Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHILL
Highway SH 22
From FM 933
To SH 171
CSJ 0121-02-056
Proj ID STP 2013(467)
Work Type REHAB RDWAY / ADD PASS LNS
 
12.575 6401417.53 0.00 7088830.07 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-06-13
Work Began 06-03-13
Work Completed 03-19-15
Time Computed 06-03-13
Contract Working Days 239
Addl Days Granted 7
Working Days Charged 246
Percent Time Used 100
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0121-02-056
CHEROKEE SERVICES(0.44%)
K & S BACKHOE SERVICES INC.(5.42%)
COWBELL TRAFFIC SERVICES, INC. (0.26%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.43%)
JOY LATTIMER, LLC. (0.00%)
ROADWAY SPECIALTIES, INC.(5.24%)
FLASHER EQUIPMENT COMPANY(1.32%)
TEX OP CONSTRUCTION, LP(0.60%)
Contract # 03133020
Totals 6401417.53 0.00 7088830.07 100.0

CountyHILL
Highway SH 22
From SH 81 IN HILLSBORO
To IH 35
CSJ 0121-03-053
Proj ID ROW 121-3-53
Work Type ROW ACQ, UTIL ADJ & RELOC ASSIST
 
0.001 827623.40 0.00 0.00 0.0
CountyHILL
Highway SH 22
From SH 81 IN HILLSBORO
To 0.9 MI EAST
CSJ 0121-03-054
Proj ID STP 1502(482)
Work Type WDN, GR, STRS & PAV
 
0.934 5692677.72 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 277
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0121-03-054
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07153235
Totals 6520301.12 0.00 0.00 0.0

CountyCORYELL
Highway SH 36 ETC
From FM 215
To US 84
CSJ 0183-04-050
Proj ID STP 2016(192)
Work Type SEAL COAT
 
180.408 8429991.09 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
F. N. PLOCH CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0183-04-050
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11153209
Totals 8429991.09 0.00 0.00 0.0

CountyBELL
Highway SL 363
From @ SP 290 (1ST ST) IN TEMPLE
To .
CSJ 0184-04-046
Proj ID NH 2015(598)
Work Type CNSTR INTCHG
 
0.768 10073433.57 0.00 0.00 0.0
CountyBELL
Highway SL 363
From CITY OF TEMPLE
To .
CSJ 0184-04-047
Proj ID NH 1502(029)
Work Type LANDSCAPE DVLP
 
0.064 1114647.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 383
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0184-04-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153062
Totals 11188080.97 0.00 0.00 0.0

CountyMCLENNAN
Highway US 77
From 0.432 MI S OF FM 2837
To FALLS CO LINE
CSJ 0209-01-057
Proj ID STP 2014(778)
Work Type PLNG, SURF, ADD PASS LNS
 
2.459 1401699.55 59286.36 886056.52 63.2
CountyFALLS
Highway US 77
From MCLENNAN CO LINE
To FM 935
CSJ 0209-02-058
Proj ID STP 2014(778)
Work Type PLNG, SURF, ADD PASS LNS
 
8.988 5193754.80 17708.06 3095309.40 59.5
CountyFALLS
Highway US 77
From FM 935
To FM 431
CSJ 0209-03-048
Proj ID STP 2014(778)
Work Type PLNG, SURF, ADD PASS LNS
 
8.699 4537538.45 84740.76 2354384.79 51.8
Work Order 08-15-14
Work Began 10-08-14
Work Completed  
Time Computed 08-31-14
Contract Working Days 276
Addl Days Granted 0
Working Days Charged 267
Percent Time Used 96
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0209-01-057
BEAR CREEK CONSTRUCTION, LLC (4.39%)
CHEROKEE SERVICES(0.46%)
FORTSON CONTRACTING, INC.(1.52%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.35%)
ROADWAY SPECIALTIES, INC.(1.57%)
SAN-ANN-CO., INC.(1.06%)
TEXAS ALTERNATIVE GRASSER, INC.(0.19%)
TEX OP CONSTRUCTION, LP(0.36%)
STRIPING TECHNOLOGY, L.P.(2.06%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
Contract # 06143201
Totals 11132992.80 161735.18 6335750.71 56.9

CountyCORYELL
Highway US 190
From LAMPASAS/CORYELL COUNTY LINE
To EAST OF COPPERAS COVE CITY
CSJ 0231-02-044
Proj ID NH 2001(110)
Work Type ACQ, RELOC. UTIL
 
