|
Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | BEXAR |
Highway | 0000000 |
From | 4615 NW LOOP 410 |
To | SAN ANTONIO TX 78229 |
CSJ | 4704-01-595 |
Proj ID | CBC - 470401595 |
Work Type | RENOVATION OR REPAIR |
|
| 0.001 | 2038650.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 270 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
QA CONSTRUCTION SERVICES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-595 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 10164224 |
| Totals | 2038650.00 | 0.00 | 0.00 | 0.0 |
|
County | UVALDE |
Highway | 0000000 |
From | 2231 US 90 WEST |
To | UVALDE TX 78801 |
CSJ | 4704-01-724 |
Proj ID | CBC - 470401724 |
Work Type | RENOVATION OR REPAIR |
|
| 0.001 | 337200.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 60 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
BRIGGS BROTHERS ENTERPRISES CORPORATION |
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-724 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 07164221 |
| Totals | 337200.00 | 0.00 | 0.00 | 0.0 |
|
County | ATASCOSA |
Highway | IH0037 |
From | VARIOUS LOCATIONS IN ATASCOSA |
To | COUNTY |
CSJ | 6354-23-001 |
Proj ID | RMC - 635423001 |
Work Type | MOWING HWY ROW AND LITTER REMOVAL |
|
| 0.001 | 519032.24 | | 828875.95 | 100.0 |
Work Order | 05-13-20 |
Work Began | 05-13-20 |
Work Completed | 02-20-24 |
Time Computed | 05-20-20 |
Contract Working Days | 222 |
Addl Days Granted | 229 |
Working Days Charged | 134 |
Percent Time Used | 29 |
Contractor(s) |
R&M INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 6354-23-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 01204216 |
| Totals | 519032.24 | 0.00 | 828875.95 | 100.0 |
|
County | FRIO |
Highway | IH0035 |
From | VARIOUS LOCATIONS IN FRIO, ATASCOSA AND |
To | LASALLE COUNTIES |
CSJ | 6354-38-001 |
Proj ID | RMC - 635438001 |
Work Type | MOWING AND LITTER REMOVAL |
|
| 0.001 | 649631.60 | | 901240.31 | 99.9 |
Work Order | 00-00-00 |
Work Began | 05-15-20 |
Work Completed | |
Time Computed | 05-11-20 |
Contract Working Days | 252 |
Addl Days Granted | 252 |
Working Days Charged | 167 |
Percent Time Used | 33 |
Contractor(s) |
R&M INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 6354-38-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 01204219 |
| Totals | 649631.60 | 0.00 | 901240.31 | 99.9 |
|
County | COMAL |
Highway | SH0046 |
From | VARIOUS LOCATIONS IN |
To | THE SAN ANTONIO DISTRICT |
CSJ | 6354-47-001 |
Proj ID | RMC - 635447001 |
Work Type | GUARDRAIL REPAIR |
|
| 0.001 | 2522000.00 | | 11256919.18 | 99.9 |
Work Order | 03-05-20 |
Work Began | 04-06-20 |
Work Completed | |
Time Computed | 04-06-20 |
Contract Working Days | 730 |
Addl Days Granted | 730 |
Working Days Charged | 1,425 |
Percent Time Used | 97 |
Contractor(s) |
SHORT-LINE CORPORATION |
SUBCONTRACTOR(S) FOR CCSJ: 6354-47-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 01204218 |
| Totals | 2522000.00 | 606668.64 | 11256919.18 | 99.9 |
|
County | BEXAR |
Highway | IH0035 |
From | VARIOUS LOCATIONS IN |
To | BEXAR COUNTY |
CSJ | 6372-50-001 |
Proj ID | RMC - 637250001 |
Work Type | ROUTINE MAINTENANCE PROJECT - SEALED |
|
| 0.010 | 14977836.16 | | 24389954.66 | 99.9 |
Work Order | 03-25-21 |
Work Began | 03-25-21 |
