Monthly State Let Construction Report For Waco District As Of May 15, 2013 Page 1 Of 3

Last Update: Wednesday, May 15, 2013
FTP Icon Text Version
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHILL
Highway SH 81
From @ MAJORS BRANCH
To (STR #025)
CSJ 0014-05-031
Proj ID BR 2012(577)
Work Type REPL BR & APPRS
 
0.293 1440525.30 68500.52 918059.36 63.7
Work Order 07-12-12
Work Began 11-27-12
Work Completed  
Time Computed 10-11-12
Contract Working Days 189
Addl Days Granted 0
Working Days Charged 102
Percent Time Used 53
Contractor(s)
ELLIS-MCGINNIS CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0014-05-031
STRIPING TECHNOLOGY, L.P.(1.21%)
TEXAS ALTERNATIVE GRASSER, INC.(0.39%)
JUST GROOVING, LTD.(0.29%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.14%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(4.36%)
SCOTT DERR PAINTING CO (0.25%)
FORTSON CONTRACTING, INC.(2.68%)
SAN-ANN-CO., INC.(0.70%)
NORTH TEXAS REBAR, LLC (0.14%)
NORTH TEXAS REBAR, LLC (0.07%)
Contract # 05123228
Totals 1440525.30 68500.52 918059.36 63.7

CountyHILL
Highway SH 81
From SH 22 (NORTH)
To 0.327 MI N OF SH 22 (NORTH)
CSJ 0014-06-040
Proj ID STP 2012(203)
Work Type REHAB RDWY
 
1.522 1512674.65 0.00 1440636.31 95.2
Work Order 02-22-12
Work Began 04-16-12
Work Completed  
Time Computed 04-16-12
Contract Working Days 107
Addl Days Granted 33
Working Days Charged 133
Percent Time Used 95
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0014-06-040
GREEN COW COMPOST(0.04%)
AMERICAN REMEDIATION OPTIONS, INC. (1.28%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. (1.35%)
FLASHER EQUIPMENT COMPANY(3.68%)
QUALITY BRICKWORKS (1.74%)
Contract # 01123214
Totals 1512674.65 0.00 1440636.31 95.2

CountyHILL
Highway IH 35
From FM 1304
To CHATT RD
CSJ 0014-07-081
Proj ID STP 2000(297)TE
Work Type CONSTR SFTY REST AREA
 
3.400 15116416.05 116955.23 14450853.24 95.5
Work Order 07-14-11
Work Began 09-12-11
Work Completed  
Time Computed 09-12-11
Contract Working Days 340
Addl Days Granted 24
Working Days Charged 361
Percent Time Used 99
Contractor(s)
SPAWGLASS CIVIL CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0014-07-081
BRAZOS VALLEY CONTRACTING CO.(9.69%)
BMP SPECIALIST, LLC(0.03%)
AUSTIN BRIDGE & ROAD, LP ( 20.59%)
BIG CREEK CONSTRUCTION, LTD. ( 10.07%)
SPERLING CONSTRUCTION(1.45%)
BOSQUEZ ELECTRICAL, LLC. (9.11%)
GARDNER MECHANICAL, LLC(2.03%)
PREMIER SERVICES (1.28%)
INNOVATIVE WATER SOLUTIONS LLC (1.58%)
FARMER MASONRY, INC. (2.64%)
MARTINEZ STEEL (0.11%)
BATTERSON,LLP(0.80%)
R.M. RODGERS, INC. (2.17%)
GRIZZLY GLASS & MIRROR, INC. (1.44%)
DIVISION 7 WATERPROOFING, LLC(0.23%)
WACO METAL BUILDING(1.48%)
PEARSON PAINT SHOP, INC. (0.62%)
ARCI, LTD(5.23%)
BREDA COMPANY, INC.(0.70%)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (1.02%)
A & H DRYWALL, INC.(0.68%)
MOODY TILE (1.36%)
PAUL E. ALLEN CO., INC.(0.97%)
CONCRETE CUTTING BY BOND (0.26%)
ABNEY CONCRETE (0.44%)
PAVE/MASTERS, INC. (0.84%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.10%)
REDEMPTION FENCE (0.01%)
M.K. BINKLEY CONSTRUCTION CO.(1.04%)
ROCK FIN COUNTERTOPS, INC. (0.14%)
CLS TECHNOLOGY, INC. (0.98%)
AMERITEK DESIGN INC. (0.06%)
H.B. BLAKE COMPANY, INC. (0.23%)
NO FAULT SPORT GROUP, LLC(0.25%)
JOHNSON ELECTRICAL CONTRACTORS, INC. (0.00%)
PROFESSIONAL SERVICE INDUSTRIES, INC.(0.07%)
Contract # 05113201
Totals 15116416.05 116955.23 14450853.24 95.5

