Monthly Local Let Maintenance Report For Tyler District As Of Mar 13, 2017 Page 2 Of 4

Last Update: Monday, March 13, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCHEROKEE
HighwayUS0069
FromVARIOUS PARKS IN THE JACKSONVILLE &
ToRUSK MAINTENANCE SECTIONS
CSJ6286-21-001
Proj IDSUP - 628621001
Work TypePICNIC AREA MAINTENANCE
 
0.01082953.1252039.8462.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-15
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged547
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6286-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08151046
Totals82953.120.0052039.8462.7

CountyCHEROKEE
HighwayUS0069
FromJACKSONVILLE/RUSK MAINTENANCE SECTION
ToCHEROKEE COUNTY
CSJ6286-22-001
Proj IDSUP - 628622001
Work TypeLITTER PICK-UP
 
0.001288378.50222949.5977.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-15
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged547
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6286-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08151047
Totals288378.500.00222949.5977.3

CountySMITH
HighwayUS0069
FromTYLER MAINTENACE SECTION
ToSMITH COUNTY
CSJ6286-23-001
Proj IDSUP - 628623001
Work TypeLITTER PICK-UP
 
0.001366042.98283433.1577.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-15
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged547
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6286-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08151048
Totals366042.980.00283433.1577.4

CountyANDERSON
HighwayUS0084
FromPALESTINE MAINTENANCE SECTION
ToANDERSON COUNTY
CSJ6286-24-001
Proj IDSUP - 628624001
Work TypeLITTER PICK-UP
 
0.001148058.79129359.1487.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-15
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged547
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6286-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08151049
Totals148058.790.00129359.1487.3

CountyWOOD
HighwayUS0069
FromMINEOLA MAINTENANCE SECTION
ToWOOD COUNTY
CSJ6286-25-001
Proj IDSUP - 628625001
Work TypeLITTER PICK UP
 
0.001136055.0889822.0166.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-15
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged547
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6286-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08151050
Totals136055.080.0089822.0166.0

CountySMITH
HighwayFM0757
FromFM 757 AND SL 323
ToIN SMITH COUNTY
CSJ6288-59-001
Proj IDRMC - 628859001
Work TypeCULVERT REPAIR
 
0.001174696.0053542.5053.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-12-16
Work Completed
Time Computed00-00-00
Contract Working Days34
Addl Days Granted0
Working Days Charged102
Percent Time Used300
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6288-59-001
NORTH TEXAS MAINTENANCE, INC. (100.00)
Contract #01161002
Totals174696.000.0053542.5053.6

CountyHENDERSON
HighwaySH0031
FromVARIOUS ROADWAYS IN THE
ToATHENS MAINTENANCE SECTION
CSJ6288-60-001
Proj IDRMC - 628860001
Work TypeTREE REMOVAL
 
0.001172950.00171238.0099.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-15
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted255
Working Days Charged312
Percent Time Used61
Contractor(s)
PATTERSON'S COMPLETE TREE SERVICE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6288-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09151005
Totals172950.000.00171238.0099.0

CountyRUSK
HighwayUS0079
FromVARIOUS ROADWAYS IN THE
ToHENDERSON MAINTENANCE SECTION
CSJ6288-62-001
Proj IDRMC - 628862001
Work TypeTREE REMOVAL
 
0.001213375.00230085.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-26-15
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted255
Working Days Charged339
Percent Time Used66
Contractor(s)
PATTERSON'S COMPLETE TREE SERVICE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6288-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09151002
Totals213375.000.00230085.0099.9

CountyRUSK
HighwayUS0079
FromVARIOUS ROADWAYS IN
ToRUSK AND CHEROKEE COUNTIES
CSJ6290-48-001
Proj IDEMC - 629048001
Work TypeEMERGENCY DEBRIS & TREE REMOVAL
 
0.010435655.003070764.75100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-26-15
Work Completed08-11-15
Time Computed00-00-00
Contract Working Days52
Addl Days Granted0
Working Days Charged33
Percent Time Used63
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6290-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06151044
Totals435655.000.003070764.75100.0

CountySMITH
HighwayFM2767
FromVARIOUS ROADWAYS IN THE
ToSMITH COUNTY
CSJ6294-77-001
Proj IDRMC - 629477001
Work TypeTREE TRIMMING & BRUSH REMOVAL
 
97.380126417.3414407.8011.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-19-17
Work Completed
Time Computed00-00-00
Contract Working Days98
Addl Days Granted0
Working Days Charged32
Percent Time Used32
Contractor(s)
DRC EMERGENCY SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6294-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12151001
Totals126417.340.0014407.8011.3

