| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | HILL |
| Highway |
SH 81 |
| From |
@ MAJORS BRANCH |
| To |
(STR #025) |
| CSJ |
0014-05-031 |
| Proj ID |
BR 2012(577) |
| Work Type |
REPL BR & APPRS |
| |
|
0.293 |
1440525.30 |
68500.52 |
918059.36 |
63.7 |
| Work Order |
07-12-12 |
| Work Began |
11-27-12 |
| Work Completed |
|
| Time Computed |
10-11-12 |
| Contract Working Days |
189 |
| Addl Days Granted |
0 |
| Working Days Charged |
102 |
| Percent Time Used |
53 |
| Contractor(s) |
| ELLIS-MCGINNIS CONSTRUCTION CO. |
SUBCONTRACTOR(S) FOR CCSJ: 0014-05-031 STRIPING TECHNOLOGY, L.P.(1.21%) TEXAS ALTERNATIVE GRASSER, INC.(0.39%) JUST GROOVING, LTD.(0.29%) M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.14%) REYNOLDS ASPHALT & CONSTRUCTION COMPANY(4.36%) SCOTT DERR PAINTING CO (0.25%) FORTSON CONTRACTING, INC.(2.68%) SAN-ANN-CO., INC.(0.70%) NORTH TEXAS REBAR, LLC (0.14%) NORTH TEXAS REBAR, LLC (0.07%)
|
| Contract # |
05123228 |
|
Totals |
1440525.30 |
68500.52 |
918059.36 |
63.7 |
|
| County | HILL |
| Highway |
SH 81 |
| From |
SH 22 (NORTH) |
| To |
0.327 MI N OF SH 22 (NORTH) |
| CSJ |
0014-06-040 |
| Proj ID |
STP 2012(203) |
| Work Type |
REHAB RDWY |
| |
|
1.522 |
1512674.65 |
0.00 |
1440636.31 |
95.2 |
| Work Order |
02-22-12 |
| Work Began |
04-16-12 |
| Work Completed |
|
| Time Computed |
04-16-12 |
| Contract Working Days |
107 |
| Addl Days Granted |
33 |
| Working Days Charged |
133 |
| Percent Time Used |
95 |
| Contractor(s) |
| BIG CREEK CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0014-06-040 GREEN COW COMPOST(0.04%) AMERICAN REMEDIATION OPTIONS, INC. (1.28%) AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. (1.35%) FLASHER EQUIPMENT COMPANY(3.68%) QUALITY BRICKWORKS (1.74%)
|
| Contract # |
01123214 |
|
Totals |
1512674.65 |
0.00 |
1440636.31 |
95.2 |
|
| County | HILL |
| Highway |
IH 35 |
| From |
FM 1304 |
| To |
CHATT RD |
| CSJ |
0014-07-081 |
| Proj ID |
STP 2000(297)TE |
| Work Type |
CONSTR SFTY REST AREA |
| |
|
3.400 |
15116416.05 |
116955.23 |
14450853.24 |
95.5 |
| Work Order |
07-14-11 |
| Work Began |
09-12-11 |
| Work Completed |
|
| Time Computed |
09-12-11 |
| Contract Working Days |
340 |
| Addl Days Granted |
24 |
| Working Days Charged |
361 |
| Percent Time Used |
99 |
| Contractor(s) |
| SPAWGLASS CIVIL CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0014-07-081 BRAZOS VALLEY CONTRACTING CO.(9.69%) BMP SPECIALIST, LLC(0.03%) AUSTIN BRIDGE & ROAD, LP ( 20.59%) BIG CREEK CONSTRUCTION, LTD. ( 10.07%) SPERLING CONSTRUCTION(1.45%) BOSQUEZ ELECTRICAL, LLC. (9.11%) GARDNER MECHANICAL, LLC(2.03%) PREMIER SERVICES (1.28%) INNOVATIVE WATER SOLUTIONS LLC (1.58%) FARMER MASONRY, INC. (2.64%) MARTINEZ STEEL (0.11%) BATTERSON,LLP(0.80%) R.M. RODGERS, INC. (2.17%) GRIZZLY GLASS & MIRROR, INC. (1.44%) DIVISION 7 WATERPROOFING, LLC(0.23%) WACO METAL BUILDING(1.48%) PEARSON PAINT SHOP, INC. (0.62%) ARCI, LTD(5.23%) BREDA COMPANY, INC.(0.70%) LANDSCAPE CONTRACTING AND IRRIGATION, INC. (1.02%) A & H DRYWALL, INC.(0.68%) MOODY TILE (1.36%) PAUL E. ALLEN CO., INC.(0.97%) CONCRETE CUTTING BY BOND (0.26%) ABNEY CONCRETE (0.44%) PAVE/MASTERS, INC. (0.84%) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.10%) REDEMPTION FENCE (0.01%) M.K. BINKLEY CONSTRUCTION CO.(1.04%) ROCK FIN COUNTERTOPS, INC. (0.14%) CLS TECHNOLOGY, INC. (0.98%) AMERITEK DESIGN INC. (0.06%) H.B. BLAKE COMPANY, INC. (0.23%) NO FAULT SPORT GROUP, LLC(0.25%) JOHNSON ELECTRICAL CONTRACTORS, INC. (0.00%) PROFESSIONAL SERVICE INDUSTRIES, INC.(0.07%)
