Monthly State Let Maintenance Report For San Antonio District As Of Aug 11, 2017 Page 1 Of 2

Last Update: Friday, August 11, 2017
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBEXAR
Highway0000000
From4615 NW LOOP 410
ToSAN ANTONIO TX 78229
CSJ4704-01-595
Proj IDCBC - 470401595
Work TypeRENOVATION OR REPAIR
 
0.0012038650.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days270
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
QA CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-595
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164224
Totals2038650.000.000.000.0

CountyBEXAR
Highway0000000
From4615 N. W. LOOP 410 SAN ANTONIO, TEXAS
To4615 N. W. LOOP 410 SAN ANTONIO, TEXAS
CSJ4704-01-602
Proj IDCBC - 470401602
Work TypeRENVOATION OR REPAIR
 
0.001477770.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SECURITAS ELECTRONIC SECURITY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-602
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04164223
Totals477770.000.000.000.0

CountyUVALDE
Highway0000000
From2231 US 90 WEST
ToUVALDE TX 78801
CSJ4704-01-724
Proj IDCBC - 470401724
Work TypeRENOVATION OR REPAIR
 
0.001337200.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRIGGS BROTHERS ENTERPRISES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-724
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164221
Totals337200.000.000.000.0

CountyMEDINA
HighwayFM0462
FromFM 462
ToAT HONDO CREEK BRIDGE
CSJ6277-89-001
Proj IDRMC - 627789001
Work TypeDITCH REPAIR
 
0.001290626.60238554.8395.2
Work Order11-08-16
Work Began01-02-17
Work Completed
Time Computed11-28-16
Contract Working Days34
Addl Days Granted0
Working Days Charged99
Percent Time Used291
Contractor(s)
ACME BRIDGE COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6277-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164220
Totals290626.60502.40238554.8395.2

CountyBEXAR
HighwayIH0010
FromVARIOUS IN EAST BEXAR
ToCOUNTY
CSJ6283-40-001
Proj IDRMC - 628340001
Work TypeROUTINE MAINTENANCE
 
0.0015928997.208114623.3999.9
Work Order03-30-15
Work Began04-07-15
Work Completed
Time Computed04-01-15
Contract Working Days730
Addl Days Granted142
Working Days Charged841
Percent Time Used96
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6283-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03154220
Totals5928997.206200.008114623.3999.9

CountyBEXAR
HighwayIH0035
FromIH 35 NEW INTERSECTION OF MAIN AVE.
ToWEST ELMIRA STREET
CSJ6296-57-001
Proj IDRMC - 629657001
Work TypePUMPSTATION REPAIRS
 
0.0011249435.001364657.6899.9
Work Order09-01-16
Work Began09-08-16
Work Completed
Time Computed09-08-16
Contract Working Days180
Addl Days Granted60
Working Days Charged227
Percent Time Used94
Contractor(s)
AUSTIN ENGINEERING CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164213
Totals1249435.0094910.001364657.6899.9

CountyCOMAL
HighwayIH0035
FromVARIOUS LOCATIONS_IN
ToSAN ANTONIO DISTRICT
CSJ6297-62-001
Proj IDRMC - 629762001
Work TypeGUARDRAIL REPAIR
 
0.0011166990.001250000.5099.9
Work Order06-15-16
Work Began07-06-16
Work Completed
Time Computed06-22-16
Contract Working Days730
Addl Days Granted0
Working Days Charged402
Percent Time Used55
Contractor(s)
SHORT-LINE CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6297-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04164020
Totals1166990.00105294.501250000.5099.9

CountyFRIO
HighwayIH0035
FromVARIOUS LOCATIONS IN
ToFRIO, ATASCOSA AND LASALLE COUNTIES
CSJ6298-17-001
Proj IDRMC - 629817001
Work TypeMOWING AND LITTER REMOVAL
 
0.001524372.82323831.1061.7
Work Order00-00-00
Work Began05-23-16
Work Completed
Time Computed05-23-16
Contract Working Days212
Addl Days Granted0
Working Days Charged67
Percent Time Used31
Contractor(s)
MISSOURI-TEXAS FARMS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6298-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01164008
Totals524372.820.00323831.1061.7

CountyATASCOSA
HighwayIH0037
FromVARIOUS LOCATIONS IN
ToATASCOSA COUNTY
CSJ6298-19-001
Proj IDRMC - 629819001
Work TypeMOWING AND LITTER REMOVAL
 
0.001421464.00233004.3056.7
Work Order06-07-16
Work Began06-28-16
Work Completed
Time Computed06-14-16
Contract Working Days191
Addl Days Granted0
Working Days Charged66
Percent Time Used34
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6298-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01164009
Totals421464.000.00233004.3056.7

CountyBEXAR
HighwayIH0035
FromVARIOUS LOCATIONS IN_BEXAR,KERR,UVALDE
ToKENDALL,BANDERA,COMAL,GUADALUPE
CSJ6299-37-001
Proj IDRMC - 629937001
Work TypeCALL OUT PAVEMENT REPAIR
 
0.0014990875.404248004.9885.1
Work Order08-31-16
Work Began09-22-16
Work Completed
Time Computed09-07-16
Contract Working Days365
Addl Days Granted0
Working Days Charged317
Percent Time Used86
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6299-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04164219
Totals4990875.4039618.364248004.9885.1

CountyFRIO
HighwayIH0035
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6300-78-001
Proj IDRMC - 630078001
Work TypePAVEMENT REPAIR
 
