Monthly Local Let Maintenance Report For Tyler District As Of Apr 12, 2024 Page 2 Of 4

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySMITH
HighwaySH0064
FromVARIOUS LOCATIONS IN
ToTHE TYLER DISTRICT
CSJ6420-87-001
Proj IDRMC - 642087001
Work TypeILLUMINATION MAINTENANCE
 
0.010336850.00122540.0036.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-12-23
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged383
Percent Time Used52
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6420-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11221001
Totals336850.00950.00122540.0036.3

CountySMITH
HighwaySL0323
FromVARIOUS BRIDGES IN
ToTHE TYLER DISTRICT
CSJ6420-97-001
Proj IDBPM - 642097001
Work TypeBRIDGE RAIL REPAIR
 
0.01099114.08143019.50100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-12-23
Work Completed01-30-24
Time Computed00-00-00
Contract Working Days78
Addl Days Granted25
Working Days Charged76
Percent Time Used73
Contractor(s)
RED BARON BUILDING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6420-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06231001
Totals99114.0845925.00143019.50100.0

CountyWOOD
HighwayUS0080
FromMINEOLA MAINTENANCE SECTION
ToWOOD COUNTY
CSJ6421-96-001
Proj IDSUP - 642196001
Work TypePICNIC AREA MAINTENANCE
 
0.010131265.4485857.9965.4
Work Order09-01-22
Work Began09-01-22
Work Completed
Time Computed09-01-22
Contract Working Days730
Addl Days Granted0
Working Days Charged576
Percent Time Used78
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6421-96-001
RUCON, INC. (0.00)
Contract #08221044
Totals131265.4410378.3085857.9965.4

CountyGREGG
HighwayUS0259
FromVARIOUS ROADWAYS IN
ToGREGG COUNTY
CSJ6422-28-001
Proj IDRMC - 642228001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010218891.14104892.2947.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days62
Addl Days Granted0
Working Days Charged34
Percent Time Used54
Contractor(s)
DOUBLE S TRACTOR SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6422-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02231003
Totals218891.140.00104892.2947.9

CountyVAN ZANDT
HighwayUS0080
FromVARIOUS LOCATIONS WITHIN
ToVAN ZANDT COUNTY
CSJ6426-22-001
Proj IDMMC - 642622001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010199488.00877600.1699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-13-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged411
Percent Time Used56
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6426-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12221004
Totals199488.000.00877600.1699.9

CountyHENDERSON
HighwayUS0175
FromHENDERSON COUNTY
ToANDERSON COUNTY
CSJ6428-04-001
Proj IDMMC - 642804001
Work TypeEMULSION
 
0.010188880.0079766.4942.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-01-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged366
Percent Time Used50
Contractor(s)
WRIGHT ASPHALT PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 6428-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12221003
Totals188880.00420.9079766.4942.2

CountyRUSK
HighwayUS0259
FromFLEXBASE MATERIAL FOR TYLER DISTRICT
ToRUSK, SMITH AND CHEROKEE COUNTIES
CSJ6430-95-001
Proj IDMMC - 643095001
Work TypeFLEXIBLE BASE
 
0.010217500.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged303
Percent Time Used83
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6430-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02231004
Totals217500.000.000.000.0

CountyWOOD
HighwayUS0080
FromATHENS PALESTINE MINEOLA CANTON MOS
ToHENDERSON ANDERSON WOOD VZ COUNTIES
CSJ6431-26-001
Proj IDMMC - 643126001
Work TypeFLEXIBLE BASE
 
0.010238000.00128984.7254.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-01-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6431-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02231005
Totals238000.0022218.70128984.7254.1

CountyHENDERSON
HighwayUS0175
FromHENDERSON COUNTY
ToANDERSON COUNTY
CSJ6431-98-001
Proj IDMMC - 643198001
Work TypeASPHALT
 
0.010227700.00219410.2196.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-01-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged334
Percent Time Used91
Contractor(s)
MARTIN RESOURCE MANAGEMENT CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6431-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02231001
Totals227700.000.00219410.2196.3

CountyGREGG
HighwayUS0080
FromLONGVIEW & HENDERSON MO
ToGREGG & RUSK COUNTIES
CSJ6432-56-001
Proj IDMMC - 643256001
Work TypeASPHALT
 
0.010229800.00213987.40100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-03-23
Work Completed04-09-24
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged362
Percent Time Used99
Contractor(s)
MARTIN RESOURCE MANAGEMENT CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6432-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02231006
Totals229800.000.00213987.40100.0

CountyWOOD
HighwayUS0080
FromMINEOLA & CANTON MTCE SECTIONS
ToWOOD & VAN ZANDT COUNTIES
CSJ6432-60-001
Proj IDMMC - 643260001
Work TypeASPHALT
 