|
| Contract # |
05113201 |
|
Totals |
15116416.05 |
116955.23 |
14450853.24 |
95.5 |
|
| County | HILL |
| Highway |
IH 35 |
| From |
MCLENNAN CL |
| To |
FM 1304 |
| CSJ |
0014-07-082 |
| Proj ID |
C 14-7-82 |
| Work Type |
WDN, GR, STRS & SURF |
| |
|
7.130 |
99737561.70 |
3261238.58 |
45217724.48 |
45.3 |
| County | HILL |
| Highway |
IH 35 |
| From |
MCLENNAN CL |
| To |
FM 1304 |
| CSJ |
0014-07-096 |
| Proj ID |
RW 14-7-96 |
| Work Type |
ACQUISITION, RELOCATION & UTILITIES |
| |
|
4.441 |
566090.50 |
0.00 |
530938.50 |
93.7 |
| County | MCLENNAN |
| Highway |
IH 35 |
| From |
FM 1858 IN WEST |
| To |
HILL CO LN |
| CSJ |
0014-08-083 |
| Proj ID |
RW 14-8-83 |
| Work Type |
ACQUISITION, RELOCATION & UTILITIES |
| |
|
3.550 |
637146.40 |
0.00 |
679734.09 |
99.9 |
| Work Order |
04-05-11 |
| Work Began |
10-17-11 |
| Work Completed |
|
| Time Computed |
10-02-11 |
| Contract Working Days |
915 |
| Addl Days Granted |
0 |
| Working Days Charged |
455 |
| Percent Time Used |
49 |
| Contractor(s) |
| WEBBER, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0014-07-082 BMP SPECIALIST, LLC(0.47%) BRAZOS VALLEY CONTRACTING CO.(8.88%) DANIEL CONSTRUCTION SERVICES, INC. (AR DANIEL...)(0.63%) FOUNDATION DRILLERS, INC.(0.59%) HAROS BROS. CO.(0.58%) PAVER SYSTEMS INTERNATIONAL(0.30%) PREMIER PAVING, LTD. (9.29%) RIVER CITIES SAWING, LLC (0.01%) SCHNABEL FOUNDATION CO. (HOUSTON)(1.92%) SILVA CONTRACTING COMPANY, INC.(0.50%) STAR OPERATIONS, INC.(1.90%) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.04%) TOTAL HIGHWAY MAINTENANCE, LLC (0.83%) WEBBER BARRIER SERVICES, INC.(1.46%) WHITNEY UNDERGROUND UTILITIES, INC.(0.58%) INDUS CONSTRUCTION, L.P. (7.77%) BEAR CREEK CONSTRUCTION, LLC (0.45%) FARR FOUNDATION, INC.(0.04%) EPCS ENVIRONMENTAL, LLC(0.34%) FORTSON CONTRACTING, INC.(0.04%) CRAIG OLDEN, INC.(1.42%) ABNEY CONCRETE (0.07%)
|
| Contract # |
02113001 |
|
Totals |
100940798.60 |
3261238.58 |
46428397.07 |
45.9 |
|
| County | HILL |
| Highway |
IH 35 |
| From |
FM 1304 |
| To |
FM 310 |
| CSJ |
0014-07-083 |
| Proj ID |
STP 2010(642) |
| Work Type |
WDN, GR, STRS & SURF |
| |
|
5.456 |
33638347.95 |
0.00 |
32242951.76 |
95.8 |
| County | HILL |
| Highway |
IH 35 |
| From |
FM 1304 |
| To |
FM 310 |
| CSJ |
0014-07-094 |
| Proj ID |
IM 35-4(222) |
| Work Type |
ROW ACQ., UTL. ADJ., RELOC. ASSIST. |
| |
|
4.880 |
2406413.00 |
0.00 |
2590609.03 |
99.9 |
| Work Order |
06-24-10 |
| Work Began |
07-12-10 |
| Work Completed |
|
| Time Computed |
07-10-10 |
| Contract Working Days |
638 |
| Addl Days Granted |
0 |
| Working Days Charged |
629 |
| Percent Time Used |
98 |
| Contractor(s) |
| W.W. WEBBER, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0014-07-083 BRAZOS VALLEY CONTRACTING CO.(7.22%) BMP SPECIALIST, LLC(1.46%) NORTH TEXAS CONTRACTING, INC.(7.04%) FORTSON CONTRACTING, INC.(0.44%) FARR FOUNDATION, INC.(0.09%) TEXAS SHAFTS, INC. (0.23%) WEBBER BARRIER SERVICES, INC.(0.24%) RIVER CITIES SAWING LLC(0.26%) UNITED RENTALS HIGHWAY TECHNOLOGIES (NEWELL RD-FTWORTH)(1.04%) HJC FARMS, INC.(0.28%) INDUS CONSTRUCTION, L.P. (5.75%) TTG UTILITIES, LP(1.82%) CB SERVICES, INC.(0.06%) SILVA CONTRACTING COMPANY, INC.(1.23%) STAR OPERATIONS, INC.(4.45%) BOOTHE BROTHERS PAVING COMPANY, INC. (0.41%) BREDA COMPANY, INC.(0.00%) PEACHTREE CONSTRUCTION, LTD. ( 22.24%) J.E.D. TRUCKING, INC.(0.14%) CURB BUILDERS, LLC (0.19%) NORTH TEXAS BOMANITE, INC. (0.09%) RG PAINTING(0.00%) URETEK USA, INC. (0.16%)
