Monthly State Let Construction Report For Wichita Falls District As Of Jul 14, 2017 Page 1 Of 3

Last Update: Monday, July 17, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMONTAGUE ETC
HighwayUS 81 ETC
FromRED RIVER
ToNEAR SL 19
CSJ0013-02-021
Proj IDNH 2017(269)
Work TypeSEAL COAT
 
180.0975209700.381027495.9119.7
Work Order12-13-16
Work Began00-00-00
Work Completed
Time Computed01-12-17
Contract Working Days74
Addl Days Granted0
Working Days Charged20
Percent Time Used27
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0013-02-021
VIZCAINO, L.P. (25.49)
BARRICADES PLUS, LLC (1.61)
Contract #11163224
Totals5209700.38138049.171027495.9119.7

CountyMONTAGUE ETC
HighwayUS 81 ETC
FromSL 19
ToBLACKMAN RD
CSJ0013-03-035
Proj IDNH 2017(603)
Work TypeREHABILITATION OF EXISTING ROAD
 
38.085758517.00138428.0018.2
Work Order03-15-17
Work Began06-13-17
Work Completed
Time Computed04-14-17
Contract Working Days50
Addl Days Granted0
Working Days Charged17
Percent Time Used34
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0013-03-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173044
Totals758517.00138428.00138428.0018.2

CountyMONTAGUE
HighwayUS 81
FromFRUITLAND ROAD
ToWISE COUNTY LINE (NBL)
CSJ0013-05-058
Proj IDNH 1602(199)
Work TypeREHABILITATION OF EXISTING ROADWAY
 
4.9873543752.803177737.5189.6
Work Order08-03-16
Work Began02-07-17
Work Completed
Time Computed09-02-16
Contract Working Days102
Addl Days Granted0
Working Days Charged50
Percent Time Used49
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0013-05-058
ALTUS TRAFFIC MANAGEMENT LLC (0.19)
WOLFE CONSTRUCTION GROUP, INC. (0.28)
TEXOP CONSTRUCTION (0.30)
O. TREVINO CONSTRUCTION, LLC (3.76)
DUSTROL, INC. (0.22)
SYNERGY SIGNS & SERVICES, LLC (0.99)
TOTAL HIGHWAY MAINTENANCE, LLC (0.70)
W.O.E. CONSTRUCTION (0.21)
WATTS EXCAVT (0.83)
Contract #06163217
Totals3543752.80448080.943177737.5189.6

CountyMONTAGUE
HighwayUS 81
From0.410 MI N OF SS 511
ToWISE CO LINE
CSJ0013-05-060
Proj IDSTP 1702(123)HES
Work TypeHAZARD ELIMINATION SAFETY
 
2.3623439171.430.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-14-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days100
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0013-05-060
ANALYTICAL TECHNOLOGY CONSULTANTS, INC. (6.32)
Contract #05173027
Totals3439171.430.000.000.0

CountyWILBARGER
HighwayUS 70
FromFM 433
ToAT US 70/287
CSJ0043-06-084
Proj IDBR 1702(470)
Work TypeBRIDGE REHABILITATION OR WIDENING
 
0.5303149693.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days204
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0043-06-084
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173229
Totals3149693.500.000.000.0

CountyWILBARGER
HighwayUS 287
FromNEAR SH 240
ToNEAR BU 287H
CSJ0043-07-109
Proj IDNH 2017(140)
Work TypeREHABILITATION OF EXISTING ROAD
 
3.4022490919.291195881.1448.0
Work Order11-22-16
Work Began04-20-17
Work Completed
Time Computed12-22-16
Contract Working Days102
Addl Days Granted10
Working Days Charged51
Percent Time Used45
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-07-109
CONTRACTORS SERVICE COMPANY (0.48)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (4.30)
STRIPING TECHNOLOGY, L.P. (1.50)
W.S. CONSTRUCTION COMPANY (1.42)
ZACK BURKETT CO. (54.49)
STRIPING SYSTEMS, INC. (0.00)
Contract #10163025
Totals2490919.29671810.141195881.1448.0

CountyWICHITA
HighwayUS 287
FromJOHSNSON ROAD
ToFM 368 ENTRANCE RAMP (SB)
CSJ0043-09-124
Proj IDNH 2016(354)
Work TypeOVERLAY
 
8.0572435987.722341268.7898.5
Work Order03-09-16
Work Began03-29-17
Work Completed
Time Computed05-16-16
Contract Working Days37
Addl Days Granted0
Working Days Charged113
Percent Time Used305
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0043-09-124
COTHRAN TRUCKING, LLC (1.84)
ALTUS TRAFFIC MANAGEMENT LLC (0.12)
DUSTROL, INC. (4.59)
WOLFE CONSTRUCTION GROUP, INC. (0.27)
STRIPE-A-ZONE, INC. (2.42)
Contract #01163221
Totals2435987.720.002341268.7898.5

CountyWICHITA
HighwayUS 287
FromAT WELLINGTON LANE
To.
CSJ0043-09-126
Proj IDBR 1602(577)
Work TypeBRIDGE REPLACEMENT
 
