Monthly Local Let Maintenance Report For San Antonio District As Of Dec 10, 2014 Page 3 Of 3

Last Update: Wednesday, December 10, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyBEXAR
Highway IH0410
From 3500 NW LOOP 410
To 3500 NW LOOP 410
CSJ 6279-15-001
Proj ID SUP - 627915001
Work Type JANITORIAL SERVICES
 
0.001 13538.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
ENDEAVORS UNLIMITED, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6279-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08141530
Totals 13538.40 0.00 0.00 0.0

CountyATASCOSA
Highway SH0097
From SH 85
To THE ATASCOSA/MCMULLEN COUNTY LINE
CSJ 6279-22-001
Proj ID EMC - 627922001
Work Type SPOT BASE REPAIR
 
0.001 956612.89 0.00 1051387.94 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-23-14
Work Completed  
Time Computed 09-16-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 46
Percent Time Used 76
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6279-22-001
FLASHER EQUIPMENT COMPANY(2.63%)
Contract # 09141531
Totals 956612.89 0.00 1051387.94 99.9

CountyATASCOSA
Highway IH0037
From IH 37 NB AND
To SB MAINLANES
CSJ 6280-12-001
Proj ID SUP - 628012001
Work Type PICNIC AREA MAINTENANCE
 
0.001 51523.90 1775.60 3951.76 7.6
Work Order 10-01-14
Work Began 10-03-14
Work Completed  
Time Computed 10-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 8
Contractor(s)
TIBH INDUSTRIES, INC.
SAN ANTONIO STATE SUPPORTED LIVING CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6280-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09141532
Totals 51523.90 1775.60 3951.76 7.6

CountyKENDALL
Highway IH0010
From 1375 N MAIN
To 1375 N MAIN
CSJ 6280-13-001
Proj ID SUP - 628013001
Work Type JANITORIAL SERVICES
 
0.001 14319.52 390.00 390.00 2.7
Work Order 10-08-14
Work Began 10-08-14
Work Completed  
Time Computed 10-08-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 24
Percent Time Used 3
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6280-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09141533
Totals 14319.52 390.00 390.00 2.7

CountyUVALDE
Highway US0090
From US 90
To US 90
CSJ 6281-38-001
Proj ID SUP - 628138001
Work Type JANITORIAL SERVICES
 
0.001 10963.80 110.65 110.65 1.0
Work Order 11-13-14
Work Began 11-29-14
Work Completed  
Time Computed 11-23-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 8
Percent Time Used 2
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6281-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10141530
Totals 10963.80 110.65 110.65 1.0

CountyFRIO
Highway FM0140
From FM 140
To FM 140
CSJ 6282-20-001
Proj ID SUP - 628220001
Work Type JANITORIAL SERVICES
 
0.001 10759.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6282-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11141530
Totals 10759.50 0.00 0.00 0.0

page 1 | page 2 | page 3