AVERAGE LOW BID UNIT PRICE - MAINTENANCE - WACO DISTRICT

Last Update: Friday, April 17, 2015
ITEMS 500 2001 TO 556 2008
Items Items Bid Code Range
0104 - 0158
0315 - 0354
0401 - 0496
0500 - 0556
0618 - 0690
0712 - 0764
1122 - 1122
3005 - 3269
5369 - 5369
6005 - 6473
7206 - 7206
8094 - 8852
500 2001 - 556 2008
Item No Description Units March 31, 2015 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
500 2001 MOBILIZATION LS     9.000 36,122.77778 9
500 2007 MOBILIZATION (EMERGENCY) EA     56.000 786.10714 6
500 2010 MOBILIZATION (PER CALL OUT) EA     308.000 392.29714 9
500 6001 MOBILIZATION LS 1.000 90,500.00000 4.000 45,275.25000 4
502 2001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO     23.000 1,751.73913 8
502 2002 BARR, SIGNS & TRAF HANDLE (TY 1) EA     2.000 1,200.00000 1
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 7,500.00000 4.000 7,500.00000 2
529 2007 CONC CURB (DOWEL) LF     650.000 28.46154 2
529 2010 CONC CURB AND GUTTER (TY II) (REINF) LF     30.000 54.39000 1
531 2005 CURB RAMPS (TY 1) EA     2.000 1,658.97000 1
531 2006 CURB RAMPS (TY 2) EA     2.000 2,414.97000 1
531 2010 CURB RAMPS (TY 7) EA     2.000 1,874.97000 1
531 2015 CONC SIDEWALKS (4") SY     60.000 54.39000 1
540 2002 MTL W - BEAM GD FEN (STEEL POST) LF     500.000 23.00000 1
540 2011 MTL BEAM GD FEN TRANS (THRIE - BEAM) EA     20.000 1,000.00000 1
544 2001 GUARDRAIL END TREATMENT (INSTALL) EA     20.000 2,400.00000 1
556 2008 PIPE UNDERDRAINS (TY 8) (6") LF     4,229.000 35.00000 1