0.3112454758.601873014.3876.3
Work Order10-12-16
Work Began12-20-16
Work Completed
Time Computed11-11-16
Contract Working Days185
Addl Days Granted0
Working Days Charged135
Percent Time Used72
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-09-126
COMEN ENTERPRISE LLC (2.39)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.33)
MARCOM"S MOWING SERVICE, LLC (1.21)
ZACK BURKETT CO. (6.28)
TOTAL HIGHWAY MAINTENANCE, LLC (1.43)
A BROTHERS MILLING, LLC (0.61)
Contract #08163208
Totals2454758.60287411.321873014.3876.3

CountyWICHITA
HighwayUS 287
FromAT RIFLE RANGE ROAD
To.
CSJ0043-09-130
Proj IDBR 1702(594)
Work TypeBRIDGE REPLACEMENT
 
0.3482398060.270.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days214
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-09-130
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173249
Totals2398060.270.000.000.0

CountyWICHITA
HighwayIH 44
FromAT 5TH STREET (NB)
To.
CSJ0043-09-132
Proj IDNH 1602(233)
Work TypeBRIDGE MAINTENANCE
 
0.10028975.0037275.0099.9
CountyWICHITA
HighwayIH 44
FromAT US 287 NB
To.
CSJ0156-07-107
Proj IDBR 1602(049)
Work TypeBRIDGE REHABILITATION OR WIDENING
 
0.2281416767.001412313.4499.7
Work Order06-20-16
Work Began09-12-16
Work Completed
Time Computed07-20-16
Contract Working Days85
Addl Days Granted10
Working Days Charged96
Percent Time Used101
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-09-132
ROCK SOLID, INC. (2.76)
GARY A. CRAIN, INC. (0.45)
BARRICADES UNLIMITED (0.73)
DUSTROL, INC. (2.87)
HOLES INCORPORATED (3.43)
HYDRO TECHNOLOGIES, INC. (5.69)
HJC FARMS, INC. (4.68)
AARON CONCRETE CONTRACTORS, L.P. (7.88)
DALLAS LITE AND BARRICADE INC. (2.65)
Contract #05163003
Totals1445742.0030397.661449588.4499.9

CountyWICHITA
HighwaySL 11
FromLOOP 11 AT WICHITA RIVER
To.
CSJ0043-14-024
Proj IDBR 2017(880)
Work TypeUPGRADE BRIDGE AND APPROACH RAILING
 
0.076351296.4077674.8922.1
Work Order04-12-17
Work Began06-05-17
Work Completed
Time Computed05-12-17
Contract Working Days51
Addl Days Granted0
Working Days Charged17
Percent Time Used33
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-14-024
DUSTIN ALLEN, INC. (4.26)
ALTUS TRAFFIC MANAGEMENT LLC (0.45)
Contract #03173004
Totals351296.4077674.8977674.8922.1

CountyWICHITA
HighwayBU 287J
FromJOHNSON ROAD.
ToFM 368/ YOSEMITE ST.
CSJ0043-17-030
Proj IDNH 2017(399)
Work TypeOVERLAY
 
7.6283440613.520.000.0
Work Order01-17-17
Work Began00-00-00
Work Completed
Time Computed02-16-17
Contract Working Days51
Addl Days Granted0
Working Days Charged17
Percent Time Used33
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0043-17-030
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12163012
Totals3440613.520.000.000.0

CountyCLAY
HighwayUS 82 ETC
FromUS 82 EASTBOUND AT DUCK CREEK
To.
CSJ0044-02-079
Proj IDBR 2016(355)
Work TypeUPGRADE BRIDGE AND APPROACH RAILING
 
24.6745938095.15619743.0010.4
Work Order03-31-16
Work Began06-05-17
Work Completed
Time Computed05-01-16
Contract Working Days197
Addl Days Granted14
Working Days Charged17
Percent Time Used8
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0044-02-079
W.S. CONSTRUCTION COMPANY (14.24)
COTHRAN TRUCKING, LLC (0.95)
WOLFE CONSTRUCTION GROUP, INC. (0.42)
DUSTROL, INC. (17.02)
HALL BROTHERS, INC. (7.12)
DUSTIN ALLEN, INC. (4.55)
TOTAL HIGHWAY MAINTENANCE, LLC (1.83)
ALTUS TRAFFIC MANAGEMENT LLC (0.47)
Contract #01163022
Totals5938095.15619743.00619743.0010.4

CountyMONTAGUE
HighwayUS 82
FromHANSON ROAD
ToNEAR NOCONA WEST CITY LIMITS
CSJ0044-04-059
Proj IDNH 2017(401)
Work TypeRESTORATION
 
20.9514894838.280.000.0
Work Order05-18-17
Work Began06-28-17
Work Completed
Time Computed06-17-17
Contract Working Days71
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0044-04-059
ALTUS TRAFFIC MANAGEMENT LLC (0.13)
LANCO TURF & SEEDING, INC. (0.56)
DUSTROL, INC. (0.94)
TOTAL HIGHWAY MAINTENANCE, LLC (4.00)
DIAMOND SURFACE, INC. (0.90)
Contract #04173235
Totals4894838.280.000.000.0