0.001 644280.00 0.00 759854.25 99.9
CountyLAMPASAS
Highway US 190
From US 190 W OF FM 2657
To CORYELL CO LINE
CSJ 0231-18-002
Proj ID C 231-18-2
Work Type GR, STRS & SURF
 
0.606 4615294.05 722.67 4126512.42 89.4
CountyCORYELL
Highway US 190
From LAMPASAS CO LINE
To US 190 W OF CLARKE RD
CSJ 0231-19-002
Proj ID DMO 2011(997)
Work Type CNSTR INTCHGS & CNTNG RDWYS
 
5.120 37819104.98 10178.78 41106693.00 99.9
Work Order 06-29-11
Work Began 07-20-11
Work Completed  
Time Computed 07-20-11
Contract Working Days 712
Addl Days Granted 13
Working Days Charged 1,046
Percent Time Used 144
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0231-19-002
SAN-ANN-CO., INC.(0.23%)
BRUSH SOLUTIONS, LLC (0.02%)
TEXAS SHAFTS, INC. (1.08%)
RICE ENVIRONMENTAL SERVICES(0.60%)
GK CONSTRUCTION, LLC (3.63%)
J.L. STEEL REINFORCING, LLC(0.00%)
PECOS FENCE, INC.(0.47%)
CRAIG OLDEN, INC.(2.02%)
CONCRETE CUTTING BY BOND (0.08%)
BIG CREEK CONSTRUCTION, LTD. ( 15.02%)
S & S BRIDGE PAINTING, INC.(0.38%)
TEX OP CONSTRUCTION, LP(0.17%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.80%)
TTG UTILITIES, INC.(1.94%)
WEST TEXAS RUMBLE STRIP(0.01%)
J.L. STEEL REINFORCING, LLC(0.01%)
SCOTT DERR PAINTING CO, LLC(0.61%)
WOLFF CONSTRUCTION (0.86%)
HOUSTON SAWING & DRILLING(0.05%)
ROADWAY SPECIALTIES, INC.(1.06%)
DANRIDGE CONSTRUCTION, LLC.(0.11%)
CHOCTAW ERECTORS, INC. (1.10%)
THE LEVY COMPANY, L.P. (1.67%)
KELLYSTONE, INC(0.14%)
ERFURT BLASTING COMPANY, INC.(0.64%)
STAMPEDE CREEK TRANSPORTATION(1.70%)
CECILIO CARRION RODRIGUEZ(0.00%)
SWS ENVIRONMENTAL SERVICES (5.62%)
HAMMACK FENCING(0.02%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
ALVIN SOWDERS(0.04%)
BACKOR TRUCKING(0.00%)
3 P TRUCKING (0.04%)
JDK SERVICES, LLC(0.04%)
DOUBLE R TRUCKING(0.04%)
MATERIALS-R-US (0.04%)
TOMMY T"S DUMP TRUCKING, INC.(0.04%)
RACHEL"S TRUCKING, LLC (0.04%)
POTTER TRUCKING(0.04%)
MSW TRUCKING, INC. (0.04%)
L2 HAULERS, LLC(0.04%)
JM DAVIS TRUCKING(0.04%)
DIAMOND K MATERIALS(0.04%)
HDB TRUCKING (0.04%)
CHUCK WHITE TRUCKING (0.04%)
BRAZOS BOTTOM TRUCKING, LLC(0.04%)
BELL CONTRACTORS (0.04%)
4D TRUCKN", LLC(0.04%)
E & R WELDING(0.08%)
J & B(0.00%)
LANDSCAPING CONTRACTING & IRRIGATION (0.00%)
Contract # 05113204
Totals 43078679.03 10901.45 45993059.67 99.9

CountyBELL
Highway US 190
From WS YOUNG
To FM 2410 IN HARKER HEIGHTS
CSJ 0231-03-103
Proj ID NH 2013(407)
Work Type WDN GR, STRS & PVMT
 
