Monthly State Let Construction Report For Waco District As Of Jun 12, 2017 Page 2 Of 4

Last Update: Monday, June 12, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCORYELL
HighwayUS 190
FromFM 2657
ToSH 9
CSJ0231-02-058
Proj IDSTP 2016(829)
Work TypeMILL/INLAY
 
3.9742940366.772511488.4185.4
CountyCORYELL
HighwayUS 190
FromDEWALD ST
ToCONSTITUTION AVE
CSJ0231-02-061
Proj IDSTP 1602(047)
Work TypeLANDSCAPE DVLP
 
0.450446992.000.000.0
Work Order05-25-16
Work Began08-05-16
Work Completed
Time Computed06-24-16
Contract Working Days75
Addl Days Granted15
Working Days Charged59
Percent Time Used98
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0231-02-058
FLASHER EQUIPMENT COMPANY (0.14)
JOY LATTIMER, LLC. (1.00)
THE LEVY COMPANY, L.P. (3.35)
D. I. J. CONSTRUCTION, INC. (1.62)
Contract #03163225
Totals3387358.770.002511488.4174.1

CountyBELL
HighwayUS 190
FromWS YOUNG
ToFM 2410 IN HARKER HEIGHTS
CSJ0231-03-103
Proj IDNH 2013(407)
Work TypeWDN GR, STRS & PVMT
 
2.8379587760.8710338610.2699.9
Work Order06-03-13
Work Began08-19-13
Work Completed
Time Computed08-02-13
Contract Working Days277
Addl Days Granted115
Working Days Charged425
Percent Time Used108
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0231-03-103
LONE STAR HIGHWAY PRODUCTS, INC. (2.04)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.39)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.26)
PRIMATE CONSTRUCTION, INC. (0.75)
ROADWAY SPECIALTIES, INC. (3.12)
NORTH TEXAS REBAR, LLC (0.05)
SIGNATURE CONTRACTING SERVICES, L.L.C. (1.53)
HJC FARMS, INC. (0.66)
SAN-ANN-CO., INC. (0.22)
SCOTT DERR PAINTING CO, LLC (0.22)
TEXAS ALTERNATIVE GRASSER, INC. (0.28)
WEST TEXAS RUMBLE STRIP (0.03)
FLASHER EQUIPMENT COMPANY (0.78)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (5.45)
KRL CONSTRUCTION INC. (0.26)
M.G. DRILLING (0.06)
JAMES CONSTRUCTION GROUP, L.L.C. (0.91)
MESA ROD BUSTERS, INC. (0.04)
BROCK CONSTRUCTION, LLC (0.14)
G. CARTER CONSTRUCTION COMPANY, INC. (0.01)
Contract #03133205
Totals9587760.870.0010338610.2699.9

CountyBELL
HighwayFM 436
FromIH 35 IN BELTON
ToBU 190J IN HEIDENHEIMER
CSJ0231-16-032
Proj IDSTP 2017(877)HESG
Work TypeCNTRLN TXTRNG
 
25.465174160.93147010.8884.4
Work Order04-19-17
Work Began05-08-17
Work Completed
Time Computed05-19-17
Contract Working Days30
Addl Days Granted0
Working Days Charged14
Percent Time Used46
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0231-16-032
BRANNAN PAVING CO., LTD. (58.28)
Contract #03173210
Totals174160.93147010.88147010.8884.4

CountyCORYELL ETC
HighwayUS 281 ETC
FromHAMILTON CO LINE
ToLAMPASAS CO LINE
CSJ0251-03-021
Proj IDNH 2017(009)
Work TypeSEAL COAT
 
212.5988827090.824449014.0950.4
Work Order11-16-16
Work Began05-03-17
Work Completed
Time Computed11-15-16
Contract Working Days45
Addl Days Granted0
Working Days Charged18
Percent Time Used40
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0251-03-021
STRIPE-A-ZONE, INC. (0.23)
FLASHER EQUIPMENT COMPANY (0.97)
Contract #09163003
Totals8827090.822868239.704449014.0950.4

CountyHAMILTON
HighwaySH 6
FromUS 281
To0.106 MI E OF SYCAMORE STREET
CSJ0258-03-042
Proj IDSTP 1702(129)HES
Work TypeMILL/OVERLAY ADD LTL
 
