Monthly Local Let Maintenance Report For Tyler District As Of Sep 21, 2017 Page 1 Of 4

Last Update: Friday, September 22, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHENDERSON
HighwayUS0175
FromVARIOUS ROADWAYS IN THE
ToATHENS MAINTENANCE SECTION
CSJ6272-05-001
Proj IDRMC - 627205001
Work TypePAINT
 
0.01023318.75379608.72100.0
CountyVAN ZANDT
HighwaySH0019
FromVARIOUS ROADWAYS IN
ToTHE CANTON MAINTENANCE SECTION
CSJ6272-05-002
Proj IDRMC - 627205002
Work TypePAINT
 
0.01023318.7559964.01100.0
CountyRUSK
HighwayUS0259
FromVARIOUS ROADWAYS IN THE
ToHENDERSON MAINTENANCE SECTIONN
CSJ6272-05-003
Proj IDRMC - 627205003
Work TypePAINT
 
0.01023318.7560837.79100.0
CountyCHEROKEE
HighwayUS0079
FromVARIOUS ROADWAYS IN THE
ToJACKSONVILLE MAINTENANCE SECTION
CSJ6272-05-004
Proj IDRMC - 627205004
Work TypePAINT
 
0.01012009.3866767.05100.0
CountyGREGG
HighwaySH0031
FromVARIOUS ROADWAYS IN THE
ToLONGVIEW MAINTENANCE SECTION
CSJ6272-05-005
Proj IDRMC - 627205005
Work TypePAINT
 
0.01023318.7549248.01100.0
CountyWOOD
HighwayUS0080
FromVARIOUS ROADWAYS IN THE
ToMINEOLA MAINTENACE SECTION
CSJ6272-05-006
Proj IDRMC - 627205006
Work TypePAINT
 
0.01023318.7535210.94100.0
CountyANDERSON
HighwayUS0287
FromVARIOUS ROADWAYS IN THE
ToPALESINE MAINTENANCE SECTION
CSJ6272-05-007
Proj IDRMC - 627205007
Work TypePAINT
 
0.01023318.758365.21100.0
CountySMITH
HighwaySH0110
FromVARIOUS ROADWAYS IN THE
ToTYLER MAINTENANCE SECTION
CSJ6272-05-008
Proj IDRMC - 627205008
Work TypePAINT
 
0.01023318.7548327.90100.0
CountyCHEROKEE
HighwayUS0069
FromVARIOUS ROADWAYS IN THE
ToRUSK MAINTENANCE SECTION
CSJ6272-05-009
Proj IDRMC - 627205009
Work TypePAINT
 
0.01012009.3834335.47100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-14-14
Work Began09-25-14
Work Completed09-15-16
Time Computed09-01-14
Contract Working Days255
Addl Days Granted255
Working Days Charged509
Percent Time Used99
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6272-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06141001
Totals187250.010.00742665.10100.0

CountyHENDERSON
HighwaySH0031
FromVARIOUS LOCATIONS IN_THE
ToATHENS AND PALESTINE SECTIONS
CSJ6285-89-001
Proj IDRMC - 628589001
Work TypeGUARDRAIL REPAIR
 
0.010123362.00266514.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-15
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted255
Working Days Charged503
Percent Time Used98
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6285-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06151001
Totals123362.0020325.00266514.0099.9

CountyWOOD
HighwayUS0080
FromVARIOUS LOCATIONS IN THE
ToMINEOLA AND CANTON SECTIONS
CSJ6285-90-001
Proj IDRMC - 628590001
Work TypeGUARDRAIL REPAIR
 
0.010107563.00152225.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-10-15
Work Completed09-06-17
Time Computed00-00-00
Contract Working Days255
Addl Days Granted255
Working Days Charged507
Percent Time Used99
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6285-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06151002
Totals107563.0033225.00152225.00100.0

CountyGREGG
HighwayUS0259
FromVARIOUS LOCATIONS IN THE
ToLONGVIEW AND HENDERSON SECTIONS
CSJ6285-91-001
Proj IDRMC - 628591001
Work TypeGUARDRAIL REPAIR
 
