| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | MONTAGUE |
| Highway |
US 81 |
| From |
FRUITLAND ROAD |
| To |
WISE COUNTY LINE (SBL) |
| CSJ |
0013-05-055 |
| Proj ID |
NH 2012(355) |
| Work Type |
REHABILITAITON OF EXISTING ROADWAY |
| |
|
5.019 |
3739358.56 |
7394.40 |
3736370.10 |
99.9 |
| Work Order |
05-16-12 |
| Work Began |
09-06-12 |
| Work Completed |
|
| Time Computed |
06-01-12 |
| Contract Working Days |
120 |
| Addl Days Granted |
16 |
| Working Days Charged |
145 |
| Percent Time Used |
106 |
| Contractor(s) |
| ED BELL CONSTRUCTION COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 0013-05-055 TOTAL HIGHWAY MAINTENANCE, LLC (3.96%) DUSTROL, INC.(1.28%) JAGOE-PUBLIC COMPANY ( 24.71%) O. TREVINO CONSTRUCTION, LLC (2.18%) W.O.E. CONSTRUCTION(1.61%) GJ SEEDING, LLC(1.40%) W.O.E. CONSTRUCTION(0.12%) INTERSTATE IMPROVEMENT, INC. (3.63%) BRENDA PRICE TRUCKING(0.68%) SOUTHEAST GRINDING & GROOVING, LLC (0.90%)
|
| Contract # |
03123016 |
|
Totals |
3739358.56 |
7394.40 |
3736370.10 |
99.9 |
|
| County | WICHITA |
| Highway |
IH 44 |
| From |
NEAR MAURINE STREET |
| To |
. |
| CSJ |
0043-09-120 |
| Proj ID |
IM 0448(015) |
| Work Type |
MISCELLANEOUS CONSTRUCTION |
| |
|
2.500 |
145604.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
30 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| ANALYTICAL TECHNOLOGY CONSULTANTS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0043-09-120 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
03133018 |
|
Totals |
145604.00 |
0.00 |
0.00 |
0.0 |
|
| County | WICHITA |
| Highway |
US 82 |
| From |
US 82/287 UNDER WINDTHORST ROAD |
| To |
. |
| CSJ |
0044-01-094 |
| Proj ID |
C 44-1-94 |
| Work Type |
REPLACE BRIDGE AND APPROACHES |
| |
|
1.000 |
2692739.05 |
279859.22 |
1955958.68 |
72.6 |
| Work Order |
07-31-12 |
| Work Began |
09-10-12 |
| Work Completed |
|
| Time Computed |
08-16-12 |
| Contract Working Days |
220 |
| Addl Days Granted |
0 |
| Working Days Charged |
159 |
| Percent Time Used |
72 |
| Contractor(s) |
| THE LANE CONSTRUCTION CORPORATION |
SUBCONTRACTOR(S) FOR CCSJ: 0044-01-094 DALLAS LITE AND BARRICADE INC. (0.62%) BRENDA PRICE TRUCKING(0.80%) TEXAS SHAFTS, INC. (2.34%) HIGHWAY TECHNOLOGIES, INC. (0.82%) HJC FARMS, INC.(0.50%) PRIMATE CONSTRUCTION, INC. (0.30%) MICA CORPORATION (0.96%) J.L. STEEL REINFORCING, LLC(1.53%) TEXAS ALTERNATIVE GRASSER, INC.(0.09%) SCOTT DERR PAINTING CO, LLC(0.33%)
|
| Contract # |
06123022 |
|
Totals |
2692739.05 |
279859.22 |
1955958.68 |
72.6 |
|
| County | CLAY |
| Highway |
US 82 |
| From |
EAST CITY LIMITS OF HENRIETTA |
| To |
MONTAGUE COUNTY LINE |
| CSJ |
0044-03-047 |
| Proj ID |
NH 2013(784) |
| Work Type |
REHABILITATION OF EXISTING ROAD |
| |
|
12.888 |
5114930.10 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
177 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| ZACK BURKETT CO. |
SUBCONTRACTOR(S) FOR CCSJ: 0044-03-047 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
05133021 |
|
Totals |
5114930.10 |
0.00 |
0.00 |
0.0 |
|
| County | MONTAGUE |
| Highway |
US 82 |
| From |
AT UP RR, 0.8 MI WEST OF US 81 |
| To |
NEAR RINGGOLD |
| CSJ |