CountyHILL
Highway IH 35
From MCLENNAN CL
To FM 1304
CSJ 0014-07-082
Proj ID C 14-7-82
Work Type WDN, GR, STRS & SURF
 
7.130 99737561.70 3261238.58 45217724.48 45.3
CountyHILL
Highway IH 35
From MCLENNAN CL
To FM 1304
CSJ 0014-07-096
Proj ID RW 14-7-96
Work Type ACQUISITION, RELOCATION & UTILITIES
 
4.441 566090.50 0.00 530938.50 93.7
CountyMCLENNAN
Highway IH 35
From FM 1858 IN WEST
To HILL CO LN
CSJ 0014-08-083
Proj ID RW 14-8-83
Work Type ACQUISITION, RELOCATION & UTILITIES
 
3.550 637146.40 0.00 679734.09 99.9
Work Order 04-05-11
Work Began 10-17-11
Work Completed  
Time Computed 10-02-11
Contract Working Days 915
Addl Days Granted 0
Working Days Charged 455
Percent Time Used 49
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0014-07-082
BMP SPECIALIST, LLC(0.47%)
BRAZOS VALLEY CONTRACTING CO.(8.88%)
DANIEL CONSTRUCTION SERVICES, INC. (AR DANIEL...)(0.63%)
FOUNDATION DRILLERS, INC.(0.59%)
HAROS BROS. CO.(0.58%)
PAVER SYSTEMS INTERNATIONAL(0.30%)
PREMIER PAVING, LTD. (9.29%)
RIVER CITIES SAWING, LLC (0.01%)
SCHNABEL FOUNDATION CO. (HOUSTON)(1.92%)
SILVA CONTRACTING COMPANY, INC.(0.50%)
STAR OPERATIONS, INC.(1.90%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.04%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.83%)
WEBBER BARRIER SERVICES, INC.(1.46%)
WHITNEY UNDERGROUND UTILITIES, INC.(0.58%)
INDUS CONSTRUCTION, L.P. (7.77%)
BEAR CREEK CONSTRUCTION, LLC (0.45%)
FARR FOUNDATION, INC.(0.04%)
EPCS ENVIRONMENTAL, LLC(0.34%)
FORTSON CONTRACTING, INC.(0.04%)
CRAIG OLDEN, INC.(1.42%)
ABNEY CONCRETE (0.07%)
Contract # 02113001
Totals 100940798.60 3261238.58 46428397.07 45.9

CountyHILL
Highway IH 35
From FM 1304
To FM 310
CSJ 0014-07-083
Proj ID STP 2010(642)
Work Type WDN, GR, STRS & SURF
 
5.456 33638347.95 0.00 32242951.76 95.8
CountyHILL
Highway IH 35
From FM 1304
To FM 310
CSJ 0014-07-094
Proj ID IM 35-4(222)
Work Type ROW ACQ., UTL. ADJ., RELOC. ASSIST.
 
4.880 2406413.00 0.00 2590609.03 99.9
Work Order 06-24-10
Work Began 07-12-10
Work Completed  
Time Computed 07-10-10
Contract Working Days 638
Addl Days Granted 0
Working Days Charged 629
Percent Time Used 98
Contractor(s)
W.W. WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0014-07-083
BRAZOS VALLEY CONTRACTING CO.(7.22%)
BMP SPECIALIST, LLC(1.46%)
NORTH TEXAS CONTRACTING, INC.(7.04%)
FORTSON CONTRACTING, INC.(0.44%)
FARR FOUNDATION, INC.(0.09%)
TEXAS SHAFTS, INC. (0.23%)
WEBBER BARRIER SERVICES, INC.(0.24%)
RIVER CITIES SAWING LLC(0.26%)
UNITED RENTALS HIGHWAY TECHNOLOGIES (NEWELL RD-FTWORTH)(1.04%)
HJC FARMS, INC.(0.28%)
INDUS CONSTRUCTION, L.P. (5.75%)
TTG UTILITIES, LP(1.82%)
CB SERVICES, INC.(0.06%)
SILVA CONTRACTING COMPANY, INC.(1.23%)
STAR OPERATIONS, INC.(4.45%)
BOOTHE BROTHERS PAVING COMPANY, INC. (0.41%)
BREDA COMPANY, INC.(0.00%)
PEACHTREE CONSTRUCTION, LTD. ( 22.24%)
J.E.D. TRUCKING, INC.(0.14%)
CURB BUILDERS, LLC (0.19%)
NORTH TEXAS BOMANITE, INC. (0.09%)
RG PAINTING(0.00%)
URETEK USA, INC. (0.16%)
Contract # 04103201
Totals 36044760.95 0.00 34833560.79 96.6

