Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyBELL
Highway SH 195
From @ KILLEEN SOUTH CITY LIMITS
To .
CSJ 0836-02-069
Proj ID C 836-2-69
Work Type LANDSCAPE ENHANCE
 
0.051 292247.00 1000.00 275266.50 94.1
Work Order 07-30-15
Work Began 08-29-15
Work Completed  
Time Computed 08-31-15
Contract Working Days 64
Addl Days Granted 0
Working Days Charged 63
Percent Time Used 98
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0836-02-069
FLASHER EQUIPMENT COMPANY(0.87%)
Contract # 06153210
Totals 292247.00 1000.00 275266.50 94.1

CountyBELL
Highway SH 195
From US 190
To FM 3470
CSJ 0836-02-070
Proj ID NH 2015(873)
Work Type MILL / INLAY
 
2.216 1516922.75 219105.50 590569.95 38.9
Work Order 10-22-15
Work Began 04-22-16
Work Completed  
Time Computed 11-23-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 52
Percent Time Used 86
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0836-02-070
DUSTROL, INC.(3.84%)
CHEROKEE SERVICES(0.73%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (1.15%)
TRP CONSTRUCTION GROUP, LLC(4.88%)
Contract # 09153008
Totals 1516922.75 219105.50 590569.95 38.9

CountyMCLENNAN
Highway CS
From ON CS 065 @ TONK CRK
To (MAP #1 - CRAWFORD)
CSJ 0909-22-166
Proj ID BR 2014(445)
Work Type REPL BR & APPRS
 
0.084 755454.92 112758.21 112758.21 14.9
Work Order 04-20-16
Work Began 08-01-16
Work Completed  
Time Computed 06-20-16
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0909-22-166
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC(0.61%)
BEAIRD DRILLING(3.73%)
ROADWAY SPECIALTIES, INC.(5.08%)
1 PRIORITY ENVIRONMENTAL SERVICES, INC.(1.25%)
Contract # 02163023
Totals 755454.92 112758.21 112758.21 14.9

CountyHAMILTON
Highway CR
From ON CR 273 @ LEON RIVER
To (MAP #210)
CSJ 0909-29-020
Proj ID BR 99(346)
Work Type REPL BR & APPRS
 
0.094 906649.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-29-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 191
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FRITCHER CONSTRUCTION SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 0909-29-020
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06163212
Totals 906649.00 0.00 0.00 0.0

CountyBELL
Highway CR
From ON CR 493 @ SALADO
To CREEK (MAP#60)
CSJ 0909-36-137
Proj ID BR 2012(427)
Work Type REPL BR & APPRS
 
0.176 1202660.75 97713.00 247792.56 20.6
Work Order 01-29-16
Work Began 00-00-00
Work Completed  
Time Computed 04-28-16
Contract Working Days 149
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0909-36-137
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10153004
Totals 1202660.75 97713.00 247792.56 20.6

CountyFALLS
Highway CR
From ON CR 425 @ BRANCH
To OF N ELM CREEK (MAP #2038)
CSJ 0909-38-052
Proj ID BR 1402(048)
Work Type REPL BR & APPRS
 
0.082 272958.30 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-05-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ELLIS-MCGINNIS CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0909-38-052
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06163229
Totals 272958.30 0.00 0.00 0.0

CountyFALLS
Highway CR
From CR 221 @ BIG SANDY CRK BR
To (MAP #40)
CSJ 0909-38-072
Proj ID BR 1402(049)
Work Type REPL BR & APPRS
 
0.345 1169676.10 81113.75 529033.41 45.2
Work Order 07-07-15
Work Began 03-15-16
Work Completed  
Time Computed 09-06-15
Contract Working Days 489
Addl Days Granted 0
Working Days Charged 222
Percent Time Used 45
Contractor(s)
ELLIS-MCGINNIS CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0909-38-072
FORTSON CONTRACTING, INC.(3.06%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (8.64%)
MCL CONTRACTING, LLC (0.82%)
SAN-ANN-CO., INC.(1.29%)
Contract # 05153253
Totals 1169676.10 81113.75 529033.41 45.2

CountyHILL
Highway FM 933
From FM 1713
To FM 1244 IN WHITNEY
CSJ 1190-01-041
Proj ID STP 2013(688)
Work Type ROW ACQ.; RELOC. ASSIST.
 