0044-04-044 |
| Proj ID |
STP 1102(216)RGS |
| Work Type |
REPLACE EXISTING BRIDGE FACILITY |
| |
|
0.589 |
6249421.47 |
339564.37 |
4843040.39 |
77.4 |
| Work Order |
09-06-11 |
| Work Began |
01-03-12 |
| Work Completed |
|
| Time Computed |
11-05-11 |
| Contract Working Days |
255 |
| Addl Days Granted |
0 |
| Working Days Charged |
210 |
| Percent Time Used |
82 |
| Contractor(s) |
| THE LANE CONSTRUCTION CORPORATION |
SUBCONTRACTOR(S) FOR CCSJ: 0044-04-044 TEXAS SHAFTS, INC. (2.66%) NORTH TEXAS REBAR, LLC (0.31%) CONCRETE CUTTING BY BOND (0.11%) JM MATERIALS, INC. (0.14%) PEACHTREE CONSTRUCTION, LTD. (0.53%) TRAC-WORK, INC.(9.59%) TOTAL HIGHWAY MAINTENANCE, LLC (0.22%) TEXAS ALTERNATIVE GRASSER, INC.(0.32%) MOBILE ENTERPRISES, INC. (1.39%) ERWIN STEEL WORKS, LLC (0.52%) ODUM SERVICES, L.P.(0.28%) NORTH TEXAS CONTRACTING, INC.(7.92%) AR DANIEL SERVICES (0.91%) J. E. GUZMAN CONSTRUCTION, INC.(0.26%) MAXIM CRANE WORKS(0.12%) LINDAMOOD DEMOLITION, INC. (0.60%)
|
| Contract # |
08113202 |
|
Totals |
6249421.47 |
339564.37 |
4843040.39 |
77.4 |
|
| County | MONTAGUE |
| Highway |
US 82 ETC |
| From |
WEST CITY LIMITS OF NOCONA |
| To |
NEAR SEVENTH STREET |
| CSJ |
0044-04-057 |
| Proj ID |
NH 2013(232) |
| Work Type |
OVERLAY |
| |
|
4.640 |
1327705.84 |
0.00 |
0.00 |
0.0 |
| Work Order |
02-13-13 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
04-14-13 |
| Contract Working Days |
60 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| ZACK BURKETT CO. |
SUBCONTRACTOR(S) FOR CCSJ: 0044-04-057 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
12123227 |
|
Totals |
1327705.84 |
0.00 |
0.00 |
0.0 |
|
| County | COOKE |
| Highway |
US 82 |
| From |
AT ROCK CREEK (WEST BOUND) |
| To |
. |
| CSJ |
0045-01-056 |
| Proj ID |
BR 2013(399) |
| Work Type |
BRIDGE REPLACEMENT |
| |
|
0.151 |
1434092.60 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
04-11-13 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
120 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| HODGES AND SON CONSTRUCTION COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0045-01-056 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
02133009 |
|
Totals |
1434092.60 |
0.00 |
0.00 |
0.0 |
|
| County | YOUNG |
| Highway |
US 380 ETC |
| From |
SH 16 |
| To |
JACK COUNTY LINE |
| CSJ |
0134-03-029 |
| Proj ID |
STP 2013(090) |
| Work Type |
SEALCOAT |
| |
|
152.503 |
6568222.50 |
758997.00 |
847424.00 |
12.9 |
| Work Order |
11-09-12 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
11-25-12 |
| Contract Working Days |
58 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| NORTHEASTERN PAVERS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0134-03-029 TOTAL HIGHWAY MAINTENANCE, LLC ( 22.91%) HIGHWAY TECHNOLOGIES, INC. (0.41%)
|
| Contract # |
10123212 |
|
Totals |
6568222.50 |
758997.00 |
847424.00 |
12.9 |
|
| County | WICHITA |
| Highway |
SH 240 |
| From |
NEAR MISSLE ROAD |
| To |
WICHITA RIVER |
| CSJ |
0156-03-045 |
| Proj ID |
STP 2013(234) |
| Work Type |
OVERLAY |
| |
|
4.518 |
844419.71 |
0.00 |
0.00 |
0.0 |
| Work Order |
02-05-13 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