CountyMCLENNAN
Highway IH 35
From HILLTOP RD
To FM 1858 IN WEST
CSJ 0014-08-075
Proj ID C 14-8-75
Work Type WDN, GR, STRS, SURF & REPL BRDGS
 
27.046 166787859.89 2576000.65 113635893.82 68.1
Work Order 08-24-10
Work Began 10-22-10
Work Completed  
Time Computed 10-22-10
Contract Working Days 1,220
Addl Days Granted 3
Working Days Charged 737
Percent Time Used 60
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0014-08-075
WOLFF CONSTRUCTION (0.38%)
BROWN"S CONCRETE CONSTRUCTION COMPANY(0.89%)
BMP SPECIALIST, LLC(0.04%)
AMERICAN INTELOCK & MODULAR CONSTRUCTION, INC. (0.14%)
BEAIRD DRILLING(0.57%)
INDUS CONSTRUCTION, L.P. (2.13%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.44%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.76%)
HAROS BROS. CO.(0.29%)
HIGHWAY TECHNOLOGIES, INC. (0.55%)
ROADWAY SPECIALTIES, INC.(0.17%)
BIG CREEK CONSTRUCTION, LTD. ( 11.78%)
BASE CONSTRUCTION, L.L.P.(7.33%)
NORTH TEXAS CONTRACTING, INC.(0.47%)
BOSQUEZ ELECTRICAL, LLC. (0.00%)
SCOTT DERR PAINTING CO (0.98%)
NORTH TEXAS BOMANITE, INC. (0.65%)
BROOKLYN SWEEPS(0.12%)
STAR OPERATIONS, INC.(1.26%)
COWBELL TRAFFIC SERVICES, INC. (0.00%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.15%)
Contract # 07103256
Totals 166787859.89 2576000.65 113635893.82 68.1

CountyHILL
Highway IH 35W
From @ LOVELACE CREEK
To (STR #302)
CSJ 0014-23-029
Proj ID BR 2013(162)
Work Type REPL BR & APPRS
 
0.597 2811815.10 155111.20 155111.20 5.5
Work Order 02-26-13
Work Began 04-08-13
Work Completed  
Time Computed 04-27-13
Contract Working Days 147
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 9
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0014-23-029
BRENDA PRICE TRUCKING(4.83%)
DUSTROL, INC.(0.91%)
ENVIRONMENTAL STANDARDS, INC.(0.47%)
HIGHWAY TECHNOLOGIES, INC. (1.31%)
PEACHTREE CONSTRUCTION, LTD. ( 18.40%)
TEXAS ALTERNATIVE GRASSER, INC.(0.31%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.24%)
Contract # 01133223
Totals 2811815.10 155111.20 155111.20 5.5

CountyMCLENNAN
Highway IH 35
From SOUTH FM 2837 IN LORENA
To FM 2063 IN HEWITT
CSJ 0015-01-186
Proj ID IM 0354(234)
Work Type WDN, GR, STRS & SURF
 
