Monthly State Let Maintenance Report For San Antonio District As Of Jan 11, 2017 Page 2 Of 2

Last Update: Thursday, January 12, 2017
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyKERR
HighwayFM1340
FromRM 1340_NORTHBOUND
ToSCHOOL STREET INTERSECTION
CSJ6301-12-001
Proj IDRMC - 630112001
Work TypeASPHALT PAVEMENT WIDENING
 
0.001417644.32415621.1499.5
Work Order07-06-16
Work Began07-26-16
Work Completed
Time Computed07-25-16
Contract Working Days60
Addl Days Granted0
Working Days Charged59
Percent Time Used98
Contractor(s)
ACME BRIDGE COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05164203
Totals417644.321579.38415621.1499.5

CountyBEXAR
HighwayIH0035
FromVARIOUS LOCATIONS IN THE
ToSAN ANTONIO DISTRICT
CSJ6303-03-001
Proj IDRMC - 630303001
Work TypeTRAFFIC CONTROL
 
0.001972749.0037405.003.8
Work Order11-07-16
Work Began11-14-16
Work Completed
Time Computed11-14-16
Contract Working Days365
Addl Days Granted0
Working Days Charged17
Percent Time Used4
Contractor(s)
ALTUS TRAFFIC MANAGEMENT LLC
SUBCONTRACTOR(S) FOR CCSJ: 6303-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164011
Totals972749.0037405.0037405.003.8

CountyBEXAR
HighwayIH0035
FromVARIOUS LOCATIONS IN
ToBEXAR COUNTY
CSJ6303-32-001
Proj IDRMC - 630332001
Work TypePAV MARKINGS & MRKRS CENTERLINE
 
0.001947692.50176783.9618.6
Work Order08-19-16
Work Began09-07-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
FLASHER EQUIPMENT COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6303-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164015
Totals947692.5050157.64176783.9618.6

CountyFRIO
HighwayIH0035
FromVARIOUS LOCATIONS IN THE
ToSAN ANTONIO DISTRICT
CSJ6303-33-001
Proj IDRMC - 630333001
Work TypePAV MARKINGS & MRKRS CENTERLINE
 
0.0011515344.30632434.0041.7
Work Order08-24-16
Work Began09-23-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
INTERSTATE BARRICADES & MARKINGS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164214
Totals1515344.3063255.47632434.0041.7

CountyFRIO
HighwayIH0035
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6304-81-001
Proj IDRMC - 630481001
Work TypeTRAFFIC CONTROL
 
0.001616539.008905.001.4
Work Order11-29-16
Work Began12-01-16
Work Completed
Time Computed12-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged31
Percent Time Used8
Contractor(s)
N-LINE TRAFFIC MAINTENANCE, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6304-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164208
Totals616539.008905.008905.001.4

CountyBEXAR
HighwayIH0035
FromIH 410
ToSPUR 422
CSJ6304-98-001
Proj IDRMC - 630498001
Work TypeREMOVE AND REPLACE MBGF
 
1.000568940.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-10-17
Work Began00-00-00
Work Completed
Time Computed01-17-17
Contract Working Days34
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164215
Totals568940.000.000.000.0

CountyBEXAR
HighwayIH0035
FromVARIOUS_LOCATIONS IN
ToBEXAR COUNTY
CSJ6307-50-001
Proj IDRMC - 630750001
Work TypeBRIDGE RAIL RETROFIT
 
0.001893837.720.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-10-17
Work Began00-00-00
Work Completed
Time Computed01-17-17
Contract Working Days104
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6307-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164219
Totals893837.720.000.000.0

CountyKERR
HighwayIH0010
FromVARIOUS LOCATIONS IN KERR, KENDALL,
ToAND BANDERA COUNTIES
CSJ6309-32-001
Proj IDRMC - 630932001
Work TypePICNIC AREA MAINTENANCE
 
0.001573120.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-21-16
Work Began00-00-00
Work Completed
Time Computed01-01-17
Contract Working Days760
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SHORT-LINE CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6309-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164022
Totals573120.000.000.000.0

CountyKENDALL
HighwayIH0010
FromVARIOUS LOCATIONS IN
ToKENDALL COUNTY
CSJ6309-87-001
Proj IDRMC - 630987001
Work TypeMOWING
 
0.001336376.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days129
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LAZER CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174009
Totals336376.000.000.000.0

CountyMEDINA
HighwayUS0090
FromVARIOUS LOCATIONS IN MEDINA,
ToATASCOSA AND FRIO COUNTIES
CSJ6309-88-001
Proj IDRMC - 630988001
Work TypeMOWING
 
0.001451020.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days276
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6309-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174010
Totals451020.000.000.000.0

CountyKERR
HighwayIH0010
FromVARIOUS LOCATIONS IN KERR
ToCOUNTY
CSJ6309-89-001
Proj IDRMC - 630989001
Work TypeMOWING
 
0.001383478.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days150
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SOUTH TEXAS MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174011
Totals383478.000.000.000.0

CountyGUADALUPE
HighwayIH0010
FromVARIOUS LOCATIONS IN
ToGUADALUPE COUNTY
CSJ6309-90-001
Proj IDRMC - 630990001
Work TypeMOWING
 
0.001399462.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days164
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SOUTH TEXAS MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174012
Totals399462.000.000.000.0

CountyWILSON
HighwayUS0181
FromVARIOUS LOCATIONS IN
ToWILSON COUNTY
CSJ6309-92-001
Proj IDRMC - 630992001
Work TypeMOWING
 
0.001336435.320.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days142
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MISSOURI-TEXAS FARMS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6309-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12164011
Totals336435.320.000.000.0

CountyUVALDE
HighwayUS0090
FromVARIOUS LOCATIONS IN
ToUVALDE COUNTY
CSJ6309-93-001
Proj IDRMC - 630993001
Work TypeMOWING
 
0.001373429.640.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days143
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MISSOURI-TEXAS FARMS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6309-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12164012
Totals373429.640.000.000.0

CountyMEDINA
HighwayFM2200
FromUS 90
ToFM 462
CSJ6310-94-001
Proj IDRMC - 631094001
Work TypeSEAL COAT
 
0.0011094848.580.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days51
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6310-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12164013
Totals1094848.580.000.000.0

CountyBEXAR
HighwayIH0035
FromVARIOUS LOCATIONS IN
ToBEXAR COUNTY
CSJ6311-41-001
Proj IDRMC - 631141001
Work TypeROUTINE MAINTENANCE
 
0.00114068094.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ICA MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174013
Totals14068094.000.000.000.0

CountyCOMAL
HighwayIH0035
FromIH 35 IN COMAL, GUADALUPE AND
ToBEXAR COUNTIES
CSJ6311-43-001
Proj IDRMC - 631143001
Work TypeROUTINE MAINTENANCE
 
0.0013586599.590.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6311-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174222
Totals3586599.590.000.000.0

page 1 | page 2