Monthly Local Let Maintenance Report For Tyler District As Of Jun 10, 2015 Page 3 Of 5

Last Update: Wednesday, June 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyGREGG
Highway SL0281
From LONGVIEW MTCE. OFFICE
To GREGG CO.
CSJ 6272-97-001
Proj ID SUP - 627297001
Work Type LAWN MTCE.
 
0.010 37260.00 1230.00 9225.00 24.7
Work Order 08-14-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 273
Percent Time Used 37
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6272-97-001
ANDREWS DIVERSIFIED INDUSTRIES (100.00%)
Contract # 07141034
Totals 37260.00 1230.00 9225.00 24.7

CountySMITH
Highway IH0020
From IH 20 EAST & WEST DERRICK PARK
To SH 31 @ FM 2661
CSJ 6272-98-001
Proj ID SUP - 627298001
Work Type PICNIC AREA MTCE.
 
0.010 124980.00 5405.00 47999.00 38.4
Work Order 08-14-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 273
Percent Time Used 37
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6272-98-001
ANDREWS DIVERSIFIED INDUSTRIES (100.00%)
Contract # 07141035
Totals 124980.00 5405.00 47999.00 38.4

CountySMITH
Highway IH0020
From IH 20 @ US 69 &
To IH 20 @ US 271
CSJ 6272-99-001
Proj ID SUP - 627299001
Work Type TRAFFIC ISLAND LANDSCAPE MTCE.
 
0.010 22158.24 461.63 4154.67 18.7
Work Order 08-14-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 273
Percent Time Used 37
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6272-99-001
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT(100.00%)
Contract # 07141036
Totals 22158.24 461.63 4154.67 18.7

CountyWOOD
Highway US0080
From US 80(2), US 69, FM 2088
To SH 37(2)
CSJ 6273-00-001
Proj ID SUP - 627300001
Work Type PICNIC AREA MTCE.
 
0.010 122429.04 3908.99 33418.29 27.2
Work Order 08-14-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 273
Percent Time Used 37
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6273-00-001
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT(100.00%)
Contract # 07141037
Totals 122429.04 3908.99 33418.29 27.2

CountyWOOD
Highway SL0564
From MINEOLA AO & MTCE. OFFICE
To SL 564, WOOD CO.
CSJ 6273-01-001
Proj ID SUP - 627301001
Work Type LAWN MTCE.
 
0.010 31945.70 364.82 6022.28 18.8
Work Order 08-14-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 273
Percent Time Used 37
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6273-01-001
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT(100.00%)
Contract # 07141038
Totals 31945.70 364.82 6022.28 18.8

CountySMITH
Highway SH0155
From TYLER AO & MTCE. OFFICE
To SH 155 S IN NOONDAY
CSJ 6273-02-001
Proj ID SUP - 627302001
Work Type JANITORIAL MTCE.
 
0.001 42749.92 1411.27 16031.22 37.5
Work Order 08-15-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 273
Percent Time Used 37
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-02-001
WORLD TECHNICAL SERVICES, INC. (100.00%)
Contract # 07141039
Totals 42749.92 1411.27 16031.22 37.5

CountyANDERSON
Highway SH0019
From PALESTINE MTCE. OFFICE
To ANDERSON CO.
CSJ 6273-03-001
Proj ID SUP - 627303001
Work Type JANITORIAL MTCE.
 
0.010 24599.52 1786.93 9681.99 39.3
Work Order 08-31-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 273
Percent Time Used 37
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-03-001
WORLD TECHNICAL SERVICES, INC. (100.00%)
Contract # 07141040
Totals 24599.52 1786.93 9681.99 39.3

CountyCHEROKEE
Highway LP0456
From JACKSONVILLE MTCE. OFFICE
To LP 456
CSJ 6273-04-001
Proj ID SUP - 627304001
Work Type LAWN MTCE.
 
0.010 18465.00 612.50 2677.50 14.5
Work Order 08-15-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 273
Percent Time Used 37
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-04-001
GATEWAY COMMUNITY PARTNERS, INC. (100.00%)
Contract # 07141041
Totals 18465.00 612.50 2677.50 14.5

CountyCHEROKEE
Highway US0069
From RUSK MTCE. OFFICE
To US 69
CSJ 6273-05-001
Proj ID SUP - 627305001
Work Type LAWN MTCE.
 
0.010 14740.00 680.00 3150.00 21.3
Work Order 08-15-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 273
Percent Time Used 37
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-05-001
GATEWAY COMMUNITY PARTNERS, INC. (100.00%)
Contract # 07141042
Totals 14740.00 680.00 3150.00 21.3

CountyCHEROKEE
Highway US0069
From JVILLE/RUSK MTCE SECTIONS
To CHEROKEE CO.
CSJ 6273-06-001
Proj ID SUP - 627306001
Work Type LANDSCAPE ISLAND MTCE.
 
0.010 22803.36 950.14 4275.63 18.7
Work Order 08-15-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 273
Percent Time Used 37
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-06-001
GATEWAY COMMUNITY PARTNERS, INC. (100.00%)
Contract # 07141043
Totals 22803.36 950.14 4275.63 18.7

CountyRUSK
Highway SH0064
From SH 64 W, US 259 N, US 259 S, SH 43 N
To HENDERSON MTCE. SECTION
CSJ 6273-07-001
Proj ID SUP - 627307001
Work Type PICNIC AREA MTCE.
 