|
| Contract # |
04103201 |
|
Totals |
36044760.95 |
0.00 |
34833560.79 |
96.6 |
|
| County | MCLENNAN |
| Highway |
IH 35 |
| From |
HILLTOP RD |
| To |
FM 1858 IN WEST |
| CSJ |
0014-08-075 |
| Proj ID |
C 14-8-75 |
| Work Type |
WDN, GR, STRS, SURF & REPL BRDGS |
| |
|
27.046 |
166787859.89 |
2576000.65 |
113635893.82 |
68.1 |
| Work Order |
08-24-10 |
| Work Began |
10-22-10 |
| Work Completed |
|
| Time Computed |
10-22-10 |
| Contract Working Days |
1,220 |
| Addl Days Granted |
3 |
| Working Days Charged |
737 |
| Percent Time Used |
60 |
| Contractor(s) |
| WILLIAMS BROTHERS CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0014-08-075 WOLFF CONSTRUCTION (0.38%) BROWN"S CONCRETE CONSTRUCTION COMPANY(0.89%) BMP SPECIALIST, LLC(0.04%) AMERICAN INTELOCK & MODULAR CONSTRUCTION, INC. (0.14%) BEAIRD DRILLING(0.57%) INDUS CONSTRUCTION, L.P. (2.13%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.44%) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.76%) HAROS BROS. CO.(0.29%) HIGHWAY TECHNOLOGIES, INC. (0.55%) ROADWAY SPECIALTIES, INC.(0.17%) BIG CREEK CONSTRUCTION, LTD. ( 11.78%) BASE CONSTRUCTION, L.L.P.(7.33%) NORTH TEXAS CONTRACTING, INC.(0.47%) BOSQUEZ ELECTRICAL, LLC. (0.00%) SCOTT DERR PAINTING CO (0.98%) NORTH TEXAS BOMANITE, INC. (0.65%) BROOKLYN SWEEPS(0.12%) STAR OPERATIONS, INC.(1.26%) COWBELL TRAFFIC SERVICES, INC. (0.00%) N-LINE TRAFFIC MAINTENANCE, L.P. (0.15%)
|
| Contract # |
07103256 |
|
Totals |
166787859.89 |
2576000.65 |
113635893.82 |
68.1 |
|
| County | HILL |
| Highway |
IH 35W |
| From |
@ LOVELACE CREEK |
| To |
(STR #302) |
| CSJ |
0014-23-029 |
| Proj ID |
BR 2013(162) |
| Work Type |
REPL BR & APPRS |
| |
|
0.597 |
2811815.10 |
155111.20 |
155111.20 |
5.5 |
| Work Order |
02-26-13 |
| Work Began |
04-08-13 |
| Work Completed |
|
| Time Computed |
04-27-13 |
| Contract Working Days |
147 |
| Addl Days Granted |
0 |
| Working Days Charged |
14 |
| Percent Time Used |
9 |
| Contractor(s) |
| O. TREVINO CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0014-23-029 BRENDA PRICE TRUCKING(4.83%) DUSTROL, INC.(0.91%) ENVIRONMENTAL STANDARDS, INC.(0.47%) HIGHWAY TECHNOLOGIES, INC. (1.31%) PEACHTREE CONSTRUCTION, LTD. ( 18.40%) TEXAS ALTERNATIVE GRASSER, INC.(0.31%) TOTAL HIGHWAY MAINTENANCE, LLC (0.24%)
|
| Contract # |
01133223 |
|
Totals |
2811815.10 |
155111.20 |
155111.20 |
5.5 |
|
| County | MCLENNAN |
| Highway |
IH 35 |
| From |
SOUTH FM 2837 IN LORENA |
| To |
FM 2063 IN HEWITT |
| CSJ |
0015-01-186 |
| Proj ID |
IM 0354(234) |
| Work Type |
WDN, GR, STRS & SURF |
| |
|
19.461 |
212440194.96 |
811757.29 |
84866251.51 |
39.9 |
| Work Order |
12-13-11 |
| Work Began |
03-05-12 |
| Work Completed |
|
| Time Computed |
03-05-12 |
| Contract Working Days |
1,138 |
| Addl Days Granted |
0 |
| Working Days Charged |
274 |
| Percent Time Used |
24 |
| Contractor(s) |
| THE LANE CONSTRUCTION CORPORATION |