0.0012637085.633448862.7199.9
Work Order06-02-16
Work Began06-08-16
Work Completed
Time Computed06-06-16
Contract Working Days365
Addl Days Granted62
Working Days Charged366
Percent Time Used85
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-78-001
INTERSTATE BARRICADES & MARKINGS, INC. (4.56)
Contract #04164006
Totals2637085.630.003448862.7199.9

CountyBEXAR
HighwayIH0035
FromVARIOUS LOCATIONS IN THE
ToSAN ANTONIO DISTRICT
CSJ6303-03-001
Proj IDRMC - 630303001
Work TypeTRAFFIC CONTROL
 
0.001972749.001826225.7299.9
Work Order11-07-16
Work Began11-14-16
Work Completed
Time Computed11-14-16
Contract Working Days365
Addl Days Granted0
Working Days Charged260
Percent Time Used71
Contractor(s)
ALTUS TRAFFIC MANAGEMENT LLC
SUBCONTRACTOR(S) FOR CCSJ: 6303-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164011
Totals972749.00324627.251826225.7299.9

CountyBEXAR
HighwayIH0035
FromVARIOUS LOCATIONS IN
ToBEXAR COUNTY
CSJ6303-32-001
Proj IDRMC - 630332001
Work TypePAV MARKINGS & MRKRS CENTERLINE TEXTURE
 
0.001947692.50707365.4074.6
Work Order08-19-16
Work Began09-07-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted365
Working Days Charged334
Percent Time Used45
Contractor(s)
FLASHER EQUIPMENT COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6303-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164015
Totals947692.509268.14707365.4074.6

CountyFRIO
HighwayIH0035
FromVARIOUS LOCATIONS IN THE
ToSAN ANTONIO DISTRICT
CSJ6303-33-001
Proj IDRMC - 630333001
Work TypePAV MARKINGS & MRKRS CENTERLINE TEXTURE
 
0.0011515344.301863030.7499.9
Work Order08-24-16
Work Began09-23-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted365
Working Days Charged334
Percent Time Used45
Contractor(s)
INTERSTATE BARRICADES & MARKINGS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164214
Totals1515344.3088360.401863030.7499.9

CountyFRIO
HighwayIH0035
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6304-81-001
Proj IDRMC - 630481001
Work TypeTRAFFIC CONTROL
 
0.001616539.00815143.0999.9
Work Order11-29-16
Work Began12-01-16
Work Completed
Time Computed12-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged243
Percent Time Used66
Contractor(s)
AREA WIDE PROTECTIVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164208
Totals616539.00109859.01815143.0999.9

CountyKERR
HighwayIH0010
FromVARIOUS LOCATIONS IN KERR, KENDALL,
ToAND BANDERA COUNTIES
CSJ6309-32-001
Proj IDRMC - 630932001
Work TypePICNIC AREA MAINTENANCE
 
0.001573120.00171148.0029.8
Work Order12-21-16
Work Began01-02-17
Work Completed
Time Computed01-01-17
Contract Working Days760
Addl Days Granted0
Working Days Charged212
Percent Time Used27
Contractor(s)
SHORT-LINE CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6309-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164022
Totals573120.0028268.00171148.0029.8

CountyKENDALL
HighwayIH0010
FromVARIOUS LOCATIONS IN
ToKENDALL COUNTY
CSJ6309-87-001
Proj IDRMC - 630987001
Work TypeMOWING
 
0.001336376.003168.000.9
Work Order06-13-17
Work Began00-00-00
Work Completed
Time Computed06-20-17
Contract Working Days129
Addl Days Granted0
Working Days Charged28
Percent Time Used21
Contractor(s)
LAZER CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174009
Totals336376.003168.003168.000.9

CountyMEDINA
HighwayUS0090
FromVARIOUS LOCATIONS IN MEDINA,
ToATASCOSA AND FRIO COUNTIES
CSJ6309-88-001
Proj IDRMC - 630988001
Work TypeMOWING
 
0.001451020.00112792.0025.0
Work Order05-25-17
Work Began05-24-17
Work Completed
Time Computed05-08-17
Contract Working Days276
Addl Days Granted0
Working Days Charged24
Percent Time Used8
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6309-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174010
Totals451020.000.00112792.0025.0

CountyKERR
HighwayIH0010
FromVARIOUS LOCATIONS IN KERR
ToCOUNTY
CSJ6309-89-001
Proj IDRMC - 630989001
Work TypeMOWING
 
0.001383478.00102377.0026.6
Work Order03-09-17
Work Began03-15-17
Work Completed
Time Computed03-15-17
Contract Working Days150
Addl Days Granted0
Working Days Charged17
Percent Time Used11
Contractor(s)
SOUTH TEXAS MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-89-001
K-BAR SERVICES, INC. (15.62)
Contract #01174011
Totals383478.0038241.00102377.0026.6

CountyGUADALUPE
HighwayIH0010
FromVARIOUS LOCATIONS IN
ToGUADALUPE COUNTY
CSJ6309-90-001
Proj IDRMC - 630990001
Work TypeMOWING
 
0.001399462.0042813.0010.7
Work Order07-19-17
Work Began07-20-17
Work Completed
Time Computed07-20-17
Contract Working Days164
Addl Days Granted0
Working Days Charged8
Percent Time Used4
Contractor(s)
SOUTH TEXAS MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174012
Totals399462.0042813.0042813.0010.7

page 1 | page 2