0.010 55264.00 1740.00 15027.00 27.1
Work Order 08-15-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 273
Percent Time Used 37
Contractor(s)
TIBH INDUSTRIES, INC.
COMMUNITY HEALTHCORE
SUBCONTRACTOR(S) FOR CCSJ: 6273-07-001
COMMUNITY REHABILITATION CENTER TRANSPORTATION, LLC(100.00%)
Contract # 07141044
Totals 55264.00 1740.00 15027.00 27.1

CountyRUSK
Highway FM0225
From HENDERSON MTCE SECTION OFFICE
To FM 225 RUSK CO.
CSJ 6273-08-001
Proj ID SUP - 627308001
Work Type LAWN MTCE.
 
0.010 12192.36 464.03 2584.06 21.1
Work Order 08-15-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 273
Percent Time Used 37
Contractor(s)
TIBH INDUSTRIES, INC.
COMMUNITY HEALTHCORE
SUBCONTRACTOR(S) FOR CCSJ: 6273-08-001
COMMUNITY REHABILITATION CENTER TRANSPORTATION, LLC(100.00%)
Contract # 07141045
Totals 12192.36 464.03 2584.06 21.1

CountyRUSK
Highway SH0064
From HENDERSON MTCE. SECTION
To RUSK CO.
CSJ 6273-09-001
Proj ID SUP - 627309001
Work Type LITTER PICK UP
 
0.010 242191.70 0.00 82587.89 34.1
Work Order 08-26-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 273
Percent Time Used 37
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-09-001
RUCON, INC.(0.00%)
Contract # 07141046
Totals 242191.70 0.00 82587.89 34.1

CountySMITH
Highway SL0323
From SPECIAL JOBS MTCE. OFFICE
To N SL 323
CSJ 6276-06-001
Proj ID SUP - 627606001
Work Type JANITORIAL
 
0.010 17811.00 1068.25 6387.50 35.8
Work Order 07-31-14
Work Began 08-01-14
Work Completed  
Time Computed 08-01-14
Contract Working Days 761
Addl Days Granted 0
Working Days Charged 304
Percent Time Used 39
Contractor(s)
TIBH INDUSTRIES, INC.
COMMUNITY HEALTHCORE
SUBCONTRACTOR(S) FOR CCSJ: 6276-06-001
COMMUNITY HEALTHCORE (100.00%)
Contract # 07141030
Totals 17811.00 1068.25 6387.50 35.8

CountySMITH
Highway SH0031
From TYLER DISTRICT HEADQUARTERS COMPLEX
To FRONT ST
CSJ 6276-07-001
Proj ID SUP - 627607001
Work Type JANITORIAL
 
0.010 265226.60 0.00 85134.56 32.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 08-01-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 761
Addl Days Granted 0
Working Days Charged 304
Percent Time Used 39
Contractor(s)
TIBH INDUSTRIES, INC.
COMMUNITY HEALTHCORE
SUBCONTRACTOR(S) FOR CCSJ: 6276-07-001
COMMUNITY HEALTHCORE (100.00%)
Contract # 07141031
Totals 265226.60 0.00 85134.56 32.0

CountySMITH
Highway SH0031
From VARIOUS ROADWAYS IN THE
To TYLER MAINTENANCE SECTION
CSJ 6278-16-001
Proj ID RMC - 627816001
Work Type ROW MOWING
 
0.001 257840.79 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 53
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6278-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02151001
Totals 257840.79 0.00 0.00 0.0

CountyWOOD
Highway US0069
From VARIOUS ROADWAY IN THE
To MINEOLA MAINTENANCE
CSJ 6278-17-001
Proj ID RMC - 627817001
Work Type ROW MOWING
 
0.001 236416.70 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 53
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HX FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6278-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02151002
Totals 236416.70 0.00 0.00 0.0

CountyCHEROKEE
Highway US0084
From VARIOUS ROADWAYS IN THE
To JACKSONVILLE MAINTENANCE SECTION
CSJ 6278-18-001
Proj ID RMC - 627818001
Work Type ROW MOWING
 
0.001 215132.80 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 49
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SERVIN MOWING
SUBCONTRACTOR(S) FOR CCSJ: 6278-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02151003
Totals 215132.80 0.00 0.00 0.0

CountyANDERSON
Highway US0287
From VARIOUS ROADWAYS IN THE
To PALESTINE MAINTENANCE SECTION
CSJ 6278-19-001
Proj ID RMC - 627819001
Work Type ROW MOWING
 
0.001 235072.32 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 49
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LAWRENCE W. SIMS
SUBCONTRACTOR(S) FOR CCSJ: 6278-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02151004
Totals 235072.32 0.00 0.00 0.0

CountyGREGG
Highway US0080
From VARIOUS LOCATION IN THE
To LONGVIEW MAINTENANCE SECTION
CSJ 6278-20-001
Proj ID RMC - 627820001
Work Type ROW MOWING
 
0.001 86822.68 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 31
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SERVIN MOWING
SUBCONTRACTOR(S) FOR CCSJ: 6278-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02151005
Totals 86822.68 0.00 0.00 0.0