Monthly State Let Maintenance Report For San Antonio District As Of Aug 10, 2015 Page 2 Of 2

Last Update: Monday, August 10, 2015
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyBEXAR
Highway IH0035
From VARIOUS LOCATIONS IN BEXAR AND
To COMAL COUNTIES
CSJ 6278-99-001
Proj ID RMC - 627899001
Work Type PERFORMANCE BASED ROADWAY MAINTENANCE
 
0.001 18456927.76 2756144.34 3976723.49 21.5
Work Order 03-25-15
Work Began 04-01-15
Work Completed  
Time Computed 04-01-15
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 91
Percent Time Used 12
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6278-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12144208
Totals 18456927.76 2756144.34 3976723.49 21.5

CountyKERR
Highway IH0010
From VARIOUS LOCATIONS IN KERR
To COUNTY
CSJ 6281-66-001
Proj ID RMC - 628166001
Work Type MOWING
 
0.001 413712.00 82260.00 82260.00 19.8
Work Order 06-24-15
Work Began 07-01-15
Work Completed  
Time Computed 07-01-15
Contract Working Days 142
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 8
Contractor(s)
SOUTH TEXAS MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6281-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01154008
Totals 413712.00 82260.00 82260.00 19.8

CountyMEDINA
Highway US0090
From VARIOUS LOCATIONS IN MEDINA,
To ATASCOSA AND FRIO COUNTIES
CSJ 6281-67-001
Proj ID RMC - 628167001
Work Type MOWING
 
0.001 478428.40 37832.80 37832.80 7.9
Work Order 06-24-15
Work Began 07-06-15
Work Completed  
Time Computed 07-01-15
Contract Working Days 196
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 10
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6281-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01154206
Totals 478428.40 37832.80 37832.80 7.9

CountyGUADALUPE
Highway IH0010
From VARIOUS LOCATIONS IN
To GUADALUPE COUNTY
CSJ 6281-68-001
Proj ID RMC - 628168001
Work Type MOWING
 
0.001 525041.00 52431.50 52431.50 9.9
Work Order 07-13-15
Work Began 07-17-15
Work Completed  
Time Computed 07-20-15
Contract Working Days 196
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 5
Contractor(s)
SOUTH TEXAS MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6281-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01154207
Totals 525041.00 52431.50 52431.50 9.9

CountyWILSON
Highway US0181
From VARIOUS
To VARIOUS
CSJ 6281-70-001
Proj ID RMC - 628170001
Work Type MOWING
 
0.001 388841.16 0.00 81881.76 21.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-06-15
Work Began 07-09-15
Work Completed  
Time Computed 07-13-15
Contract Working Days 149
Addl Days Granted 0
Working Days Charged 16
Percent Time Used 10
Contractor(s)
MISSOURI-TEXAS FARMS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6281-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01154208
Totals 388841.16 0.00 81881.76 21.0

CountyUVALDE
Highway US0090
From VARIOUS LOCATIONS IN
To UVALDE COUNTY
CSJ 6281-72-001
Proj ID RMC - 628172001
Work Type MOWING
 
0.001 381625.60 55497.60 55497.60 14.5
Work Order 07-08-15
Work Began 07-16-15
Work Completed  
Time Computed 07-15-15
Contract Working Days 148
Addl Days Granted 0
Working Days Charged 13
Percent Time Used 8
Contractor(s)
MISSOURI-TEXAS FARMS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6281-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01154009
Totals 381625.60 55497.60 55497.60 14.5

CountyKENDALL
Highway IH0010
From VARIOUS LOCATIONS IN
To KENDALL COUNTY
CSJ 6281-73-001
Proj ID RMC - 628173001
Work Type MOWING
 
0.001 403760.00 12708.00 82438.00 20.4
Work Order 06-17-15
Work Began 06-17-15
Work Completed  
Time Computed 06-24-15
Contract Working Days 137
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 8
Contractor(s)
SOUTH TEXAS MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6281-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01154010
Totals 403760.00 12708.00 82438.00 20.4

CountyBEXAR
Highway IH0035
From CONNECTOR IH 10 WB MAINLANES
To IH 35 SB MAIN LANES
CSJ 6283-13-001
Proj ID BPM - 628313001
Work Type REPLACE BRIDGE RAIL
 
0.001 418285.00 190944.59 267984.59 64.0
Work Order 06-03-15
Work Began 06-25-15
Work Completed  
Time Computed 06-10-15
Contract Working Days 54
Addl Days Granted 0
Working Days Charged 39
Percent Time Used 72
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6283-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04154227
Totals 418285.00 190944.59 267984.59 64.0

CountyBEXAR
Highway IH0010
From VARIOUS IN EAST BEXAR
To COUNTY
CSJ 6283-40-001
Proj ID RMC - 628340001
Work Type ROUTINE MAINTENANCE
 
0.001 5928997.20 430231.65 1311208.23 22.1
Work Order 03-30-15
Work Began 04-07-15
Work Completed  
Time Computed 04-01-15
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 110
Percent Time Used 15
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6283-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03154220
Totals 5928997.20 430231.65 1311208.23 22.1

CountyATASCOSA
Highway SH0097
From 2.559 MI NORTH OF MCMULLEN COUNTY LINE
To SH 85
CSJ 6283-44-001
Proj ID RMC - 628344001
Work Type SPOT BASE REPAIR
 
1.000 660723.00 654735.40 654735.40 99.0
Work Order 05-21-15
Work Began 06-15-15
Work Completed  
Time Computed 06-15-15
Contract Working Days 24
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 62
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6283-44-001
FLASHER EQUIPMENT COMPANY(1.51%)
Contract # 03154020
Totals 660723.00 654735.40 654735.40 99.0

CountyATASCOSA
Highway SH0016
From FROM FM 1332 TO
To MCMULLEN COUNTY LINE
CSJ 6285-80-001
Proj ID RMC - 628580001
Work Type BASE REPAIR
 
0.001 829392.67 1016860.41 1016860.41 99.9
Work Order 06-10-15
Work Began 06-11-15
Work Completed  
Time Computed 06-17-15
Contract Working Days 35
Addl Days Granted 0
Working Days Charged 8
Percent Time Used 22
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6285-80-001
INTERSTATE BARRICADES & MARKINGS, INC. (1.29%)
Contract # 04154027
Totals 829392.67 1016860.41 1016860.41 99.9

CountyFRIO
Highway IH0035
From VARIOUS LOCATIONS IN THE
To SAN ANTONIO DISTRICT
CSJ 6287-58-001
Proj ID RMC - 628758001
Work Type PAV MARKINGS & MRKRS CENTERLINE TEXTURING
 
0.001 1648659.10 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
INTERSTATE BARRICADES & MARKINGS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07154001
Totals 1648659.10 0.00 0.00 0.0

CountyBEXAR
Highway IH0035
From VARIOUS LOCATIONS IN
To BEXAR COUNTY
CSJ 6287-83-001
Proj ID RMC - 628783001
Work Type PAV MARKINGS & MRKRS CENTERLINE TEXTURE
 
0.001 994687.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
INTERSTATE BARRICADES & MARKINGS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07154211
Totals 994687.50 0.00 0.00 0.0

page 1 | page 2