Monthly State Let Maintenance Report For San Antonio District As Of May 11, 2017 Page 2 Of 2

Last Update: Wednesday, May 17, 2017
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMEDINA
HighwayUS0090
FromVARIOUS LOCATIONS IN MEDINA,
ToATASCOSA AND FRIO COUNTIES
CSJ6309-88-001
Proj IDRMC - 630988001
Work TypeMOWING
 
0.001451020.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-27-17
Work Began00-00-00
Work Completed
Time Computed05-08-17
Contract Working Days276
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6309-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174010
Totals451020.000.000.000.0

CountyKERR
HighwayIH0010
FromVARIOUS LOCATIONS IN KERR
ToCOUNTY
CSJ6309-89-001
Proj IDRMC - 630989001
Work TypeMOWING
 
0.001383478.007719.002.0
Work Order03-09-17
Work Began03-15-17
Work Completed
Time Computed03-15-17
Contract Working Days150
Addl Days Granted0
Working Days Charged3
Percent Time Used2
Contractor(s)
SOUTH TEXAS MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174011
Totals383478.000.007719.002.0

CountyGUADALUPE
HighwayIH0010
FromVARIOUS LOCATIONS IN
ToGUADALUPE COUNTY
CSJ6309-90-001
Proj IDRMC - 630990001
Work TypeMOWING
 
0.001399462.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-10-17
Work Began00-00-00
Work Completed
Time Computed05-17-17
Contract Working Days164
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SOUTH TEXAS MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174012
Totals399462.000.000.000.0

CountyWILSON
HighwayUS0181
FromVARIOUS LOCATIONS IN
ToWILSON COUNTY
CSJ6309-92-001
Proj IDRMC - 630992001
Work TypeMOWING
 
0.001336435.320.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days142
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MISSOURI-TEXAS FARMS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6309-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12164011
Totals336435.320.000.000.0

CountyUVALDE
HighwayUS0090
FromVARIOUS LOCATIONS IN
ToUVALDE COUNTY
CSJ6309-93-001
Proj IDRMC - 630993001
Work TypeMOWING
 
0.001373429.640.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days143
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MISSOURI-TEXAS FARMS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6309-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12164012
Totals373429.640.000.000.0

CountyMEDINA
HighwayFM2200
FromUS 90
ToFM 462
CSJ6310-94-001
Proj IDRMC - 631094001
Work TypeSEAL COAT
 
0.0011094848.58883344.6880.6
Work Order01-20-17
Work Began00-00-00
Work Completed
Time Computed04-01-17
Contract Working Days51
Addl Days Granted0
Working Days Charged16
Percent Time Used31
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6310-94-001
INTERSTATE BARRICADES & MARKINGS, INC. (22.51)
Contract #12164013
Totals1094848.58875934.68883344.6880.6

CountyBEXAR
HighwayIH0035
FromVARIOUS LOCATIONS IN
ToBEXAR COUNTY
CSJ6311-41-001
Proj IDRMC - 631141001
Work TypeROUTINE MAINTENANCE
 
0.00114068094.00269711.641.9
Work Order03-23-17
Work Began04-04-17
Work Completed
Time Computed04-01-17
Contract Working Days730
Addl Days Granted0
Working Days Charged30
Percent Time Used4
Contractor(s)
ICA MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174013
Totals14068094.00269711.64269711.641.9

CountyBEXAR
HighwayIH0010
FromVARIOUS LOCATIONS IN
ToBEXAR COUNTY
CSJ6311-42-001
Proj IDRMC - 631142001
Work TypeROUTINE MAINTENANCE
 
0.00112422429.32255518.032.0
Work Order03-23-17
Work Began04-07-17
Work Completed
Time Computed04-01-17
Contract Working Days730
Addl Days Granted0
Working Days Charged30
Percent Time Used4
Contractor(s)
ICA MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02174005
Totals12422429.32255518.03255518.032.0

CountyCOMAL
HighwayIH0035
FromIH 35 IN COMAL, GUADALUPE AND
ToBEXAR COUNTIES
CSJ6311-43-001
Proj IDRMC - 631143001
Work TypeROUTINE MAINTENANCE
 
0.0013586599.5924965.230.6
Work Order03-21-17
Work Began04-01-17
Work Completed
Time Computed04-01-17
Contract Working Days730
Addl Days Granted0
Working Days Charged30
Percent Time Used4
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6311-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174222
Totals3586599.5924965.2324965.230.6