0.508278277.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LELAND & BRADLEE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0258-03-042
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05173232
Totals278277.500.000.000.0

CountyMCLENNAN
HighwaySH 6
FromBUFFALO COUNTRY RD IN VALLEY MILLS
ToLADY BIRD RD
CSJ0258-08-032
Proj IDSTP 2013(587)
Work TypeREHAB RDWY, ADD PASS LNS
 
9.6694687935.114569005.2497.4
Work Order08-17-16
Work Began09-26-16
Work Completed
Time Computed09-16-16
Contract Working Days234
Addl Days Granted0
Working Days Charged170
Percent Time Used72
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0258-08-032
COWBELL TRAFFIC SERVICES, INC. (0.29)
D.I.J. CONSTRUCTION, INC (1.90)
FORTSON CONTRACTING, INC. (1.96)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.11)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.21)
TEXAS ALTERNATIVE GRASSER, INC. (0.44)
W.S. CONSTRUCTION COMPANY (12.96)
NIXON ENGINEERING (0.00)
Contract #06163015
Totals4687935.11847267.854569005.2497.4

CountyMCLENNAN
HighwaySH 6
FromSP 412
To0.5 MI N OF SP 412
CSJ0258-08-034
Proj IDNH 2016(830)
Work TypeMILL/SEAL/INLAY
 
0.549288197.4083520.0028.9
CountyMCLENNAN
HighwaySH 6
FromFM 3476
ToSP 412
CSJ0258-09-139
Proj IDNH 2016(830)
Work TypeMILL/SEAL/INLAY
 
9.2265380793.711427174.1126.5
CountyMCLENNAN
HighwaySH 6
From@ LAKE WACO (NB MAINLANE)
To(STR #067)
CSJ0258-09-140
Proj IDBR 1602(037)
Work TypeREHAB BR & APPRS
 
0.7434331178.402850215.9065.8
CountyMCLENNAN
HighwaySH 6
From@ LAKE WACO (SB MAINLANE)
To(STR #068)
CSJ0258-09-141
Proj IDBR 1602(037)
Work TypeREHAB BR & APPRS
 
0.7434481138.90696690.0015.5
Work Order05-12-16
Work Began10-03-16
Work Completed
Time Computed07-11-16
Contract Working Days255
Addl Days Granted0
Working Days Charged103
Percent Time Used40
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0258-08-034
N-LINE TRAFFIC MAINTENANCE, L.P. (0.37)
APAC-TEXAS, INC. (22.26)
ROADWAY SPECIALTIES, INC. (0.06)
GK CONSTRUCTION, LLC (1.01)
A. H. BECK FOUNDATION CO., INC. (20.45)
ODUM SERVICES, L.P. (0.08)
FLASHER EQUIPMENT COMPANY (2.19)
A BROTHERS MILLING, LLC (0.97)
WEST TEXAS RUMBLE STRIP (0.10)
CHEROKEE SERVICES (1.91)
C-HOP CONSTRUCTION (0.60)
POTTER TRUCKING (0.89)
ADCOCK 4 INVESTMENTS, LLC, DBA BRADCO (0.17)
PIONEER UTILITIES, INC. (0.13)
Contract #03163002
Totals14481308.41775043.785057600.0134.9

CountyMCLENNAN
HighwaySH 6
FromIH 35
ToUS 77
CSJ0258-09-111
Proj IDC 258-9-111
Work TypeCONSTR OP/RAMPS; EXTEND FRTG RDS
 
1.94922387388.2610433562.9646.6
Work Order02-10-16
Work Began03-07-16
Work Completed
Time Computed03-07-16
Contract Working Days701
Addl Days Granted0
Working Days Charged283
Percent Time Used40
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0258-09-111
ANALYTICAL TECHNOLOGY CONSULTANTS, INC. (3.62)
FLASHER EQUIPMENT COMPANY (0.55)
BRICK PAVING PLUS, INC. (0.56)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.65)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.37)
JUST GROOVING, LTD. (0.04)
ROADWAY SPECIALTIES, INC. (0.49)
FORTSON CONTRACTING, INC. (0.38)
WEST TEXAS RUMBLE STRIP (0.02)
ABC EROSION CONTROL, INC. (0.36)
MESA ROD BUSTERS, INC. (0.08)
Contract #12153203
Totals22387388.26819369.9410433562.9646.6

