Monthly State Let Maintenance Report For San Antonio District As Of May 15, 2013 Page 1 Of 1

Last Update: Wednesday, May 15, 2013
FTP Icon Text Version
page 1

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyBEXAR
Highway IH0010
From WEST
To BEXAR COUNTY
CSJ 6203-78-001
Proj ID RMC - 620378001
Work Type BEXAR BUNDLED BID WEST
 
0.001 6246379.20 85249.42 7714515.80 99.9
Work Order 03-25-10
Work Began 04-01-10
Work Completed  
Time Computed 04-01-10
Contract Working Days 1,096
Addl Days Granted 61
Working Days Charged 1,126
Percent Time Used 97
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6203-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01104007
Totals 6246379.20 85249.42 7714515.80 99.9

CountyBEXAR
Highway IH0010
From VARIOUS LOCATIONS IN
To BEXAR COUNTY
CSJ 6226-24-001
Proj ID RMC - 622624001
Work Type PERFORMANCE BASED STRIPING
 
0.001 13999999.99 359961.99 7516403.84 56.8
Work Order 08-23-11
Work Began 09-06-11
Work Completed  
Time Computed 09-01-11
Contract Working Days 1,095
Addl Days Granted 0
Working Days Charged 608
Percent Time Used 55
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6226-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06114022
Totals 13999999.99 359961.99 7516403.84 56.8

CountyKERR
Highway SH0027
From SH 39
To FM 783 ETC
CSJ 6227-58-001
Proj ID RMC - 622758001
Work Type PLANING, SEALCOAT, OVERLAY & PVMNT MKGS
 
5.223 2377247.75 0.00 2304748.90 97.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-10-11
Work Began 10-17-11
Work Completed  
Time Computed 10-17-11
Contract Working Days 60
Addl Days Granted 15
Working Days Charged 65
Percent Time Used 86
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6227-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07114012
Totals 2377247.75 0.00 2304748.90 97.1

CountyATASCOSA
Highway FM0099
From KARNES COUNTY LINE
To LIVE OAK COUNTY LINE
CSJ 6235-95-001
Proj ID RMC - 623595001
Work Type RESTORE EXISTING ROADWAY
 
0.001 3964879.97 586221.53 2025541.36 51.0
Work Order 10-01-12
Work Began 10-01-12
Work Completed  
Time Computed 10-08-12
Contract Working Days 242
Addl Days Granted 0
Working Days Charged 129
Percent Time Used 53
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6235-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07124025
Totals 3964879.97 586221.53 2025541.36 51.0

CountyFRIO
Highway IH0035
From VARIOUS LOCATIONS_IN FRIO
To ATASCOSA AND LASALLE COUNTIES
CSJ 6236-30-001
Proj ID RMC - 623630001
Work Type MOWING
 
0.001 390186.72 0.00 156038.40 39.9
Work Order 06-07-12
Work Began 06-28-12
Work Completed  
Time Computed 06-25-12
Contract Working Days 178
Addl Days Granted 0
Working Days Charged 43
Percent Time Used 24
Contractor(s)
MISSOURI-TEXAS FARMS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6236-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12114008
Totals 390186.72 0.00 156038.40 39.9

CountyATASCOSA
Highway IH0037
From VARIOUS LOCATIONS IN
To ATASCOSA COUNTY
CSJ 6236-31-001
Proj ID RMC - 623631001
Work Type MOWING
 
0.001 324760.32 0.00 127146.72 39.1
Work Order 06-25-12
Work Began 07-05-12
Work Completed  
Time Computed 07-02-12
Contract Working Days 163
Addl Days Granted 0
Working Days Charged 42
Percent Time Used 25
Contractor(s)
WALLA BROTHERS
SUBCONTRACTOR(S) FOR CCSJ: 6236-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12114013
Totals 324760.32 0.00 127146.72 39.1

CountyBEXAR
Highway IH0035
From VARIOUS LOCATIONS IN
To SAT AND AUS DISTRICTS
CSJ 6240-33-001
Proj ID RMC - 624033001
Work Type SIGN INSTALLATION
 
0.001 596266.27 13247.20 24121.73 4.0
CountyBEXAR
Highway IH0035
From VARIOUS LOCATIONS IN THE AUSTIN
To DISTRICT
CSJ 6240-33-002
Proj ID RMC - 624033001
Work Type SIGN INSTALLATION
 
0.001 172161.79 0.00 0.00 0.0
Work Order 02-07-13
Work Began 02-14-13
Work Completed  
Time Computed 02-14-13
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STAR OPERATIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6240-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12124028
Totals 768428.06 13247.20 24121.73 3.1

CountyBEXAR
Highway IH0035
From VARIOUS LOCATIONS IN
To BEXAR COUNTY
CSJ 6240-80-001
Proj ID RMC - 624080001
Work Type PAVEMENT REPAIR
 