19.461 212440194.96 811757.29 84866251.51 39.9
Work Order 12-13-11
Work Began 03-05-12
Work Completed  
Time Computed 03-05-12
Contract Working Days 1,138
Addl Days Granted 0
Working Days Charged 274
Percent Time Used 24
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0015-01-186
NORTH TEXAS CONTRACTING, INC.(3.29%)
PAVER SYSTEMS INTERNATIONAL(0.09%)
WALKER CONSTRUCTION(0.03%)
FREYSSINET, INC. (1.22%)
HJC FARMS, INC.(0.01%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.13%)
W.O.E. CONSTRUCTION(0.21%)
INDUS CONSTRUCTION, L.P. (1.35%)
HAROS PARTNERS, LP (0.58%)
HIGHWAY TECHNOLOGIES, INC. (0.94%)
STAR OPERATIONS, INC.(2.36%)
ROADWAY SPECIALTIES, INC.(0.12%)
CB SERVICES, INC.(0.38%)
J.E.D. TRUCKING, INC.(0.36%)
EGGEMEYER LAND CLEARING, LLC (0.08%)
PRIMATE CONSTRUCTION, INC. (0.04%)
W. W. FOUNDATION DRILLING, LTD.(1.20%)
DANRIDGE CONSTRUCTION, LLC.(0.24%)
ARROWHEAD CONCRETE, INC. (0.03%)
INDUS CONSTRUCTION, L.P. (0.04%)
TEX OP CONSTRUCTION, LP(0.00%)
TTG UTILITIES, LP(0.40%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.71%)
FARR FOUNDATION, INC.(1.06%)
DGI-MENARD, INC. (2.06%)
NORTH TEXAS CONTRACTING, INC.(0.95%)
TRANSAMERICAN UNDERGROUND, LTD (0.43%)
AR DANIEL SERVICES (0.20%)
WALLACE CONTROL"S & ELECTRIC, INC. (0.06%)
J. E. GUZMAN CONSTRUCTION, INC.(0.03%)
DCCS, LLC(0.07%)
J.C. COMMUNICATION (0.08%)
STEEL EFFECTS(0.12%)
SHOWS UTILITIES, INC.(0.01%)
Contract # 09113001
Totals 212440194.96 811757.29 84866251.51 39.9

CountyMCLENNAN
Highway IH 35
From FALLS COUNTY LINE
To WOODLAWN RD
CSJ 0015-02-048
Proj ID IM 0354(235)
Work Type WDN, GR, STR, & SURF
 
18.183 120722098.70 1139996.24 22031030.71 18.2
Work Order 12-27-11
Work Began 06-25-12
Work Completed  
Time Computed 06-24-12
Contract Working Days 1,210
Addl Days Granted 0
Working Days Charged 246
Percent Time Used 20
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0015-02-048
ALTEX LANDSCAPE CONSTRUCTION, INC. (0.54%)
APAC-TEXAS, INC. (9.61%)
BCG INVESTMENTS(0.24%)
BEAIRD DRILLING(0.71%)
BOSQUEZ ELECTRICAL, LLC. (1.03%)
DANRIDGE CONSTRUCTION, LLC.(0.19%)
DUSTROL, INC.(0.64%)
FORTSON CONTRACTING, INC.(0.22%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.28%)
HIGHWAY TECHNOLOGIES, INC. (1.17%)
ISBELL CONSTRUCTION(0.30%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.48%)
SOUTH TEXAS PAINTING COMPANY (0.11%)
SPEEDY PAVING(0.21%)
STEEL EFFECTS(0.15%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.44%)
WOLFF CONSTRUCTION (3.46%)
DRILL TECH DRILLING & SHORING, INC.(0.68%)
TTG UTILITIES, INC.(1.57%)
BECO CONSTRUCTION, L.L.C.(7.90%)
CTBX, INC. (0.02%)
GK CONSTRUCTION, LLC (0.04%)
STAMPEDE CREEK TRANSPORTATION(0.03%)
DIAMOND K MATERIALS(0.03%)
DOUBLE R TRUCKING(0.00%)
J & B(0.00%)
KYKO HAULING (0.00%)
R K STEPHENS CONSTRUCTION, LLC (0.17%)
CHUCK WHITE TRUCKING (0.03%)
BAR B CONTRACTING, INC.(0.01%)
JM DAVIS TRUCKING(0.00%)
DIVINE TRINITY, INC. (0.00%)
HDB TRUCKING (0.03%)
MSW TRUCKING, INC. (0.03%)
N. ROCK SOLUTIONS(0.03%)
ALAN JOHNSON TRUCKING(0.01%)
PRECISION CONTRACTORS(0.00%)
STP HAULERS, INC.(0.00%)
TEXAS BAR J TRUCKING, LLC(0.00%)
4D TRUCKN", LLC(0.00%)
BACKOR TRUCKING(0.00%)
PANTHER CREEK TRANSPORTATION, INC. (0.00%)
Contract # 10113001
Totals 120722098.70 1139996.24 22031030.71 18.2

CountyBELL
Highway IH 35
From NORTH LP 363
To N OF TROY
CSJ 0015-04-067
Proj ID C 15-4-67
Work Type WDN, GR, STRS & SURF
 