04-06-13 |
| Contract Working Days |
32 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| ZACK BURKETT CO. |
SUBCONTRACTOR(S) FOR CCSJ: 0156-03-045 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
12123032 |
|
Totals |
844419.71 |
0.00 |
0.00 |
0.0 |
|
| County | BAYLOR |
| Highway |
US 277 |
| From |
2.78 MILES EAST OF RM 1919 |
| To |
0.64 MILES EAST OF US 183/283 |
| CSJ |
0156-06-039 |
| Proj ID |
C 156-6-39 |
| Work Type |
WIDEN NON - FREEWAY |
| |
|
5.896 |
10550963.24 |
348744.81 |
5283310.28 |
50.0 |
| Work Order |
08-20-12 |
| Work Began |
09-10-12 |
| Work Completed |
|
| Time Computed |
09-10-12 |
| Contract Working Days |
269 |
| Addl Days Granted |
10 |
| Working Days Charged |
144 |
| Percent Time Used |
51 |
| Contractor(s) |
| A. L. HELMCAMP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0156-06-039 CONTRACTORS SERVICE COMPANY(0.26%) TEX OP CONSTRUCTION, LP(0.28%) W.S. CONSTRUCTION COMPANY(6.55%) TOTAL HIGHWAY MAINTENANCE, LLC (1.10%) ZACK BURKETT CO. ( 26.33%) WILLIS ELECTRIC CO., LP(1.32%) WEST TEXAS RUMBLE STRIP(0.08%)
|
| Contract # |
06123203 |
|
Totals |
10550963.24 |
348744.81 |
5283310.28 |
50.0 |
|
| County | BAYLOR |
| Highway |
US 277 |
| From |
KNOX COUNTY LINE |
| To |
2.155 MILES WEST OF US 183 |
| CSJ |
0157-01-062 |
| Proj ID |
NH 2013(235) |
| Work Type |
WIDEN NON - FREEWAY |
| |
|
11.161 |
11926754.60 |
615039.37 |
1128349.57 |
9.4 |
| Work Order |
02-06-13 |
| Work Began |
03-25-13 |
| Work Completed |
|
| Time Computed |
03-25-13 |
| Contract Working Days |
385 |
| Addl Days Granted |
0 |
| Working Days Charged |
23 |
| Percent Time Used |
5 |
| Contractor(s) |
| A. L. HELMCAMP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0157-01-062 W.S. CONSTRUCTION COMPANY(5.55%) CONTRACTORS SERVICE COMPANY(0.36%) WEST TEXAS RUMBLE STRIP(0.07%) ZACK BURKETT CO. ( 26.21%) TOTAL HIGHWAY MAINTENANCE, LLC (1.40%)
|
| Contract # |
12123202 |
|
Totals |
11926754.60 |
615039.37 |
1128349.57 |
9.4 |
|
| County | COOKE |
| Highway |
IH 35 ETC |
| From |
NEAR FM 1202 |
| To |
NEAR US 82 |
| CSJ |
0194-02-087 |
| Proj ID |
STP 2011(441)ES |
| Work Type |
UPGRADING OF FREEWAY FACILITY |
| |
|
12.652 |
14049262.01 |
162661.39 |
13950084.87 |
99.2 |
| Work Order |
11-04-10 |
| Work Began |
02-14-11 |
| Work Completed |
|
| Time Computed |
02-14-11 |
| Contract Working Days |
600 |
| Addl Days Granted |
0 |
| Working Days Charged |
558 |
| Percent Time Used |
93 |
| Contractor(s) |
| ED BELL CONSTRUCTION COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 0194-02-087 WRIGHT CONSTRUCTION CO., INC.( 13.36%) ALLSTATE SIGNAL & CONSTRUCTION, LLC(9.73%) HIGHWAY TECHNOLOGIES, INC. (1.12%) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.04%) FARR FOUNDATION, INC.(0.14%) JAGOE-PUBLIC COMPANY (7.70%) LONE STAR MANHOLE & STRUCTURES, LLC(1.98%) BRENDA PRICE TRUCKING(0.23%) TEXAS SHAFTS, INC. (0.18%) SCOTT DERR PAINTING CO (0.25%) DUSTROL, INC. (ROANOKE)(0.15%) BREDA COMPANY, INC.(0.78%) SKAGGS ROAD BORING INC.(3.17%) C & C DIRECTIONAL BORING (0.20%) J. E. GUZMAN CONSTRUCTION, INC.(0.09%) RUSSO CORPORATION(0.19%) KEY'S TAPPING & CONSTRUCTION SERVICES, INC.(0.00%) A & A CONSTRUCTION (0.59%) A-1 ASPHALT PAVING (0.08%) MCRYAN HAULING, INC. (0.51%) SOUTHWEST CONSTRUCTION SERVICES(0.56%) PACIFICPAINT CO. (1.17%) ANTIGO CONSTRUCTION, INC.(0.17%) FORTSON CONTRACTING, INC.(0.36%) STOMPER DEMOLITION COMPANY, INC. (0.30%) SOUTHEAST GRINDING & GROOVING, LLC (0.07%) GLS MASONRY, INC.(0.50%) DOWN UNDER CONSTRUCTION(0.02%)