Work Completed | |
Time Computed | 04-01-21 |
Contract Working Days | 730 |
Addl Days Granted | 731 |
Working Days Charged | 1,065 |
Percent Time Used | 72 |
Contractor(s) |
ROY JORGENSEN ASSOCIATES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6372-50-001 SWEEPING SERVICES OF TEXAS - OPERATING, L.P. (11.33) BK FIELD OPERATIONS LLC (23.83) AIMS COMPANIES (0.97) JCW CONSTRUCTION, LLC (0.33) YES AMERICA NOW, INC. (11.10) BOEN LANDSCAPING & IRRIGATION, LLC (0.00) AUSTIN BARRICADE COMPANY, L.L.C. (0.00)
|
Contract # | 01214020 |
| Totals | 14977836.16 | 585216.44 | 24389954.66 | 99.9 |
|
County | KERR |
Highway | IH0010 |
From | VARIOUS LOCATIONS IN |
To | KERR, KENDALL AND BANDERA COUNTIES |
CSJ | 6383-15-001 |
Proj ID | RMC - 638315001 |
Work Type | PICNIC AREA MAINTENANCE |
|
| 0.010 | 599880.00 | | 813894.27 | 99.9 |
Work Order | 00-00-00 |
Work Began | 09-02-21 |
Work Completed | |
Time Computed | 09-02-21 |
Contract Working Days | 730 |
Addl Days Granted | 730 |
Working Days Charged | 910 |
Percent Time Used | 62 |
Contractor(s) |
JCW CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6383-15-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 07214214 |
| Totals | 599880.00 | 29308.83 | 813894.27 | 99.9 |
|
County | BEXAR |
Highway | IH0035 |
From | VARIOUS LOCATIONS |
To | VARIOUS LOCATIONS |
CSJ | 6388-36-001 |
Proj ID | RMC - 638836001 |
Work Type | PAVEMENT MARKINGS |
|
| 0.010 | 3077767.50 | | 3863584.09 | 99.9 |
Work Order | 09-26-22 |
Work Began | 09-30-22 |
Work Completed | |
Time Computed | 10-03-22 |
Contract Working Days | 365 |
Addl Days Granted | 365 |
Working Days Charged | 508 |
Percent Time Used | 69 |
Contractor(s) |
INTERSTATE BARRICADES & MARKINGS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6388-36-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 10214022 |
| Totals | 3077767.50 | 928802.50 | 3863584.09 | 99.9 |
|
County | MCMULLEN |
Highway | SH0016 |
From | VARIOUS LOCATIONS IN MCMULLEN, |
To | ATASCOSA, AND FRIO COUNTIES |
CSJ | 6395-05-001 |
Proj ID | RMC - 639505001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 503637.68 | | 330482.44 | 65.6 |
Work Order | 00-00-00 |
Work Began | 02-28-22 |
Work Completed | |
Time Computed | 03-01-22 |
Contract Working Days | 730 |
Addl Days Granted | 730 |
Working Days Charged | 700 |
Percent Time Used | 47 |
Contractor(s) |
R&M INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 6395-05-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 01224018 |
| Totals | 503637.68 | 0.00 | 330482.44 | 65.6 |
|
County | BEXAR |
Highway | IH0010 |
From | VARIOUS LOCATIONS IN |
To | BEXAR COUNTY |
CSJ | 6395-40-001 |
Proj ID | RMC - 639540001 |
Work Type | BUNDLED BID |
|
| 0.010 | 17507039.23 | | 7130801.26 | 40.7 |
Work Order | 00-00-00 |
Work Began | 04-01-23 |
Work Completed | |
Time Computed | 04-01-23 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 335 |
Percent Time Used | 45 |
Contractor(s) |
ROY JORGENSEN ASSOCIATES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6395-40-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 01234207 |
| Totals | 17507039.23 | 686556.01 | 7130801.26 | 40.7 |
|
County | MEDINA |
Highway | IH0035 |
From | VARIOUS LOCATIONS IN HONDO |
To | MAINTENANCE SECTION |