5.469 120853801.57 1106339.03 29141678.36 24.1
CountyBELL
Highway IH 35
From NORTH LP 363
To N OF TROY
CSJ 0015-04-083
Proj ID RW 15-4-83
Work Type ACQUISITION, RELOCATION & UTILITIES
 
5.569 2774870.75 241714.74 1834474.97 66.1
Work Order 07-22-11
Work Began 03-12-12
Work Completed  
Time Computed 01-18-12
Contract Working Days 1,166
Addl Days Granted 0
Working Days Charged 309
Percent Time Used 26
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0015-04-067
BEAIRD DRILLING(0.52%)
BELL CONTRACTORS (1.66%)
BIG CREEK CONSTRUCTION, LTD. (8.35%)
GK CONSTRUCTION, LLC (0.57%)
HJC FARMS, INC.(0.26%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.25%)
JAVELINA CONSTRUCTION SOUTH, INC.(0.41%)
KELLYSTONE, INC(0.22%)
SOUTH TEXAS PAINTING COMPANY (0.24%)
HIGHWAY TECHNOLOGIES, INC. (1.34%)
ISBELL CONSTRUCTION(0.58%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.35%)
SCOTT DERR PAINTING CO (0.03%)
WOLFF CONSTRUCTION (2.95%)
STAR OPERATIONS, INC.(1.48%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.09%)
STAMPEDE CREEK TRANSPORTATION(0.19%)
J & G CONCRETE PRODUCTS(1.46%)
3 P TRUCKING (0.19%)
4D TRUCKN", LLC(0.19%)
BELL CONTRACTORS (0.19%)
CHUCK WHITE TRUCKING (0.19%)
DIAMOND K MATERIALS(0.19%)
HDB TRUCKING (0.19%)
JM DAVIS TRUCKING(0.19%)
MSW TRUCKING, INC. (0.19%)
R & A HAULING(0.19%)
STP HAULERS, INC.(0.19%)
VICTOR THOMAS(0.19%)
ALVIN SOWDERS(0.19%)
BRAZOS BOTTOM TRUCKING, LLC(0.19%)
DOUBLE R TRUCKING(0.19%)
L2 HAULERS, LLC(0.19%)
MATERIALS-R-US (0.19%)
RACHEL"S TRUCKING, LLC (0.19%)
TOMMY T"S DUMP TRUCKING, INC.(0.19%)
INDUS CONSTRUCTION, L.P. (0.62%)
BRYANT & FREY CONSTRUCTION (0.19%)
SHOWS UTILITIES, INC.(0.29%)
DAKOTA UTILITY CONTRACTORS, INC. (0.16%)
NY-MAC ENTERPRISES, INC. (0.06%)
DIVINE TRINITY, INC. (0.19%)
PRECISION CONTRACTORS(0.03%)
TEXAS BAR J TRUCKING, LLC(0.03%)
SMITH & SMITH(0.03%)
J & B CONSTRUCTION COMPANY (0.03%)
PERFORMANCE EQUIPMENT(0.41%)
JOY LATTIMER, LLC. (0.03%)
BAR B CONTRACTING, INC.(0.01%)
ALAN JOHNSON TRUCKING(0.03%)
VAUGHAN HAULING(0.00%)
BACKOR TRUCKING(0.00%)
Contract # 06113201
Totals 123628672.32 1348053.77 30976153.33 25.0

CountyBELL
Highway IH 35
From AMITY ROAD
To US 190
CSJ 0015-06-071
Proj ID STP 2009(531)ES
Work Type WDN, GR, STRS & SURF
 
