Monthly State Let Maintenance Report For Waco District As Of Jul 14, 2017 Page 1 Of 3

Last Update: Monday, July 17, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMCLENNAN
Highway0000000
From100 SOUTH LOOP DR
ToWACO TX 76704
CSJ4704-01-518
Proj IDCBC - 470401518
Work TypeRENOVATION OR REPAIR
 
0.001448094.490.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TD INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-518
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164222
Totals448094.490.000.000.0

CountyFALLS
HighwaySH0014
FromVARIOUS ROADWAYS IN
ToFALLS COUNTY
CSJ6270-61-001
Proj IDRMC - 627061001
Work TypeBASE FAILURE PAVEMENT REPAIR
 
0.010670190.00658724.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-14-14
Work Began10-17-14
Work Completed12-31-14
Time Computed09-15-14
Contract Working Days60
Addl Days Granted0
Working Days Charged40
Percent Time Used66
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6270-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06144002
Totals670190.000.00658724.00100.0

CountyLIMESTONE
HighwaySH0007
FromVARIOUS ROADWAYS IN
ToLIMESTONE COUNTY
CSJ6270-64-001
Proj IDRMC - 627064001
Work TypeBASE FAILURE PVMNT REPAIR AND ACP O/L
 
0.010571952.00728745.77100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-01-14
Work Began11-19-14
Work Completed01-31-15
Time Computed11-17-14
Contract Working Days60
Addl Days Granted0
Working Days Charged32
Percent Time Used53
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6270-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06144204
Totals571952.000.00728745.77100.0

CountyLIMESTONE
HighwayFM0027
FromVARIOUS ROADWAYS IN LIMESTONE, CORYELL,
ToBELL AND HILL COUNTIES
CSJ6275-39-001
Proj IDRMC - 627539001
Work TypeCULVERT REPLACEMENT
 
0.010656534.42545433.5983.0
Work Order11-09-16
Work Began11-15-16
Work Completed
Time Computed11-15-16
Contract Working Days101
Addl Days Granted12
Working Days Charged92
Percent Time Used81
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6275-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164006
Totals656534.4242437.88545433.5983.0

CountyMCLENNAN
HighwayUS0084
FromVARIOUS ROADWAYS IN THE
ToWACO DISTRICT
CSJ6277-22-001
Proj IDRMC - 627722001
Work TypeTRAFFIC SIGNAL INSTALL & MAINTAIN
 
0.010778699.43356849.93100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-23-15
Work Began03-16-15
Work Completed02-02-17
Time Computed02-02-15
Contract Working Days730
Addl Days Granted0
Working Days Charged730
Percent Time Used100
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6277-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10144005
Totals778699.430.00356849.93100.0

CountyMCLENNAN
HighwayUS0084
FromVARIOUS ROADWAYS IN FALLS, HILL,
ToLIMESTONE AND MCLENNAN COUNTIES
CSJ6279-09-001
Proj IDRMC - 627909001
Work TypeMETAL BEAM GUARD TENCE, ETC.
 
0.010305968.00416050.50100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-13-15
Work Began01-23-15
Work Completed02-29-16
Time Computed01-20-15
Contract Working Days365
Addl Days Granted120
Working Days Charged405
Percent Time Used83
Contractor(s)
T & L CLEANING SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6279-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11144210
Totals305968.000.00416050.50100.0

CountyBOSQUE
HighwaySH0006
FromVARIOUS LOCATIONS IN BELL,BOSQUE,CORYELL
ToFALLS,HAMILTON,HILL,LIMSTONE & MCLENNAN
CSJ6279-70-001
Proj IDRMC - 627970001
Work TypeFLAGGING AND TRAFFIC CONTROL
 
0.1001686130.002580334.8499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-23-15
Work Began02-02-15
Work Completed
Time Computed02-09-15
Contract Working Days365
Addl Days Granted109
Working Days Charged474
Percent Time Used100
Contractor(s)
N-LINE TRAFFIC MAINTENANCE, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6279-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11144211
Totals1686130.000.002580334.8499.9