2.837 9587760.87 392108.60 6127537.60 63.9
Work Order 06-03-13
Work Began 08-19-13
Work Completed  
Time Computed 08-02-13
Contract Working Days 277
Addl Days Granted 0
Working Days Charged 241
Percent Time Used 87
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0231-03-103
LONE STAR HIGHWAY PRODUCTS, INC. (2.04%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.39%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.26%)
PRIMATE CONSTRUCTION, INC. (0.75%)
ROADWAY SPECIALTIES, INC.(3.12%)
NORTH TEXAS REBAR, LLC (0.05%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (1.53%)
HJC FARMS, INC.(0.66%)
SAN-ANN-CO., INC.(0.22%)
SCOTT DERR PAINTING CO, LLC(0.22%)
TEXAS ALTERNATIVE GRASSER, INC.(0.28%)
WEST TEXAS RUMBLE STRIP(0.03%)
FLASHER EQUIPMENT COMPANY(0.78%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (5.45%)
KRL CONSTRUCTION INC.(0.26%)
PAVETEX ENGINEERING & TESTING, INC.(0.00%)
M.G. DRILLING(0.06%)
JAMES CONSTRUCTION GROUP, L.L.C. (0.91%)
MESA ROD BUSTERS, INC. (0.04%)
Contract # 03133205
Totals 9587760.87 392108.60 6127537.60 63.9

CountyBELL
Highway US 190
From SP 172 (FT HOOD MAIN GATE)
To WS YOUNG
CSJ 0231-03-107
Proj ID NH 2012(638)
Work Type WDN, GR, STRS & SURF
 
5.948 55361501.09 71203.92 58439999.82 99.9
Work Order 12-14-12
Work Began 03-04-13
Work Completed  
Time Computed 02-12-13
Contract Working Days 763
Addl Days Granted 37
Working Days Charged 800
Percent Time Used 100
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0231-03-107
ENVIRONMENTAL SAFETY SERVICES, INC.(2.58%)
MCKINNEY DRILLING COMPANY(0.54%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.29%)
PRIMATE CONSTRUCTION, INC. (0.20%)
BUILDER SERVICES CO. (0.01%)
WEST TEXAS RUMBLE STRIP(0.01%)
DUSTROL, INC.(0.57%)
SCHNABEL FOUNDATION CO. (HOUSTON)(1.58%)
GK CONSTRUCTION, LLC (0.47%)
PANTHER CREEK TRANSPORTATION, INC. (3.02%)
HIGHWAY TECHNOLOGIES, INC. (0.81%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (3.17%)
ROADWAY SPECIALTIES, INC.(0.91%)
APAC-TEXAS, INC. ( 29.32%)
SCOTT DERR PAINTING CO (0.74%)
KRL CONSTRUCTION INC.(0.12%)
FLASHER EQUIPMENT COMPANY(0.46%)
EARTH REINFORCEMENT SPECIALISTS(1.56%)
PIONEER UTILITIES, INC.(1.84%)
Contract # 10123207
Totals 55361501.09 71203.92 58439999.82 99.9

CountyBELL
Highway BU 190F
From @ FM 439 INTERS
To .
CSJ 0231-10-017
Proj ID STP 1402(041)HES
Work Type IMPRV TRAF SIG
 
0.100 114526.30 1.00 136920.65 100.0
CountyBELL
Highway FM 439
From @ SPARTA RD
To .
CSJ 0836-03-059
Proj ID STP 1402(042)HESG
Work Type INSTL TRAF SIG
 
0.001 121255.20 510.00 146169.82 100.0
Work Order 09-11-14
Work Began 12-08-14
Work Completed 10-09-15
Time Computed 10-27-14
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 75
Percent Time Used 88
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0231-10-017
BAILEY H.D.D.(8.60%)
M.G. DRILLING(2.23%)
Contract # 08143210
Totals 235781.50 511.00 283090.47 100.0

CountyBELL
Highway FM 436
From @ LEON RIVER
To (STR #042)
CSJ 0231-16-030
Proj ID BR 2013(589)
Work Type REPL BR & APPRS
 
0.334 1748781.04 0.00 1761451.97 99.9
Work Order 05-14-14
Work Began 11-10-14
Work Completed  
Time Computed 11-10-14
Contract Working Days 213
Addl Days Granted 0
Working Days Charged 242
Percent Time Used 113
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0231-16-030
BEAIRD DRILLING(3.85%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.86%)
HOUSTON SAWING & DRILLING(0.18%)
GK CONSTRUCTION, LLC (0.67%)
BIG CREEK CONSTRUCTION, LTD. (7.62%)
D. I. J. CONSTRUCTION, INC.(1.15%)
ROADWAY SPECIALTIES, INC.(7.64%)
GK CONSTRUCTION, LLC (0.16%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.18%)
Contract # 04143210
Totals 1748781.04 0.00 1761451.97 99.9

CountyHAMILTON
Highway US 281
From HICO CITY LIMIT
To HAMILTON CITY LIMIT
CSJ 0251-01-056
Proj ID STP 2014(010)
Work Type ADD PASS LNS
 
