Monthly Local Let Maintenance Report For Tyler District As Of Dec 9, 2016 Page 3 Of 4

Last Update: Friday, December 9, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyANDERSON
Highway SH0019
From VARIOUS ROADWAYS IN
To ANDERSON COUNTY
CSJ 6299-59-001
Proj ID RMC - 629959001
Work Type TREE REMOVAL
 
0.001 205450.00 0.00 114645.00 55.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-12-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 56
Percent Time Used 21
Contractor(s)
PLANT FUEL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6299-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04161001
Totals 205450.00 0.00 114645.00 55.8

CountyHENDERSON
Highway SH0019
From VARIOUS ROADWAYS IN
To THE TYLER DISTRICT
CSJ 6300-22-001
Proj ID RMC - 630022001
Work Type PAINT
 
0.001 239245.00 0.00 150081.01 62.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-22-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 51
Percent Time Used 20
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6300-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04161003
Totals 239245.00 0.00 150081.01 62.7

CountySMITH
Highway SL0323
From SL 323 IN
To SMITH COUNTY
CSJ 6303-40-001
Proj ID RMC - 630340001
Work Type SLOPE FAILURE
 
0.100 182290.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6303-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08161001
Totals 182290.00 0.00 0.00 0.0

CountyHENDERSON
Highway SH0031
From ATHENS MTCE. SECTION
To HENDERSON CO.
CSJ 6303-70-001
Proj ID SUP - 630370001
Work Type LANDSCAPE ROW MTCE.
 
0.010 14898.00 0.00 3438.00 23.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 91
Percent Time Used 12
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6303-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07161030
Totals 14898.00 0.00 3438.00 23.0

CountyHENDERSON
Highway SH0031
From ATHENS MTCE. OFFICE
To HENDERSON CO
CSJ 6303-71-001
Proj ID SUP - 630371001
Work Type LAWN MTCE.
 
0.010 16782.00 0.00 2029.00 12.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 91
Percent Time Used 12
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6303-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07161031
Totals 16782.00 0.00 2029.00 12.0

CountyGREGG
Highway SL0281
From LONGVIEW MTCE. OFFICE
To GREGG CO
CSJ 6303-72-001
Proj ID SUP - 630372001
Work Type LAWN MTCE
 
0.010 31110.00 0.00 3690.00 11.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 91
Percent Time Used 12
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6303-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07161032
Totals 31110.00 0.00 3690.00 11.8

CountySMITH
Highway IH0020
From IH 20 EAST & WEST DERRICK PARK
To SH 31 @ FM 2661
CSJ 6303-73-001
Proj ID SUP - 630373001
Work Type PICNIC AREA MTCE.
 
0.010 124980.00 0.00 15869.00 12.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 91
Percent Time Used 12
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6303-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07161033
Totals 124980.00 0.00 15869.00 12.6

CountySMITH
Highway IH0020
From IH 20 @ US 69 &
To IH 20 @ US 271
CSJ 6303-74-001
Proj ID SUP - 630374001
Work Type TRAFFIC ISLAND LANDSCAPE MTCE
 
0.010 29450.00 0.00 3875.00 13.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 91
Percent Time Used 12
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07161034
Totals 29450.00 0.00 3875.00 13.1

CountyWOOD
Highway US0080
From US 80(2), US 69, FM 2088
To SH 37(2)
CSJ 6303-75-001
Proj ID SUP - 630375001
Work Type PICNIC AREA MTCE
 
0.010 122429.04 0.00 17670.93 14.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 91
Percent Time Used 12
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6303-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07161035
Totals 122429.04 0.00 17670.93 14.4

CountyWOOD
Highway SL0564
From MINEOLA AO & MTCE OFFICE
To SL 564, WOOD CO
CSJ 6303-76-001
Proj ID SUP - 630376001
Work Type LAWN MTCE
 
0.010 26367.00 0.00 3968.16 15.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 91
Percent Time Used 12
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6303-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07161036
Totals 26367.00 0.00 3968.16 15.0

