Monthly Local Let Maintenance Report For Tyler District As Of Jan 14, 2022 Page 6 Of 6
Last Update: Sunday, January 16, 2022
|
Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | ANDERSON |
Highway | US0079 |
From | PALESTINE MAINTENANCE SECTION |
To | ANDERSON COUNTY |
CSJ | 6390-00-001 |
Proj ID | MMC - 639000001 |
Work Type | HOT MIX |
|
| 0.010 | 210600.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 120 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
BIG CREEK CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 6390-00-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 11211001 |
| Totals | 210600.00 | 0.00 | 0.00 | 0.0 |
|