18.939 10087610.99 3159.31 10586149.37 99.9
Work Order 12-04-13
Work Began 12-16-13
Work Completed  
Time Computed 12-16-13
Contract Working Days 468
Addl Days Granted 0
Working Days Charged 464
Percent Time Used 99
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0251-01-056
TEXAS ALTERNATIVE GRASSER, INC.(0.20%)
SAN-ANN-CO., INC.(1.25%)
J & M CONTRACTING, COMPANY (8.11%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.10%)
FORTSON CONTRACTING, INC.(1.70%)
D. I. J. CONSTRUCTION, INC.(1.09%)
CHEROKEE SERVICES(0.32%)
NIXON ENGINEERING(0.00%)
BRYDL CONTRACTING, INC.(0.12%)
BROCK CONSTRUCTION, LLC(0.11%)
TRAFCO INDUSTRIES, INC.(0.00%)
JOY LATTIMER, LLC. (0.00%)
Contract # 09133207
Totals 10087610.99 3159.31 10586149.37 99.9

CountyHAMILTON
Highway US 281
From SOUTH HAMILTON C/L
To US 84 IN EVANT
CSJ 0251-02-047
Proj ID STP 2014(011)
Work Type REHAB RDWY & ADD PASS LNS
 
14.545 9687836.94 2250.00 9945157.29 99.9
Work Order 12-03-13
Work Began 12-16-13
Work Completed  
Time Computed 12-16-13
Contract Working Days 426
Addl Days Granted 18
Working Days Charged 444
Percent Time Used 100
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0251-02-047
D. I. J. CONSTRUCTION, INC.(0.99%)
DUSTROL, INC.(0.11%)
SAN-ANN-CO., INC.(0.45%)
TEXAS ALTERNATIVE GRASSER, INC.(0.80%)
ROADWAY SPECIALTIES, INC.(2.91%)
PRIMATE CONSTRUCTION, INC. (0.26%)
J & M CONTRACTING, COMPANY ( 10.61%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.09%)
NIXON ENGINEERING(0.00%)
BRYDL CONTRACTING, INC.(0.07%)
BROCK CONSTRUCTION, LLC(0.22%)
Contract # 09133019
Totals 9687836.94 2250.00 9945157.29 99.9

CountyMCLENNAN
Highway SH 6
From LADY BIRD RD
To 0.5 MI N OF SP 412
CSJ 0258-08-033
Proj ID NH 2013(945)
Work Type ADD LFT TRN LN & SHLDRS
 
1.100 1946235.87 2464.00 1864460.73 96.4
Work Order 09-30-14
Work Began 06-26-15
Work Completed  
Time Computed 12-29-14
Contract Working Days 107
Addl Days Granted 0
Working Days Charged 122
Percent Time Used 114
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0258-08-033
FORTSON CONTRACTING, INC.(1.78%)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.(8.86%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.51%)
TEXAS ALTERNATIVE GRASSER, INC.(0.51%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.58%)
JOY LATTIMER, LLC. (1.54%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.57%)
PIPE WHOLESALERS OF TEXAS, INC.(2.19%)
Contract # 07143029
Totals 1946235.87 2464.00 1864460.73 96.4

CountyMCLENNAN
Highway SH 6
From IH 35
To US 77
CSJ 0258-09-111
Proj ID C 258-9-111
Work Type CONSTR OP / RAMPS; EXTEND FRTG RDS
 
1.949 22387388.26 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 701
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0258-09-111
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12153203
Totals 22387388.26 0.00 0.00 0.0

CountyBELL
Highway SH 95
From FM 2268 IN HOLLAND
To WILLIAMSON CO LINE
CSJ 0320-02-033
Proj ID STP 2015(477)
Work Type WDN, GR, BS, SURF & ADD SHLDRS
 
5.337 6989387.63 510582.50 1994273.18 28.7
CountyBELL
Highway SH 95
From @ INDIAN CREEK
To (STR #054)
CSJ 0320-02-037
Proj ID BR 2015(476)
Work Type REPL BR & APPRS
 