CountyMCLENNAN
HighwaySH 6
FromBRAZOS RIVER
ToSP 484 / SH 6
CSJ0258-09-124
Proj IDNH 1602(305)
Work TypeWDN TO 4 LN FRWY
 
1.36514733502.655444522.9036.9
Work Order10-11-16
Work Began11-14-16
Work Completed
Time Computed11-10-16
Contract Working Days617
Addl Days Granted0
Working Days Charged129
Percent Time Used20
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0258-09-124
N-LINE TRAFFIC MAINTENANCE, L.P. (0.14)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.40)
ADCOCK 4 INVESTMENTS, LLC (2.65)
ROADWAY SPECIALTIES, INC. (0.75)
GK CONSTRUCTION, LLC (0.62)
ATS DRILLING, L.P. (4.59)
THE LEVY COMPANY, L.P. (0.67)
D.I.J. CONSTRUCTION, INC (0.30)
TEXOP CONSTRUCTION (0.15)
S & S BRIDGE PAINTING, INC. (0.06)
HOUSTON SAWING & DRILLING (0.04)
C-HOP CONSTRUCTION (9.05)
OLDCASTLE MATERIALS TEXAS, INC. (12.44)
BOWMAN ENGINEERING & CONSULTING, INC (0.09)
Contract #07163205
Totals14733502.65635867.835444522.9036.9

CountyMCLENNAN
HighwaySH 317
FromMOODY CITY LIMITS
ToBELL CO LINE
CSJ0398-03-058
Proj IDSTP 2016(834)
Work TypeWDN, GR, SURF, ADD SHLDRS
 
9.2799139073.582511165.2027.4
Work Order10-19-16
Work Began12-13-16
Work Completed
Time Computed11-18-16
Contract Working Days361
Addl Days Granted0
Working Days Charged120
Percent Time Used33
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0398-03-058
SAN-ANN-CO., INC. (1.00)
BMP SPECIALIST, LLC (0.81)
W.S. CONSTRUCTION COMPANY (16.31)
TEXOP CONSTRUCTION (0.08)
CHEROKEE SERVICES (0.19)
D.I.J. CONSTRUCTION, INC (1.00)
TEXAS ALTERNATIVE GRASSER, INC. (0.44)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.18)
WEST TEXAS RUMBLE STRIP (0.05)
FORTSON CONTRACTING, INC. (1.02)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.05)
Contract #08163036
Totals9139073.58437752.172511165.2027.4

CountyBELL
HighwaySH 317
From0.2 MI S OF FM 2305
To0.4 MI N OF FM 439
CSJ0398-04-059
Proj IDC 398-4-59
Work TypeWDN, GR, STRS & SURF
 
2.14916887376.628147508.1148.2
Work Order07-13-16
Work Began08-19-16
Work Completed
Time Computed08-12-16
Contract Working Days532
Addl Days Granted0
Working Days Charged193
Percent Time Used36
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0398-04-059
BRICK PAVING PLUS, INC. (0.70)
CHEROKEE SERVICES (0.31)
ENCINO LANDSCAPE, INC. (0.87)
FLASHER EQUIPMENT COMPANY (0.22)
FORTSON CONTRACTING, INC. (0.18)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (1.43)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.04)
LONE STAR HIGHWAY PRODUCTS, INC. (0.79)
R K STEPHENS CONSTRUCTION, LLC (3.94)
ROADWAY SPECIALTIES, INC. (1.53)
SAN-ANN-CO., INC. (0.24)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.52)
W. W. FOUNDATION DRILLING, LTD. (1.09)
MCL CONTRACTING, LLC (0.06)
GK CONSTRUCTION, LLC (0.02)
NIXON ENGINEERING (0.00)
Contract #05163006
Totals16887376.62384972.898147508.1148.2

CountyCORYELL
HighwayFM 1996
FromUS 84
ToFM 107
CSJ0567-01-027
Proj IDSTP 1602(306)
Work TypeREHAB RDWY
 
4.5082775913.742019190.9072.7
Work Order10-06-16
Work Began11-14-16
Work Completed
Time Computed11-07-16
Contract Working Days170
Addl Days Granted0
Working Days Charged120
Percent Time Used70
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0567-01-027
N-LINE TRAFFIC MAINTENANCE, L.P. (2.20)
ROADWAY SPECIALTIES, INC. (1.19)
D. I. J. CONSTRUCTION, INC. (1.23)
BEAR CREEK CONSTRUCTION, LLC (13.68)
Contract #07163012
Totals2775913.74397864.302019190.9072.7

