Monthly State Let Construction Report For Wichita Falls District As Of Oct 14, 2014 Page 2 Of 2

Last Update: Tuesday, October 14, 2014
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWICHITA
Highway VA
From VARIOUS LOCATIONS DISTRICT WIDE
To .
CSJ 0903-00-072
Proj ID STP 2014(086)
Work Type MISCELLANEOUS WORK
 
1.000 399924.61 12156.87 78832.40 19.7
Work Order 04-15-14
Work Began 08-25-14
Work Completed  
Time Computed 07-14-14
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 4
Percent Time Used 8
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-00-072
ALTUS TRAFFIC MANAGEMENT LLC (2.07%)
Contract # 03143032
Totals 399924.61 12156.87 78832.40 19.7

CountyWICHITA
Highway VA
From AT VARIOUS LOCATIONS IN WICHITA
To FALLS DISTRICT
CSJ 0903-00-075
Proj ID NH 2015(078)
Work Type CONSTRUCT ADA CURB RAMPS
 
0.001 3132333.32 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 223
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-00-075
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143037
Totals 3132333.32 0.00 0.00 0.0

CountyWICHITA
Highway CR
From CR 126 (BOHNER ROAD) AT WILDHORSE
To CREEK
CSJ 0903-03-101
Proj ID BR 1102(538)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.068 323285.45 0.00 0.00 0.0
Work Order 08-13-14
Work Began 00-00-00
Work Completed  
Time Computed 08-29-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PIERCE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-03-101
ALTUS TRAFFIC MANAGEMENT LLC (0.79%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.03%)
DUSTIN ALLEN, INC. (2.90%)
WOLFE CONSTRUCTION GROUP, INC. (1.61%)
Contract # 07143039
Totals 323285.45 0.00 0.00 0.0

CountyCLAY
Highway CR
From CR 151 (FRIENDSHIP ROAD) AT BUFFALO
To CREEK
CSJ 0903-06-017
Proj ID BR 2013(145)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.114 344865.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-20-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 68
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-06-017
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143011
Totals 344865.50 0.00 0.00 0.0

CountyCOOKE
Highway VA
From WITHIN LAKE RAY ROBERTS STATE PARK
To JOHNSON BRANCH UNIT
CSJ 0903-15-098
Proj ID C 903-15-98
Work Type RESTORATION
 
0.100 739395.08 9855.76 752432.56 100.0
Work Order 03-13-14
Work Began 07-15-14
Work Completed 09-22-14
Time Computed 03-29-14
Contract Working Days 28
Addl Days Granted 0
Working Days Charged 22
Percent Time Used 78
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0903-15-098
TOTAL HIGHWAY MAINTENANCE, LLC (6.16%)
ALTUS TRAFFIC MANAGEMENT LLC (0.06%)
TEX OP CONSTRUCTION, LP(5.53%)
Contract # 02143207
Totals 739395.08 9855.76 752432.56 100.0

CountyBAYLOR
Highway CR
From ON CR 113 (MOSS ROAD)
To AT BRANCH OF BRIAR CREEK
CSJ 0903-31-006
Proj ID BR 2012(779)
Work Type BRIDGE REPLACEMENT
 
0.200 400053.00 112682.52 112682.52 28.1
Work Order 07-18-14
Work Began 09-08-14
Work Completed  
Time Computed 08-03-14
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 19
Percent Time Used 25
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-31-006
ALTUS TRAFFIC MANAGEMENT LLC (1.22%)
LANCO TURF & SEEDING, INC. (3.50%)
DUSTIN ALLEN, INC. (8.46%)
HOUSTON SAWING & DRILLING(0.37%)
Contract # 06143005
Totals 400053.00 112682.52 112682.52 28.1

CountyMONTAGUE
Highway FM 1758
From BISHOP STREET
To DARWIN STREET (IN SECTIONS)
CSJ 1610-01-011
Proj ID STP 2014(271)HRR
Work Type REHABILITATION OF EXISTING HIGHWAY
 
3.943 2069552.90 262871.29 1228075.35 59.3
CountyMONTAGUE
Highway FM 1758
From SH 59
To END OF PAVEMENT
CSJ 1610-01-013
Proj ID STP 2014(272)
Work Type REHABILITATION
 
7.600 1253596.53 258134.64 689492.05 55.0
Work Order 02-19-14
Work Began 03-25-14
Work Completed  
Time Computed 03-25-14
Contract Working Days 204
Addl Days Granted 0
Working Days Charged 104
Percent Time Used 50
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1610-01-011
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.40%)
VANN/ELLI, INC.(0.81%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.25%)
W.S. CONSTRUCTION COMPANY( 10.93%)
BUYERS BARRICADES, INC.(0.57%)
DURABLE SPECIALTIES, INC.(0.13%)
Contract # 12133019
Totals 3323149.43 521005.93 1917567.40 57.7

CountyCOOKE
Highway FM 902
From 0.088 MILES SE OF KIOWA
To GRAYSON COUNTY LINE
CSJ 2459-01-021
Proj ID STP 2014(013)HES
Work Type REHABILTATION OF EXISTING ROAD
 
4.626 2939410.05 7376.60 2249992.07 76.5
Work Order 11-19-13
Work Began 01-07-14
Work Completed  
Time Computed 01-07-14
Contract Working Days 145
Addl Days Granted 0
Working Days Charged 93
Percent Time Used 64
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2459-01-021
GJ SEEDING, LLC(2.44%)
J.V. CONCRETE CONSTRUCTION ( 10.21%)
MARCOM"S MOWING SERVICE, LLC (2.34%)
ALTUS TRAFFIC MANAGEMENT LLC (0.54%)
STRIPING TECHNOLOGY, L.P.(1.49%)
MELS ELECTRIC, L.P.(0.40%)
MIKE ALBERT, INC.(1.03%)
LJ TRUCKING(0.31%)
Contract # 09133011
Totals 2939410.05 7376.60 2249992.07 76.5

page 1 | page 2