SUBCONTRACTOR(S) FOR CCSJ: 0015-01-186 NORTH TEXAS CONTRACTING, INC.(3.29%) PAVER SYSTEMS INTERNATIONAL(0.09%) WALKER CONSTRUCTION(0.03%) FREYSSINET, INC. (1.22%) HJC FARMS, INC.(0.01%) TOTAL HIGHWAY MAINTENANCE, LLC (0.13%) W.O.E. CONSTRUCTION(0.21%) INDUS CONSTRUCTION, L.P. (1.35%) HAROS PARTNERS, LP (0.58%) HIGHWAY TECHNOLOGIES, INC. (0.94%) STAR OPERATIONS, INC.(2.36%) ROADWAY SPECIALTIES, INC.(0.12%) CB SERVICES, INC.(0.38%) J.E.D. TRUCKING, INC.(0.36%) EGGEMEYER LAND CLEARING, LLC (0.08%) PRIMATE CONSTRUCTION, INC. (0.04%) W. W. FOUNDATION DRILLING, LTD.(1.20%) DANRIDGE CONSTRUCTION, LLC.(0.24%) ARROWHEAD CONCRETE, INC. (0.03%) INDUS CONSTRUCTION, L.P. (0.04%) TEX OP CONSTRUCTION, LP(0.00%) TTG UTILITIES, LP(0.40%) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.71%) FARR FOUNDATION, INC.(1.06%) DGI-MENARD, INC. (2.06%) NORTH TEXAS CONTRACTING, INC.(0.95%) TRANSAMERICAN UNDERGROUND, LTD (0.43%) AR DANIEL SERVICES (0.20%) WALLACE CONTROL"S & ELECTRIC, INC. (0.06%) J. E. GUZMAN CONSTRUCTION, INC.(0.03%) DCCS, LLC(0.07%) J.C. COMMUNICATION (0.08%) STEEL EFFECTS(0.12%) SHOWS UTILITIES, INC.(0.01%)
|
| Contract # |
09113001 |
|
Totals |
212440194.96 |
811757.29 |
84866251.51 |
39.9 |
|
| County | MCLENNAN |
| Highway |
IH 35 |
| From |
FALLS COUNTY LINE |
| To |
WOODLAWN RD |
| CSJ |
0015-02-048 |
| Proj ID |
IM 0354(235) |
| Work Type |
WDN, GR, STR, & SURF |
| |
|
18.183 |
120722098.70 |
1139996.24 |
22031030.71 |
18.2 |
| Work Order |
12-27-11 |
| Work Began |
06-25-12 |
| Work Completed |
|
| Time Computed |
06-24-12 |
| Contract Working Days |
1,210 |
| Addl Days Granted |
0 |
| Working Days Charged |
246 |
| Percent Time Used |
20 |
| Contractor(s) |
| JAMES CONSTRUCTION GROUP, L.L.C. |
SUBCONTRACTOR(S) FOR CCSJ: 0015-02-048 ALTEX LANDSCAPE CONSTRUCTION, INC. (0.54%) APAC-TEXAS, INC. (9.61%) BCG INVESTMENTS(0.24%) BEAIRD DRILLING(0.71%) BOSQUEZ ELECTRICAL, LLC. (1.03%) DANRIDGE CONSTRUCTION, LLC.(0.19%) DUSTROL, INC.(0.64%) FORTSON CONTRACTING, INC.(0.22%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.28%) HIGHWAY TECHNOLOGIES, INC. (1.17%) ISBELL CONSTRUCTION(0.30%) N-LINE TRAFFIC MAINTENANCE, L.P. (0.48%) SOUTH TEXAS PAINTING COMPANY (0.11%) SPEEDY PAVING(0.21%) STEEL EFFECTS(0.15%) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.44%) WOLFF CONSTRUCTION (3.46%) DRILL TECH DRILLING & SHORING, INC.(0.68%) TTG UTILITIES, INC.(1.57%) BECO CONSTRUCTION, L.L.C.(7.90%) CTBX, INC. (0.02%) GK CONSTRUCTION, LLC (0.04%) STAMPEDE CREEK TRANSPORTATION(0.03%) DIAMOND K MATERIALS(0.03%) DOUBLE R TRUCKING(0.00%) J & B(0.00%) KYKO HAULING (0.00%) R K STEPHENS CONSTRUCTION, LLC (0.17%) CHUCK WHITE TRUCKING (0.03%) BAR B CONTRACTING, INC.(0.01%) JM DAVIS TRUCKING(0.00%) DIVINE TRINITY, INC. (0.00%) HDB TRUCKING (0.03%) MSW TRUCKING, INC. (0.03%) N. ROCK SOLUTIONS(0.03%) ALAN JOHNSON TRUCKING(0.01%) PRECISION CONTRACTORS(0.00%) STP HAULERS, INC.(0.00%) TEXAS BAR J TRUCKING, LLC(0.00%) 4D TRUCKN", LLC(0.00%) BACKOR TRUCKING(0.00%) PANTHER CREEK TRANSPORTATION, INC. (0.00%)
|
| Contract # |
10113001 |
|
Totals |
120722098.70 |
1139996.24 |
22031030.71 |
18.2 |
|
| County | BELL |
| Highway |
IH 35 |
| From |
NORTH LP 363 |
| To |
N OF TROY |
| CSJ |
0015-04-067 |
| Proj ID |
C 15-4-67 |
| Work Type |
WDN, GR, STRS & SURF |
| |
|
5.469 |
120853801.57 |
1106339.03 |
29141678.36 |
24.1 |
| County | BELL |
| Highway |
IH 35 |
| From |
NORTH LP 363 |
| To |
N OF TROY |
| CSJ |
0015-04-083 |
| Proj ID |
RW 15-4-83 |
| Work Type |
ACQUISITION, RELOCATION & UTILITIES |
| |
|
5.569 |
2774870.75 |
241714.74 |
1834474.97 |
66.1 |
| Work Order |
07-22-11 |
