Monthly State Let Maintenance Report For Waco District As Of Apr 12, 2024 Page 1 Of 3

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyFALLS
HighwaySH0014
FromVARIOUS ROADWAYS IN
ToFALLS COUNTY
CSJ6270-61-001
Proj IDRMC - 627061001
Work TypeBASE FAILURE PAVEMENT REPAIR
 
0.010670190.00658724.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-14-14
Work Began10-17-14
Work Completed12-31-14
Time Computed09-15-14
Contract Working Days60
Addl Days Granted0
Working Days Charged40
Percent Time Used66
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6270-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06144002
Totals670190.000.00658724.00100.0

CountyMCLENNAN
HighwayFM1858
FromVAR RDWYS IN BELL, CORYELL, FALLS, HILL,
ToLIMESTONE AND MCLENNAN COUNTIES
CSJ6347-55-001
Proj IDRMC - 634755001
Work TypeSEAL COAT
 
0.0101537362.721733040.97100.0
Work Order00-00-00
Work Began06-08-20
Work Completed06-26-20
Time Computed03-02-20
Contract Working Days26
Addl Days Granted0
Working Days Charged16
Percent Time Used61
Contractor(s)
F. N. PLOCH CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6347-55-001
FLASHER EQUIPMENT COMPANY (1.43)
STRIPE-A-ZONE, INC. (16.58)
BRYDL CONTRACTING, INC. (1.21)
Contract #09194018
Totals1537362.7217605.401733040.97100.0

CountyCORYELL
HighwayFM0185
FromVARIOUS ROADWAYS
ToIN THE WACO DISTRICT
CSJ6377-87-001
Proj IDRMC - 637787001
Work TypeCULVERT REPAIR
 
0.010486782.00328750.50100.0
Work Order01-24-22
Work Began03-16-22
Work Completed02-26-24
Time Computed10-31-21
Contract Working Days365
Addl Days Granted365
Working Days Charged730
Percent Time Used100
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6377-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08214216
Totals486782.000.00328750.50100.0

CountyMCLENNAN
HighwaySH0317
FromVARIOUS NON SITE-SPECIFIC LOCATION
ToDISTRICTWIDE
CSJ6379-48-001
Proj IDRMC - 637948001
Work TypeREFLECTIVE PAVEMENT MARKINGS (LONG LINE)
 
0.01041110.0030789.00100.0
Work Order01-09-24
Work Began01-19-24
Work Completed04-05-24
Time Computed12-25-23
Contract Working Days45
Addl Days Granted0
Working Days Charged41
Percent Time Used91
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6379-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10234028
Totals41110.002121.0030789.00100.0

CountyHILL
HighwaySH0081
FromVARIOUS ROADWAYS
ToIN HILL COUNTY
CSJ6389-03-001
Proj IDRMC - 638903001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010474772.28923041.76100.0
Work Order06-01-22
Work Began06-03-22
Work Completed03-11-24
Time Computed01-15-22
Contract Working Days365
Addl Days Granted365
Working Days Charged622
Percent Time Used85
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6389-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11214227
Totals474772.280.00923041.76100.0

CountyLIMESTONE
HighwaySH0014
FromVARIOUS ROADWAYS
ToIN LIMESTONE COUNTY
CSJ6389-05-001
Proj IDRMC - 638905001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010302523.79627595.87100.0
Work Order05-18-22
Work Began05-23-22
Work Completed03-11-24
Time Computed01-15-22
Contract Working Days365
Addl Days Granted365
Working Days Charged655
Percent Time Used89
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6389-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11214027
Totals302523.790.00627595.87100.0

CountyHILL
HighwaySH0171
FromVARIOUS LOCATIONS
ToACROSS DISTRICT
CSJ6393-00-001
Proj IDRMC - 639300001
Work TypeBRIDGE REPAIR
 
0.010762432.00814109.50100.0
Work Order06-01-22
Work Began06-01-22
Work Completed10-12-23
Time Computed03-31-22
Contract Working Days365
Addl Days Granted23
Working Days Charged388
Percent Time Used100
Contractor(s)
STRUCTURAL INTEGRITY GROUP LLC
SUBCONTRACTOR(S) FOR CCSJ: 6393-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01224020
Totals762432.000.00814109.50100.0

CountyMCLENNAN
HighwayUS0084
FromVARIOUS NON-SITE SPECIFIC LOCATIONS
ToIN WACO DISTRICT
CSJ6393-10-001
Proj IDRMC - 639310001
Work TypeILLUMINATION MAINTENANCE
 
0.010992172.50446120.2544.9
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed12-20-23
Contract Working Days135
Addl Days Granted90
Working Days Charged26
Percent Time Used11
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6393-10-001
KRL CONSTRUCTION INC. (0.80)
PRIMETEX MATERIALS LLC (1.00)
Contract #11234224
Totals992172.50446120.25446120.2544.9

CountyBELL
HighwaySH0317
FromVARIOUS LOCATIONS
ToDISTRICTWIDE
CSJ6396-65-001
Proj IDRMC - 639665001
Work TypeRAISED PAVEMENT MARKERS
 
0.010383593.601108116.6599.9
Work Order00-00-00
Work Began06-15-22
Work Completed
Time Computed04-30-22
Contract Working Days365
Addl Days Granted365
Working Days Charged650
Percent Time Used89
Contractor(s)
BRYDL CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6396-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03224020
Totals383593.60281573.941108116.6599.9

CountyBELL
HighwaySH0317
FromVARIOUS ROADWAYS
ToDISTRICTWIDE
CSJ6398-50-001
Proj IDRMC - 639850001
Work TypePAVEMENT MARKINGS
 
