Monthly State Let Construction Report For Waco District As Of Feb 10, 2017 Page 3 Of 4

Last Update: Friday, February 10, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMCLENNAN
HighwayCR
FromON CR 489 @ RICE CREEK
To(MAP #651)
CSJ0909-22-174
Proj IDBR 2016(885)
Work TypeREPL BR & APPRS
 
0.076453594.100.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days128
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ELLIS-MCGINNIS CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0909-22-174
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173223
Totals453594.100.000.000.0

CountyHAMILTON
HighwayCR
FromON CR 273 @ LEON RIVER
To(MAP #210)
CSJ0909-29-020
Proj IDBR 99(346)
Work TypeREPL BR & APPRS
 
0.094906649.00582810.7064.2
Work Order07-29-16
Work Began09-19-16
Work Completed
Time Computed08-15-16
Contract Working Days191
Addl Days Granted0
Working Days Charged94
Percent Time Used49
Contractor(s)
FRITCHER CONSTRUCTION SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 0909-29-020
N-LINE TRAFFIC MAINTENANCE, L.P. (0.38)
JM YANEZ CONSTRUCTION, INC. (46.02)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.72)
DIIBS SPECIALISTS (1.29)
TEXAS SHAFTS, INC. (7.48)
MCL CONTRACTING, LLC (0.33)
Contract #06163212
Totals906649.00138288.10582810.7064.2

CountyBELL
HighwayCR
FromON CR 493 @ SALADO
ToCREEK (MAP#60)
CSJ0909-36-137
Proj IDBR 2012(427)
Work TypeREPL BR & APPRS
 
0.1761202660.75247792.5615.4
Work Order01-29-16
Work Began00-00-00
Work Completed
Time Computed04-28-16
Contract Working Days149
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0909-36-137
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10153004
Totals1202660.750.00247792.5615.4

CountyFALLS
HighwayCR
FromON CR 425 @ BRANCH
ToOF N ELM CREEK (MAP #2038)
CSJ0909-38-052
Proj IDBR 1402(048)
Work TypeREPL BR & APPRS
 
0.082272958.30246527.8090.3
Work Order08-05-16
Work Began10-17-16
Work Completed
Time Computed09-04-16
Contract Working Days85
Addl Days Granted0
Working Days Charged63
Percent Time Used74
Contractor(s)
ELLIS-MCGINNIS CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0909-38-052
GK CONSTRUCTION, LLC (1.16)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (1.09)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (8.60)
GK CONSTRUCTION, LLC (0.25)
Contract #06163229
Totals272958.30750.00246527.8090.3

CountyFALLS
HighwayCR
FromCR 221 @ BIG SANDY CRK BR
To(MAP #40)
CSJ0909-38-072
Proj IDBR 1402(049)
Work TypeREPL BR & APPRS
 
0.3451169676.10980762.0783.8
Work Order07-07-15
Work Began03-15-16
Work Completed
Time Computed09-06-15
Contract Working Days489
Addl Days Granted0
Working Days Charged352
Percent Time Used71
Contractor(s)
ELLIS-MCGINNIS CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0909-38-072
FORTSON CONTRACTING, INC. (3.06)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (8.64)
MCL CONTRACTING, LLC (0.82)
SAN-ANN-CO., INC. (1.29)
Contract #05153253
Totals1169676.1089944.67980762.0783.8

CountyCORYELL
HighwayVA
FromAT VARIOUS LOCATIONS
ToIN CORYELL COUNTY
CSJ0909-39-128
Proj IDSTP 2016(368)
Work TypeCONSTRUCT CURB RAMPS
 
0.100663079.060.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days107
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PROJECT ALLIED RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0909-39-128
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173014
Totals663079.060.000.000.0

CountyLIMESTONE
HighwayCR
FromCR 212 @ TEHUACANA CRK
To(MAP #35)
CSJ0909-40-059
Proj IDBR 2014(333)
Work TypeREPL BR & APPRS
 
0.099438543.550.000.0
CountyLIMESTONE
HighwayCR
FromCR 330 @ LAKE LIMESTONE
To(MAP #133)
CSJ0909-40-071
Proj IDBR 2015(446)
Work TypeREPL BR & APPRS
 
0.066302747.000.000.0
CountyLIMESTONE
HighwayCR
FromON CR 181 @ PIN OAK CR RELIEF
To(MAP #22)
CSJ0909-40-072
Proj IDBR 2015(447)
Work TypeREPL BR & APPRS
 
0.074399986.000.000.0
CountyLIMESTONE
HighwayCR
FromCR 416 @ SOWDERS CRK TRIB
To(MAP #209) (LCR 707)
CSJ0909-40-073
Proj IDBR 2015(448)
Work TypeREPL BR & APPRS
 