CSJ | 6406-28-001 |
Proj ID | MMC - 640628001 |
Work Type | LIMESTONE ROCK ASPHALT |
|
| 0.010 | 486216.00 | | 687712.02 | 99.9 |
Work Order | 02-22-23 |
Work Began | 03-15-23 |
Work Completed | |
Time Computed | 03-01-23 |
Contract Working Days | 365 |
Addl Days Granted | 366 |
Working Days Charged | 366 |
Percent Time Used | 50 |
Contractor(s) |
VULCAN CONSTRUCTION MATERIALS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6406-28-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 01234008 |
| Totals | 486216.00 | 89503.36 | 687712.02 | 99.9 |
|
County | UVALDE |
Highway | US0090 |
From | VARIOUS LOCATIONS IN UVALDE |
To | MAINTENANCE SECTION |
CSJ | 6406-34-001 |
Proj ID | MMC - 640634001 |
Work Type | LIMESTONE ROCK ASPHALT |
|
| 0.010 | 693912.00 | | 1526162.95 | 99.9 |
Work Order | 00-00-00 |
Work Began | 03-07-23 |
Work Completed | |
Time Computed | 02-27-23 |
Contract Working Days | 365 |
Addl Days Granted | 365 |
Working Days Charged | 368 |
Percent Time Used | 50 |
Contractor(s) |
VULCAN CONSTRUCTION MATERIALS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6406-34-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 01234208 |
| Totals | 693912.00 | 263909.89 | 1526162.95 | 99.9 |
|
County | BEXAR |
Highway | IH0010 |
From | VARIOUS LOCATIONS THROUGHOUT |
To | SAN ANTONIO DISTRICT |
CSJ | 6406-59-001 |
Proj ID | MMC - 640659001 |
Work Type | AGGREGATE |
|
| 0.010 | 447366.30 | | 267563.97 | 59.8 |
Work Order | 02-23-23 |
Work Began | 04-20-23 |
Work Completed | |
Time Computed | 03-02-23 |
Contract Working Days | 365 |
Addl Days Granted | 366 |
Working Days Charged | 365 |
Percent Time Used | 49 |
Contractor(s) |
VULCAN CONSTRUCTION MATERIALS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6406-59-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 01234009 |
| Totals | 447366.30 | 0.00 | 267563.97 | 59.8 |
|
County | BEXAR |
Highway | IH0010 |
From | VARIOUS LOCATIONS IN EAST BEXAR |
To | MAINTENANCE SECTION |
CSJ | 6406-61-001 |
Proj ID | MMC - 640661001 |
Work Type | HOT MIX |
|
| 0.010 | 661764.60 | | 836134.14 | 99.9 |
Work Order | 03-01-23 |
Work Began | 03-13-23 |
Work Completed | |
Time Computed | 03-08-23 |
Contract Working Days | 365 |
Addl Days Granted | 365 |
Working Days Charged | 359 |
Percent Time Used | 49 |
Contractor(s) |
VULCAN CONSTRUCTION MATERIALS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6406-61-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 01234209 |
| Totals | 661764.60 | 14923.02 | 836134.14 | 99.9 |
|
County | BEXAR |
Highway | IH0010 |
From | VARIOUS LOCATIONS IN WEST BEXAR |
To | MAINTENANCE SECTION |
CSJ | 6406-69-001 |
Proj ID | MMC - 640669001 |
Work Type | HOT MIX |
|
| 0.010 | 693912.50 | | 428704.75 | 61.7 |
Work Order | 02-22-23 |
Work Began | 04-03-23 |
Work Completed | |
Time Computed | 03-01-23 |
Contract Working Days | 365 |
Addl Days Granted | 366 |
Working Days Charged | 366 |
Percent Time Used | 50 |
Contractor(s) |
TEXAS MATERIALS GROUP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6406-69-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 01234010 |
| Totals | 693912.50 | 0.00 | 428704.75 | 61.7 |
|
County | COMAL |
Highway | IH0035 |
From | VARIOUS LOCATIONS IN NEW BRAUNFELS |
To | MAINTENANCE SECTION |