|
| Contract # |
09103002 |
|
Totals |
14049262.01 |
162661.39 |
13950084.87 |
99.2 |
|
| County | COOKE |
| Highway |
FM 51 |
| From |
FM 1306 |
| To |
FM 922 |
| CSJ |
0312-01-072 |
| Proj ID |
STP 2013(469) |
| Work Type |
ASPHALTIC CONCRETE PAVEMENT OVERLAY |
| |
|
11.855 |
2224039.60 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
39 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| THE LANE CONSTRUCTION CORPORATION |
SUBCONTRACTOR(S) FOR CCSJ: 0312-01-072 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
03133212 |
|
Totals |
2224039.60 |
0.00 |
0.00 |
0.0 |
|
| County | BAYLOR |
| Highway |
FM 422 |
| From |
US 82 |
| To |
EAST CITY LIMITS OF SEYMOUR |
| CSJ |
0814-01-027 |
| Proj ID |
C 814-1-27 |
| Work Type |
UPGRADING OF A NON - FREEWAY FACILITY |
| |
|
0.847 |
3332046.95 |
89766.00 |
1347124.26 |
40.4 |
| Work Order |
09-13-12 |
| Work Began |
02-11-13 |
| Work Completed |
|
| Time Computed |
02-11-13 |
| Contract Working Days |
245 |
| Addl Days Granted |
0 |
| Working Days Charged |
45 |
| Percent Time Used |
18 |
| Contractor(s) |
| A. L. HELMCAMP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0814-01-027 W.S. CONSTRUCTION COMPANY( 36.49%) CONTRACTORS SERVICE COMPANY(0.56%) TEXAS ALTERNATIVE GRASSER, INC.(0.55%) ZACK BURKETT CO. ( 26.68%) TOTAL HIGHWAY MAINTENANCE, LLC (1.02%) WILLIS ELECTRIC CO., LP(4.81%)
|
| Contract # |
07123006 |
|
Totals |
3332046.95 |
89766.00 |
1347124.26 |
40.4 |
|
| County | COOKE |
| Highway |
FM 373 |
| From |
NEAR CR 450 |
| To |
US 82 |
| CSJ |
0823-01-028 |
| Proj ID |
STP 2013(337) |
| Work Type |
RESTORATION |
| |
|
16.030 |
1701551.66 |
0.00 |
0.00 |
0.0 |
| Work Order |
03-19-13 |
| Work Began |
05-01-13 |
| Work Completed |
|
| Time Computed |
04-04-13 |
| Contract Working Days |
69 |
| Addl Days Granted |
0 |
| Working Days Charged |
10 |
| Percent Time Used |
14 |
| Contractor(s) |
| JAGOE-PUBLIC COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 0823-01-028 HIGHWAY TECHNOLOGIES, INC. (0.30%) LANCO TURF & SEEDING, INC. (1.30%) STRIPING TECHNOLOGY, L.P.(3.19%)
|
| Contract # |
01133214 |
|
Totals |
1701551.66 |
0.00 |
0.00 |
0.0 |
|
| County | MONTAGUE |
| Highway |
FM 455 |
| From |
MONTAGUE |
| To |
FM 1749 |
| CSJ |
0845-01-016 |
| Proj ID |
STP 2013(686) |
| Work Type |
REHABILTATION OF EXISTING ROADWAY |
| |
|
14.179 |
3371976.79 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
151 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| THE LANE CONSTRUCTION CORPORATION |
SUBCONTRACTOR(S) FOR CCSJ: 0845-01-016 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
05133231 |
|
Totals |
3371976.79 |
0.00 |
0.00 |
0.0 |
|
| County | WICHITA |
| Highway |
CS |
| From |
IN CITY OF WFS, AT CITY VIEW ELEM |
| To |
ON CITY VIEW DRIVE AND CRESCENT LN |
| CSJ |