0.068418722.450.000.0
Work Order12-28-16
Work Began00-00-00
Work Completed
Time Computed01-27-17
Contract Working Days277
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PIERCE R & B LLC
SUBCONTRACTOR(S) FOR CCSJ: 0909-40-059
FORTSON CONTRACTING, INC. (2.63)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (10.24)
WOLFE CONSTRUCTION GROUP, INC. (1.50)
SAN-ANN-CO., INC. (0.00)
OLDCASTLE MATERIALS TEXAS, INC. (3.74)
Contract #10163009
Totals1559999.000.000.000.0

CountyHILL
HighwayFM 933
FromFM 1713
ToFM 1244 IN WHITNEY
CSJ1190-01-041
Proj IDSTP 2013(688)
Work TypeROW ACQ.; RELOC. ASSIST.
 
2.894318318.15307278.3396.5
CountyHILL
HighwayFM 933
FromFM 1713
ToFM 1244 IN WHITNEY
CSJ1190-01-043
Proj IDHP 2013(358)
Work TypeWDN, GR, STRS & SURF
 
3.0029598789.167297984.1176.0
Work Order02-13-15
Work Began04-20-15
Work Completed
Time Computed04-15-15
Contract Working Days574
Addl Days Granted0
Working Days Charged319
Percent Time Used55
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 1190-01-041
ANALYTICAL TECHNOLOGY CONSULTANTS, INC. (1.80)
ROADWAY SPECIALTIES, INC. (0.98)
SAN-ANN-CO., INC. (0.38)
STRIPING TECHNOLOGY, L.P. (0.73)
TEXOP CONSTRUCTION (0.11)
JMJ CONTRACTOR (36.58)
K & S BACKHOE SERVICES INC. (36.58)
N LINE TRAFFIC CONTROL (0.13)
Contract #12143218
Totals9917107.31122046.027605262.4476.6

CountyBELL
HighwayFM 2670
FromMAXDALE RD
ToSH 195
CSJ1198-03-009
Proj IDSTP 1602(307)HES
Work TypeSFTY TR FX OBJS
 
3.362521758.00402621.1277.1
Work Order09-19-16
Work Began12-12-16
Work Completed
Time Computed10-19-16
Contract Working Days128
Addl Days Granted0
Working Days Charged69
Percent Time Used53
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1198-03-009
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (1.22)
CLASSIC TEJAS CONSTRUCTION, INC. (4.89)
Contract #07163236
Totals521758.0059157.17402621.1277.1

CountyHILL
HighwayFM 339
From@ TEHUACANA CRK
To(STR #003)
CSJ1662-01-015
Proj IDBR 1602(223)
Work TypeREPL BR & APPRS
 
0.114653974.75520766.3079.6
Work Order08-16-16
Work Began10-10-16
Work Completed
Time Computed09-15-16
Contract Working Days106
Addl Days Granted0
Working Days Charged78
Percent Time Used73
Contractor(s)
ELLIS-MCGINNIS CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 1662-01-015
WOLFE CONSTRUCTION GROUP, INC. (1.61)
TEXAS SHAFTS, INC. (5.90)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.72)
APAC-TEXAS, INC. (7.81)
JUST GROOVING, LTD. (0.29)
FLASHER EQUIPMENT COMPANY (0.54)
FORTSON CONTRACTING, INC. (2.85)
BOWMAN ENGINEERING & CONSULTING, INC (0.69)
Contract #06163008
Totals653974.7581595.12520766.3079.6

CountyHILL
HighwayFM 934
From0.056 MI W OF AQUILLA CREEK
ToSH 171
CSJ1831-01-019
Proj IDSTP 2017(599)
Work TypeWDN, GR, BS, SURF, ADD SHLDRS
 
2.7942487232.280.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days170
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1831-01-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173227
Totals2487232.280.000.000.0

CountyMCLENNAN
HighwayFM 2311
FromFM 2114
ToFM 308
CSJ2174-01-016
Proj IDSTP 2015(479)
Work TypeWDN, GR, BS, SURF, ADD SHLDRS
 
7.0603380323.063147959.0993.5
Work Order02-24-15
Work Began05-29-15
Work Completed
Time Computed05-11-15
Contract Working Days213
Addl Days Granted0
Working Days Charged227
Percent Time Used106
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2174-01-016
BEAR CREEK CONSTRUCTION, LLC (30.46)
D.I.J. CONSTRUCTION, INC (1.35)
ENVIRONMENTAL SAFETY SERVICES, INC. (3.57)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.64)
COWBELL TRAFFIC SERVICE, INC. (0.37)
Contract #01153019
Totals3380323.0661229.263147959.0993.5

CountyBELL
HighwayFM 2410
FromROY REYNOLDS DRIVE
ToANN BLVD
CSJ2304-02-036
Proj IDSTP 2013(588)
Work TypeWDN, GR, BS, SURF
 