| Work Began |
03-12-12 |
| Work Completed |
|
| Time Computed |
01-18-12 |
| Contract Working Days |
1,166 |
| Addl Days Granted |
0 |
| Working Days Charged |
309 |
| Percent Time Used |
26 |
| Contractor(s) |
| JAMES CONSTRUCTION GROUP, L.L.C. |
SUBCONTRACTOR(S) FOR CCSJ: 0015-04-067 BEAIRD DRILLING(0.52%) BELL CONTRACTORS (1.66%) BIG CREEK CONSTRUCTION, LTD. (8.35%) GK CONSTRUCTION, LLC (0.57%) HJC FARMS, INC.(0.26%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.25%) JAVELINA CONSTRUCTION SOUTH, INC.(0.41%) KELLYSTONE, INC(0.22%) SOUTH TEXAS PAINTING COMPANY (0.24%) HIGHWAY TECHNOLOGIES, INC. (1.34%) ISBELL CONSTRUCTION(0.58%) N-LINE TRAFFIC MAINTENANCE, L.P. (0.35%) SCOTT DERR PAINTING CO (0.03%) WOLFF CONSTRUCTION (2.95%) STAR OPERATIONS, INC.(1.48%) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.09%) STAMPEDE CREEK TRANSPORTATION(0.19%) J & G CONCRETE PRODUCTS(1.46%) 3 P TRUCKING (0.19%) 4D TRUCKN", LLC(0.19%) BELL CONTRACTORS (0.19%) CHUCK WHITE TRUCKING (0.19%) DIAMOND K MATERIALS(0.19%) HDB TRUCKING (0.19%) JM DAVIS TRUCKING(0.19%) MSW TRUCKING, INC. (0.19%) R & A HAULING(0.19%) STP HAULERS, INC.(0.19%) VICTOR THOMAS(0.19%) ALVIN SOWDERS(0.19%) BRAZOS BOTTOM TRUCKING, LLC(0.19%) DOUBLE R TRUCKING(0.19%) L2 HAULERS, LLC(0.19%) MATERIALS-R-US (0.19%) RACHEL"S TRUCKING, LLC (0.19%) TOMMY T"S DUMP TRUCKING, INC.(0.19%) INDUS CONSTRUCTION, L.P. (0.62%) BRYANT & FREY CONSTRUCTION (0.19%) SHOWS UTILITIES, INC.(0.29%) DAKOTA UTILITY CONTRACTORS, INC. (0.16%) NY-MAC ENTERPRISES, INC. (0.06%) DIVINE TRINITY, INC. (0.19%) PRECISION CONTRACTORS(0.03%) TEXAS BAR J TRUCKING, LLC(0.03%) SMITH & SMITH(0.03%) J & B CONSTRUCTION COMPANY (0.03%) PERFORMANCE EQUIPMENT(0.41%) JOY LATTIMER, LLC. (0.03%) BAR B CONTRACTING, INC.(0.01%) ALAN JOHNSON TRUCKING(0.03%) VAUGHAN HAULING(0.00%) BACKOR TRUCKING(0.00%)
|
| Contract # |
06113201 |
|
Totals |
123628672.32 |
1348053.77 |
30976153.33 |
25.0 |
|
| County | BELL |
| Highway |
IH 35 |
| From |
AMITY ROAD |
| To |
US 190 |
| CSJ |
0015-06-071 |
| Proj ID |
STP 2009(531)ES |
| Work Type |
WDN, GR, STRS & SURF |
| |
|
13.546 |
106887770.94 |
1402148.24 |
54579097.98 |
51.0 |
| Work Order |
06-10-10 |
| Work Began |
07-28-10 |
| Work Completed |
|
| Time Computed |
06-26-10 |
| Contract Working Days |
1,224 |
| Addl Days Granted |
0 |
| Working Days Charged |
686 |
| Percent Time Used |
56 |
| Contractor(s) |
| JAMES CONSTRUCTION GROUP, L.L.C. |
SUBCONTRACTOR(S) FOR CCSJ: 0015-06-071 N-LINE TRAFFIC MAINTENANCE, L.P. (0.62%) BEAIRD DRILLING(0.60%) BIG CREEK CONSTRUCTION, LTD. ( 11.96%) BOOTHE BROTHERS PAVING COMPANY, INC. (0.07%) CENTRAL NORTH CONSTRUCTION, LLC(0.45%) CHOCTAW ERECTORS, INC. (0.43%) DANRIDGE CONSTRUCTION, LLC.(0.11%) UNITED RENTALS HIGHWAY TECHNOLOGIES (AUSTIN) (0.68%) PARKER COUNTY EROSION CONTROL(0.03%) HJC FARMS, INC.(0.43%) INDUS CONSTRUCTION, L.P. (1.79%) KELLYSTONE, INC(0.11%) PRIMATE CONSTRUCTION, INC. (0.10%) SOUTH TEXAS PAINTING COMPANY (0.25%) STAR OPERATIONS, INC.(3.00%) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.26%) TTG UTILITIES, INC.(2.34%) WEST TEXAS RUMBLE STRIP(0.00%) WOLFF CONSTRUCTION (0.17%) STAMPEDE CREEK TRANSPORTATION(4.34%) DYWIDAG SYSTEMS INTERNATIONAL USA, INC.