Monthly State Let Construction Report For Wichita Falls District As Of May 15, 2013 Page 1 Of 1

Last Update: Wednesday, May 15, 2013
FTP Icon Text Version
page 1

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyMONTAGUE
Highway US 81
From FRUITLAND ROAD
To WISE COUNTY LINE (SBL)
CSJ 0013-05-055
Proj ID NH 2012(355)
Work Type REHABILITAITON OF EXISTING ROADWAY
 
5.019 3739358.56 7394.40 3736370.10 99.9
Work Order 05-16-12
Work Began 09-06-12
Work Completed  
Time Computed 06-01-12
Contract Working Days 120
Addl Days Granted 16
Working Days Charged 145
Percent Time Used 106
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0013-05-055
TOTAL HIGHWAY MAINTENANCE, LLC (3.96%)
DUSTROL, INC.(1.28%)
JAGOE-PUBLIC COMPANY ( 24.71%)
O. TREVINO CONSTRUCTION, LLC (2.18%)
W.O.E. CONSTRUCTION(1.61%)
GJ SEEDING, LLC(1.40%)
W.O.E. CONSTRUCTION(0.12%)
INTERSTATE IMPROVEMENT, INC. (3.63%)
BRENDA PRICE TRUCKING(0.68%)
SOUTHEAST GRINDING & GROOVING, LLC (0.90%)
Contract # 03123016
Totals 3739358.56 7394.40 3736370.10 99.9

CountyWICHITA
Highway IH 44
From NEAR MAURINE STREET
To .
CSJ 0043-09-120
Proj ID IM 0448(015)
Work Type MISCELLANEOUS CONSTRUCTION
 
2.500 145604.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-09-120
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03133018
Totals 145604.00 0.00 0.00 0.0

CountyWICHITA
Highway US 82
From US 82/287 UNDER WINDTHORST ROAD
To .
CSJ 0044-01-094
Proj ID C 44-1-94
Work Type REPLACE BRIDGE AND APPROACHES
 
1.000 2692739.05 279859.22 1955958.68 72.6
Work Order 07-31-12
Work Began 09-10-12
Work Completed  
Time Computed 08-16-12
Contract Working Days 220
Addl Days Granted 0
Working Days Charged 159
Percent Time Used 72
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0044-01-094
DALLAS LITE AND BARRICADE INC. (0.62%)
BRENDA PRICE TRUCKING(0.80%)
TEXAS SHAFTS, INC. (2.34%)
HIGHWAY TECHNOLOGIES, INC. (0.82%)
HJC FARMS, INC.(0.50%)
PRIMATE CONSTRUCTION, INC. (0.30%)
MICA CORPORATION (0.96%)
J.L. STEEL REINFORCING, LLC(1.53%)
TEXAS ALTERNATIVE GRASSER, INC.(0.09%)
SCOTT DERR PAINTING CO, LLC(0.33%)
Contract # 06123022
Totals 2692739.05 279859.22 1955958.68 72.6

CountyCLAY
Highway US 82
From EAST CITY LIMITS OF HENRIETTA
To MONTAGUE COUNTY LINE
CSJ 0044-03-047
Proj ID NH 2013(784)
Work Type REHABILITATION OF EXISTING ROAD
 
12.888 5114930.10 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 177
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0044-03-047
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05133021
Totals 5114930.10 0.00 0.00 0.0

CountyMONTAGUE
Highway US 82
From AT UP RR, 0.8 MI WEST OF US 81
To NEAR RINGGOLD
CSJ 0044-04-044
Proj ID STP 1102(216)RGS
Work Type REPLACE EXISTING BRIDGE FACILITY
 
