Monthly State Let Construction Report For Wichita Falls District As Of Nov 9, 2016 Page 2 Of 3

Last Update: Wednesday, November 9, 2016
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyCOOKE
Highway IH 35 ETC
From ON IH 35
To AT FM 51 (NB & SB)
CSJ 0195-01-099
Proj ID NH 1502(347)
Work Type MISCELLANEOUS
 
1.039 2144827.68 63704.48 1281420.38 59.7
Work Order 11-10-15
Work Began 01-25-16
Work Completed  
Time Computed 11-10-15
Contract Working Days 200
Addl Days Granted 8
Working Days Charged 149
Percent Time Used 71
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0195-01-099
ALTUS TRAFFIC MANAGEMENT LLC (0.78%)
EROSION CONTROL MANAGEMENT SERVICES(0.22%)
STRIPING TECHNOLOGY, L.P.(4.11%)
S & S BRIDGE PAINTING, INC.(9.11%)
HJC FARMS, INC.( 18.98%)
TEXAS CUTTING & CORING, INC. (1.37%)
Contract # 06153016
Totals 2144827.68 63704.48 1281420.38 59.7

CountyWICHITA
Highway US 281 ETC
From 0.1 MI W OF WINDTHORST RD
To US 281 CONNECTOR
CSJ 0249-01-045
Proj ID NH 2016(381)
Work Type OVERLAY
 
10.480 2947967.38 -3925.00 3925.00 0.0
Work Order 03-02-16
Work Began 10-24-16
Work Completed  
Time Computed 04-01-16
Contract Working Days 59
Addl Days Granted 0
Working Days Charged 86
Percent Time Used 145
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0249-01-045
COTHRAN TRUCKING, LLC(1.52%)
COWBELL TRAFFIC SERVICES, INC. (0.22%)
ALTUS TRAFFIC MANAGEMENT LLC (0.55%)
TEX OP CONSTRUCTION, LP(1.11%)
PAVEMENT MARKINGS INC. (2.97%)
Contract # 01163008
Totals 2947967.38 3925.00 3925.00 0.0

CountyARCHER
Highway US 281
From SH 25
To JACK COUNTY LINE
CSJ 0249-04-039
Proj ID STP 2013(624)
Work Type REHABLIITAITION OF EXISTING ROAD
 
8.737 10168493.22 1122910.47 5959243.73 58.6
Work Order 05-08-15
Work Began 07-13-15
Work Completed  
Time Computed 05-24-15
Contract Working Days 345
Addl Days Granted 1
Working Days Charged 218
Percent Time Used 63
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0249-04-039
W.S. CONSTRUCTION COMPANY(6.30%)
CROSSROADS, L.P. (0.23%)
STRIPING TECHNOLOGY, L.P.(1.55%)
DUSTROL, INC.(2.47%)
WOLFE CONSTRUCTION GROUP, INC. (0.85%)
MARCOM"S MOWING SERVICE, LLC (0.35%)
WEST TEXAS RUMBLE STRIP(0.08%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.30%)
Contract # 03153034
Totals 10168493.22 1122910.47 5959243.73 58.6

CountyYOUNG
Highway FM 61
From US 380
To FM 3003
CSJ 0529-01-023
Proj ID STP 1602(001)
Work Type OVERLAY
 
8.797 4288948.68 139335.18 952350.81 22.2
Work Order 06-24-16
Work Began 08-03-16
Work Completed  
Time Computed 07-24-16
Contract Working Days 186
Addl Days Granted 19
Working Days Charged 60
Percent Time Used 29
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0529-01-023
W.S. CONSTRUCTION COMPANY( 10.39%)
DALLAS LITE AND BARRICADE INC. (0.41%)
BARRICADES UNLIMITED (2.30%)
HJC FARMS, INC.(1.63%)
ZACK BURKETT CO. ( 29.82%)
Contract # 04163003
Totals 4288948.68 139335.18 952350.81 22.2

CountyWICHITA
Highway SH 258
From 0.2 MILES WEST OF FM 2226
To US 82
CSJ 0544-01-020
Proj ID STP 2013(903)HES
Work Type REHABILITATION OF EXISTING ROAD
 
7.000 3882193.04 0.00 3910414.66 99.9
CountyWICHITA
Highway SH 258
From SH 25
To 0.2 MILES WEST OF FM 2226
CSJ 0544-01-021
Proj ID STP 2013(904)
Work Type REHABILITATION OF EXISTING ROAD
 
