Monthly Local Let Maintenance Report For Tyler District As Of Apr 11, 2016 Page 5 Of 8

Last Update: Monday, April 11, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHENDERSON
Highway SH0031
From VARIOUS LOCATIONS IN_THE
To ATHENS AND PALESTINE SECTIONS
CSJ 6285-89-001
Proj ID RMC - 628589001
Work Type GUARDRAIL REPAIR
 
0.010 123362.00 0.00 90371.00 73.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 144
Percent Time Used 56
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6285-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06151001
Totals 123362.00 0.00 90371.00 73.2

CountyWOOD
Highway US0080
From VARIOUS LOCATIONS IN THE
To MINEOLA AND CANTON SECTIONS
CSJ 6285-90-001
Proj ID RMC - 628590001
Work Type GUARDRAIL REPAIR
 
0.010 107563.00 0.00 49923.00 46.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-10-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 143
Percent Time Used 56
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6285-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06151002
Totals 107563.00 0.00 49923.00 46.4

CountyGREGG
Highway US0259
From VARIOUS LOCATIONS IN THE
To LONGVIEW AND HENDERSON SECTIONS
CSJ 6285-91-001
Proj ID RMC - 628591001
Work Type GUARDRAIL REPAIR
 
0.010 107213.00 0.00 117595.00 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 147
Percent Time Used 57
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6285-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06151003
Totals 107213.00 0.00 117595.00 99.9

CountySMITH
Highway US0069
From VARIOUS LOCATIONS IN THE
To TYLER AND JACKSONVILLE SECTIONS
CSJ 6285-92-001
Proj ID RMC - 628592001
Work Type GUARDRAIL REPAIR
 
0.010 105963.00 0.00 142409.00 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 145
Percent Time Used 56
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6285-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06151004
Totals 105963.00 0.00 142409.00 99.9

CountySMITH
Highway SL0323
From SPECIAL CREWS OFFICE-FORMERLY N TYLER
To SPECIAL CREWS OFFICE
CSJ 6286-05-001
Proj ID SUP - 628605001
Work Type LAWN MAINTENANCE
 
0.001 15200.00 0.00 1275.00 8.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 213
Percent Time Used 29
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6286-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08151030
Totals 15200.00 0.00 1275.00 8.3

CountySMITH
Highway IH0020
From VAN ZANDT/KAUFMAN CL TO
To GREGG/HARRISON CL IH 20
CSJ 6286-06-001
Proj ID SUP - 628606001
Work Type LITTER REMOVAL ON IH 20
 
0.001 183894.56 0.00 44551.13 24.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 213
Percent Time Used 29
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6286-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08151031
Totals 183894.56 0.00 44551.13 24.2

CountyVAN ZANDT
Highway FM1255
From CANTON MAINTENANCE SECTION
To CANTON MAINTENANCE SECTION
CSJ 6286-07-001
Proj ID SUP - 628607001
Work Type LAWN MAINTENANCE
 
0.001 27600.00 0.00 1900.00 6.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 213
Percent Time Used 29
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6286-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08151032
Totals 27600.00 0.00 1900.00 6.8

CountyVAN ZANDT
Highway SH0064
From PICNIC AREA ON SH 64
To EAST OF CANTON
CSJ 6286-08-001
Proj ID SUP - 628608001
Work Type PICNIC AREA MAINTENANCE
 
0.001 25220.00 0.00 5385.00 21.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 213
Percent Time Used 29
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6286-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08151033
Totals 25220.00 0.00 5385.00 21.3

CountyVAN ZANDT
Highway SH0019
From CANTON MAINTENANCE SECTION
To VAN ZANDT COUNTY
CSJ 6286-09-001
Proj ID SUP - 628609001
Work Type LITTER PICK UP
 
0.001 146763.20 0.00 52137.21 35.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 213
Percent Time Used 29
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6286-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08151034
Totals 146763.20 0.00 52137.21 35.5

CountyHENDERSON
Highway US0175
From ATHENS MAINTENANCE SECTION
To VARIOUS LOCATIONS
CSJ 6286-10-001
Proj ID SUP - 628610001
Work Type PICNIC AREA MAINTENANCE
 
0.001 41786.00 0.00 9448.00 22.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 213
Percent Time Used 29
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6286-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08151035
Totals 41786.00 0.00 9448.00 22.6