(0.02%) HAROS PARTNERS, LP (0.48%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.24%) HTM CONSTRUCTION COMPANY (0.65%) GK CONSTRUCTION, LLC (0.02%) POTTER TRUCKING(1.26%) MSW TRUCKING, INC. (0.11%) JDK SERVICES, LLC(0.03%) 4-P TRUCKING, LLC(0.70%) PLOWBOY ROCKS, LLC (0.24%) JM DAVIS TRUCKING(0.24%) SMITH & SMITH(0.10%) HDB TRUCKING (0.10%) R & A HAULING(0.02%) JOHNNY SHEETS(0.03%) STP HAULERS, INC.(0.10%) VICTOR THOMAS(0.10%) TEXAS CUTTING & CORING, INC. (0.00%) BRUSH SOLUTIONS, LLC (0.01%) CHUCK WHITE TRUCKING (0.02%) DIAMOND K MATERIALS(0.24%) BELL CONTRACTORS (0.02%) 4D TRUCKN", LLC(0.02%) 3 P TRUCKING (0.10%) RACHEL"S TRUCKING, LLC (0.02%) MATERIALS-R-US (0.02%) DOUBLE R TRUCKING(0.02%) ELITE HAULING, LLC (0.02%) APAC-TEXAS, INC. (0.01%) RON ISCHY MASONRY(0.02%) TEXAS BAR J TRUCKING, LLC(0.02%) PRECISION CONTRACTORS, LLC (0.02%) J & B(0.02%) BACKOR TRUCKING(0.02%)
|
| Contract # |
04103002 |
|
Totals |
106887770.94 |
1402148.24 |
54579097.98 |
51.0 |
|
| County | BELL |
| Highway |
IH 35 |
| From |
FM 2843 |
| To |
FM 2484 |
| CSJ |
0015-07-065 |
| Proj ID |
C 15-7-65 |
| Work Type |
WDN, GR, STRS & SURF |
| |
|
3.333 |
69902149.68 |
1025555.12 |
20392003.62 |
29.1 |
| County | BELL |
| Highway |
IH 35 |
| From |
FM 2843 |
| To |
FM 2484 |
| CSJ |
0015-07-078 |
| Proj ID |
RW 15-7-78 |
| Work Type |
ROW ACQ., UTL. ADJ.; RELOC ASSIST. |
| |
|
2.843 |
547207.45 |
0.00 |
557379.01 |
99.9 |
| Work Order |
08-30-11 |
| Work Began |
01-05-12 |
| Work Completed |
|
| Time Computed |
12-28-11 |
| Contract Working Days |
920 |
| Addl Days Granted |
0 |
| Working Days Charged |
265 |
| Percent Time Used |
28 |
| Contractor(s) |
| JAMES CONSTRUCTION GROUP, L.L.C. |
SUBCONTRACTOR(S) FOR CCSJ: 0015-07-065 BEAIRD DRILLING(0.94%) BECO CONSTRUCTION, L.L.C.(1.23%) CONCRETE PAVER SYSTEMS, INC. (0.14%) FORTSON CONTRACTING, INC.(0.12%) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.29%) HIGHWAY TECHNOLOGIES, INC. (1.23%) HTM CONSTRUCTION COMPANY (2.47%) JAVELINA CONSTRUCTION SOUTH, INC.(0.44%) J.D. RAMMING PAVING CO., LTD.(6.27%) N-LINE TRAFFIC MAINTENANCE, L.P. (0.52%) SCOTT DERR PAINTING CO (0.06%) SOUTH TEXAS PAINTING COMPANY (0.61%) STAMPEDE CREEK TRANSPORTATION(4.54%) STAR OPERATIONS, INC.(1.11%) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.19%) TTG UTILITIES, INC.(0.79%) WOLFF CONSTRUCTION (4.02%) BCG INVESTMENTS(0.24%) E-CLEAR(0.01%) CTBX, INC. (0.51%) HECTOR TAMEZ (0.04%) LEE TRUCKING-NATHAN LEE MORRIS (0.02%) KRUNC TRANSPORTATION (0.04%) CLT TRANSPORTATION ENTERPRISES, INC. (0.02%) MAX FRANCO M & D TRANSPORT (0.03%) TIM ARMSTRONG TRUCKING, INC. (0.02%) FRANK PRASIFKA & SONS, INC.(0.04%) EDGAR GALAVAN DBA TRISA TRUCKING (0.06%) TRANSGLOBAL, LLC (0.01%) JM DAVIS TRUCKING(0.22%) 4D TRUCKN", LLC(0.22%) TEXAS BAR J TRUCKING, LLC(0.09%) PRECISION CONTRACTORS, LLC (0.09%) DIVINE TRINITY, INC. (0.22%) MSW TRUCKING, INC. (0.22%) HDB TRUCKING (0.22%) STP HAULERS, INC.(0.22%) DIAMOND K MATERIALS(0.22%) CHUCK WHITE TRUCKING (0.22%) J & B(0.09%) PERFORMANCE EQUIPMENT(0.55%) BMP SPECIALIST, LLC(0.00%) GK CONSTRUCTION, LLC (0.04%) BACKOR TRUCKING(0.02%) PANTHER CREEK TRANSPORTATION, INC. (0.00%)
|
| Contract # |
07113001 |
|
Totals |
70449357.13 |
1025555.12 |
20949382.63 |
29.7 |
|
| County | BELL |
| Highway |
IH 35 |
| From |
S LP 363 IN TEMPLE |
| To |
NUGENT AVE |
| CSJ |
0015-14-091 |
| Proj ID |
NH 2012(691) |
| Work Type |
WDN GR, STRS & SURF |
| |
|
12.836 |
241296935.09 |
97400.00 |
2412331.98 |
0.9 |
| Work Order |
11-15-12 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
