| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | BELL |
| Highway |
0000000 |
| From |
SOUTH LOOP 121 |
| To |
SOUT LOOP 122 AT CONNELL ST |
| CSJ |
4704-00-668 |
| Proj ID |
CBC - 470400668 |
| Work Type |
NEW AREA ENGINEER / MAINTENANCE FACILITY |
| |
|
0.001 |
3339453.00 |
0.00 |
3250331.00 |
97.3 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
05-03-07 |
| Work Began |
05-19-07 |
| Work Completed |
|
| Time Computed |
05-19-07 |
| Contract Working Days |
360 |
| Addl Days Granted |
0 |
| Working Days Charged |
356 |
| Percent Time Used |
98 |
| Contractor(s) |
| ROTH CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 4704-00-668 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
04074024 |
|
Totals |
3339453.00 |
0.00 |
3250331.00 |
97.3 |
|
| County | MCLENNAN |
| Highway |
0000000 |
| From |
7703 BAGBY |
| To |
7703 BAGBY |
| CSJ |
4704-00-672 |
| Proj ID |
CBC - 470400672 |
| Work Type |
NEW CONSTRUCTION |
| |
|
0.010 |
3260000.00 |
0.00 |
2589211.80 |
83.6 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
08-21-07 |
| Work Began |
09-06-07 |
| Work Completed |
|
| Time Computed |
09-06-07 |
| Contract Working Days |
360 |
| Addl Days Granted |
0 |
| Working Days Charged |
331 |
| Percent Time Used |
91 |
| Contractor(s) |
| RBR CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 4704-00-672 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
07074025 |
|
Totals |
3260000.00 |
0.00 |
2589211.80 |
83.6 |
|
| County | MCLENNAN |
| Highway |
IH0035 |
| From |
WILLIAMSON/BELL COUNTY LINE |
| To |
HILL/JOHNSON COUNTY LINE |
| CSJ |
6114-26-001 |
| Proj ID |
RMC - 611426001 |
| Work Type |
TOTAL MAINTENANCE AND OPERATION OF HWY |
| |
|
115.000 |
29420000.00 |
404014.41 |
22202738.93 |
81.2 |
| Work Order |
11-01-04 |
| Work Began |
11-01-04 |
| Work Completed |
|
| Time Computed |
11-01-04 |
| Contract Working Days |
1,826 |
| Addl Days Granted |
0 |
| Working Days Charged |
1,461 |
| Percent Time Used |
80 |
| Contractor(s) |
| VMS MAINTENANCE SYSTEMS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6114-26-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
08044001 |
|
Totals |
29420000.00 |
404014.41 |
22202738.93 |
81.2 |
|
| County | CORYELL |
| Highway |
US0084 |
| From |
ALL STATE MAINTAINED ROADWAYS IN BELL |
| To |
BOSQUE, CORYELL, AND HAMILTON COUNTIES |
| CSJ |
6165-40-001 |
| Proj ID |
RMC - 616540001 |
| Work Type |
MOWING HIGHWAY RIGHT OF WAY |
| |
|
999.990 |
1845304.24 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
160 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| TEXAS MOWING SERVICE |
SUBCONTRACTOR(S) FOR CCSJ: 6165-40-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
08074010 |
|
Totals |
1845304.24 |
0.00 |
0.00 |
0.0 |
|
| County | MCLENNAN |
| Highway |
US0084 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6167-24-001 |
| Proj ID |
RMC - 616724001 |
| Work Type |
BASE REP, PLANING, ACP INLAY & OVERLAY |
| |
|
0.100 |
655050.00 |
118359.90 |
546691.25 |
84.0 |
| Work Order |
12-03-07 |
| Work Began |
12-17-07 |
| Work Completed |
|
| Time Computed |
12-12-07 |
| Contract Working Days |
60 |
| Addl Days Granted |
0 |
| Working Days Charged |
63 |
| Percent Time Used |
105 |
| Contractor(s) |
| BIG CREEK CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 6167-24-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10074003 |
|
Totals |
655050.00 |
118359.90 |
546691.25 |
84.0 |
|
| County | BELL |
| Highway |
US0190 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6170-18-001 |
| Proj ID |
RMC - 617018001 |
| Work Type |
METAL BEAM GUARD FENCE AND BRIDGE RAIL |
| |
|
1.000 |
583385.00 |
32026.25 |
535375.25 |
91.7 |
| Work Order |
03-28-08 |
| Work Began |
04-04-08 |
| Work Completed |
|
| Time Computed |
04-07-08 |
| Contract Working Days |
210 |
| Addl Days Granted |
0 |
| Working Days Charged |
19 |
| Percent Time Used |
9 |
| Contractor(s) |
| VANN/ELLI, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6170-18-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
01084026 |
|
Totals |
583385.00 |
32026.25 |
535375.25 |
91.7 |
|
| County | MCLENNAN |
| Highway |
SH0006 |
| From |
VARIOUS LOCATIONS IN BOSQUE, HAMILTON, |
| To |
HILL, LIMESTONE AND MCLENNAN COUNTIES |
| CSJ |
6171-77-001 |
| Proj ID |
RMC - 617177001 |
| Work Type |
GUARDRAIL, BRIDGERAIL AND DELIN REP / UPGR |
| |
|
0.010 |
1163550.00 |
0.00 |
151799.50 |
16.2 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
04-22-08 |
| Work Began |
05-31-08 |
| Work Completed |
|
| Time Computed |
05-31-08 |
| Contract Working Days |
200 |
| Addl Days Granted |
0 |
| Working Days Charged |
31 |
| Percent Time Used |
15 |
| Contractor(s) |
| T & L CLEANING SERVICES |
SUBCONTRACTOR(S) FOR CCSJ: 6171-77-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
01084006 |
|
Totals |
1163550.00 |
0.00 |
151799.50 |
16.2 |
|