0903-03-096 |
| Proj ID |
STP 1102(526)SRS |
| Work Type |
SAFE ROUTES TO SCHOOL 2009 PROGRAM |
| |
|
1.500 |
781215.78 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
06-03-13 |
| Contract Working Days |
60 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| KEN-DO CONTRACTING, LP |
SUBCONTRACTOR(S) FOR CCSJ: 0903-03-096 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
03133209 |
|
Totals |
781215.78 |
0.00 |
0.00 |
0.0 |
|
| County | MONTAGUE |
| Highway |
CR |
| From |
CR 410 (DEEN ROAD) AT BRANCH OF |
| To |
DENTON CREEK |
| CSJ |
0903-28-049 |
| Proj ID |
BR 2012(768) |
| Work Type |
REPLACE BRIDGE AND APPROACHES |
| |
|
0.200 |
616009.30 |
0.00 |
0.00 |
0.0 |
| Work Order |
04-10-13 |
| Work Began |
04-30-13 |
| Work Completed |
|
| Time Computed |
04-26-13 |
| Contract Working Days |
101 |
| Addl Days Granted |
0 |
| Working Days Charged |
2 |
| Percent Time Used |
1 |
| Contractor(s) |
| HODGES AND SON CONSTRUCTION COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0903-28-049 ODUM SERVICES, L.P.(3.23%) CROSSROADS, L.P. (0.68%) TEXAS ALTERNATIVE GRASSER, INC.(0.42%)
|
| Contract # |
02133221 |
|
Totals |
616009.30 |
0.00 |
0.00 |
0.0 |
|
| County | MONTAGUE |
| Highway |
FM 677 |
| From |
1.42 MILES NORTH OF STAR MANN ROAD |
| To |
0.136 MILES SW OF FM 1630 |
| CSJ |
1352-01-019 |
| Proj ID |
STP 2013(152)HES |
| Work Type |
REHABILITATION OF EXISTING ROADWAY |
| |
|
5.000 |
2497972.59 |
170020.55 |
607547.48 |
24.3 |
| County | MONTAGUE |
| Highway |
FM 677 |
| From |
US 82 |
| To |
1.42 MI NORTH OF STAR MANN ROAD |
| CSJ |
1352-01-020 |
| Proj ID |
STP 2013(153) |
| Work Type |
REHABILITATION OF EXISTING ROADWAY |
| |
|
4.112 |
606688.27 |
0.00 |
0.00 |
0.0 |
| Work Order |
12-03-12 |
| Work Began |
01-21-13 |
| Work Completed |
|
| Time Computed |
01-21-13 |
| Contract Working Days |
150 |
| Addl Days Granted |
0 |
| Working Days Charged |
45 |
| Percent Time Used |
30 |
| Contractor(s) |
| JAGOE-PUBLIC COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 1352-01-019 NORTH TEXAS CONTRACTING, INC.(8.81%) HIGHWAY TECHNOLOGIES, INC. (1.85%) HJC FARMS, INC.(0.95%) HIGHWAY TECHNOLOGIES, INC. (0.45%) J. E. GUZMAN CONSTRUCTION, INC.(1.94%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.42%)
|
| Contract # |
11123219 |
|
Totals |
3104660.86 |
170020.55 |
607547.48 |
19.5 |
|
| County | WILBARGER |
| Highway |
FM 3207 |
| From |
US 70 |
| To |
FM 433 |
| CSJ |
3317-01-005 |
| Proj ID |
STP 2012(687) |
| Work Type |
REHABILITATION OF EXISTING ROAD |
| |
|
4.982 |
2961200.50 |
238528.74 |
1425951.75 |
48.1 |
| Work Order |
09-17-12 |
| Work Began |
11-19-12 |
| Work Completed |
|
| Time Computed |
11-16-12 |
| Contract Working Days |
180 |
| Addl Days Granted |
0 |
| Working Days Charged |
89 |
| Percent Time Used |
49 |
| Contractor(s) |
| ZACK BURKETT CO. |
SUBCONTRACTOR(S) FOR CCSJ: 3317-01-005 HIGHWAY TECHNOLOGIES, INC. (2.73%) DUSTROL, INC.(0.21%) W.S. CONSTRUCTION COMPANY( 16.17%) WILLIS ELECTRIC CO., LP(1.18%) TEXAS ALTERNATIVE GRASSER, INC.(0.30%) COTHRAN TRUCKING, LLC(1.14%)
|
| Contract # |
08123242 |
|
Totals |
2961200.50 |
238528.74 |
1425951.75 |
48.1 |
|