05-14-13 |
| Contract Working Days |
1,200 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| JAMES CONSTRUCTION GROUP, L.L.C. |
SUBCONTRACTOR(S) FOR CCSJ: 0015-14-091 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
09123001 |
|
Totals |
241296935.09 |
97400.00 |
2412331.98 |
0.9 |
|
| County | MCLENNAN |
| Highway |
LP 574 |
| From |
BU 77 |
| To |
IH 35 |
| CSJ |
0049-10-003 |
| Proj ID |
HP 2013(333) |
| Work Type |
GR, STRS & SURF |
| |
|
1.002 |
14436151.22 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
277 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| THE LANE CONSTRUCTION CORPORATION |
SUBCONTRACTOR(S) FOR CCSJ: 0049-10-003 A & A CONSTRUCTION (0.61%) DRILL TECH DRILLING & SHORING, INC.(0.51%) INTEGRATED ROADWAY SERVICES, INC.(5.01%) J.E.D. TRUCKING, INC.(0.00%) NORTH TEXAS REBAR, LLC (1.21%) ROADWAY SPECIALTIES, INC.(0.79%) SCOTT DERR PAINTING CO, LLC(0.19%) SIGNATURE CONTRACTING SERVICES, L.L.C. (2.13%) STRIPING TECHNOLOGY, L.P.(0.49%) W. W. FOUNDATION DRILLING, LTD.(1.93%)
|
| Contract # |
02133204 |
|
Totals |
14436151.22 |
0.00 |
0.00 |
0.0 |
|
| County | CORYELL |
| Highway |
US 84 |
| From |
FM 932 |
| To |
HAMILTON C/L |
| CSJ |
0055-03-023 |
| Proj ID |
STP 2009(589)ES |
| Work Type |
ADD PASS LNS & SHLDRS |
| |
|
10.235 |
8735023.01 |
4800.00 |
9118676.67 |
99.9 |
| Work Order |
06-18-09 |
| Work Began |
06-24-09 |
| Work Completed |
|
| Time Computed |
07-04-09 |
| Contract Working Days |
408 |
| Addl Days Granted |
0 |
| Working Days Charged |
345 |
| Percent Time Used |
84 |
| Contractor(s) |
| JAY MILLS CONTRACTING, INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 0055-03-023 CENTRAL NORTH CONSTRUCTION, LLC(0.00%) T-6 BUILDERS (1.24%) WHEELER COATINGS ASPHALT, L.P. (0.00%) SERVICELINE TRANSPORT(4.80%) LONE STAR HIGHWAY PRODUCTS, INC. (0.73%) D. I. J. CONSTRUCTION, INC.(1.21%) ENVIRONMENTAL ALLIES, L.P. (0.22%) TEXAS ALTERNATIVE GRASSER, INC.(0.44%) APAC-TEXAS, INC. ( 50.97%) WEST TEXAS RUMBLE STRIP(0.37%) CEN TEX HYDROSEED, INC.(0.27%)
|
| Contract # |
04093401 |
|
Totals |
8735023.01 |
4800.00 |
9118676.67 |
99.9 |
|
| County | MCLENNAN |
| Highway |
US 84 |
| From |
@ FM 1695 |
| To |
. |
| CSJ |
0055-08-113 |
| Proj ID |
STP 2012(366) |
| Work Type |
CNSTR RGHT TRN LN |
| |
|
1.159 |
1179583.30 |
10830.35 |
1285320.92 |
99.9 |
| Work Order |
05-22-12 |
| Work Began |
08-03-12 |
| Work Completed |
|
| Time Computed |
07-21-12 |
| Contract Working Days |
91 |
| Addl Days Granted |
21 |
| Working Days Charged |
110 |
| Percent Time Used |
98 |
| Contractor(s) |
| APAC-TEXAS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0055-08-113 FORTSON CONTRACTING, INC.(1.74%) SOUTHWEST ENVIRONMENT SERVICES LLC (1.18%) J & M CONTRACTING, COMPANY ( 16.00%) N-LINE TRAFFIC MAINTENANCE, L.P. (1.62%) FLASHER EQUIPMENT COMPANY(2.36%) AUSTIN TRAFFIC SIGNAL CONSTRUCTION (OLD PRIME) (0.83%)
|
| Contract # |
03123215 |
|
Totals |
1179583.30 |
10830.35 |
1285320.92 |
99.9 |
|
| County | MCLENNAN |
| Highway |
US 84 |
| From |
43RD ST |
| To |
0.2 MI N OF WALKER ST |
| CSJ |
0055-15-064 |
| Proj ID |
NH 2013(334) |
| Work Type |
CONCR PV RPR, DIAMOND GR & PAV MRK |
| |
|
4.906 |
1279258.85 |
0.00 |
180345.82 |
14.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
02-26-13 |
| Work Began |
04-08-13 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
107 |
| Addl Days Granted |