0.010107213.00363445.50100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-15
Work Completed08-31-17
Time Computed00-00-00
Contract Working Days255
Addl Days Granted255
Working Days Charged510
Percent Time Used100
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6285-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06151003
Totals107213.0015281.00363445.50100.0

CountySMITH
HighwayUS0069
FromVARIOUS LOCATIONS IN THE
ToTYLER AND JACKSONVILLE SECTIONS
CSJ6285-92-001
Proj IDRMC - 628592001
Work TypeGUARDRAIL REPAIR
 
0.010105963.00453562.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-15
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted255
Working Days Charged503
Percent Time Used98
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6285-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06151004
Totals105963.0012049.00453562.0099.9

CountySMITH
HighwayFM0757
FromFM 757 AND SL 323
ToIN SMITH COUNTY
CSJ6288-59-001
Proj IDRMC - 628859001
Work TypeCULVERT REPAIR
 
0.001174696.0096691.56100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-12-16
Work Completed09-01-17
Time Computed00-00-00
Contract Working Days34
Addl Days Granted0
Working Days Charged157
Percent Time Used461
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6288-59-001
NORTH TEXAS MAINTENANCE, INC. (100.00)
Contract #01161002
Totals174696.000.0096691.56100.0

CountyHENDERSON
HighwaySH0031
FromVARIOUS ROADWAYS IN THE
ToATHENS MAINTENANCE SECTION
CSJ6288-60-001
Proj IDRMC - 628860001
Work TypeTREE REMOVAL
 
0.001172950.00272429.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-15
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted255
Working Days Charged440
Percent Time Used86
Contractor(s)
PATTERSON'S COMPLETE TREE SERVICE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6288-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09151005
Totals172950.0020801.00272429.0099.9

CountyRUSK
HighwayUS0079
FromVARIOUS ROADWAYS IN THE
ToHENDERSON MAINTENANCE SECTION
CSJ6288-62-001
Proj IDRMC - 628862001
Work TypeTREE REMOVAL
 
0.001213375.00330440.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-26-15
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted255
Working Days Charged467
Percent Time Used91
Contractor(s)
PATTERSON'S COMPLETE TREE SERVICE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6288-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09151002
Totals213375.0010425.00330440.0099.9

CountyRUSK
HighwayUS0079
FromVARIOUS ROADWAYS IN
ToRUSK AND CHEROKEE COUNTIES
CSJ6290-48-001
Proj IDEMC - 629048001
Work TypeEMERGENCY DEBRIS & TREE REMOVAL
 
0.010435655.003070764.75100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-26-15
Work Completed08-11-15
Time Computed00-00-00
Contract Working Days52
Addl Days Granted0
Working Days Charged33
Percent Time Used63
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6290-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06151044
Totals435655.000.003070764.75100.0

CountyGREGG
HighwaySH0031
FromVARIOUS ROADWAYS IN
ToGREGG COUNTY
CSJ6294-86-001
Proj IDRMC - 629486001
Work TypeTREE REMOVAL
 
0.001159225.00200445.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-16-16
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted255
Working Days Charged333
Percent Time Used65
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6294-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11151001
Totals159225.000.00200445.0099.9

CountyHENDERSON
HighwaySH0031
FromVARIOUS LOCATIONS
ToIN THE TYLER DISTRICT
CSJ6299-58-001
Proj IDRMC - 629958001
Work TypeSHORT LINE THERMO
 
0.001288607.50280201.0597.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-13-16
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted110
Working Days Charged352
Percent Time Used96
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6299-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05161002
Totals288607.505810.50280201.0597.0

CountyANDERSON
HighwaySH0019
FromVARIOUS ROADWAYS IN
ToANDERSON COUNTY
CSJ6299-59-001
Proj IDRMC - 629959001
Work TypeTREE REMOVAL
 