CountyBELL
HighwayUS0190
FromVARIOUS ROADWAYS IN
ToBELL COUNTY
CSJ6284-31-001
Proj IDRMC - 628431001
Work TypeBASE FAILURE PAVEMENT REPAIR
 
0.1001131366.901309171.9999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-10-15
Work Began00-00-00
Work Completed
Time Computed09-21-15
Contract Working Days42
Addl Days Granted0
Working Days Charged31
Percent Time Used73
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6284-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04154204
Totals1131366.900.001309171.9999.9

CountyMCLENNAN
HighwayIH0035
FromIH 35, IH 35E & IH 35W IN BELL, FALLS
ToHILL AND MCLENNAN COUNTIES
CSJ6285-72-001
Proj IDRMC - 628572001
Work TypePERFORMANCE BASED MAINT. OF HIGHWAYS
 
115.50020967966.007786272.7137.1
Work Order08-24-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days1,095
Addl Days Granted0
Working Days Charged303
Percent Time Used27
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6285-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05164007
Totals20967966.00510237.557786272.7137.1

CountyFALLS
HighwaySH0006
FromVARIOUS ROADWAYS IN BELL, BOSQUE, FALLS,
ToCORYELL AND MCLENNAN COUNTIES
CSJ6285-76-001
Proj IDRMC - 628576001
Work TypeMISC. CONCRETE REPAIRS
 
0.010856608.20594962.8969.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-25-16
Work Began01-27-16
Work Completed
Time Computed02-03-16
Contract Working Days50
Addl Days Granted50
Working Days Charged100
Percent Time Used100
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6285-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07154002
Totals856608.200.00594962.8969.4

CountyMCLENNAN
HighwayUS0084
FromVARIOUS ROADWAYS IN BOSQUE, HAMILTON,
ToHILL AND MCLENNAN COUNTIES
CSJ6286-37-001
Proj IDRMC - 628637001
Work TypeMULTI-COUNTY PAVEMENT MARKINGS
 
0.010994910.25799890.67100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-12-15
Work Began11-16-15
Work Completed11-22-16
Time Computed11-16-15
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6286-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06154003
Totals994910.250.00799890.67100.0

CountyBELL
HighwayUS0190
FromVARIOUS ROADWAYS IN BELL, CORYELL, FALLS
ToAND LIMESTONE COUNTIES
CSJ6286-38-001
Proj IDRMC - 628638001
Work TypeDISTRICT WIDE PAVEMENT MARKINGS
 
0.100938936.001287172.99100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-09-15
Work Began11-10-15
Work Completed11-09-16
Time Computed11-10-15
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6286-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06154203
Totals938936.000.001287172.99100.0

CountyHAMILTON
HighwayFM0221
FromVARIOUS ROADWAYS IN HAMILTON AND
ToCORYELL COUNTIES
CSJ6289-04-001
Proj IDRMC - 628904001
Work TypeCEMENT STABILIZED BASE REPAIR
 
0.1001632623.401392706.50100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-18-15
Work Began01-04-16
Work Completed10-14-16
Time Computed11-30-15
Contract Working Days31
Addl Days Granted0
Working Days Charged31
Percent Time Used100
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6289-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08154201
Totals1632623.400.001392706.50100.0

CountyBELL
HighwayFS1237
FromBELL-BOSQUE-CORYELL-FALLS-HAMILTON
ToHILL-LIMESTONE-MCLENNAN
CSJ6292-90-001
Proj IDRMC - 629290001
Work TypeSEAL COAT
 
0.1003195392.723086596.79100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-31-16
Work Began06-06-16
Work Completed09-13-16
Time Computed05-23-16
Contract Working Days40
Addl Days Granted8
Working Days Charged54
Percent Time Used112
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6292-90-001
FLASHER EQUIPMENT COMPANY (2.45)
PAVEMENT MARKINGS INC. (17.74)
Contract #12154004
Totals3195392.720.003086596.79100.0

