
HighwayCR
FromCR 479 (HANCOCK RD) AT PANTHER CRK
To.
CSJ0903-28-043
Proj IDBR 2006(805)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.3001149466.651092850.0895.0
Work Order01-29-16
Work Began03-16-16
Work Completed
Time Computed03-15-16
Contract Working Days153
Addl Days Granted0
Working Days Charged116
Percent Time Used75
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-28-043
ODUM SERVICES, L.P. (4.57)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (0.83)
TEXAS SHAFTS, INC. (13.04)
LANCO TURF & SEEDING, INC. (1.08)
Contract #11153219
Totals1149466.650.001092850.0895.0

CountyCOOKE
HighwayFM 1201
FromCR 406 NORTH OF MOSS LAKE
ToFM 1200
CSJ1356-01-027
Proj IDSTP 2017(273)
Work TypeRESTORATION
 
15.9171250025.000.000.0
Work Order12-12-16
Work Began01-31-17
Work Completed
Time Computed01-11-17
Contract Working Days82
Addl Days Granted0
Working Days Charged2
Percent Time Used2
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1356-01-027
EROSION CONTROL MANAGEMENT SERVICES (2.60)
TOTAL HIGHWAY MAINTENANCE, LLC (1.68)
PEACHTREE CONSTRUCTION, LTD. (5.22)
TEXAS ALTERNATIVE GRASSER, INC. (0.29)
COMEN ENTERPRISE LLC (3.02)
Contract #11163017
Totals1250025.000.000.000.0

CountyCOOKE
HighwayFM 678
FromFM 3164
To0.339 MILES SOUTH OF US 82.
CSJ1357-02-012
Proj IDSTP 1602(201)
Work TypeREHABILITATION OF EXISTING ROADWAY
 
2.5451677816.78238474.0014.2
Work Order08-17-16
Work Began10-24-16
Work Completed
Time Computed09-16-16
Contract Working Days125
Addl Days Granted0
Working Days Charged34
Percent Time Used27
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1357-02-012
ALTUS TRAFFIC MANAGEMENT LLC (0.49)
W.S. CONSTRUCTION COMPANY (12.10)
TOTAL HIGHWAY MAINTENANCE, LLC (1.19)
MARCOM"S MOWING SERVICE, LLC (0.52)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (8.99)
TEXAS ALTERNATIVE GRASSER, INC. (0.52)
OSCAR ORDUNO, INC. (2.62)
Contract #06163009
Totals1677816.7886174.00238474.0014.2

CountyWICHITA
HighwayFM 2650
FromFM 369
ToARCHER COUNTY LINE
CSJ2644-01-010
Proj IDSTP 2013(623)
Work TypeREHABILITATION OF EXISTING ROADWAY
 
3.4934231186.982536193.0259.9
Work Order07-22-15
Work Began01-18-16
Work Completed
Time Computed08-07-15
Contract Working Days149
Addl Days Granted37
Working Days Charged165
Percent Time Used88
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2644-01-010
ALTUS TRAFFIC MANAGEMENT LLC (0.18)
BARRICADES UNLIMITED (0.80)
HJC FARMS, INC. (1.87)
ZACK BURKETT CO. (33.52)
W.S. CONSTRUCTION COMPANY (5.56)
Contract #05153050
Totals4231186.98291169.482536193.0259.9

CountyCOOKE
HighwayFM 3092
FromFM 678
ToFM 902
CSJ3308-01-012
Proj IDSTP 1502(101)HES
Work TypeREHABILITATION OF EXISTING ROADWAY
 
4.6661969043.182023906.3199.9
Work Order07-22-15
Work Began09-30-15
Work Completed
Time Computed08-22-15
Contract Working Days71
Addl Days Granted0
Working Days Charged66
Percent Time Used92
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 3308-01-012
ALTUS TRAFFIC MANAGEMENT LLC (0.21)
STORM WATER MANAGEMENT, INC. (0.22)
VENUS CONSTRUCTION (22.06)
TOTAL HIGHWAY MAINTENANCE, LLC (1.29)
HJC FARMS, INC. (1.48)
R & A TRANSPORT, INC. (6.98)
HAYWARD BAKER, INC. (5.01)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.77)
Contract #05153214
Totals1969043.180.002023906.3199.9

page 1 | page 2