0.001205450.00202090.0098.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-12-16
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted0
Working Days Charged253
Percent Time Used99
Contractor(s)
PLANT FUEL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6299-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04161001
Totals205450.000.00202090.0098.3

CountyHENDERSON
HighwaySH0019
FromVARIOUS ROADWAYS IN
ToTHE TYLER DISTRICT
CSJ6300-22-001
Proj IDRMC - 630022001
Work TypePAINT
 
0.001239245.00575447.4699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-22-16
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted255
Working Days Charged243
Percent Time Used47
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6300-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04161003
Totals239245.0071731.77575447.4699.9

CountyVAN ZANDT
HighwayIH0020
FromIH-20 VARIOUS LOCATIONS
ToIN VAN ZANDT COUNTY
CSJ6301-83-001
Proj IDBPM - 630183001
Work TypeBRIDGE PREVENTIVE MAINTENANCE
 
0.001171979.00157130.5191.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-28-17
Work Completed
Time Computed00-00-00
Contract Working Days82
Addl Days Granted0
Working Days Charged77
Percent Time Used93
Contractor(s)
RED BARON BUILDING COMPANY, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6301-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161011
Totals171979.0054868.60157130.5191.3

CountyVAN ZANDT
HighwaySH0110
FromVARIOUS LOCATIONS CANTON MTCE.
ToIN VAN ZANDT COUNTY
CSJ6301-84-001
Proj IDBPM - 630184001
Work TypeBRIDGE PREVENTIVE MAINTENANCE
 
0.001223998.91244487.9599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-15-17
Work Completed
Time Computed00-00-00
Contract Working Days82
Addl Days Granted7
Working Days Charged91
Percent Time Used102
Contractor(s)
RED BARON BUILDING COMPANY, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6301-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161012
Totals223998.910.00244487.9599.9

CountyRUSK
HighwayFM2276
FromVARIOUS LOCATIONS IN HENDERSON MTCE.
ToIN RUSK COUNTY
CSJ6301-85-001
Proj IDBPM - 630185001
Work TypeBRIDGE PREVENTIVE MAINTENANCE
 
0.001212350.00191542.5091.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-06-17
Work Completed
Time Computed00-00-00
Contract Working Days82
Addl Days Granted0
Working Days Charged86
Percent Time Used104
Contractor(s)
IIPL USA LLC
SUBCONTRACTOR(S) FOR CCSJ: 6301-85-001
SJ&J CONSTRUCTION, LLC (98.00)
Contract #12161013
Totals212350.0012770.00191542.5091.3

CountySMITH
HighwaySL0323
FromSL 323 IN
ToSMITH COUNTY
CSJ6303-40-001
Proj IDRMC - 630340001
Work TypeSLOPE FAILURE
 
0.100182290.00351385.6699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-05-16
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted3
Working Days Charged29
Percent Time Used67
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6303-40-001
NEWSTAR DRILLING, INC (2.22)
Contract #08161001
Totals182290.00278957.60351385.6699.9

CountyHENDERSON
HighwaySH0031
FromATHENS MTCE. SECTION
ToHENDERSON CO.
CSJ6303-70-001
Proj IDSUP - 630370001
Work TypeLANDSCAPE ROW MTCE.
 
0.01014898.0010314.0069.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged365
Percent Time Used50
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6303-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161030
Totals14898.001146.0010314.0069.2

CountyHENDERSON
HighwaySH0031
FromATHENS MTCE. OFFICE
ToHENDERSON CO
CSJ6303-71-001
Proj IDSUP - 630371001
Work TypeLAWN MTCE.
 
0.01016782.007101.5042.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged365
Percent Time Used50
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6303-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161031
Totals16782.00700.507101.5042.3

CountyGREGG
HighwaySL0281
FromLONGVIEW MTCE. OFFICE
ToGREGG CO
CSJ6303-72-001
Proj IDSUP - 630372001
Work TypeLAWN MTCE
 
0.01031110.0015375.0049.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged365
Percent Time Used50
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6303-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161032
Totals31110.001845.0015375.0049.4

page 1 | page 2 | page 3 | page 4