| County | MCLENNAN |
| Highway |
US0084 |
| From |
DISTRICT WIDE |
| To |
DISTRICT WIDE |
| CSJ |
6175-19-001 |
| Proj ID |
RMC - 617519001 |
| Work Type |
DISTRICT WIDE PAVEMENT MARKINGS |
| |
|
0.001 |
864196.40 |
318662.61 |
526543.79 |
60.9 |
| Work Order |
08-11-08 |
| Work Began |
08-13-08 |
| Work Completed |
|
| Time Computed |
08-20-08 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
80 |
| Percent Time Used |
21 |
| Contractor(s) |
| PAVEMENT MARKINGS INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6175-19-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
04084003 |
|
Totals |
864196.40 |
318662.61 |
526543.79 |
60.9 |
|
| County | HILL |
| Highway |
SH0171 |
| From |
VARIOUS ROADWAYS IN |
| To |
HILL COUNTY |
| CSJ |
6176-82-001 |
| Proj ID |
RMC - 617682001 |
| Work Type |
BASE REPAIR |
| |
|
1.000 |
484469.11 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
30 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| LINDSEY CONTRACTORS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6176-82-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
09084010 |
|
Totals |
484469.11 |
0.00 |
0.00 |
0.0 |
|
| County | HILL |
| Highway |
SH0171 |
| From |
VARIOUS LOCATIONS IN HILL, HAMILTON, |
| To |
AND MCLENNAN COUNTIES |
| CSJ |
6176-84-001 |
| Proj ID |
BPM - 617684001 |
| Work Type |
BRIDGE PREVENTIVE MAINTENANCE |
| |
|
0.100 |
437350.00 |
100419.60 |
447775.00 |
100.0 |
| Work Order |
06-24-08 |
| Work Began |
07-14-08 |
| Work Completed |
10-22-08 |
| Time Computed |
07-21-08 |
| Contract Working Days |
35 |
| Addl Days Granted |
0 |
| Working Days Charged |
36 |
| Percent Time Used |
102 |
| Contractor(s) |
| SCR CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6176-84-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
04084018 |
|
Totals |
437350.00 |
100419.60 |
447775.00 |
100.0 |
|
| County | MCLENNAN |
| Highway |
US0084 |
| From |
VARIOUS LOCATIONS |
| To |
IN MCLENNAN COUNTY |
| CSJ |
6177-03-001 |
| Proj ID |
RMC - 617703001 |
| Work Type |
BASE REPAIR, ACP INLAY AND OVERLAY |
| |
|
0.010 |
397306.50 |
327728.91 |
327728.91 |
82.4 |
| Work Order |
10-06-08 |
| Work Began |
10-21-08 |
| Work Completed |
|
| Time Computed |
10-06-08 |
| Contract Working Days |
45 |
| Addl Days Granted |
0 |
| Working Days Charged |
16 |
| Percent Time Used |
35 |
| Contractor(s) |
| LINDSEY CONTRACTORS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6177-03-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
05084002 |
|
Totals |
397306.50 |
327728.91 |
327728.91 |
82.4 |
|
| County | MCLENNAN |
| Highway |
IH0035 |
| From |
VARIOUS LOCATIONS ON IH 35 IN BELL, HILL |
| To |
FALLS, AND MCLENNAN COUNTIES |
| CSJ |
6177-31-001 |
| Proj ID |
RMC - 617731001 |
| Work Type |
MILL AND INLAY |
| |
|
0.010 |
777704.96 |
0.00 |
765331.70 |
99.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
06-25-08 |
| Work Began |
07-08-08 |
| Work Completed |
|
| Time Computed |
07-07-08 |
| Contract Working Days |
35 |
| Addl Days Granted |
11 |
| Working Days Charged |
47 |
| Percent Time Used |
102 |
| Contractor(s) |
| BIG CREEK CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 6177-31-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
04084017 |
|
Totals |
777704.96 |
0.00 |
765331.70 |
99.9 |
|
| County | LIMESTONE |
| Highway |
US0084 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6179-14-001 |
| Proj ID |
RMC - 617914001 |
| Work Type |
REPAIR OF BASE FAILURES |
| |
|
0.010 |
820558.30 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
10-10-08 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
11-03-08 |
| Contract Working Days |
30 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| LINDSEY CONTRACTORS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6179-14-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
08084019 |
|
Totals |
820558.30 |
0.00 |
0.00 |
0.0 |
|
| County | BELL |
| Highway |
SH0036 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6184-21-001 |
| Proj ID |
RMC - 618421001 |
| Work Type |
MBGF AND BRIDGE RAIL REPAIR / UPGRADE |
| |
|
0.010 |
729490.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
210 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| VANN/ELLI, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6184-21-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
09084011 |
|
Totals |
729490.00 |
0.00 |
0.00 |
0.0 |
|
| County | FALLS |
| Highway |
SH0006 |
| From |
VARIOUS |
| To |
VARIOUS |
| CSJ |
6185-12-001 |
| Proj ID |
RMC - 618512001 |
| Work Type |
CRACK SEAL |
| |
|
705.080 |
387794.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
71 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| KUNTZ CONTRACTING CORP. |
SUBCONTRACTOR(S) FOR CCSJ: 6185-12-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10084003 |
|
Totals |
387794.00 |
0.00 |
0.00 |
0.0 |
|