3.353 1941339.06 0.00 1990388.25 99.9
Work Order 12-19-13
Work Began 03-06-14
Work Completed  
Time Computed 02-17-14
Contract Working Days 150
Addl Days Granted 23
Working Days Charged 360
Percent Time Used 208
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0544-01-020
ALTUS TRAFFIC MANAGEMENT LLC (0.48%)
ZACK BURKETT CO. ( 42.92%)
FLAT LINE, INC.(0.83%)
J.V. CONCRETE CONSTRUCTION ( 15.86%)
MARCOM"S MOWING SERVICE, LLC (2.95%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
W.S. CONSTRUCTION COMPANY(4.69%)
Contract # 09133206
Totals 5823532.10 0.00 5900802.91 99.9

CountyWICHITA
Highway FM 171
From FM 890
To CLAY COUNTY LINE
CSJ 0681-01-021
Proj ID STP 2015(875)HES
Work Type REHABILITATION OF EXISTING ROADWAY
 
6.577 4534926.90 110185.00 3961055.98 88.2
Work Order 06-01-15
Work Began 07-07-15
Work Completed  
Time Computed 07-02-15
Contract Working Days 170
Addl Days Granted 11
Working Days Charged 221
Percent Time Used 122
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0681-01-021
ALTUS TRAFFIC MANAGEMENT LLC (0.22%)
W.S. CONSTRUCTION COMPANY( 28.48%)
BARRICADES UNLIMITED (1.45%)
MARCOM"S MOWING SERVICE, LLC (0.40%)
JE CASEY, LLC(2.03%)
ZACK BURKETT CO. ( 27.96%)
LONE STAR BARRIER SERVICES, LLC(0.57%)
Contract # 04153244
Totals 4534926.90 110185.00 3961055.98 88.2

CountyWILBARGER
Highway FM 91
From FM 91 AT WANDERERS CREEK
To .
CSJ 0702-01-014
Proj ID BR 2016(928)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.767 2458571.50 334743.18 723222.43 29.4
Work Order 06-02-16
Work Began 09-13-16
Work Completed  
Time Computed 07-02-16
Contract Working Days 187
Addl Days Granted 0
Working Days Charged 33
Percent Time Used 17
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0702-01-014
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.47%)
DALLAS LITE AND BARRICADE INC. (0.76%)
BARRICADES UNLIMITED (1.40%)
HOUSTON SAWING & DRILLING(0.30%)
LANCO TURF & SEEDING, INC. (2.01%)
MCL CONTRACTING, LLC (0.57%)
Contract # 04163019
Totals 2458571.50 334743.18 723222.43 29.4

CountyCOOKE
Highway FM 678
From FM 3092
To FM 3164
CSJ 0782-01-033
Proj ID STP 1502(097)
Work Type REHABILITATION OF EXISTING ROADWAY
 
9.586 3375961.86 91661.79 3592374.26 99.9
Work Order 07-06-15
Work Began 01-25-16
Work Completed  
Time Computed 08-06-15
Contract Working Days 162
Addl Days Granted 0
Working Days Charged 126
Percent Time Used 77
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0782-01-033
TOTAL HIGHWAY MAINTENANCE, LLC (1.13%)
VENUS CONSTRUCTION ( 24.18%)
ALTUS TRAFFIC MANAGEMENT LLC (0.26%)
HJC FARMS, INC.(0.88%)
RAMBO CONTRACTING, INC.(4.48%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.59%)
HAYWARD BAKER, INC.(2.17%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(6.91%)
WITHERS CONSTRUCTION, LLC(0.49%)
Contract # 05153014
Totals 3375961.86 91661.79 3592374.26 99.9

CountyWICHITA
Highway FM 369
From AT FAIRWAY INT, NEAR HUGHES ST
To NEAR MCNIEL AVE
CSJ 0802-02-052
Proj ID STP 2013(622)
Work Type MISCELLANEOUS WORK
 
0.331 1792483.50 78686.00 1457018.15 81.2
Work Order 07-24-15
Work Began 03-14-16
Work Completed  
Time Computed 08-23-15
Contract Working Days 202
Addl Days Granted 0
Working Days Charged 135
Percent Time Used 66
Contractor(s)
NORTH TEXAS CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0802-02-052
ALTUS TRAFFIC MANAGEMENT LLC (0.41%)
OSCAR ORDUNO, INC. (2.96%)
PEACHTREE CONSTRUCTION, LTD. (4.50%)
J. E. GUZMAN CONSTRUCTION, INC.(3.90%)
WOLFE CONSTRUCTION GROUP, INC. (0.29%)
Contract # 05153250
Totals 1792483.50 78686.00 1457018.15 81.2