0.114 1361222.86 101268.76 902955.35 66.3
Work Order 03-31-15
Work Began 07-06-15
Work Completed  
Time Computed 09-27-15
Contract Working Days 319
Addl Days Granted 0
Working Days Charged 119
Percent Time Used 37
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0320-02-033
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.11%)
AUSTIN LAND SERVICE(0.52%)
BEAR CREEK CONSTRUCTION, LLC ( 14.81%)
D. I. J. CONSTRUCTION, INC.(0.89%)
ELLIS-MCGINNIS CONSTRUCTION CO.( 13.81%)
ROADWAY SPECIALTIES, INC.(2.20%)
SAN-ANN-CO., INC.(0.69%)
W. W. FOUNDATION DRILLING, LTD.(0.81%)
MCL CONTRACTING, LLC (0.20%)
JUST GROOVING, LTD.(0.06%)
1 PRIORITY ENVIRONMENTAL SERVICES, INC.(0.23%)
Contract # 02153225
Totals 8350610.49 611851.26 2897228.53 34.8

CountyLIMESTONE
Highway SH 7
From SH 14
To ROBERTSON CO LINE
CSJ 0382-03-031
Proj ID STP 2015(074)
Work Type REHAB RDWY
 
33.422 6079899.56 268199.40 6482291.74 99.9
Work Order 10-29-14
Work Began 02-05-15
Work Completed  
Time Computed 02-26-15
Contract Working Days 404
Addl Days Granted 0
Working Days Charged 229
Percent Time Used 56
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0382-03-031
BEAR CREEK CONSTRUCTION, LLC ( 14.05%)
DUSTROL, INC.(1.71%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.27%)
ROADWAY SPECIALTIES, INC.(3.67%)
STRIPING TECHNOLOGY, L.P.(3.43%)
TEXAS ALTERNATIVE GRASSER, INC.(1.67%)
WEST TEXAS RUMBLE STRIP(0.15%)
Contract # 09143217
Totals 6079899.56 268199.40 6482291.74 99.9

CountyBELL
Highway SH 317
From 0.2 MI S OF FM 2305
To 0.4 MI N OF FM 439
CSJ 0398-04-059
Proj ID C 398-4-59
Work Type WDN, GR, STRS & SURF
 
2.149 16671723.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 532
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0398-04-059
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153002
Totals 16671723.60 0.00 0.00 0.0

CountyBELL
Highway SH 317
From FM 439
To 0.5 MI N OF FM 439
CSJ 0398-04-072
Proj ID HP 2012(776)
Work Type WDN, GR, STRS & SURF
 
0.788 3649334.61 0.00 3641329.53 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-03-13
Work Began 06-05-13
Work Completed 02-27-15
Time Computed 04-03-13
Contract Working Days 171
Addl Days Granted 199
Working Days Charged 370
Percent Time Used 100
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0398-04-072
APAC-TEXAS, INC. ( 31.20%)
FLASHER EQUIPMENT COMPANY(1.25%)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (0.59%)
PERFORMANCE EQUIPMENT(0.26%)
RICE ENVIRONMENTAL SERVICES(0.22%)
WOLFF CONSTRUCTION (3.54%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.26%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.32%)
SPEEDY PAVING(0.98%)
R K STEPHENS CONSTRUCTION, LLC (3.57%)
HTM CONSTRUCTION COMPANY (1.10%)
STAMPEDE CREEK TRANSPORTATION(2.94%)
HDB TRUCKING (0.14%)
DIAMOND K MATERIALS(0.14%)
DOUBLE R TRUCKING(0.14%)
THE LEVY COMPANY, L.P. (3.28%)
BEAIRD DRILLING(0.06%)
DIAMOND K MATERIALS(0.00%)
Contract # 10123030
Totals 3649334.61 0.00 3641329.53 100.0

CountyBELL
Highway SH 317
From SH 36
To FM 2305
CSJ 0398-04-073
Proj ID STP 1502(565)HES
Work Type INST CONT LFT TRN LN
 
2.600 2346791.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-30-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 128
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0398-04-073
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153212
Totals 2346791.50 0.00 0.00 0.0

CountyHAMILTON
Highway SH 220
From ERATH CO LINE
To SH 6
CSJ 0467-01-008
Proj ID STP 2015(478)
Work Type SEAL / INLAY
 
2.091 539546.45 -29650.95 581634.74 100.0
Work Order 02-18-15
Work Began 03-16-15
Work Completed 08-31-15
Time Computed 05-19-15
Contract Working Days 43
Addl Days Granted 0
Working Days Charged 40
Percent Time Used 93
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0467-01-008
FLASHER EQUIPMENT COMPANY(2.75%)
BRICK PAVING PLUS, INC.(1.28%)
SAN-ANN-CO., INC.(0.66%)
BIG CREEK CONSTRUCTION, LTD. ( 53.74%)
TEXOP CONSTRUCTION (8.80%)
Contract # 01153210
Totals 539546.45 29650.95 581634.74 100.0