| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | SUTTON |
| Highway |
RM1312 |
| From |
IRION COUNTY |
| To |
SUTTON COUNTY |
| CSJ |
6205-40-001 |
| Proj ID |
RMC - 620540001 |
| Work Type |
INSTALL BRIDGE RAIL & GUARD RAIL END TRE |
| |
|
0.001 |
308769.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
70 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| K-BAR SERVICES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6205-40-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
04104022 |
|
Totals |
308769.00 |
0.00 |
0.00 |
0.0 |
|
| County | MENARD |
| Highway |
RM0864 |
| From |
3 MILES SOUTH OF US 190 |
| To |
US 190 |
| CSJ |
6223-80-001 |
| Proj ID |
RMC - 622380001 |
| Work Type |
BASE, CEMENT TREAT, SEAL COAT, PAVMENT MRKS |
| |
|
3.000 |
947518.38 |
278564.66 |
439403.01 |
46.3 |
| Work Order |
01-26-12 |
| Work Began |
02-01-12 |
| Work Completed |
|
| Time Computed |
02-01-12 |
| Contract Working Days |
100 |
| Addl Days Granted |
0 |
| Working Days Charged |
50 |
| Percent Time Used |
50 |
| Contractor(s) |
| REECE ALBERT, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6223-80-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11114016 |
|
Totals |
947518.38 |
278564.66 |
439403.01 |
46.3 |
|
| County | EDWARDS |
| Highway |
SH0055 |
| From |
VARIOUS ROADS IN SJT DISTRICT |
| To |
VARIOUS ROADS IN SJT DISTRICT |
| CSJ |
6230-37-001 |
| Proj ID |
RMC - 623037001 |
| Work Type |
SAN ANGELO DISTRICT SEAL COAT |
| |
|
106.743 |
2641886.29 |
86230.60 |
86230.60 |
3.2 |
| Work Order |
04-30-12 |
| Work Began |
04-30-12 |
| Work Completed |
|
| Time Computed |
04-30-12 |
| Contract Working Days |
100 |
| Addl Days Granted |
0 |
| Working Days Charged |
1 |
| Percent Time Used |
1 |
| Contractor(s) |
| RONALD R. WAGNER & CO., LP |
SUBCONTRACTOR(S) FOR CCSJ: 6230-37-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11114035 |
|
Totals |
2641886.29 |
86230.60 |
86230.60 |
3.2 |
|
| County | COKE |
| Highway |
US0277 |
| From |
VARIOUS LOCATIONS IN COKE_COUNTY |
| To |
VARIOUS LOCATIONS IN COKE COUNTY |
| CSJ |
6232-08-001 |
| Proj ID |
RMC - 623208001 |
| Work Type |
MOWING THE RIGHT OF WAY |
| |
|
0.001 |
46758.40 |
0.00 |
23379.20 |
50.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
12-09-11 |
| Work Began |
01-02-12 |
| Work Completed |
|
| Time Computed |
01-02-12 |
| Contract Working Days |
22 |
| Addl Days Granted |
0 |
| Working Days Charged |
6 |
| Percent Time Used |
27 |
| Contractor(s) |
| EGGEMEYER MOWING & CONTRACTING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6232-08-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10114004 |
|
Totals |
46758.40 |
0.00 |
23379.20 |
50.0 |
|
| County | CROCKETT |
| Highway |
SH0163 |
| From |
VARIOUS LOCATIONS IN CROCKETT COUNTY |
| To |
VARIOUS LOCATIONS IN CROCKETT COUNTY |
| CSJ |
6232-09-001 |
| Proj ID |
RMC - 623209001 |
| Work Type |
STRIP MOWING OF RIGHT OF WAY CROCKETT CO |
| |
|
0.001 |
103536.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
44 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| SPARKLES TRUCKING |
SUBCONTRACTOR(S) FOR CCSJ: 6232-09-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10114005 |
|
Totals |
103536.00 |
0.00 |
0.00 |
0.0 |
|
| County | REAGAN |
| Highway |
US0067 |
| From |
VARIOUS LOCATIONS IN REAGAN COUNTY |
| To |
VARIOUS LOCATIONS IN REAGAN COUNTY |
| CSJ |
6232-10-001 |
| Proj ID |
RMC - 623210001 |
| Work Type |
STRIP MOWING OF RIGHT OF WAY REAGAN ETC |
| |
|
0.001 |
48551.40 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
