Monthly State Let Maintenance Report For San Antonio District As Of Jan 11, 2016 Page 2 Of 2

Last Update: Tuesday, January 12, 2016
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyBEXAR
Highway IH0035
From VARIOUS LOCATIONS IN BEXAR AND
To COMAL COUNTIES
CSJ 6278-99-001
Proj ID RMC - 627899001
Work Type PERFORMANCE BASED ROADWAY MAINTENANCE
 
0.001 18456927.76 87214.37 7301205.05 39.5
Work Order 03-25-15
Work Began 04-01-15
Work Completed  
Time Computed 04-01-15
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 245
Percent Time Used 33
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6278-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12144208
Totals 18456927.76 87214.37 7301205.05 39.5

CountyKERR
Highway IH0010
From VARIOUS LOCATIONS IN KERR
To COUNTY
CSJ 6281-66-001
Proj ID RMC - 628166001
Work Type MOWING
 
0.001 413712.00 42624.00 164520.00 39.7
Work Order 06-24-15
Work Began 07-01-15
Work Completed  
Time Computed 07-01-15
Contract Working Days 142
Addl Days Granted 0
Working Days Charged 23
Percent Time Used 16
Contractor(s)
SOUTH TEXAS MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6281-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01154008
Totals 413712.00 42624.00 164520.00 39.7

CountyMEDINA
Highway US0090
From VARIOUS LOCATIONS IN MEDINA,
To ATASCOSA AND FRIO COUNTIES
CSJ 6281-67-001
Proj ID RMC - 628167001
Work Type MOWING
 
0.001 478428.40 84474.90 187714.60 39.2
Work Order 06-24-15
Work Began 07-06-15
Work Completed  
Time Computed 07-01-15
Contract Working Days 196
Addl Days Granted 0
Working Days Charged 59
Percent Time Used 30
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6281-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01154206
Totals 478428.40 84474.90 187714.60 39.2

CountyGUADALUPE
Highway IH0010
From VARIOUS LOCATIONS IN
To GUADALUPE COUNTY
CSJ 6281-68-001
Proj ID RMC - 628168001
Work Type MOWING
 
0.001 525041.00 0.00 104405.50 19.8
Work Order 07-13-15
Work Began 07-17-15
Work Completed  
Time Computed 07-20-15
Contract Working Days 196
Addl Days Granted 0
Working Days Charged 18
Percent Time Used 9
Contractor(s)
SOUTH TEXAS MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6281-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01154207
Totals 525041.00 0.00 104405.50 19.8

CountyWILSON
Highway US0181
From VARIOUS
To VARIOUS
CSJ 6281-70-001
Proj ID RMC - 628170001
Work Type MOWING
 
0.001 388841.16 34965.57 163134.54 41.9
Work Order 07-06-15
Work Began 07-09-15
Work Completed  
Time Computed 07-13-15
Contract Working Days 149
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 20
Contractor(s)
MISSOURI-TEXAS FARMS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6281-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01154208
Totals 388841.16 34965.57 163134.54 41.9

CountyUVALDE
Highway US0090
From VARIOUS LOCATIONS IN
To UVALDE COUNTY
CSJ 6281-72-001
Proj ID RMC - 628172001
Work Type MOWING
 
0.001 381625.60 82724.52 166330.92 43.5
Work Order 07-08-15
Work Began 07-16-15
Work Completed  
Time Computed 07-15-15
Contract Working Days 148
Addl Days Granted 0
Working Days Charged 29
Percent Time Used 19
Contractor(s)
MISSOURI-TEXAS FARMS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6281-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01154009
Totals 381625.60 82724.52 166330.92 43.5

CountyKENDALL
Highway IH0010
From VARIOUS LOCATIONS IN
To KENDALL COUNTY
CSJ 6281-73-001
Proj ID RMC - 628173001
Work Type MOWING
 
0.001 403760.00 81826.00 164264.00 40.6
Work Order 06-17-15
Work Began 06-17-15
Work Completed  
Time Computed 06-24-15
Contract Working Days 137
Addl Days Granted 0
Working Days Charged 25
Percent Time Used 18
Contractor(s)
SOUTH TEXAS MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6281-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01154010
Totals 403760.00 81826.00 164264.00 40.6

CountyBEXAR
Highway IH0035
From CONNECTOR IH 10 WB MAINLANES
To IH 35 SB MAIN LANES
CSJ 6283-13-001
Proj ID BPM - 628313001
Work Type REPLACE BRIDGE RAIL
 
0.001 418285.00 0.00 450311.79 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-03-15
Work Began 06-25-15
Work Completed 08-25-15
Time Computed 06-10-15
Contract Working Days 54
Addl Days Granted 0
Working Days Charged 50
Percent Time Used 92
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6283-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04154227
Totals 418285.00 0.00 450311.79 100.0

CountyBEXAR
Highway IH0010
From VARIOUS IN EAST BEXAR
To COUNTY
CSJ 6283-40-001
Proj ID RMC - 628340001
Work Type ROUTINE MAINTENANCE
 
0.001 5928997.20 355297.50 2813034.08 47.4
Work Order 03-30-15
Work Began 04-07-15
Work Completed  
Time Computed 04-01-15
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 263
Percent Time Used 36
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6283-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03154220
Totals 5928997.20 355297.50 2813034.08 47.4

