AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - WACO DISTRICT

Last Update: Friday, June 26, 2015
ITEMS 305 2002 TO 354 6119
Items Items Bid Code Range
0100 - 0193
0216 - 0275
0305 - 0354
0400 - 0497
0500 - 0560
0610 - 0688
0752 - 0772
1002 - 1122
2147 - 2147
3002 - 3271
4116 - 4116
5009 - 5946
6001 - 6834
8206 - 8999
305 2002 - 354 6119
Item No Description Units June 30, 2015 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
305 2002 SALV, HAUL & STKPL RCL APH PV (0 TO 2" SY 3,854.000 5.50000 3,854.000 5.50000 1
305 6021 SALV, HAUL & STKPL RCL APH PV (2 1 / 2") SY 61,701.000 1.50000 61,701.000 1.50000 1
305 6022 SALV, HAUL & STKPL RCL APH PV (4") SY     148,663.000 1.55000 1
310 2005 PRIME COAT (MC - 30 OR AE - P) GAL 14,300.000 4.29000 126,800.000 3.65949 11
310 6027 PRIME COAT (MC - 30 OR AE - P) GAL 68,838.000 3.85008 131,532.000 3.85847 4
316 2010 ASPH (CRS - 2) GAL 32,114.000 3.22000 316,215.000 2.56594 10
316 2209 AGGR (TY - L GR - 5 SAC - B) CY     167.000 60.00000 1
316 2258 AGGR (TY - PL GR - 5 SAC - B) CY     101.000 75.00000 1
316 2363 AGGR (TY - PD GR - 4 OR TY - PL GR - 4) (SAC - B) CY     7,611.400 92.16852 10
316 2378 AGGR (TY - D GR - 4 OR TY - L GR - 4) (SAC - B) CY 593.000 144.76000 14,145.000 67.58408 9
316 2616 ASPH (AC - 15P, AC - 20XP, AC10 - 2TR, AC - 12 - 5TR GAL     186,924.000 3.42009 9
316 2621 AGGR (TY D GR - 3 OR TY L GR - 3) (SAC B) CY     37.100 207.91105 2
316 2680 AGGR (TY - PD GR - 4 OR TY - PL GR - 4) CY     19,713.000 67.00000 1
316 2705 ASPH (TIER I) GAL     898,932.000 2.97000 1
316 2706 ASPH (TIER II) GAL     171,801.000 2.97000 1
316 2707 ASPH (TIER III) GAL     460,393.000 2.51000 1
316 2785 AGGR (TY - PL GR - 5) CY     861.000 75.00000 1
316 6022 ASPH (CRS - 2) GAL 191,903.000 2.41703 337,906.000 2.64869 4
316 6397 AGGR (TY - D GR - 4 OR TY - L GR - 4) CY 3,416.000 98.32459 5,949.000 100.66441 4
341 6008 D - GR HMA TY - B PG64 - 22 TON 23,749.000 71.28000 108,919.000 67.58608 3
341 6027 D - GR HMA TY - C SAC - B PG70 - 22 TON 58,452.000 65.00000 58,452.000 65.00000 1
341 6030 D - GR HMA TY - C SAC - B PG76 - 22 TON 11,300.000 77.67000 42,873.000 77.54481 2
341 6040 D - GR HMA TY - D PG64 - 22 TON 310.000 111.71000 310.000 111.71000 1
341 6043 D - GR HMA TY - D PG70 - 22 TON     25,894.000 78.45000 1
341 6062 D - GR HMA TY - D PG64 - 22 (LEVEL - UP) TON 33,593.000 65.00000 36,739.000 66.55444 3
351 2004 FLEXIBLE PAVEMENT STRUCTURE REPAIR (8") SY     75,081.000 37.42914 5
351 2005 FLEXIBLE PAVEMENT STRUCTURE REPAIR (9") SY     6,207.000 40.00000 1
351 6004 FLEXIBLE PAVEMENT STRUCTURE REPAIR (8") SY 2,000.000 40.00000 2,267.000 42.94442 2
354 2021 PLANE ASPH CONC PAV (0" TO 2") SY     41,241.000 .79178 2
354 2024 PLANE ASPH CONC PAV (2" TO 4") SY     921.000 10.00000 1
354 2026 PLANE ASPH CONC PAV (6" TO 8") SY     76,757.000 .74000 1
354 2041 PLANE ASPH CONC PAV (1.5") SY     623,196.000 1.00000 2
354 2045 PLANE ASPH CONC PAV (2") SY     150,813.000 1.04765 2
354 2051 PLANE ASPH CONC PAV (0" TO 1 1 / 2") SY     13,388.000 1.70000 1
354 2064 PLANE ASPH CONC PAV (2 1 / 2") SY     242,927.000 .65000 1
354 2114 PLAN & TEXT ASPH CONC PAV (0" TO 1 1 / 2" SY     2,808.000 3.00000 1
354 2174 PLANE ASPH CONC PAV (1.5" TO 5") SY     10,070.000 3.00000 2
354 6021 PLANE ASPH CONC PAV (0" TO 2") SY 4,327.000 3.37301 12,307.000 3.13114 3
354 6057 PLANE ASPH CONC PAV (4") SY     747.000 10.00000 1
354 6114 PLAN & TEXT ASPH CONC PAV (0" TO 1 1 / 2" SY     1,023.000 6.50000 1
354 6119 PLAN & TEXT ASPH CONC PAV (1.5") SY     2,445.000 4.85000 1