22 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| G.K.C., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6232-10-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10114021 |
|
Totals |
48551.40 |
0.00 |
0.00 |
0.0 |
|
| County | RUNNELS |
| Highway |
SH0158 |
| From |
VARIOUS LOCATIONS IN RUNNELS_COUNTY |
| To |
VARIOUS LOCATIONS IN RUNNELS_COUNTY |
| CSJ |
6232-11-001 |
| Proj ID |
RMC - 623211001 |
| Work Type |
STRIP MOWING OF RIGHT OF WAY |
| |
|
0.001 |
70822.50 |
0.00 |
35411.25 |
50.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
11-30-11 |
| Work Began |
12-05-11 |
| Work Completed |
|
| Time Computed |
12-05-11 |
| Contract Working Days |
32 |
| Addl Days Granted |
0 |
| Working Days Charged |
15 |
| Percent Time Used |
46 |
| Contractor(s) |
| K. S. & R. MOWING SERVICES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6232-11-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10114022 |
|
Totals |
70822.50 |
0.00 |
35411.25 |
50.0 |
|
| County | STERLING |
| Highway |
US0087 |
| From |
VARIOUS LOCATIONS IN STERLING COUNTY |
| To |
VARIOUS LOCATIONS IN STERLING COUNTY |
| CSJ |
6232-12-001 |
| Proj ID |
RMC - 623212001 |
| Work Type |
STRIP MOWING OF RIGHT OF WAY STERLING ET |
| |
|
0.001 |
74751.66 |
0.00 |
37375.83 |
50.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
02-13-12 |
| Work Began |
02-27-12 |
| Work Completed |
|
| Time Computed |
02-27-12 |
| Contract Working Days |
36 |
| Addl Days Granted |
0 |
| Working Days Charged |
10 |
| Percent Time Used |
27 |
| Contractor(s) |
| G.K.C., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6232-12-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10114023 |
|
Totals |
74751.66 |
0.00 |
37375.83 |
50.0 |
|
| County | SUTTON |
| Highway |
US0277 |
| From |
VARIOUS LOCATIONS IN SUTTON COUNTY |
| To |
VARIOUS LOCATIONS IN SUTTON COUNTY |
| CSJ |
6232-13-001 |
| Proj ID |
RMC - 623213001 |
| Work Type |
STRIP MOWING OF RIGHT OF WAY_SUTTON ETC |
| |
|
0.001 |
129427.20 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
44 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| SQUARE G, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6232-13-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10114024 |
|
Totals |
129427.20 |
0.00 |
0.00 |
0.0 |
|
| County | TOM GREEN |
| Highway |
US0067 |
| From |
VARIOUS LOCATIONS IN TOM GREEN COUNTY |
| To |
VARIOUS LOCATIONS IN TOM GREEN COUNTY |
| CSJ |
6232-14-001 |
| Proj ID |
RMC - 623214001 |
| Work Type |
STRIP MOWING OF RIGHT OF WAY TOM GREEN |
| |
|
0.001 |
57349.50 |
0.00 |
28674.75 |
50.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
01-09-12 |
| Work Began |
01-11-12 |
| Work Completed |
|
| Time Computed |
01-11-12 |
| Contract Working Days |
28 |
| Addl Days Granted |
0 |
| Working Days Charged |
8 |
| Percent Time Used |
28 |
| Contractor(s) |
| EGGEMEYER MOWING & CONTRACTING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6232-14-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10114006 |
|
Totals |
57349.50 |
0.00 |
28674.75 |
50.0 |
|
| County | TOM GREEN |
| Highway |
US0277 |
| From |
VARIOUS LOCATIONS IN SAN ANGELO |
| To |
VARIOUS LOCATIONS IN SAN ANGELO |
| CSJ |
6232-15-001 |
| Proj ID |
RMC - 623215001 |
| Work Type |
FULL WIDTH MOWING TOM GREEN URBAN |
| |
|
0.001 |
94770.00 |
0.00 |
25640.00 |
33.3 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
01-04-12 |
| Work Began |
01-09-12 |
| Work Completed |
|
| Time Computed |
01-23-12 |
| Contract Working Days |
24 |
| Addl Days Granted |
0 |
| Working Days Charged |
8 |
| Percent Time Used |
33 |
| Contractor(s) |
| SPARKLES TRUCKING |
SUBCONTRACTOR(S) FOR CCSJ: 6232-15-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10114025 |