CountyWICHITA
Highway FM 369
From NEAR US 82/277
To LP 473/ SH 79 INTERCHANGE
CSJ 0802-02-066
Proj ID NH 1602(002)
Work Type REHABILITATION OF EXISTING ROAD
 
6.941 2496814.42 0.00 0.00 0.0
Work Order 09-20-16
Work Began 00-00-00
Work Completed  
Time Computed 10-20-16
Contract Working Days 268
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0802-02-066
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07163033
Totals 2496814.42 0.00 0.00 0.0

CountyCOOKE
Highway FM 922
From MONTAGUE COUNTY LINE
To FM 373
CSJ 0845-03-056
Proj ID STP 2014(357)
Work Type RESTORATION
 
13.082 4230047.49 14623.20 4415332.25 99.9
Work Order 04-15-14
Work Began 10-21-14
Work Completed  
Time Computed 06-14-14
Contract Working Days 213
Addl Days Granted 29
Working Days Charged 237
Percent Time Used 97
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0845-03-056
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.84%)
ALTUS TRAFFIC MANAGEMENT LLC (0.33%)
J.V. CONCRETE CONSTRUCTION (6.52%)
LONE STAR BARRIER SERVICES, LLC(3.84%)
MARCOM"S MOWING SERVICE, LLC (1.06%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.42%)
STORM WATER MANAGEMENT, INC. (0.96%)
MIKE ALBERT, INC.(3.19%)
DUSTIN ALLEN, INC. (4.80%)
TRANSPORT TRUST(2.83%)
Contract # 02143007
Totals 4230047.49 14623.20 4415332.25 99.9

CountyCOOKE
Highway FM 922
From AT FM 51
To .
CSJ 0845-03-060
Proj ID STP 2016(847)
Work Type REHABILITATION OF EXISTING ROAD
 
0.248 332007.54 87879.60 346859.36 99.9
Work Order 04-07-16
Work Began 08-29-16
Work Completed  
Time Computed 05-07-16
Contract Working Days 54
Addl Days Granted 2
Working Days Charged 32
Percent Time Used 57
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0845-03-060
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION ( 19.63%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.45%)
TRP CONSTRUCTION GROUP, LLC(1.07%)
WOLFE CONSTRUCTION GROUP, INC. (1.83%)
Contract # 03163209
Totals 332007.54 87879.60 346859.36 99.9

CountyWICHITA
Highway VA
From AT VARIOUS LOCATIONS IN WICHITA
To FALLS DISTRICT
CSJ 0903-00-075
Proj ID NH 2015(078)
Work Type CONSTRUCT ADA CURB RAMPS
 
0.001 3132333.32 0.00 2942781.71 95.2
Work Order 11-03-14
Work Began 01-07-15
Work Completed  
Time Computed 11-19-14
Contract Working Days 223
Addl Days Granted 0
Working Days Charged 264
Percent Time Used 118
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-00-075
W.S. CONSTRUCTION COMPANY(7.60%)
MELS ELECTRIC, L.P.(5.66%)
STRIPING TECHNOLOGY, L.P.(0.74%)
BTA SERVICES, LTD. (1.00%)
SHAW BROS. WELDING (0.64%)
Contract # 09143037
Totals 3132333.32 0.00 2942781.71 95.2

CountyWICHITA
Highway CR
From CR 155 (ENTERPRISE ROAD) AT CHINA
To CREEK
CSJ 0903-03-081
Proj ID BR 2006(198)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.280 1519578.50 18714.00 1474982.51 97.0
Work Order 07-31-15
Work Began 12-09-15
Work Completed  
Time Computed 08-01-15
Contract Working Days 188
Addl Days Granted 0
Working Days Charged 181
Percent Time Used 96
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-03-081
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.98%)
GARY A. CRAIN, INC.(0.12%)
S & S BRIDGE PAINTING, INC.(5.94%)
DUSTIN ALLEN, INC. (5.05%)
LANCO TURF & SEEDING, INC. (1.65%)
CONTRACTORS SERVICE COMPANY(0.73%)
MCL CONTRACTING, LLC (0.45%)
Contract # 06153258
Totals 1519578.50 18714.00 1474982.51 97.0