2.894 318318.15 14140.00 257100.38 80.7
CountyHILL
Highway FM 933
From FM 1713
To FM 1244 IN WHITNEY
CSJ 1190-01-043
Proj ID HP 2013(358)
Work Type WDN, GR, STRS & SURF
 
3.002 9598789.16 366713.79 5115276.52 53.2
Work Order 02-13-15
Work Began 04-20-15
Work Completed  
Time Computed 04-15-15
Contract Working Days 574
Addl Days Granted 0
Working Days Charged 192
Percent Time Used 33
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 1190-01-043
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(1.80%)
ROADWAY SPECIALTIES, INC.(0.98%)
SAN-ANN-CO., INC.(0.38%)
STRIPING TECHNOLOGY, L.P.(0.73%)
TEXOP CONSTRUCTION (0.11%)
JMJ CONTRACTOR ( 36.58%)
K & S BACKHOE SERVICES INC.( 36.58%)
N LINE TRAFFIC CONTROL (0.13%)
Contract # 12143218
Totals 9917107.31 380853.79 5372376.90 54.1

CountyBELL
Highway FM 2670
From MAXDALE RD
To SH 195
CSJ 1198-03-009
Proj ID STP 1602(307)HES
Work Type SFTY TR FX OBJS
 
3.362 521758.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 128
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1198-03-009
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07163236
Totals 521758.00 0.00 0.00 0.0

CountyHILL
Highway FM 339
From @ TEHUACANA CRK
To (STR #003)
CSJ 1662-01-015
Proj ID BR 1602(223)
Work Type REPL BR & APPRS
 
0.114 653974.75 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-16-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 106
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ELLIS-MCGINNIS CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 1662-01-015
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06163008
Totals 653974.75 0.00 0.00 0.0

CountyMCLENNAN
Highway FM 185
From SH 317
To SH 6
CSJ 1969-01-017
Proj ID STP 2014(939)
Work Type WDN, GR, BS, SURF, ADD SHLDRS
 
9.119 4636733.87 0.00 5264882.36 99.9
Work Order 10-02-14
Work Began 11-10-14
Work Completed  
Time Computed 12-01-14
Contract Working Days 255
Addl Days Granted 3
Working Days Charged 266
Percent Time Used 105
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1969-01-017
ALPHA EROSION PRODUCTS, LLC(0.35%)
ROADWAY SPECIALTIES, INC.(3.11%)
COLD CREEK CONSTRUCTION, LTD (0.58%)
FORTSON CONTRACTING, INC.(2.72%)
JOY LATTIMER, LLC. (1.55%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.76%)
TEXAS ALTERNATIVE GRASSER, INC.(1.37%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.95%)
SAN-ANN-CO., INC.(0.99%)
PAVETEX ENGINEERING & TESTING, INC.(0.14%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.10%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.86%)
Contract # 07143234
Totals 4636733.87 0.00 5264882.36 99.9

CountyMCLENNAN
Highway FM 2311
From FM 2114
To FM 308
CSJ 2174-01-016
Proj ID STP 2015(479)
Work Type WDN, GR, BS, SURF, ADD SHLDRS
 
7.060 3380323.06 394379.91 1636821.41 48.4
Work Order 02-24-15
Work Began 05-29-15
Work Completed  
Time Computed 05-11-15
Contract Working Days 213
Addl Days Granted 0
Working Days Charged 148
Percent Time Used 69
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2174-01-016
BEAR CREEK CONSTRUCTION, LLC ( 30.46%)
D.I.J. CONSTRUCTION, INC (1.35%)
ENVIRONMENTAL SAFETY SERVICES, INC.(3.57%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.64%)
COWBELL TRAFFIC SERVICE, INC.(0.37%)
Contract # 01153019
Totals 3380323.06 394379.91 1636821.41 48.4

CountyBELL
Highway FM 2410
From ROY REYNOLDS DRIVE
To ANN BLVD
CSJ 2304-02-036
Proj ID STP 2013(588)
Work Type WDN, GR, BS, SURF
 
1.264 6800753.05 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 617
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TTG UTILITIES, LP
SUBCONTRACTOR(S) FOR CCSJ: 2304-02-036
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07163018
Totals 6800753.05 0.00 0.00 0.0

CountyMCLENNAN
Highway FM 3051
From @ INTERS OF MLK/LAKE BRAZOS PKWY
To .
CSJ 2311-01-037
Proj ID NH 2015(400)
Work Type LANDSCAPE ENHANCE
 
0.200 897015.06 0.00 413715.80 46.1
Work Order 06-01-15
Work Began 07-14-15
Work Completed  
Time Computed 06-17-15
Contract Working Days 107
Addl Days Granted 0
Working Days Charged 88
Percent Time Used 82
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2311-01-037
CLASSIC TEJAS CONSTRUCTION, INC. (9.02%)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC(0.77%)
Contract # RS
Totals SUB %: 1.50      