CSJ | 6406-73-001 |
Proj ID | MMC - 640673001 |
Work Type | HOT MIX |
|
| 0.010 | 854150.00 | | 1009661.27 | 99.9 |
Work Order | 00-00-00 |
Work Began | 04-03-23 |
Work Completed | |
Time Computed | 03-12-23 |
Contract Working Days | 365 |
Addl Days Granted | 365 |
Working Days Charged | 355 |
Percent Time Used | 48 |
Contractor(s) |
TEXAS MATERIALS GROUP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6406-73-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 01234210 |
| Totals | 854150.00 | 0.00 | 1009661.27 | 99.9 |
|
County | KERR |
Highway | SH0173 |
From | VARIOUS LOCATIONS IN KERR, BANDERA, |
To | KENDALL AND UVALDE COUNTIES |
CSJ | 6410-37-001 |
Proj ID | RMC - 641037001 |
Work Type | FLEXIBLE PAVEMENT STRUCTURE REPAIR |
|
| 0.010 | 1410326.00 | | 1841498.05 | 99.9 |
Work Order | 00-00-00 |
Work Began | 01-23-23 |
Work Completed | |
Time Computed | 01-23-23 |
Contract Working Days | 365 |
Addl Days Granted | 182 |
Working Days Charged | 403 |
Percent Time Used | 73 |
Contractor(s) |
TEXAS MATERIALS GROUP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6410-37-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 09224217 |
| Totals | 1410326.00 | 473885.44 | 1841498.05 | 99.9 |
|
County | MEDINA |
Highway | US0090 |
From | VARIOUS LOCATIONS IN MEDINA, ATASCOSA, |
To | FRIO AND MCMULLEN COUNTIES |
CSJ | 6410-63-001 |
Proj ID | RMC - 641063001 |
Work Type | FLEXIBLE PAVEMENT STRUCTURE REPAIR |
|
| 0.010 | 2351122.04 | | 4150879.57 | 99.9 |
Work Order | 11-30-22 |
Work Began | 12-07-22 |
Work Completed | |
Time Computed | 12-07-22 |
Contract Working Days | 365 |
Addl Days Granted | 279 |
Working Days Charged | 450 |
Percent Time Used | 69 |
Contractor(s) |
CLARK CONSTRUCTION OF TEXAS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6410-63-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 09224028 |
| Totals | 2351122.04 | 257657.54 | 4150879.57 | 99.9 |
|
County | COMAL |
Highway | SH0046 |
From | VARIOUS LOCATIONS IN COMAL, GUADALUPE, |
To | AND WILSON COUNTIES |
CSJ | 6410-67-001 |
Proj ID | RMC - 641067001 |
Work Type | FLEXIBLE PAVEMENT STRUCTURE REPAIR |
|
| 0.010 | 2637042.50 | | 1960059.41 | 74.3 |
Work Order | 10-26-22 |
Work Began | 11-02-22 |
Work Completed | |
Time Computed | 11-02-22 |
Contract Working Days | 365 |
Addl Days Granted | 304 |
Working Days Charged | 485 |
Percent Time Used | 72 |
Contractor(s) |
TEXAS MATERIALS GROUP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6410-67-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 09224029 |
| Totals | 2637042.50 | 0.00 | 1960059.41 | 74.3 |
|
County | BEXAR |
Highway | IH0410 |
From | VARIOUS LOCATIONS IN |
To | BEXAR COUNTY |
CSJ | 6411-41-001 |
Proj ID | RMC - 641141001 |
Work Type | FLEXIBLE PAVEMENT STRUCTURE REPAIR |
|
| 0.010 | 1289459.40 | | 2813518.77 | 99.9 |
Work Order | 02-15-23 |
Work Began | 02-15-23 |
Work Completed | |
Time Computed | 02-15-23 |
Contract Working Days | 365 |
Addl Days Granted | 229 |
Working Days Charged | 380 |
Percent Time Used | 63 |
Contractor(s) |
TEXAS MATERIALS GROUP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6411-41-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 09224030 |
| Totals | 1289459.40 | 89254.58 | 2813518.77 | 99.9 |
|