CountyATASCOSA
Highway SH0097
From 2.559 MI NORTH OF MCMULLEN COUNTY LINE
To SH 85
CSJ 6283-44-001
Proj ID RMC - 628344001
Work Type SPOT BASE REPAIR
 
1.000 660723.00 0.00 666545.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-21-15
Work Began 06-15-15
Work Completed 09-30-15
Time Computed 06-15-15
Contract Working Days 24
Addl Days Granted 0
Working Days Charged 18
Percent Time Used 75
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6283-44-001
FLASHER EQUIPMENT COMPANY(1.51%)
Contract # 03154020
Totals 660723.00 0.00 666545.00 100.0

CountyATASCOSA
Highway SH0016
From FROM FM 1332 TO
To MCMULLEN COUNTY LINE
CSJ 6285-80-001
Proj ID RMC - 628580001
Work Type BASE REPAIR
 
0.001 829392.67 0.00 1439609.77 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-10-15
Work Began 06-11-15
Work Completed 09-30-15
Time Computed 06-17-15
Contract Working Days 35
Addl Days Granted 0
Working Days Charged 29
Percent Time Used 82
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6285-80-001
INTERSTATE BARRICADES & MARKINGS, INC. (1.29%)
Contract # 04154027
Totals 829392.67 0.00 1439609.77 100.0

CountyFRIO
Highway IH0035
From VARIOUS LOCATIONS IN THE
To SAN ANTONIO DISTRICT
CSJ 6287-58-001
Proj ID RMC - 628758001
Work Type PAV MARKINGS & MRKRS CENTERLINE TEXTURING
 
0.001 1648659.10 339722.55 590612.14 35.8
Work Order 09-11-15
Work Began 09-21-15
Work Completed  
Time Computed 09-21-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 102
Percent Time Used 27
Contractor(s)
INTERSTATE BARRICADES & MARKINGS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07154001
Totals 1648659.10 339722.55 590612.14 35.8

CountyBEXAR
Highway IH0035
From VARIOUS LOCATIONS IN
To BEXAR COUNTY
CSJ 6287-83-001
Proj ID RMC - 628783001
Work Type PAV MARKINGS & MRKRS CENTERLINE TEXTURE
 
0.001 994687.50 189819.84 301402.44 30.3
Work Order 08-31-15
Work Began 09-08-15
Work Completed  
Time Computed 09-01-15
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 122
Percent Time Used 33
Contractor(s)
INTERSTATE BARRICADES & MARKINGS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07154211
Totals 994687.50 189819.84 301402.44 30.3

CountyATASCOSA
Highway US0281
From VARIOUS HIGHWAYS IN UVALDE, ATASCOSA,
To FRIO, AND WILSON COUNTIES
CSJ 6289-49-001
Proj ID RMC - 628949001
Work Type SPOT BASE REPAIR
 
0.001 1342089.83 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6289-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01164212
Totals 1342089.83 0.00 0.00 0.0

CountyFRIO
Highway FM0472
From VARIOUS HIGHWAYS
To -
CSJ 6291-96-001
Proj ID RMC - 629196001
Work Type CRACK SEAL
 
0.001 276383.71 8161.51 8161.51 2.9
Work Order 00-00-00
Work Began 12-07-15
Work Completed  
Time Computed 12-07-15
Contract Working Days 48
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 29
Contractor(s)
M & M STRIPING & POWER WASHING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6291-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09154209
Totals 276383.71 8161.51 8161.51 2.9

CountyGUADALUPE
Highway IH0010
From VARIOUS LOCATIONS IN GUADALUPE, COMAL
To AND WILSON COUNTIES
CSJ 6292-94-001
Proj ID RMC - 629294001
Work Type CRACK SEAL
 
0.001 262808.00 51976.40 73788.40 28.0
Work Order 11-10-15
Work Began 11-16-15
Work Completed  
Time Computed 11-16-15
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 18
Percent Time Used 36
Contractor(s)
M & M STRIPING & POWER WASHING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6292-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09154011
Totals 262808.00 51976.40 73788.40 28.0

CountyMEDINA
Highway FM1796
From VARIOUS_LOCATIONS IN THE
To SAN ANTONIO DISTRICT
CSJ 6296-12-001
Proj ID RMC - 629612001
Work Type SEAL COAT
 
0.001 1823723.31 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 43
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12154207
Totals 1823723.31 0.00 0.00 0.0

CountyBEXAR
Highway IH0035
From IH 35 NEW INTERSECTION OF MAINE AVE.
To AND WEST ELMIRA STREET
CSJ 6296-57-001
Proj ID RMC - 629657001
Work Type PUMPSTATION REPAIRS
 
0.001 678800.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 6296-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01164213
Totals 678800.00 0.00 0.00 0.0

CountyFRIO
Highway IH0035
From VARIOUS LOCATIONS IN
To FRIO, ATASCOSA AND LASALLE COUNTIES
CSJ 6298-17-001
Proj ID RMC - 629817001
Work Type MOWING AND LITTER REMOVAL
 
0.001 524372.82 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 212
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MISSOURI-TEXAS FARMS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6298-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01164008
Totals 524372.82 0.00 0.00 0.0

CountyATASCOSA
Highway IH0037
From VARIOUS LOCATIONS IN
To ATASCOSA COUNTY
CSJ 6298-19-001
Proj ID RMC - 629819001
Work Type MOWING AND LITTER REMOVAL
 
0.001 421464.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 191
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6298-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01164009
Totals 421464.00 0.00 0.00 0.0

page 1 | page 2