CountyCORYELL
HighwayFM 116
FromUS 84
ToCACTUS LANE
CSJ0724-01-044
Proj IDSTP 1502(343)
Work TypeADD PASS LNS/SHLDRS
 
18.89117587091.4713682459.8177.7
Work Order08-20-15
Work Began11-11-15
Work Completed
Time Computed12-19-15
Contract Working Days510
Addl Days Granted0
Working Days Charged397
Percent Time Used77
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0724-01-044
ABC EROSION CONTROL, INC. (2.03)
SAN-ANN-CO., INC. (0.30)
W. W. FOUNDATION DRILLING, LTD. (0.67)
GK CONSTRUCTION, LLC (0.11)
PRIMATE CONSTRUCTION, INC. (0.13)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.26)
COWBELL TRAFFIC SERVICES, INC. (0.13)
DS TEXAS ICON CONSTRUCTION (0.61)
ROADWAY SPECIALTIES, INC. (0.85)
JOY LATTIMER, LLC. (4.01)
D. I. J. CONSTRUCTION, INC. (1.47)
FORTSON CONTRACTING, INC. (1.05)
MCL CONTRACTING, LLC (0.00)
NIXON ENGINEERING (0.00)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.01)
Contract #06153203
Totals17587091.47408199.0413682459.8177.7

CountyCORYELL
HighwayFM 116
FromANDERSON AVE
ToAVENUE B
CSJ0724-01-049
Proj IDSTP 2013(586)
Work TypeWDN, GR & STR
 
0.7044531202.352988546.1465.9
CountyCORYELL
HighwayFM 116
FromANDERSON AVE
ToAVENUE B
CSJ0724-01-052
Proj IDROW 724-1-52
Work TypeROW ACQUISITION
 
0.7041012118.22442975.1343.7
Work Order11-13-15
Work Began02-11-16
Work Completed
Time Computed02-11-16
Contract Working Days340
Addl Days Granted0
Working Days Charged197
Percent Time Used57
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0724-01-049
SAN-ANN-CO., INC. (0.78)
ROADWAY SPECIALTIES, INC. (1.24)
TEX OP CONSTRUCTION, LP (0.25)
R K STEPHENS CONSTRUCTION, LLC (7.97)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.36)
TRP CONSTRUCTION GROUP, LLC (0.97)
MCLEAN CONSTRUCTION, INC. (39.03)
Contract #09153013
Totals5543320.57216837.003431521.2761.9

CountyCORYELL
HighwayFM 116
FromCACTUS LANE
ToHOUSE CREEK BRIDGE
CSJ0724-01-050
Proj IDSTP 2017(011)
Work TypeADD LFT TRN LN
 
3.4924345840.870.000.0
Work Order04-19-17
Work Began00-00-00
Work Completed
Time Computed07-15-17
Contract Working Days234
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0724-01-050
AWP, INC. (0.23)
COMEN ENTERPRISE LLC (3.11)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (2.54)
D.I.J. CONSTRUCTION, INC (1.01)
WOLFE CONSTRUCTION GROUP, INC. (0.54)
Contract #03173029
Totals4345840.870.000.000.0

CountyLIMESTONE
HighwayFM 147
FromSH 14
ToFALLS CO LINE
CSJ0752-06-022
Proj IDSTP 2016(103)
Work TypeWDN, GR, BS, SURF, ADD SHLDRS
 
10.0554469649.323713313.3783.7
Work Order11-16-15
Work Began02-29-16
Work Completed
Time Computed02-15-16
Contract Working Days234
Addl Days Granted15
Working Days Charged278
Percent Time Used111
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0752-06-022
BEAR CREEK CONSTRUCTION, LLC (15.29)
D.I.J. CONSTRUCTION, INC (1.51)
FORTSON CONTRACTING, INC. (0.81)
ROADWAY SPECIALTIES, INC. (4.43)
SAN-ANN-CO., INC. (1.81)
TEXAS ALTERNATIVE GRASSER, INC. (1.15)
WEST TEXAS RUMBLE STRIP (0.10)
BRETT CONSTRUCTION COMPANY (0.37)
Contract #09153221
Totals4469649.32124056.283713313.3783.7