1.2646800753.05448540.006.5
Work Order12-06-16
Work Began01-09-17
Work Completed
Time Computed01-05-17
Contract Working Days617
Addl Days Granted0
Working Days Charged15
Percent Time Used2
Contractor(s)
TTG UTILITIES, LP
SUBCONTRACTOR(S) FOR CCSJ: 2304-02-036
D.I.J. CONSTRUCTION, INC (0.66)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.53)
OLDCASTLE MATERIALS TEXAS, INC. (25.51)
TACH SERVICES, INC. (0.47)
ROADWAY SPECIALTIES, INC. (0.84)
Contract #07163018
Totals6800753.05448540.00448540.006.5

CountyBELL
HighwayFM 2484
From2.1 MI E OF FM 3481
ToIH 35
CSJ2304-03-012
Proj IDSTP 2017(600)HES
Work TypeMILLED CL RUMBLE STRIP
 
10.530824244.800.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days165
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2304-03-012
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173225
Totals824244.800.000.000.0

CountyMCLENNAN
HighwayFM 3051
From@ INTERS OF MLK/LAKE BRAZOS PKWY
To.
CSJ2311-01-037
Proj IDNH 2015(400)
Work TypeLANDSCAPE ENHANCE
 
0.200897015.06420572.3046.8
Work Order06-01-15
Work Began07-14-15
Work Completed
Time Computed06-17-15
Contract Working Days107
Addl Days Granted0
Working Days Charged88
Percent Time Used82
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2311-01-037
CLASSIC TEJAS CONSTRUCTION, INC. (9.02)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (0.77)
QUALITY W CONTRACTORS LLC DBA: QUALITYW CONTRACTORS (1.50)
Contract #04153229
Totals897015.06856.50420572.3046.8

CountyMCLENNAN
HighwayFM 3051
From0.418 MI W OF FM 1637
ToBU 77L
CSJ2311-01-038
Proj IDSTP 2017(012)HES
Work TypeMILLED CL RUMBLE STRIP
 
26.132195682.450.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NEWMAN & KENG PAVING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2311-01-038
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173031
Totals195682.450.000.000.0

CountyMCLENNAN
HighwayFM 1695
FromFM 2063
ToUS 84
CSJ2506-01-036
Proj IDSTP 2017(465)
Work TypeMILL/SEAL/INLAY
 
2.501717978.810.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2506-01-036
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173249
Totals717978.810.000.000.0

CountyLIMESTONE
HighwayFM 2705
FromUS 84
ToFM 1633
CSJ2754-01-008
Proj IDSTP 2016(370)
Work TypeWDN, GR, BS, SURF & ADD SHLDRS
 
5.8094733942.791554185.3332.8
Work Order06-23-16
Work Began08-08-16
Work Completed
Time Computed06-15-16
Contract Working Days294
Addl Days Granted0
Working Days Charged117
Percent Time Used39
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 2754-01-008
CEN TEX HYDROSEED, INC. (1.13)
BEAR CREEK CONSTRUCTION, LLC (16.21)
CHEROKEE SERVICES (0.37)
COWBELL TRAFFIC SERVICES, INC. (0.18)
D. I. J. CONSTRUCTION, INC. (1.01)
FORTSON CONTRACTING, INC. (0.39)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.26)
TEXAS ALTERNATIVE GRASSER, INC. (0.80)
TEXOP CONSTRUCTION (1.02)
Contract #04163012
Totals4733942.79202276.451554185.3332.8

CountyLIMESTONE
HighwayFM 3371
FromFM 937
ToSH 164
CSJ3459-01-024
Proj IDSTP 2017(602)HES
Work TypeSFTY TR FX OBJS
 
9.183651104.750.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WEST TEXAS REBAR PLACERS INC.
SUBCONTRACTOR(S) FOR CCSJ: 3459-01-024
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173217
Totals651104.750.000.000.0

CountyMCLENNAN
HighwayFM 2837
FromIH 35
To0.2 MI W OF IH 35
CSJ3521-01-016
Proj IDSTP 2014(782)
Work TypeINTERS IMPRVMT
 
0.3601787727.681768112.5099.9
Work Order08-20-14
Work Began09-15-14
Work Completed
Time Computed09-15-14
Contract Working Days127
Addl Days Granted3
Working Days Charged154
Percent Time Used118
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 3521-01-016
N-LINE TRAFFIC MAINTENANCE, L.P. (0.49)
STRIPING TECHNOLOGY, L.P. (1.95)
SAN-ANN-CO., INC. (0.53)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (6.21)
BRICK PAVING PLUS, INC. (0.69)
STEIN LAWN AND LANDSCAPE (0.54)
Contract #06143027
Totals1787727.681500.001768112.5099.9