13.546 106887770.94 1402148.24 54579097.98 51.0
Work Order 06-10-10
Work Began 07-28-10
Work Completed  
Time Computed 06-26-10
Contract Working Days 1,224
Addl Days Granted 0
Working Days Charged 686
Percent Time Used 56
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0015-06-071
N-LINE TRAFFIC MAINTENANCE, L.P. (0.62%)
BEAIRD DRILLING(0.60%)
BIG CREEK CONSTRUCTION, LTD. ( 11.96%)
BOOTHE BROTHERS PAVING COMPANY, INC. (0.07%)
CENTRAL NORTH CONSTRUCTION, LLC(0.45%)
CHOCTAW ERECTORS, INC. (0.43%)
DANRIDGE CONSTRUCTION, LLC.(0.11%)
UNITED RENTALS HIGHWAY TECHNOLOGIES (AUSTIN) (0.68%)
PARKER COUNTY EROSION CONTROL(0.03%)
HJC FARMS, INC.(0.43%)
INDUS CONSTRUCTION, L.P. (1.79%)
KELLYSTONE, INC(0.11%)
PRIMATE CONSTRUCTION, INC. (0.10%)
SOUTH TEXAS PAINTING COMPANY (0.25%)
STAR OPERATIONS, INC.(3.00%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.26%)
TTG UTILITIES, INC.(2.34%)
WEST TEXAS RUMBLE STRIP(0.00%)
WOLFF CONSTRUCTION (0.17%)
STAMPEDE CREEK TRANSPORTATION(4.34%)
DYWIDAG SYSTEMS INTERNATIONAL USA, INC.(0.02%)
HAROS PARTNERS, LP (0.48%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.24%)
HTM CONSTRUCTION COMPANY (0.65%)
GK CONSTRUCTION, LLC (0.02%)
POTTER TRUCKING(1.26%)
MSW TRUCKING, INC. (0.11%)
JDK SERVICES, LLC(0.03%)
4-P TRUCKING, LLC(0.70%)
PLOWBOY ROCKS, LLC (0.24%)
JM DAVIS TRUCKING(0.24%)
SMITH & SMITH(0.10%)
HDB TRUCKING (0.10%)
R & A HAULING(0.02%)
JOHNNY SHEETS(0.03%)
STP HAULERS, INC.(0.10%)
VICTOR THOMAS(0.10%)
TEXAS CUTTING & CORING, INC. (0.00%)
BRUSH SOLUTIONS, LLC (0.01%)
CHUCK WHITE TRUCKING (0.02%)
DIAMOND K MATERIALS(0.24%)
BELL CONTRACTORS (0.02%)
4D TRUCKN", LLC(0.02%)
3 P TRUCKING (0.10%)
RACHEL"S TRUCKING, LLC (0.02%)
MATERIALS-R-US (0.02%)
DOUBLE R TRUCKING(0.02%)
ELITE HAULING, LLC (0.02%)
APAC-TEXAS, INC. (0.01%)
RON ISCHY MASONRY(0.02%)
TEXAS BAR J TRUCKING, LLC(0.02%)
PRECISION CONTRACTORS, LLC (0.02%)
J & B(0.02%)
BACKOR TRUCKING(0.02%)
Contract # 04103002
Totals 106887770.94 1402148.24 54579097.98 51.0

CountyBELL
Highway IH 35
From FM 2843
To FM 2484
CSJ 0015-07-065
Proj ID C 15-7-65
Work Type WDN, GR, STRS & SURF
 
3.333 69902149.68 1025555.12 20392003.62 29.1
CountyBELL
Highway IH 35
From FM 2843
To FM 2484
CSJ 0015-07-078
Proj ID RW 15-7-78
Work Type ROW ACQ., UTL. ADJ.; RELOC ASSIST.
 
2.843 547207.45 0.00 557379.01 99.9
Work Order 08-30-11
Work Began 01-05-12
Work Completed  
Time Computed 12-28-11
Contract Working Days 920
Addl Days Granted 0
Working Days Charged 265
Percent Time Used 28
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0015-07-065
BEAIRD DRILLING(0.94%)
BECO CONSTRUCTION, L.L.C.(1.23%)
CONCRETE PAVER SYSTEMS, INC. (0.14%)
FORTSON CONTRACTING, INC.(0.12%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.29%)
HIGHWAY TECHNOLOGIES, INC. (1.23%)
HTM CONSTRUCTION COMPANY (2.47%)
JAVELINA CONSTRUCTION SOUTH, INC.(0.44%)
J.D. RAMMING PAVING CO., LTD.(6.27%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.52%)
SCOTT DERR PAINTING CO (0.06%)
SOUTH TEXAS PAINTING COMPANY (0.61%)
STAMPEDE CREEK TRANSPORTATION(4.54%)
STAR OPERATIONS, INC.(1.11%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.19%)
TTG UTILITIES, INC.(0.79%)
WOLFF CONSTRUCTION (4.02%)
BCG INVESTMENTS(0.24%)
E-CLEAR(0.01%)
CTBX, INC. (0.51%)
HECTOR TAMEZ (0.04%)
LEE TRUCKING-NATHAN LEE MORRIS (0.02%)
KRUNC TRANSPORTATION (0.04%)
CLT TRANSPORTATION ENTERPRISES, INC. (0.02%)
MAX FRANCO M & D TRANSPORT (0.03%)
TIM ARMSTRONG TRUCKING, INC. (0.02%)
FRANK PRASIFKA & SONS, INC.(0.04%)
EDGAR GALAVAN DBA TRISA TRUCKING (0.06%)
TRANSGLOBAL, LLC (0.01%)
JM DAVIS TRUCKING(0.22%)
4D TRUCKN", LLC(0.22%)
TEXAS BAR J TRUCKING, LLC(0.09%)
PRECISION CONTRACTORS, LLC (0.09%)
DIVINE TRINITY, INC. (0.22%)
MSW TRUCKING, INC. (0.22%)
HDB TRUCKING (0.22%)
STP HAULERS, INC.(0.22%)
DIAMOND K MATERIALS(0.22%)
CHUCK WHITE TRUCKING (0.22%)
J & B(0.09%)
PERFORMANCE EQUIPMENT(0.55%)
BMP SPECIALIST, LLC(0.00%)
GK CONSTRUCTION, LLC (0.04%)
BACKOR TRUCKING(0.02%)
PANTHER CREEK TRANSPORTATION, INC. (0.00%)
Contract # 07113001
Totals 70449357.13 1025555.12 20949382.63 29.7