CountyMCLENNAN
HighwayFM 1637
FromFM 3051
To0.65 MI W OF FM 2490
CSJ0833-03-035
Proj IDHP 1502(059)
Work TypeWDN GR, STRS & SURF
 
4.33727836847.9911869914.5142.6
Work Order06-30-15
Work Began04-04-16
Work Completed
Time Computed12-28-15
Contract Working Days574
Addl Days Granted0
Working Days Charged259
Percent Time Used45
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0833-03-035
RAMBO CONTRACTING, INC. (2.78)
APEX LANDSCAPE & IRRIGATION, LLC (0.00)
BRICK PAVING PLUS, INC. (2.72)
DUSTROL, INC. (0.52)
ROADWAY SPECIALTIES, INC. (1.35)
FLASHER EQUIPMENT COMPANY (0.56)
SAN-ANN-CO., INC. (0.27)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC. (2.19)
LONE STAR HIGHWAY PRODUCTS, INC. (4.07)
POTTER TRUCKING (0.49)
B-CORP UTILITIES, INC. (0.17)
BEAR CREEK CONSTRUCTION, LLC (2.34)
I & H CONCRETE CUTTING, INC. (0.09)
AARON CONCRETE CONTRACTORS, L.P. (1.07)
BOEN LANDSCAPING & IRRIGATION, LLC (0.59)
Contract #04153257
Totals27836847.991128270.2311869914.5142.6

CountyMCLENNAN
HighwayCR
FromON CR 174 @ TONK CREEK
To(MAP #493)
CSJ0909-22-167
Proj IDBR 2015(489)
Work TypeREPL BR & APPRS
 
0.065243405.4550414.9920.7
CountyMCLENNAN
HighwayCR
FromON CR 277 @ S FORK COW BAYOU
To(MAP #129)
CSJ0909-22-168
Proj IDBR 2015(543)
Work TypeREPL BR & APPRS
 
0.079454304.10415845.0091.5
Work Order02-27-17
Work Began03-13-17
Work Completed
Time Computed03-13-17
Contract Working Days234
Addl Days Granted0
Working Days Charged57
Percent Time Used24
Contractor(s)
ELLIS-MCGINNIS CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0909-22-167
OLDCASTLE MATERIALS TEXAS, INC. (5.63)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (1.02)
ROADWAY SPECIALTIES, INC. (3.57)
H & H SIGN CO., INC. (DBA WACO DRILLING CO.) (2.83)
LONE STAR HIGHWAY PRODUCTS, INC. (1.45)
Contract #01173024
Totals697709.5596637.61466259.9966.8

CountyMCLENNAN
HighwayCS
From1260' S OF MT CARMEL DR
To2350' S OF MT CARMEL DR
CSJ0909-22-173
Proj IDSTP 2017(464)HES
Work TypeINCR SUPRELV
 
0.191372720.55109398.6029.3
Work Order04-19-17
Work Began05-17-17
Work Completed
Time Computed05-19-17
Contract Working Days107
Addl Days Granted0
Working Days Charged10
Percent Time Used9
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0909-22-173
FLASHER EQUIPMENT COMPANY (5.79)
ROADWAY SPECIALTIES, INC. (6.03)
Contract #03173039
Totals372720.55109398.60109398.6029.3

CountyMCLENNAN
HighwayCR
FromON CR 489 @ RICE CREEK
To(MAP #651)
CSJ0909-22-174
Proj IDBR 2016(885)
Work TypeREPL BR & APPRS
 
0.076453594.10303179.1366.8
Work Order02-27-17
Work Began03-13-17
Work Completed
Time Computed03-13-17
Contract Working Days128
Addl Days Granted0
Working Days Charged57
Percent Time Used44
Contractor(s)
ELLIS-MCGINNIS CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0909-22-174
OLDCASTLE MATERIALS TEXAS, INC. (4.65)
FORTSON CONTRACTING, INC. (2.13)
SAN-ANN-CO., INC. (0.78)
WOLFE CONSTRUCTION GROUP, INC. (0.29)
WYLIE DRILLING & DRAINAGE, INC. (6.34)
Contract #01173223
Totals453594.1074224.00303179.1366.8

page 1 | page 2 | page 3 | page 4