CountySMITH
Highway SH0155
From TYLER AO & MTCE OFFICE
To SH 155 S IN NOONDAY
CSJ 6303-78-001
Proj ID SUP - 630378001
Work Type JANITORIAL MTCE
 
0.001 43605.04 0.00 5450.63 12.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 91
Percent Time Used 12
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07161037
Totals 43605.04 0.00 5450.63 12.5

CountyANDERSON
Highway SH0019
From PALESTINE MTCE OFFICE
To ANDERSON CO
CSJ 6303-79-001
Proj ID SUP - 630379001
Work Type JANITORIAL MTCE
 
0.010 22127.04 0.00 2299.77 10.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 91
Percent Time Used 12
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07161038
Totals 22127.04 0.00 2299.77 10.3

CountyCHEROKEE
Highway SL0456
From JACKSONVILLE MTCE OFFICE
To SL 456
CSJ 6303-80-001
Proj ID SUP - 630380001
Work Type LAWN MTCE
 
0.010 12060.00 0.00 1162.50 9.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 91
Percent Time Used 12
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07161039
Totals 12060.00 0.00 1162.50 9.6

CountyCHEROKEE
Highway US0069
From RUSK MTCE OFFICE
To US 69
CSJ 6303-81-001
Proj ID SUP - 630381001
Work Type LAWN MTCE
 
0.010 14160.00 0.00 1310.00 9.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 91
Percent Time Used 12
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07161040
Totals 14160.00 0.00 1310.00 9.2

CountyCHEROKEE
Highway US0069
From JVILLE/RUSK MTCE SECTIONS
To CHEROKEE CO
CSJ 6303-82-001
Proj ID SUP - 630382001
Work Type LANDSCAPE ISLAND MTCE
 
0.010 18052.66 0.00 1900.28 10.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 91
Percent Time Used 12
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07161041
Totals 18052.66 0.00 1900.28 10.5

CountyRUSK
Highway SH0064
From HENDERSON MTCE. SECTION
To RUSK CO.
CSJ 6303-86-001
Proj ID SUP - 630386001
Work Type LITTER PICK UP
 
0.001 373499.73 0.00 26336.18 7.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-01-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 1,095
Addl Days Granted 0
Working Days Charged 91
Percent Time Used 8
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07161045
Totals 373499.73 0.00 26336.18 7.0

CountyVAN ZANDT
Highway US0080
From US 80 NEAR THE UNION
To PACIFIC RAILROAD
CSJ 6305-75-001
Proj ID RMC - 630575001
Work Type REPAIR OF RETAINING WALL
 
0.001 65000.00 0.00 46961.67 72.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 10-31-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 31
Addl Days Granted 10
Working Days Charged 16
Percent Time Used 39
Contractor(s)
RED BARON BUILDING COMPANY, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6305-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09161001
Totals 65000.00 0.00 46961.67 72.2

CountyVAN ZANDT
Highway SH0064
From VARIOUS LOCATIONS IN
To VAN ZANDT COUNTY
CSJ 6307-33-001
Proj ID RMC - 630733001
Work Type TREE REMOVAL
 
0.001 209992.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09161002
Totals 209992.00 0.00 0.00 0.0

CountyCHEROKEE
Highway US0079
From VARIOUS ROADWAYS IN
To CHEROKEE COUNTY
CSJ 6307-34-001
Proj ID RMC - 630734001
Work Type TREE REMOVAL
 
0.001 215004.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SG COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6307-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09161003
Totals 215004.00 0.00 0.00 0.0

CountyANDERSON
Highway FM0315
From VARIOUS ROADWAYS
To IN ANDERSON COUNTY
CSJ 6307-35-001
Proj ID RMC - 630735001
Work Type TREE TRIMMING
 
73.260 138031.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 74
Addl Days Granted 0
Working Days Charged 1
Percent Time Used 1
Contractor(s)
TERRY ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6307-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09161004
Totals 138031.00 0.00 0.00 0.0