0.0104082624.003846056.6394.2
Work Order00-00-00
Work Began01-17-23
Work Completed
Time Computed10-20-22
Contract Working Days365
Addl Days Granted365
Working Days Charged435
Percent Time Used59
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6398-50-001
BATTERSON, LLP (35.70)
Contract #09224219
Totals4082624.00685201.503846056.6394.2

CountyHILL
HighwayFM3050
FromHILL, FALLS, AND LIMESTONE COUNTIES
ToHILL, FALLS, AND LIMESTONE COUNTIES
CSJ6401-10-001
Proj IDRMC - 640110001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.010368714.00671958.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-04-22
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged572
Percent Time Used78
Contractor(s)
PATHFIELD INVESTMENTS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6401-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06224431
Totals368714.000.00671958.0099.9

CountyBELL
HighwayUS0190
FromVARIOUS LOCATIONS
ToIN VARIOU COUNTIES
CSJ6413-59-001
Proj IDRMC - 641359001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010821056.001368022.9599.9
Work Order12-01-22
Work Began12-07-22
Work Completed
Time Computed12-01-22
Contract Working Days365
Addl Days Granted365
Working Days Charged481
Percent Time Used65
Contractor(s)
T&L CLEANING SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6413-59-001
CROSS PLUS CONSTRUCTION, LLC (3.65)
Contract #10224026
Totals821056.00193768.601368022.9599.9

CountyMCLENNAN
HighwaySH0006
FromVARIOUS LOCATIONS
ToIN VARIOUS COUNTIES
CSJ6413-61-001
Proj IDRMC - 641361001
Work TypeBRIDGE RAIL REPAIR
 
0.010970926.001382137.7099.9
Work Order12-12-22
Work Began12-20-22
Work Completed
Time Computed12-13-22
Contract Working Days365
Addl Days Granted365
Working Days Charged469
Percent Time Used64
Contractor(s)
T&L CLEANING SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6413-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10224221
Totals970926.0038683.201382137.7099.9

CountyMCLENNAN
HighwayUS0084
FromVARIOUS ROADWAYS
ToIN WACO DISTRICT
CSJ6418-45-001
Proj IDMMC - 641845001
Work TypeFLEXIBLE BASE
 
0.0101237214.00790636.37100.0
Work Order01-24-23
Work Began03-20-23
Work Completed02-23-24
Time Computed01-25-23
Contract Working Days183
Addl Days Granted182
Working Days Charged365
Percent Time Used100
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6418-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12224212
Totals1237214.000.00790636.37100.0

CountyCORYELL
HighwayFM0116
FromVARIOUS LOCATIONS
ToACROSS CORYELL COUNTY
CSJ6420-83-001
Proj IDRMC - 642083001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010503987.28442431.4887.7
Work Order03-01-23
Work Began05-15-23
Work Completed
Time Computed03-01-23
Contract Working Days365
Addl Days Granted365
Working Days Charged397
Percent Time Used54
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6420-83-001
THE RANGER CO (10.85)
Contract #12224013
Totals503987.2831443.20442431.4887.7

CountyBOSQUE
HighwayFM0056
FromVARIOUS LOCATIONS
ToIN WACO DISTRICT
CSJ6420-99-001
Proj IDRMC - 642099001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0102857805.002744666.2596.0
Work Order02-17-23
Work Began03-01-23
Work Completed
Time Computed03-01-23
Contract Working Days365
Addl Days Granted365
Working Days Charged391
Percent Time Used53
Contractor(s)
AWP SAFETY
SUBCONTRACTOR(S) FOR CCSJ: 6420-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11224214
Totals2857805.00202391.252744666.2596.0

CountyMCLENNAN
HighwaySH0006
FromVARIOUS LOCATIONS
ToIN WACO DISTRICT
CSJ6421-19-001
Proj IDRMC - 642119001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.010305123.97286954.27100.0
Work Order03-08-23
Work Began04-04-23
Work Completed03-25-24
Time Computed03-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged348
Percent Time Used95
Contractor(s)
T & M LAWN-FENCE SERVICE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6421-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12224216
Totals305123.970.00286954.27100.0

CountyMCLENNAN
HighwayUS0084
FromVARIOUS LOCATIONS
ToACROSS MCLENNAN, BELL, AND HILL
CSJ6427-15-001
Proj IDRMC - 642715001
Work TypeCONCRETE SPALL REPAIR
 
0.0101892905.001481450.6178.2
Work Order00-00-00
Work Began07-18-23
Work Completed
Time Computed07-15-23
Contract Working Days365
Addl Days Granted0
Working Days Charged253
Percent Time Used69
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6427-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05234027
Totals1892905.0082654.731481450.6178.2

CountyLIMESTONE
HighwayUS0084
FromVARIOUS ROADWAYS
ToIN WACO DISTRICT
CSJ6428-86-001
Proj IDMMC - 642886001
Work TypeEMULSION
 
0.010423500.00203086.37100.0
Work Order03-30-23
Work Began04-01-23
Work Completed04-05-24
Time Computed04-03-23
Contract Working Days183
Addl Days Granted182
Working Days Charged365
Percent Time Used100
Contractor(s)
WRIGHT ASPHALT PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 6428-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234233
Totals423500.0026958.48203086.37100.0

CountyMCLENNAN
HighwayFM3148
FromVARIOUS LOCATIONS
ToIN MCLENNAN COUNTY
CSJ6432-14-001
Proj IDRMC - 643214001
Work TypeBASE FAILURE PAVEMENT REPAIR
 
0.0101115328.671725097.8599.9
Work Order07-31-23
Work Began08-01-23
Work Completed
Time Computed08-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged228
Percent Time Used62
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6432-14-001
D. I. J. CONSTRUCTION, INC. (4.43)
Contract #03234235
Totals1115328.670.001725097.8599.9

page 1 | page 2 | page 3