CountyCOOKE
Highway CR
From CR 145 (CR 411) AT BLACK HOLLOW CRK
To .
CSJ 0903-15-081
Proj ID BR 2006(652)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.300 1009366.40 0.00 990501.40 98.1
Work Order 03-26-15
Work Began 06-18-15
Work Completed  
Time Computed 04-11-15
Contract Working Days 230
Addl Days Granted 0
Working Days Charged 187
Percent Time Used 81
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-15-081
ALTUS TRAFFIC MANAGEMENT LLC (0.51%)
MORRIS COUNTY CONTRACTORS, L.L.C.(6.54%)
TEXAS ALTERNATIVE GRASSER, INC.(0.70%)
Contract # 02153238
Totals 1009366.40 0.00 990501.40 98.1

CountyYOUNG
Highway CR
From CR 108 (HALL ROAD) AT SALT CREEK
To .
CSJ 0903-27-026
Proj ID BR 2009(196)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.132 685496.10 0.00 711014.48 99.9
Work Order 06-15-15
Work Began 07-13-15
Work Completed  
Time Computed 07-16-15
Contract Working Days 145
Addl Days Granted 0
Working Days Charged 148
Percent Time Used 102
Contractor(s)
PIERCE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-27-026
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.89%)
ALTUS TRAFFIC MANAGEMENT LLC (0.82%)
TEXAS ALTERNATIVE GRASSER, INC.(0.73%)
PEACHTREE CONSTRUCTION, LTD. (2.96%)
ODUM SERVICES, L.P.(3.97%)
Contract # 04153246
Totals 685496.10 0.00 711014.48 99.9

CountyMONTAGUE
Highway CR
From CR 479 (HANCOCK RD) AT PANTHER CRK
To .
CSJ 0903-28-043
Proj ID BR 2006(805)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.300 1149466.65 97434.80 1035907.73 90.1
Work Order 01-29-16
Work Began 03-16-16
Work Completed  
Time Computed 03-15-16
Contract Working Days 153
Addl Days Granted 0
Working Days Charged 113
Percent Time Used 73
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-28-043
ODUM SERVICES, L.P.(4.57%)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC(0.83%)
TEXAS SHAFTS, INC. ( 13.04%)
LANCO TURF & SEEDING, INC. (1.08%)
Contract # 11153219
Totals 1149466.65 97434.80 1035907.73 90.1

CountyCOOKE
Highway FM 1201
From CR 406 NORTH OF MOSS LAKE
To FM 1200
CSJ 1356-01-027
Proj ID STP 2017(273)
Work Type RESTORATION
 
15.917 1250025.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 82
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1356-01-027
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11163017
Totals 1250025.00 0.00 0.00 0.0

CountyCOOKE
Highway FM 678
From FM 3164
To 0.339 MILES SOUTH OF US 82.
CSJ 1357-02-012
Proj ID STP 1602(201)
Work Type REHABILITATION OF EXISTING ROADWAY
 
2.545 1677816.78 0.00 0.00 0.0
Work Order 08-17-16
Work Began 10-24-16
Work Completed  
Time Computed 09-16-16
Contract Working Days 125
Addl Days Granted 0
Working Days Charged 6
Percent Time Used 4
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1357-02-012
ALTUS TRAFFIC MANAGEMENT LLC (0.49%)
W.S. CONSTRUCTION COMPANY( 12.10%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.19%)
MARCOM"S MOWING SERVICE, LLC (0.52%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(8.99%)
TEXAS ALTERNATIVE GRASSER, INC.(0.52%)
Contract # 06163009
Totals 1677816.78 0.00 0.00 0.0

CountyWICHITA
Highway FM 2650
From FM 369
To ARCHER COUNTY LINE
CSJ 2644-01-010
Proj ID STP 2013(623)
Work Type REHABILITATION OF EXISTING ROADWAY
 
3.493 4231186.98 483781.80 2011501.36 47.5
Work Order 07-22-15
Work Began 01-18-16
Work Completed  
Time Computed 08-07-15
Contract Working Days 149
Addl Days Granted 17
Working Days Charged 128
Percent Time Used 77
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2644-01-010
ALTUS TRAFFIC MANAGEMENT LLC (0.18%)
BARRICADES UNLIMITED (0.80%)
HJC FARMS, INC.(1.87%)
ZACK BURKETT CO. ( 33.52%)
Contract # 05153050
Totals 4231186.98 483781.80 2011501.36 47.5

page 1 | page 2 | page 3