|
Totals |
94770.00 |
0.00 |
25640.00 |
33.3 |
|
| County | TOM GREEN |
| Highway |
FM1692 |
| From |
NORTH OF CROWS NEST CREEK |
| To |
FM 2872 |
| CSJ |
6232-51-001 |
| Proj ID |
RMC - 623251001 |
| Work Type |
WIDENING EXISTING ROADWAY SHOULDERS |
| |
|
7.540 |
798662.03 |
227597.04 |
636959.57 |
79.7 |
| Work Order |
01-03-12 |
| Work Began |
01-09-12 |
| Work Completed |
|
| Time Computed |
01-09-12 |
| Contract Working Days |
120 |
| Addl Days Granted |
0 |
| Working Days Charged |
61 |
| Percent Time Used |
50 |
| Contractor(s) |
| REECE ALBERT, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6232-51-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10114003 |
|
Totals |
798662.03 |
227597.04 |
636959.57 |
79.7 |
|
| County | CONCHO |
| Highway |
US0087 |
| From |
VARIOUS LOCATIONS IN CONCHO COUNTY |
| To |
VARIOUS LOCATIONS IN CONCHO COUNTY |
| CSJ |
6232-84-001 |
| Proj ID |
RMC - 623284001 |
| Work Type |
STRIP MOWING OF RIGHT OF WAY CONCHO ETC. |
| |
|
0.001 |
69794.62 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
32 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| K. S. & R. MOWING SERVICES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6232-84-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10114026 |
|
Totals |
69794.62 |
0.00 |
0.00 |
0.0 |
|
| County | EDWARDS |
| Highway |
SH0041 |
| From |
VARIOUS LOCATIONS IN EDWARDS COUNTY |
| To |
VARIOUS LOCATIONS IN EDWARDS COUNTY |
| CSJ |
6232-85-001 |
| Proj ID |
RMC - 623285001 |
| Work Type |
STRIP MOWING OF RIGHT OF WAY_EDWARDS CO. |
| |
|
0.001 |
37304.80 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
16 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| R&M INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 6232-85-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10114027 |
|
Totals |
37304.80 |
0.00 |
0.00 |
0.0 |
|
| County | KIMBLE |
| Highway |
US0083 |
| From |
VARIOUS LOCATIONS IN KIMBLE COUNTY |
| To |
VARIOUS LOCATIONS IN KIMBLE COUNTY |
| CSJ |
6232-86-001 |
| Proj ID |
RMC - 623286001 |
| Work Type |
MODIFIED STRIP MOWING OF RIGHT OF WAY |
| |
|
0.001 |
116615.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
40 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| R&M INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 6232-86-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10114007 |
|
Totals |
116615.00 |
0.00 |
0.00 |
0.0 |
|
| County | REAL |
| Highway |
SH0041 |
| From |
VARIOUS LOCATION IN REAL COUNTY |
| To |
VARIOUS LOCATION IN REAL COUNTY |
| CSJ |
6232-87-001 |
| Proj ID |
RMC - 623287001 |
| Work Type |
STRIP MOWING OF RIGHT OF WAY_REAL CO |
| |
|
0.001 |
45768.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
20 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| SPARKLES TRUCKING |
SUBCONTRACTOR(S) FOR CCSJ: 6232-87-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10114008 |
|
Totals |
45768.00 |
0.00 |
0.00 |
0.0 |
|
| County | CONCHO |
| Highway |
FM1929 |
| From |
AT CONCHO RIVER |
| To |
AT CONCHO RIVER |
| CSJ |
6235-68-001 |
| Proj ID |
BPM - 623568001 |
| Work Type |
CONCRETE REPAIR |
| |
|
0.001 |
332558.00 |
300989.32 |
321358.28 |
96.6 |
| Work Order |
03-16-12 |
| Work Began |
03-26-12 |
| Work Completed |
|
| Time Computed |
03-26-12 |
| Contract Working Days |
45 |
| Addl Days Granted |
5 |
| Working Days Charged |
29 |
| Percent Time Used |
58 |
| Contractor(s) |
| GIBSON & ASSOCIATES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6235-68-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
12114007 |
|
Totals |
332558.00 |
300989.32 |
321358.28 |
96.6 |
|