0.589 6249421.47 339564.37 4843040.39 77.4
Work Order 09-06-11
Work Began 01-03-12
Work Completed  
Time Computed 11-05-11
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 210
Percent Time Used 82
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0044-04-044
TEXAS SHAFTS, INC. (2.66%)
NORTH TEXAS REBAR, LLC (0.31%)
CONCRETE CUTTING BY BOND (0.11%)
JM MATERIALS, INC. (0.14%)
PEACHTREE CONSTRUCTION, LTD. (0.53%)
TRAC-WORK, INC.(9.59%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.22%)
TEXAS ALTERNATIVE GRASSER, INC.(0.32%)
MOBILE ENTERPRISES, INC. (1.39%)
ERWIN STEEL WORKS, LLC (0.52%)
ODUM SERVICES, L.P.(0.28%)
NORTH TEXAS CONTRACTING, INC.(7.92%)
AR DANIEL SERVICES (0.91%)
J. E. GUZMAN CONSTRUCTION, INC.(0.26%)
MAXIM CRANE WORKS(0.12%)
LINDAMOOD DEMOLITION, INC. (0.60%)
Contract # 08113202
Totals 6249421.47 339564.37 4843040.39 77.4

CountyMONTAGUE
Highway US 82 ETC
From WEST CITY LIMITS OF NOCONA
To NEAR SEVENTH STREET
CSJ 0044-04-057
Proj ID NH 2013(232)
Work Type OVERLAY
 
4.640 1327705.84 0.00 0.00 0.0
Work Order 02-13-13
Work Began 00-00-00
Work Completed  
Time Computed 04-14-13
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0044-04-057
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12123227
Totals 1327705.84 0.00 0.00 0.0

CountyCOOKE
Highway US 82
From AT ROCK CREEK (WEST BOUND)
To .
CSJ 0045-01-056
Proj ID BR 2013(399)
Work Type BRIDGE REPLACEMENT
 
0.151 1434092.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-11-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0045-01-056
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02133009
Totals 1434092.60 0.00 0.00 0.0

CountyYOUNG
Highway US 380 ETC
From SH 16
To JACK COUNTY LINE
CSJ 0134-03-029
Proj ID STP 2013(090)
Work Type SEALCOAT
 
152.503 6568222.50 758997.00 847424.00 12.9
Work Order 11-09-12
Work Began 00-00-00
Work Completed  
Time Computed 11-25-12
Contract Working Days 58
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0134-03-029
TOTAL HIGHWAY MAINTENANCE, LLC ( 22.91%)
HIGHWAY TECHNOLOGIES, INC. (0.41%)
Contract # 10123212
Totals 6568222.50 758997.00 847424.00 12.9

CountyWICHITA
Highway SH 240
From NEAR MISSLE ROAD
To WICHITA RIVER
CSJ 0156-03-045
Proj ID STP 2013(234)
Work Type OVERLAY
 
4.518 844419.71 0.00 0.00 0.0
Work Order 02-05-13
Work Began 00-00-00
Work Completed  
Time Computed 04-06-13
Contract Working Days 32
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0156-03-045
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12123032
Totals 844419.71 0.00 0.00 0.0

CountyBAYLOR
Highway US 277
From 2.78 MILES EAST OF RM 1919
To 0.64 MILES EAST OF US 183/283
CSJ 0156-06-039
Proj ID C 156-6-39
Work Type WIDEN NON - FREEWAY
 
5.896 10550963.24 348744.81 5283310.28 50.0
Work Order 08-20-12
Work Began 09-10-12
Work Completed  
Time Computed 09-10-12
Contract Working Days 269
Addl Days Granted 10
Working Days Charged 144
Percent Time Used 51
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0156-06-039
CONTRACTORS SERVICE COMPANY(0.26%)
TEX OP CONSTRUCTION, LP(0.28%)
W.S. CONSTRUCTION COMPANY(6.55%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.10%)
ZACK BURKETT CO. ( 26.33%)
WILLIS ELECTRIC CO., LP(1.32%)
WEST TEXAS RUMBLE STRIP(0.08%)
Contract # 06123203
Totals 10550963.24 348744.81 5283310.28 50.0

CountyBAYLOR
Highway US 277
From KNOX COUNTY LINE
To 2.155 MILES WEST OF US 183
CSJ 0157-01-062
Proj ID NH 2013(235)
Work Type WIDEN NON - FREEWAY
 
11.161 11926754.60 615039.37 1128349.57 9.4
Work Order 02-06-13
Work Began 03-25-13
Work Completed  
Time Computed 03-25-13
Contract Working Days 385
Addl Days Granted 0
Working Days Charged 23
Percent Time Used 5
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0157-01-062
W.S. CONSTRUCTION COMPANY(5.55%)
CONTRACTORS SERVICE COMPANY(0.36%)
WEST TEXAS RUMBLE STRIP(0.07%)
ZACK BURKETT CO. ( 26.21%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.40%)
Contract # 12123202
Totals 11926754.60 615039.37 1128349.57 9.4