CountyLIMESTONE
Highway FM 2705
From US 84
To FM 1633
CSJ 2754-01-008
Proj ID STP 2016(370)
Work Type WDN, GR, BS, SURF & ADD SHLDRS
 
5.809 4733942.79 0.00 0.00 0.0
Work Order 06-23-16
Work Began 08-08-16
Work Completed  
Time Computed 06-15-16
Contract Working Days 294
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 2754-01-008
CEN TEX HYDROSEED, INC.(1.13%)
BEAR CREEK CONSTRUCTION, LLC ( 16.21%)
CHEROKEE SERVICES(0.37%)
COWBELL TRAFFIC SERVICES, INC. (0.18%)
D. I. J. CONSTRUCTION, INC.(1.01%)
FORTSON CONTRACTING, INC.(0.39%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.26%)
TEXAS ALTERNATIVE GRASSER, INC.(0.80%)
TEXOP CONSTRUCTION (1.02%)
Contract # 04163012
Totals 4733942.79 0.00 0.00 0.0

CountyMCLENNAN
Highway FM 2837
From IH 35
To 0.2 MI W OF IH 35
CSJ 3521-01-016
Proj ID STP 2014(782)
Work Type INTERS IMPRVMT
 
0.360 1787727.68 1706.99 1755443.52 99.3
Work Order 08-20-14
Work Began 09-15-14
Work Completed  
Time Computed 09-15-14
Contract Working Days 127
Addl Days Granted 0
Working Days Charged 154
Percent Time Used 121
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 3521-01-016
N-LINE TRAFFIC MAINTENANCE, L.P. (0.49%)
STRIPING TECHNOLOGY, L.P.(1.95%)
SAN-ANN-CO., INC.(0.53%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (6.21%)
BRICK PAVING PLUS, INC.(0.69%)
STEIN LAWN AND LANDSCAPE (0.54%)
Contract # 06143027
Totals 1787727.68 1706.99 1755443.52 99.3

CountyCORYELL
Highway SH 9
From US 190
To FM 116
CSJ 3623-01-001
Proj ID STP 2011(191)
Work Type WDN, GR, STRS & SURF
 
3.176 31147896.24 3533.27 31903074.59 99.9
CountyCORYELL
Highway SH 9
From US 190
To FM 116
CSJ 3623-01-002
Proj ID RW 3623-1-2
Work Type ROW ACQ., AND UTL. ADJ.
 
4.200 753345.03 0.00 710188.83 94.2
Work Order 01-24-11
Work Began 02-14-11
Work Completed  
Time Computed 02-14-11
Contract Working Days 609
Addl Days Granted 60
Working Days Charged 774
Percent Time Used 115
Contractor(s)
LEDCOR CMI INC.
SUBCONTRACTOR(S) FOR CCSJ: 3623-01-001
J.H. PAINTING COMPANY(0.51%)
CHOCTAW ERECTORS, INC. (6.20%)
RICE ENVIRONMENTAL SERVICES(2.28%)
DIVERSIFIED HIGHWAY PRODUCTS AND SERVICES(0.56%)
PECOS FENCE, INC.(0.72%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION (OLD PRIME) (0.91%)
DUSTROL, INC. (ROANOKE)(0.01%)
BEAIRD DRILLING(0.95%)
AARON CONCRETE CONTRACTORS, L.P. (0.49%)
GK CONSTRUCTION, LLC (0.51%)
MCLEAN CONSTRUCTION, INC.(1.95%)
LINDSEY CONTRACTORS, INC.( 20.36%)
CRAIG OLDEN, INC.(0.78%)
E-CLEAR(0.05%)
EARTHTECH WEST II, LTD (0.24%)
HIGHWAY TECHNOLOGIES, INC. (0.87%)
MATOKA, INC. (0.35%)
ODUM SERVICES, L.P.(0.48%)
RANGER EXCAVATING, L.P.(1.32%)
HOUSTON SAWING & DRILLING(0.09%)
TEXAS ALTERNATIVE GRASSER, INC.(1.04%)
ROADWAY SPECIALTIES, INC.(0.14%)
ELLIS-MCGINNIS CONSTRUCTION CO.(0.26%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.60%)
CAPITOL CONCRETE CONTRACTORS, INC. (0.00%)
DETON, INC. DBA SLATON BROS., INC. (0.24%)
PENNTEX MILLING INC. (0.01%)
C-HOP CONSTRUCTION (0.16%)
CENTRAL NORTH CONSTRUCTION, LLC(0.23%)
PENHALL COMPANY(0.12%)
RAMPART HYDRO SERVICES (0.23%)
TEXAS CUTTING & CORING, INC. (0.03%)
Contract # 12103016
Totals 31901241.27 3533.27 32613263.42 99.9