0.010231300.00277089.7299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-06-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged359
Percent Time Used98
Contractor(s)
MARTIN RESOURCE MANAGEMENT CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6432-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02231007
Totals231300.000.00277089.7299.9

CountyVAN ZANDT
HighwayUS0080
FromCANTON MAINTENANCE SECTION
ToVAN ZANDT COUNTY
CSJ6439-47-001
Proj IDRMC - 643947001
Work TypeTREE REMOVAL
 
0.010229135.53275643.5199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-05-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged269
Percent Time Used73
Contractor(s)
ALLIES LAND CLEARING
SUBCONTRACTOR(S) FOR CCSJ: 6439-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05231001
Totals229135.5389361.17275643.5199.9

CountySMITH
HighwaySL0323
FromSPECIAL CREWS OFFICE
ToSMITH COUNTY
CSJ6440-61-001
Proj IDSUP - 644061001
Work TypeSTATE USE CONTRACT
 
0.01012200.001350.0011.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged181
Percent Time Used24
Contractor(s)
WORKQUEST
ANDREWS CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6440-61-001
ANDREWS CENTER (100.00)
Contract #08231020
Totals12200.00225.001350.0011.0

CountyGREGG
HighwayIH0020
FromIH 20
ToIH 20
CSJ6440-63-001
Proj IDSUP - 644063001
Work TypeLITTER REMOVAL
 
0.010178164.9241331.2323.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged211
Percent Time Used28
Contractor(s)
WORKQUEST
ANDREWS CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6440-63-001
ANDREWS DIVERSIFIED INDUSTRIES (100.00)
Contract #08231025
Totals178164.9228454.3541331.2323.1

CountyVAN ZANDT
HighwayFM1255
FromCANTON MAINTENANCE OFFICE
ToVAN ZANDT COUNTY
CSJ6440-65-001
Proj IDSUP - 644065001
Work TypeSTATE USE CONTRACT
 
0.01015800.003325.0021.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged211
Percent Time Used28
Contractor(s)
WORKQUEST
ANDREWS CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6440-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08231008
Totals15800.00950.003325.0021.0

CountyVAN ZANDT
HighwayFM1255
FromVARIOUS LOCATIONS IN VAN ZANDT COUNTY
ToVARIOUS LOCATIONS IN VAN ZANDT COUNTY
CSJ6440-69-001
Proj IDSUP - 644069001
Work TypeLITTER REMOVAL
 
0.010139637.1231126.9822.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged211
Percent Time Used28
Contractor(s)
WORKQUEST
ANDREWS CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6440-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08231024
Totals139637.125202.4231126.9822.2

CountyHENDERSON
HighwayUS0175
FromATHENS MAINTENANCE SECTION
ToHENDERSON COUNTY
CSJ6440-71-001
Proj IDSUP - 644071001
Work TypePICNIC AREA MAINTENANCE
 
0.01045816.008363.0018.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged211
Percent Time Used28
Contractor(s)
WORKQUEST
ANDREWS CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6440-71-001
ANDREWS CENTER (100.00)
Contract #08231018
Totals45816.001084.008363.0018.2

CountyHENDERSON
HighwaySH0019
FromATHENS MAINTENANCE SECTION
ToVARIOUS LOCATION IN HENDERSON COUNTY
CSJ6440-73-001
Proj IDSUP - 644073001
Work TypeLITTER REMOVAL
 
0.0106857.3244279.8899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged210
Percent Time Used28
Contractor(s)
WORKQUEST
ANDREWS CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6440-73-001
ANDREWS CENTER (1867.19)
Contract #08231023
Totals6857.324777.2844279.8899.9

CountyGREGG
HighwayUS0259
FromLONGVIEW MAINTENANCE SECTION
ToVARIOUS LOCATIONS IN GREGG COUNTY
CSJ6440-75-001
Proj IDSUP - 644075001
Work TypeLITTER REMOVAL
 
0.010108762.6034027.4831.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged211
Percent Time Used28
Contractor(s)
WORKQUEST
ANDREWS CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6440-75-001
ANDREWS DIVERSIFIED INDUSTRIES (100.00)
Contract #08231026
Totals108762.606770.0934027.4831.2

CountyANDERSON
HighwaySH0019
FromPALESTINE MAINTENANCE OFFICE
ToANDERSON COUNTY
CSJ6440-77-001
Proj IDSUP - 644077001
Work TypeSTATE USE CONTRACT
 
0.01014400.001250.008.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged211
Percent Time Used28
Contractor(s)
WORKQUEST
ANDREWS CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6440-77-001
ANDREWS DIVERSIFIED INDUSTRIES (6.25)
ANDREWS CENTER (93.75)
Contract #08231017
Totals14400.00200.001250.008.6

page 1 | page 2 | page 3 | page 4