0.001 4737599.92 0.00 2302426.52 48.5
Work Order 07-27-12
Work Began 07-27-12
Work Completed  
Time Computed 07-27-12
Contract Working Days 250
Addl Days Granted 0
Working Days Charged 69
Percent Time Used 27
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6240-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04124023
Totals 4737599.92 0.00 2302426.52 48.5

CountyCOMAL
Highway IH0035
From VARIOUS LOCATION IN THE
To SAN ANTONIO DISTRICT
CSJ 6240-85-001
Proj ID RMC - 624085001
Work Type GUARDRAIL REPAIR
 
0.001 356300.00 14833.50 275706.00 77.3
Work Order 06-05-12
Work Began 06-12-12
Work Completed  
Time Computed 06-12-12
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 323
Percent Time Used 44
Contractor(s)
SHORT-LINE CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6240-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04124028
Totals 356300.00 14833.50 275706.00 77.3

CountyFRIO
Highway IH0035
From VARIOUS LOCATIONS IN THE SAN ANTONIO
To DISTRICT
CSJ 6241-46-001
Proj ID RMC - 624146001
Work Type PAV MARKINGS AND CENTERLINE TEXTURING
 
0.001 1377777.77 76848.93 787865.93 61.0
Work Order 08-15-12
Work Began 08-22-12
Work Completed  
Time Computed 08-22-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 252
Percent Time Used 69
Contractor(s)
INTERSTATE BARRICADES & MARKINGS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6241-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07124009
Totals 1377777.77 76848.93 787865.93 61.0

CountyFRIO
Highway SH0085
From IH 35 TO
To DEMMIT CL
CSJ 6242-81-001
Proj ID RMC - 624281001
Work Type MILL SEAL AND OVERLAY
 
0.001 3449739.90 2309480.53 3730082.48 99.9
Work Order 01-28-13
Work Began 02-04-13
Work Completed  
Time Computed 02-04-13
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 46
Percent Time Used 57
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6242-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07124026
Totals 3449739.90 2309480.53 3730082.48 99.9

CountyATASCOSA
Highway FM0791
From VARIOUS HIGHWAYS IN ATASCOSA, FRIO,
To MCMULLEN, AND WILSON COUNTIES
CSJ 6245-57-001
Proj ID RMC - 624557001
Work Type SPOT BASE REPAIR
 
0.100 1034993.56 0.00 566582.63 72.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-11-12
Work Began 10-19-12
Work Completed  
Time Computed 10-22-12
Contract Working Days 50
Addl Days Granted 14
Working Days Charged 65
Percent Time Used 101
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6245-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08124042
Totals 1034993.56 0.00 566582.63 72.7

CountyBEXAR
Highway US0281
From US 281 AT
To BROOKHOLLOW
CSJ 6249-87-001
Proj ID BPM - 624987001
Work Type REPAIR RETAINING WALL
 
0.001 558585.32 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 46
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6249-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03134021
Totals 558585.32 0.00 0.00 0.0

CountyGUADALUPE
Highway IH0010
From VARIOUS LOCATIONS IN
To GUADALUPE COUNTY
CSJ 6251-89-001
Proj ID RMC - 625189001
Work Type MOWING
 
0.001 355822.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 198
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SOUTH TEXAS MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6251-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01134010
Totals 355822.00 0.00 0.00 0.0

CountyMEDINA
Highway US0090
From VARIOUS LOCATIONS IN MEDINA,
To ATASCOSA AND FRIO COUNTIES
CSJ 6251-90-001
Proj ID RMC - 625190001
Work Type MOWING
 
0.001 363520.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 194
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6251-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01134028
Totals 363520.00 0.00 0.00 0.0

CountyBEXAR
Highway IH0035
From VARIOUS LOCATIONS IN EAST
To BEXAR COUNTY
CSJ 6251-98-001
Proj ID RMC - 625198001
Work Type BUNDLED BID EAST
 
0.001 6385301.00 259148.81 259148.81 4.3
Work Order 03-25-13
Work Began 04-01-13
Work Completed  
Time Computed 04-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 4
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6251-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01134011
Totals 6385301.00 259148.81 259148.81 4.3

CountyBEXAR
Highway IH0010
From VARIOUS LOCATIONS IN WEST
To BEXAR COUNTY
CSJ 6251-99-001
Proj ID RMC - 625199001
Work Type BUNDLED BID WEST
 
0.001 5969046.00 122762.85 122762.85 2.3
Work Order 03-25-13
Work Began 04-01-13
Work Completed  
Time Computed 04-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 4
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6251-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01134039
Totals 5969046.00 122762.85 122762.85 2.3

page 1