CountyCOOKE
Highway IH 35 ETC
From NEAR FM 1202
To NEAR US 82
CSJ 0194-02-087
Proj ID STP 2011(441)ES
Work Type UPGRADING OF FREEWAY FACILITY
 
12.652 14049262.01 162661.39 13950084.87 99.2
Work Order 11-04-10
Work Began 02-14-11
Work Completed  
Time Computed 02-14-11
Contract Working Days 600
Addl Days Granted 0
Working Days Charged 558
Percent Time Used 93
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0194-02-087
WRIGHT CONSTRUCTION CO., INC.( 13.36%)
ALLSTATE SIGNAL & CONSTRUCTION, LLC(9.73%)
HIGHWAY TECHNOLOGIES, INC. (1.12%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.04%)
FARR FOUNDATION, INC.(0.14%)
JAGOE-PUBLIC COMPANY (7.70%)
LONE STAR MANHOLE & STRUCTURES, LLC(1.98%)
BRENDA PRICE TRUCKING(0.23%)
TEXAS SHAFTS, INC. (0.18%)
SCOTT DERR PAINTING CO (0.25%)
DUSTROL, INC. (ROANOKE)(0.15%)
BREDA COMPANY, INC.(0.78%)
SKAGGS ROAD BORING INC.(3.17%)
C & C DIRECTIONAL BORING (0.20%)
J. E. GUZMAN CONSTRUCTION, INC.(0.09%)
RUSSO CORPORATION(0.19%)
KEY'S TAPPING & CONSTRUCTION SERVICES, INC.(0.00%)
A & A CONSTRUCTION (0.59%)
A-1 ASPHALT PAVING (0.08%)
MCRYAN HAULING, INC. (0.51%)
SOUTHWEST CONSTRUCTION SERVICES(0.56%)
PACIFICPAINT CO. (1.17%)
ANTIGO CONSTRUCTION, INC.(0.17%)
FORTSON CONTRACTING, INC.(0.36%)
STOMPER DEMOLITION COMPANY, INC. (0.30%)
SOUTHEAST GRINDING & GROOVING, LLC (0.07%)
GLS MASONRY, INC.(0.50%)
DOWN UNDER CONSTRUCTION(0.02%)
Contract # 09103002
Totals 14049262.01 162661.39 13950084.87 99.2

CountyCOOKE
Highway FM 51
From FM 1306
To FM 922
CSJ 0312-01-072
Proj ID STP 2013(469)
Work Type ASPHALTIC CONCRETE PAVEMENT OVERLAY
 
11.855 2224039.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 39
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0312-01-072
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03133212
Totals 2224039.60 0.00 0.00 0.0

CountyBAYLOR
Highway FM 422
From US 82
To EAST CITY LIMITS OF SEYMOUR
CSJ 0814-01-027
Proj ID C 814-1-27
Work Type UPGRADING OF A NON - FREEWAY FACILITY
 
0.847 3332046.95 89766.00 1347124.26 40.4
Work Order 09-13-12
Work Began 02-11-13
Work Completed  
Time Computed 02-11-13
Contract Working Days 245
Addl Days Granted 0
Working Days Charged 45
Percent Time Used 18
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0814-01-027
W.S. CONSTRUCTION COMPANY( 36.49%)
CONTRACTORS SERVICE COMPANY(0.56%)
TEXAS ALTERNATIVE GRASSER, INC.(0.55%)
ZACK BURKETT CO. ( 26.68%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.02%)
WILLIS ELECTRIC CO., LP(4.81%)
Contract # 07123006
Totals 3332046.95 89766.00 1347124.26 40.4

CountyCOOKE
Highway FM 373
From NEAR CR 450
To US 82
CSJ 0823-01-028
Proj ID STP 2013(337)
Work Type RESTORATION
 