CountyHENDERSON
Highway SH0019
From ATHENS MAINTENANCE_SECTION
To HENDERSON COUNTY
CSJ 6286-11-001
Proj ID SUP - 628611001
Work Type LITTER PICK - UP
 
0.001 138559.95 0.00 45181.79 32.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 213
Percent Time Used 29
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6286-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08151036
Totals 138559.95 0.00 45181.79 32.6

CountyGREGG
Highway US0259
From LONGVIEW MAINTENANCE SECTION
To GREGG COUNTY
CSJ 6286-12-001
Proj ID SUP - 628612001
Work Type LITTER PICK - UP
 
0.001 120414.10 0.00 33806.66 28.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 213
Percent Time Used 29
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6286-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08151037
Totals 120414.10 0.00 33806.66 28.0

CountyANDERSON
Highway SH0019
From PALESTINE MAINTENANCE OFFICE
To PALESTINE MAINTENANCE OFFICE
CSJ 6286-13-001
Proj ID SUP - 628613001
Work Type LAWN MAINTENANCE
 
0.010 32250.00 0.00 1875.00 5.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 213
Percent Time Used 29
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6286-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08151038
Totals 32250.00 0.00 1875.00 5.8

CountyANDERSON
Highway SL0256
From JCT SL 256
To & OLD ELKHART RD
CSJ 6286-14-001
Proj ID SUP - 628614001
Work Type LANDSCAPE ROW MTCE.
 
0.001 15390.00 0.00 1140.00 7.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 213
Percent Time Used 29
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6286-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08151039
Totals 15390.00 0.00 1140.00 7.4

CountySMITH
Highway SH0155
From SOUTH TYLER MTCE OFFICE
To SOUTH TYLER AREA OFFICE
CSJ 6286-15-001
Proj ID SUP - 628615001
Work Type LAWN MAINTENANCE
 
0.001 23800.00 0.00 1675.00 7.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 213
Percent Time Used 29
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6286-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08151040
Totals 23800.00 0.00 1675.00 7.0

CountyHENDERSON
Highway SL0007
From ATHENS MTCE OFFICE
To ATHENS AREA OFFICE
CSJ 6286-16-001
Proj ID SUP - 628616001
Work Type JANITORIAL MAINTENANCE
 
0.001 118864.00 0.00 37002.00 31.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 213
Percent Time Used 29
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6286-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08151041
Totals 118864.00 0.00 37002.00 31.1

CountyGREGG
Highway SL0281
From LONGVIEW AREA OFFICE
To LONGVIEW AREA OFFICE
CSJ 6286-17-001
Proj ID SUP - 628617001
Work Type JANITORIAL MAINTENANCE
 
0.001 55658.40 0.00 14457.70 25.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 213
Percent Time Used 29
Contractor(s)
TIBH INDUSTRIES, INC.
COMMUNITY HEALTHCORE
SUBCONTRACTOR(S) FOR CCSJ: 6286-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08151042
Totals 55658.40 0.00 14457.70 25.9

CountyRUSK
Highway US0259
From US 259 AND SH 79
To US 259 AND SH 322
CSJ 6286-18-001
Proj ID SUP - 628618001
Work Type LANDSCAPE MAINTENANCE
 
0.001 39600.00 0.00 3960.00 10.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 213
Percent Time Used 29
Contractor(s)
TIBH INDUSTRIES, INC.
COMMUNITY HEALTHCORE
SUBCONTRACTOR(S) FOR CCSJ: 6286-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08151043
Totals 39600.00 0.00 3960.00 10.0

CountyWOOD
Highway SL0564
From MINEOLA MTCE OFFICE
To MINEOLA AREA OFFICE
CSJ 6286-19-001
Proj ID SUP - 628619001
Work Type JANITORIAL MAINTENANCE
 
0.001 35884.90 0.00 9018.33 25.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 213
Percent Time Used 29
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6286-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08151044
Totals 35884.90 0.00 9018.33 25.1

CountyCHEROKEE
Highway SL0456
From JACKSONVILLE OFFICE
To JACKSONVILLE OFFICE
CSJ 6286-20-001
Proj ID SUP - 628620001
Work Type JANITORIAL MAINTENANCE
 
0.001 52047.36 0.00 13519.84 25.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 213
Percent Time Used 29
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6286-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08151045
Totals 52047.36 0.00 13519.84 25.9