CountyBELL
Highway IH 35
From S LP 363 IN TEMPLE
To NUGENT AVE
CSJ 0015-14-091
Proj ID NH 2012(691)
Work Type WDN GR, STRS & SURF
 
12.836 241296935.09 97400.00 2412331.98 0.9
Work Order 11-15-12
Work Began 00-00-00
Work Completed  
Time Computed 05-14-13
Contract Working Days 1,200
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0015-14-091
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09123001
Totals 241296935.09 97400.00 2412331.98 0.9

CountyMCLENNAN
Highway LP 574
From BU 77
To IH 35
CSJ 0049-10-003
Proj ID HP 2013(333)
Work Type GR, STRS & SURF
 
1.002 14436151.22 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 277
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0049-10-003
A & A CONSTRUCTION (0.61%)
DRILL TECH DRILLING & SHORING, INC.(0.51%)
INTEGRATED ROADWAY SERVICES, INC.(5.01%)
J.E.D. TRUCKING, INC.(0.00%)
NORTH TEXAS REBAR, LLC (1.21%)
ROADWAY SPECIALTIES, INC.(0.79%)
SCOTT DERR PAINTING CO, LLC(0.19%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (2.13%)
STRIPING TECHNOLOGY, L.P.(0.49%)
W. W. FOUNDATION DRILLING, LTD.(1.93%)
Contract # 02133204
Totals 14436151.22 0.00 0.00 0.0

CountyCORYELL
Highway US 84
From FM 932
To HAMILTON C/L
CSJ 0055-03-023
Proj ID STP 2009(589)ES
Work Type ADD PASS LNS & SHLDRS
 
10.235 8735023.01 4800.00 9118676.67 99.9
Work Order 06-18-09
Work Began 06-24-09
Work Completed  
Time Computed 07-04-09
Contract Working Days 408
Addl Days Granted 0
Working Days Charged 345
Percent Time Used 84
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0055-03-023
CENTRAL NORTH CONSTRUCTION, LLC(0.00%)
T-6 BUILDERS (1.24%)
WHEELER COATINGS ASPHALT, L.P. (0.00%)
SERVICELINE TRANSPORT(4.80%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.73%)
D. I. J. CONSTRUCTION, INC.(1.21%)
ENVIRONMENTAL ALLIES, L.P. (0.22%)
TEXAS ALTERNATIVE GRASSER, INC.(0.44%)
APAC-TEXAS, INC. ( 50.97%)
WEST TEXAS RUMBLE STRIP(0.37%)
CEN TEX HYDROSEED, INC.(0.27%)
Contract # 04093401
Totals 8735023.01 4800.00 9118676.67 99.9

CountyMCLENNAN
Highway US 84
From @ FM 1695
To .
CSJ 0055-08-113
Proj ID STP 2012(366)
Work Type CNSTR RGHT TRN LN
 
1.159 1179583.30 10830.35 1285320.92 99.9
Work Order 05-22-12
Work Began 08-03-12
Work Completed  
Time Computed 07-21-12
Contract Working Days 91
Addl Days Granted 21
Working Days Charged 110
Percent Time Used 98
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0055-08-113
FORTSON CONTRACTING, INC.(1.74%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.18%)
J & M CONTRACTING, COMPANY ( 16.00%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.62%)
FLASHER EQUIPMENT COMPANY(2.36%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION (OLD PRIME) (0.83%)
Contract # 03123215
Totals 1179583.30 10830.35 1285320.92 99.9