16.030 1701551.66 0.00 0.00 0.0
Work Order 03-19-13
Work Began 05-01-13
Work Completed  
Time Computed 04-04-13
Contract Working Days 69
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 14
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0823-01-028
HIGHWAY TECHNOLOGIES, INC. (0.30%)
LANCO TURF & SEEDING, INC. (1.30%)
STRIPING TECHNOLOGY, L.P.(3.19%)
Contract # 01133214
Totals 1701551.66 0.00 0.00 0.0

CountyMONTAGUE
Highway FM 455
From MONTAGUE
To FM 1749
CSJ 0845-01-016
Proj ID STP 2013(686)
Work Type REHABILTATION OF EXISTING ROADWAY
 
14.179 3371976.79 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 151
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0845-01-016
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05133231
Totals 3371976.79 0.00 0.00 0.0

CountyWICHITA
Highway CS
From IN CITY OF WFS, AT CITY VIEW ELEM
To ON CITY VIEW DRIVE AND CRESCENT LN
CSJ 0903-03-096
Proj ID STP 1102(526)SRS
Work Type SAFE ROUTES TO SCHOOL 2009 PROGRAM
 
1.500 781215.78 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 06-03-13
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KEN-DO CONTRACTING, LP
SUBCONTRACTOR(S) FOR CCSJ: 0903-03-096
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03133209
Totals 781215.78 0.00 0.00 0.0

CountyMONTAGUE
Highway CR
From CR 410 (DEEN ROAD) AT BRANCH OF
To DENTON CREEK
CSJ 0903-28-049
Proj ID BR 2012(768)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.200 616009.30 0.00 0.00 0.0
Work Order 04-10-13
Work Began 04-30-13
Work Completed  
Time Computed 04-26-13
Contract Working Days 101
Addl Days Granted 0
Working Days Charged 2
Percent Time Used 1
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-28-049
ODUM SERVICES, L.P.(3.23%)
CROSSROADS, L.P. (0.68%)
TEXAS ALTERNATIVE GRASSER, INC.(0.42%)
Contract # 02133221
Totals 616009.30 0.00 0.00 0.0

CountyMONTAGUE
Highway FM 677
From 1.42 MILES NORTH OF STAR MANN ROAD
To 0.136 MILES SW OF FM 1630
CSJ 1352-01-019
Proj ID STP 2013(152)HES
Work Type REHABILITATION OF EXISTING ROADWAY
 
5.000 2497972.59 170020.55 607547.48 24.3
CountyMONTAGUE
Highway FM 677
From US 82
To 1.42 MI NORTH OF STAR MANN ROAD
CSJ 1352-01-020
Proj ID STP 2013(153)
Work Type REHABILITATION OF EXISTING ROADWAY
 
4.112 606688.27 0.00 0.00 0.0
Work Order 12-03-12
Work Began 01-21-13
Work Completed  
Time Computed 01-21-13
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 45
Percent Time Used 30
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1352-01-019
NORTH TEXAS CONTRACTING, INC.(8.81%)
HIGHWAY TECHNOLOGIES, INC. (1.85%)
HJC FARMS, INC.(0.95%)
HIGHWAY TECHNOLOGIES, INC. (0.45%)
J. E. GUZMAN CONSTRUCTION, INC.(1.94%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.42%)
Contract # 11123219
Totals 3104660.86 170020.55 607547.48 19.5

CountyWILBARGER
Highway FM 3207
From US 70
To FM 433
CSJ 3317-01-005
Proj ID STP 2012(687)
Work Type REHABILITATION OF EXISTING ROAD
 
4.982 2961200.50 238528.74 1425951.75 48.1
Work Order 09-17-12
Work Began 11-19-12
Work Completed  
Time Computed 11-16-12
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 89
Percent Time Used 49
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 3317-01-005
HIGHWAY TECHNOLOGIES, INC. (2.73%)
DUSTROL, INC.(0.21%)
W.S. CONSTRUCTION COMPANY( 16.17%)
WILLIS ELECTRIC CO., LP(1.18%)
TEXAS ALTERNATIVE GRASSER, INC.(0.30%)
COTHRAN TRUCKING, LLC(1.14%)
Contract # 08123242
Totals 2961200.50 238528.74 1425951.75 48.1

page 1