CountyGREGG
HighwaySH0031
FromVARIOUS ROADWAYS IN
ToGREGG COUNTY
CSJ6294-86-001
Proj IDRMC - 629486001
Work TypeTREE REMOVAL
 
0.001159225.00148590.0093.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-16-16
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted0
Working Days Charged203
Percent Time Used79
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6294-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11151001
Totals159225.000.00148590.0093.3

CountySMITH
HighwaySH0031
FromTYLER DISTRICT HEADQUARTERS COMPLEX
ToFRONT ST.
CSJ6296-27-001
Proj IDSUP - 629627001
Work TypeJANITORIAL
 
0.010248874.20158895.8663.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-15-15
Work Completed
Time Computed00-00-00
Contract Working Days685
Addl Days Granted0
Working Days Charged503
Percent Time Used73
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6296-27-001
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT (82.99)
Contract #10151030
Totals248874.200.00158895.8663.8

CountyHENDERSON
HighwaySH0031
FromVARIOUS ROADWAYS IN
ToTHE TYLER DISTRICT
CSJ6299-18-001
Proj IDRMC - 629918001
Work TypeRAISED PAVEMENT MARKERS
 
0.001259388.00452274.2099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-08-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged175
Percent Time Used47
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6299-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161001
Totals259388.000.00452274.2099.9

CountyHENDERSON
HighwaySH0031
FromVARIOUS LOCATIONS
ToIN THE TYLER DISTRICT
CSJ6299-58-001
Proj IDRMC - 629958001
Work TypeSHORT LINE THERMO
 
0.001288607.50105943.0036.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-13-16
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted0
Working Days Charged169
Percent Time Used66
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6299-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05161002
Totals288607.500.00105943.0036.7

CountyANDERSON
HighwaySH0019
FromVARIOUS ROADWAYS IN
ToANDERSON COUNTY
CSJ6299-59-001
Proj IDRMC - 629959001
Work TypeTREE REMOVAL
 
0.001205450.00177035.0086.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-12-16
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted0
Working Days Charged123
Percent Time Used48
Contractor(s)
PLANT FUEL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6299-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04161001
Totals205450.000.00177035.0086.1

CountyHENDERSON
HighwaySH0019
FromVARIOUS ROADWAYS IN
ToTHE TYLER DISTRICT
CSJ6300-22-001
Proj IDRMC - 630022001
Work TypePAINT
 
0.001239245.00255196.3299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-22-16
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted0
Working Days Charged115
Percent Time Used45
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6300-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04161003
Totals239245.000.00255196.3299.9

CountyVAN ZANDT
HighwayIH0020
FromIH-20 VARIOUS LOCATIONS
ToIN VAN ZANDT COUNTY
CSJ6301-83-001
Proj IDBPM - 630183001
Work TypeBRIDGE PREVENTIVE MAINTENANCE
 
0.001171979.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days82
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RED BARON BUILDING COMPANY, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6301-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161011
Totals171979.000.000.000.0

CountyVAN ZANDT
HighwaySH0110
FromVARIOUS LOCATIONS CANTON MTCE.
ToIN VAN ZANDT COUNTY
CSJ6301-84-001
Proj IDBPM - 630184001
Work TypeBRIDGE PREVENTIVE MAINTENANCE
 
0.001223998.9173021.6532.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days82
Addl Days Granted0
Working Days Charged10
Percent Time Used12
Contractor(s)
RED BARON BUILDING COMPANY, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6301-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161012
Totals223998.910.0073021.6532.5

CountyRUSK
HighwayFM2276
FromVARIOUS LOCATIONS IN HENDERSON MTCE.
ToIN RUSK COUNTY
CSJ6301-85-001
Proj IDBPM - 630185001
Work TypeBRIDGE PREVENTIVE MAINTENANCE
 
0.001212350.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days82
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
IIPL USA LLC
SUBCONTRACTOR(S) FOR CCSJ: 6301-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161013
Totals212350.000.000.000.0

CountySMITH
HighwaySL0323
FromSL 323 IN
ToSMITH COUNTY
CSJ6303-40-001
Proj IDRMC - 630340001
Work TypeSLOPE FAILURE
 
0.100182290.0072428.0639.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-05-16
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged16
Percent Time Used40
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6303-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08161001
Totals182290.000.0072428.0639.7

page 1 | page 2 | page 3 | page 4