CountyHILL
HighwaySH0171
FromVARIOUS RDWAYS IN HILL-BELL-BOSQUE-
ToCORYELL-FALLS-HAMILTON-LIMESTON-MCLENNAN
CSJ6295-20-001
Proj IDRMC - 629520001
Work TypeDRIFT/DEBRIS REMOVAL
 
0.100493500.00230837.4046.7
Work Order04-05-16
Work Began04-11-16
Work Completed
Time Computed04-11-16
Contract Working Days210
Addl Days Granted0
Working Days Charged21
Percent Time Used10
Contractor(s)
M & S CONCRETE CO.
SUBCONTRACTOR(S) FOR CCSJ: 6295-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12154204
Totals493500.000.00230837.4046.7

CountyMCLENNAN
HighwayUS0084
FromVARIOUS ROADWAYS IN FALLS, HILL,
ToLIMESTONE AND MCLENNAN COUNTIES
CSJ6295-39-001
Proj IDRMC - 629539001
Work TypeMBGF, CABLE BARRIER & BRIDGE RAIL REP/IN
 
0.010740600.00337886.5045.6
Work Order03-14-16
Work Began03-21-16
Work Completed
Time Computed03-24-16
Contract Working Days365
Addl Days Granted180
Working Days Charged465
Percent Time Used85
Contractor(s)
T & L CLEANING SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6295-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01164003
Totals740600.0033655.00337886.5045.6

CountyBELL
HighwayUS0190
FromVARIOUS ROADWAYS IN BELL, BOSQUE,
ToCORYELL & HAMILTON COUNTIES
CSJ6295-40-001
Proj IDRMC - 629540001
Work TypeMBGF, CABLE BARRIER & BRIDGE RAIL REP/IN
 
0.010386912.50510132.02100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-10-16
Work Began03-14-16
Work Completed04-30-17
Time Computed03-14-16
Contract Working Days365
Addl Days Granted0
Working Days Charged345
Percent Time Used94
Contractor(s)
T & L CLEANING SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6295-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01164013
Totals386912.500.00510132.02100.0

CountyBOSQUE
HighwaySH0006
FromVAR RDWYS IN BELL, BOSQUE, FALLS, HILL,
ToCORYELL, HAMILTON, LIMESTONE & MCLENNAN
CSJ6296-38-001
Proj IDRMC - 629638001
Work TypeFLAGGING AND TRAFFIC CONTROL
 
0.0102032835.001691929.4483.2
Work Order05-26-16
Work Began06-01-16
Work Completed
Time Computed06-01-16
Contract Working Days365
Addl Days Granted92
Working Days Charged389
Percent Time Used85
Contractor(s)
N-LINE TRAFFIC MAINTENANCE, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6296-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03164203
Totals2032835.00165543.811691929.4483.2

CountyBELL
HighwayUS0190
FromVARIOUS ROADWAYS IN
ToBELL COUNTY
CSJ6298-26-001
Proj IDRMC - 629826001
Work TypeBASE FAILURE PAVEMENT REPAIR
 
0.1001855386.001536032.95100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-30-16
Work Began10-03-16
Work Completed01-26-17
Time Computed10-01-16
Contract Working Days80
Addl Days Granted0
Working Days Charged35
Percent Time Used43
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6298-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03164204
Totals1855386.000.001536032.95100.0

CountyBOSQUE
HighwaySH0022
FromVARIOUS ROADWAYS IN
ToBOSQUE COUNTY
CSJ6298-27-001
Proj IDRMC - 629827001
Work TypeBASE FAILURE PAVEMENT REPAIR
 
0.010568330.60426153.0074.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-22-16
Work Began09-06-16
Work Completed
Time Computed05-09-16
Contract Working Days40
Addl Days Granted0
Working Days Charged16
Percent Time Used40
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6298-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02164215
Totals568330.600.00426153.0074.9

page 1 | page 2 | page 3