CountyMONTAGUE
HighwayUS 82
FromSH 175
ToGRAYSON ST.
CSJ0044-04-060
Proj IDNH 1702(173)
Work TypeTRAFFIC SIGNAL
 
0.215268000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-14-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0044-04-060
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05173041
Totals268000.000.000.000.0

CountyCOOKE
HighwayUS 82
FromNEAR WEBER DRIVE
ToNEAR IH 35
CSJ0044-08-067
Proj IDNH 2016(693)
Work TypeREHABILITATION OF EXISTING ROAD
 
7.3214684274.464124662.1388.0
Work Order05-18-16
Work Began08-29-16
Work Completed
Time Computed06-17-16
Contract Working Days192
Addl Days Granted15
Working Days Charged176
Percent Time Used85
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0044-08-067
DALLAS LIGHT & BARRICADES (0.87)
MARCOM"S MOWING SERVICE, LLC (0.39)
DUSTROL, INC. (1.65)
DRILL TECH DRILLING & SHORING, INC. (4.89)
METRO CUTTING AND SEALING, INC. (3.55)
STRIPING TECHNOLOGY, L.P. (1.97)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (5.05)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.88)
W.O.E. CONSTRUCTION (0.59)
FARR FOUNDATION, INC. (5.16)
JSS BORI GROUP, LLC (3.56)
OSCAR ORDUNO, INC. (6.19)
Contract #02163209
Totals4684274.46346977.224124662.1388.0

CountyWILBARGER
HighwayUS 183
FromBEAVER CREEK
ToNEAR FM 2585
CSJ0124-04-031
Proj IDSTP 2017(141)
Work TypeREHABILITATION OF EXISTING ROAD
 
6.0976688994.611572708.1523.5
Work Order11-22-16
Work Began01-03-17
Work Completed
Time Computed12-22-16
Contract Working Days208
Addl Days Granted0
Working Days Charged92
Percent Time Used44
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0124-04-031
CONTRACTORS SERVICE COMPANY (0.23)
HJC FARMS, INC. (1.75)
W.S. CONSTRUCTION COMPANY (11.63)
TOTAL HIGHWAY MAINTENANCE, LLC (1.21)
WEST TEXAS RUMBLE STRIP (0.13)
ZACK BURKETT CO. (45.77)
Contract #10163005
Totals6688994.61405466.021572708.1523.5

CountyARCHER ETC
HighwaySH 114 ETC
From0.902 MI E OF FM 210
ToYOUNG COUNTY LINE
CSJ0133-07-026
Proj IDSTP 1702(138)HES
Work TypeHAZARD ELIMINATION SAFETY
 
73.760273290.91239805.9387.7
Work Order05-11-17
Work Began06-14-17
Work Completed
Time Computed06-10-17
Contract Working Days27
Addl Days Granted0
Working Days Charged13
Percent Time Used48
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0133-07-026
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04173039
Totals273290.91239805.93239805.9387.7

CountyWICHITA
HighwaySH 240
FromAT SINCLAIR ROAD DRAIN
To.
CSJ0156-03-046
Proj IDBR 2015(693)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.021320260.00288366.6490.9
Work Order04-20-15
Work Began07-11-16
Work Completed
Time Computed05-06-15
Contract Working Days161
Addl Days Granted0
Working Days Charged166
Percent Time Used103
Contractor(s)
NORTH TEXAS CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0156-03-046
WOLFE CONSTRUCTION GROUP, INC. (1.28)
PEACHTREE CONSTRUCTION, LTD. (9.08)
J. E. GUZMAN CONSTRUCTION, INC. (22.73)
SITE BARRICADES (4.35)
HJC FARMS, INC. (15.41)
STRIPING TECHNOLOGY, L.P. (1.44)
Contract #03153229
Totals320260.0050.00288366.6490.9

CountyARCHER
HighwayUS 277
From2.083 MILES WEST OF FM 2846
To1.69 MILES WEST OF FM 368
CSJ0156-05-049
Proj IDNH 1302(006)
Work TypeWIDEN NON-FREEWAY
 
4.00514393280.5712713254.8588.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-05-15
Work Began06-18-15
Work Completed
Time Computed06-21-15
Contract Working Days313
Addl Days Granted15
Working Days Charged340
Percent Time Used103
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0156-05-049
W.S. CONSTRUCTION COMPANY (11.44)
ALTUS TRAFFIC MANAGEMENT LLC (0.19)
BARRICADES UNLIMITED (0.94)
MARCOM"S MOWING SERVICE, LLC (0.39)
WEST TEXAS RUMBLE STRIP (0.02)
ZACK BURKETT CO. (24.93)
SPIRES LANDSCAPING, INC. (0.40)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC. (2.95)
Contract #04153007
Totals14393280.570.0012713254.8588.4

page 1 | page 2 | page 3