0 |
| Working Days Charged |
17 |
| Percent Time Used |
15 |
| Contractor(s) |
| O. TREVINO CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0055-15-064 BRENDA PRICE TRUCKING(0.81%) HIGHWAY TECHNOLOGIES, INC. (2.94%) PENHALL COMPANY( 50.81%) N-LINE TRAFFIC MAINTENANCE, L.P. (0.78%)
|
| Contract # |
01133212 |
|
Totals |
1279258.85 |
0.00 |
180345.82 |
14.0 |
|
| County | HILL |
| Highway |
SH 22 |
| From |
LAKE WHITNEY |
| To |
FM 933 |
| CSJ |
0121-02-055 |
| Proj ID |
STP 2012(145) |
| Work Type |
REPAIR / RESURF RDWY |
| |
|
6.168 |
5456559.89 |
307310.50 |
4708396.70 |
86.2 |
| Work Order |
02-06-12 |
| Work Began |
04-23-12 |
| Work Completed |
|
| Time Computed |
04-06-12 |
| Contract Working Days |
304 |
| Addl Days Granted |
25 |
| Working Days Charged |
250 |
| Percent Time Used |
75 |
| Contractor(s) |
| APAC-TEXAS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0121-02-055 FLASHER EQUIPMENT COMPANY(1.12%) MPB, INC.( 17.38%) PRIMATE CONSTRUCTION, INC. (0.04%) ROADWAY SPECIALTIES, INC.(2.62%) SAN-ANN-CO., INC.(0.18%) WEST TEXAS RUMBLE STRIP(0.08%) TEX OP CONSTRUCTION, LP(0.09%) N-LINE TRAFFIC MAINTENANCE, L.P. (0.11%)
|
| Contract # |
12113220 |
|
Totals |
5456559.89 |
307310.50 |
4708396.70 |
86.2 |
|
| County | HILL |
| Highway |
SH 22 |
| From |
FM 933 |
| To |
SH 171 |
| CSJ |
0121-02-056 |
| Proj ID |
STP 2013(467) |
| Work Type |
REHAB RDWAY / ADD PASS LNS |
| |
|
12.575 |
6401417.53 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
05-06-13 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
239 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| KNIFE RIVER CORPORATION - SOUTH |
SUBCONTRACTOR(S) FOR CCSJ: 0121-02-056 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
03133020 |
|
Totals |
6401417.53 |
0.00 |
0.00 |
0.0 |
|
| County | MCLENNAN |
| Highway |
SH 31 |
| From |
SH 31 & US 84 WYE |
| To |
HILL C/L |
| CSJ |
0162-01-056 |
| Proj ID |
C 162-1-56 |
| Work Type |
GR, STRS & SURF |
| |
|
14.526 |
55780217.33 |
27740.16 |
53391109.46 |
96.3 |
| Work Order |
04-13-09 |
| Work Began |
05-13-09 |
| Work Completed |
|
| Time Computed |
04-29-09 |
| Contract Working Days |
814 |
| Addl Days Granted |
57 |
| Working Days Charged |
916 |
| Percent Time Used |
121 |
| Contractor(s) |
| SAFECO INSURANCE COMPANIES |
SUBCONTRACTOR(S) FOR CCSJ: 0162-01-056 WEST TEXAS RUMBLE STRIP(0.03%) SCOTT DERR PAINTING CO (0.00%) MCKINNEY DRILLING__(BUDA)(0.70%) LINDSEY CONTRACTORS, INC.( 12.88%) ALLIED FENCE COMPANY (0.09%) DAKOTA UTILITY CONTRACTORS, INC. (0.01%) AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. (0.29%) HIGHWAY TECHNOLOGIES, INC. (1.23%) N-LINE TRAFFIC MAINTENANCE, L.P. (0.34%) CHATFIELD ELECTRIC (0.06%) ASSOCIATED DRILLING(0.00%) JAG TRUCKING INC (1.84%) 5A TRANSPORTATION, INC.(1.84%) MATOKA, INC. (0.04%) SOUTH TEXAS INDUSTRIAL COATINGS, L.L.C.(0.11%) FORTSON CONTRACTING, INC.(0.03%) AAA FENCE CO.(0.01%) BMP SPECIALIST, LLC(0.01%) AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., L.P. (0.56%) N-LINE TRAFFIC MAINTENANCE, L.P. (0.05%) D. I. J. CONSTRUCTION, INC.(0.86%) TEXAS TREE & LANDSCAPE, LTD. (0.12%) SOUTH TEXAS INDUSTRIAL COATINGS, L.L.C.(0.07%) ROADWAY SPECIALTIES, INC.(0.70%) SAN-ANN-CO., INC.(0.28%) ADAY & ASSOCIATES, LLC (2.72%) USA SWPPP INSPECTIONS, INC.(0.00%)
|
| Contract # |
03093001 |
|
Totals |
55780217.33 |
27740.16 |
53391109.46 |
96.3 |
|