CountyMCLENNAN
Highway US 84
From 43RD ST
To 0.2 MI N OF WALKER ST
CSJ 0055-15-064
Proj ID NH 2013(334)
Work Type CONCR PV RPR, DIAMOND GR & PAV MRK
 
4.906 1279258.85 0.00 180345.82 14.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-26-13
Work Began 04-08-13
Work Completed  
Time Computed 00-00-00
Contract Working Days 107
Addl Days Granted 0
Working Days Charged 17
Percent Time Used 15
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0055-15-064
BRENDA PRICE TRUCKING(0.81%)
HIGHWAY TECHNOLOGIES, INC. (2.94%)
PENHALL COMPANY( 50.81%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.78%)
Contract # 01133212
Totals 1279258.85 0.00 180345.82 14.0

CountyHILL
Highway SH 22
From LAKE WHITNEY
To FM 933
CSJ 0121-02-055
Proj ID STP 2012(145)
Work Type REPAIR / RESURF RDWY
 
6.168 5456559.89 307310.50 4708396.70 86.2
Work Order 02-06-12
Work Began 04-23-12
Work Completed  
Time Computed 04-06-12
Contract Working Days 304
Addl Days Granted 25
Working Days Charged 250
Percent Time Used 75
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0121-02-055
FLASHER EQUIPMENT COMPANY(1.12%)
MPB, INC.( 17.38%)
PRIMATE CONSTRUCTION, INC. (0.04%)
ROADWAY SPECIALTIES, INC.(2.62%)
SAN-ANN-CO., INC.(0.18%)
WEST TEXAS RUMBLE STRIP(0.08%)
TEX OP CONSTRUCTION, LP(0.09%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.11%)
Contract # 12113220
Totals 5456559.89 307310.50 4708396.70 86.2

CountyHILL
Highway SH 22
From FM 933
To SH 171
CSJ 0121-02-056
Proj ID STP 2013(467)
Work Type REHAB RDWAY / ADD PASS LNS
 
12.575 6401417.53 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-06-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 239
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0121-02-056
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03133020
Totals 6401417.53 0.00 0.00 0.0

CountyMCLENNAN
Highway SH 31
From SH 31 & US 84 WYE
To HILL C/L
CSJ 0162-01-056
Proj ID C 162-1-56
Work Type GR, STRS & SURF
 
14.526 55780217.33 27740.16 53391109.46 96.3
Work Order 04-13-09
Work Began 05-13-09
Work Completed  
Time Computed 04-29-09
Contract Working Days 814
Addl Days Granted 57
Working Days Charged 916
Percent Time Used 121
Contractor(s)
SAFECO INSURANCE COMPANIES
SUBCONTRACTOR(S) FOR CCSJ: 0162-01-056
WEST TEXAS RUMBLE STRIP(0.03%)
SCOTT DERR PAINTING CO (0.00%)
MCKINNEY DRILLING__(BUDA)(0.70%)
LINDSEY CONTRACTORS, INC.( 12.88%)
ALLIED FENCE COMPANY (0.09%)
DAKOTA UTILITY CONTRACTORS, INC. (0.01%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. (0.29%)
HIGHWAY TECHNOLOGIES, INC. (1.23%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.34%)
CHATFIELD ELECTRIC (0.06%)
ASSOCIATED DRILLING(0.00%)
JAG TRUCKING INC (1.84%)
5A TRANSPORTATION, INC.(1.84%)
MATOKA, INC. (0.04%)
SOUTH TEXAS INDUSTRIAL COATINGS, L.L.C.(0.11%)
FORTSON CONTRACTING, INC.(0.03%)
AAA FENCE CO.(0.01%)
BMP SPECIALIST, LLC(0.01%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. (0.56%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.05%)
D. I. J. CONSTRUCTION, INC.(0.86%)
TEXAS TREE & LANDSCAPE, LTD. (0.12%)
SOUTH TEXAS INDUSTRIAL COATINGS, L.L.C.(0.07%)
ROADWAY SPECIALTIES, INC.(0.70%)
SAN-ANN-CO., INC.(0.28%)
ADAY & ASSOCIATES, LLC (2.72%)
USA SWPPP INSPECTIONS, INC.(0.00%)
Contract # 03093001
Totals 55780217.33 27740.16 53391109.46 96.3

page 1 | page 2 | page 3