Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyGUADALUPE
Highway SH0046
From 2024 HWY 46 N
To SEGUIN
CSJ 6247-55-001
Proj ID SUP - 624755001
Work Type GROUNDS MAINTENANCE
 
0.001 4000.00 200.00 1200.00 30.0
Work Order 08-01-12
Work Began 08-12-12
Work Completed  
Time Computed 08-01-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 58
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6247-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07121530
Totals 4000.00 200.00 1200.00 30.0

CountyBEXAR
Highway IH0410
From 3500 NW LOOP 410
To 3500 NW LOOP 410
CSJ 6249-74-001
Proj ID SUP - 624974001
Work Type JANITORIAL SERVICES
 
0.001 43174.08 0.00 12592.44 29.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-01-12
Work Began 09-01-12
Work Completed  
Time Computed 09-01-12
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 29
Contractor(s)
TIBH INDUSTRIES, INC.
ENDEAVORS UNLIMITED, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6249-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08121530
Totals 43174.08 0.00 12592.44 29.1

CountyKENDALL
Highway IH0010
From 1375 N MAIN
To 1375 N MAIN
CSJ 6250-80-001
Proj ID SUP - 625080001
Work Type JANITORIAL SERVICES
 
0.001 12000.00 500.00 3250.00 27.0
Work Order 10-04-12
Work Began 10-08-12
Work Completed  
Time Computed 10-08-12
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 205
Percent Time Used 28
Contractor(s)
TIBH INDUSTRIES, INC.
WORSHIP ANOINTED MINISTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6250-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09121530
Totals 12000.00 500.00 3250.00 27.0

CountyATASCOSA
Highway IH0037
From IH 37 NB AND
To SB MAINLANES
CSJ 6250-88-001
Proj ID SUP - 625088001
Work Type PICNIC AREA MAINTENANCE
 
0.001 50925.60 1098.00 12647.52 24.8
Work Order 10-01-12
Work Began 10-11-12
Work Completed  
Time Computed 10-01-12
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 29
Contractor(s)
TIBH INDUSTRIES, INC.
SAN ANTONIO STATE SUPPORTED LIVING CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6250-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09121531
Totals 50925.60 1098.00 12647.52 24.8

CountyWILSON
Highway US0181
From VARIOUS LOCATIONS IN
To WILSON COUNTY
CSJ 6251-91-001
Proj ID RMC - 625191001
Work Type MOWING
 
0.001 343024.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 154
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MISSOURI-TEXAS FARMS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6251-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12121501
Totals 343024.00 0.00 0.00 0.0

CountyCOMAL
Highway IH0035
From VARIOUS LOCATIONS IN
To COMAL COUNTY
CSJ 6251-92-001
Proj ID RMC - 625192001
Work Type MOWING
 
0.001 292043.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 117
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SOUTH TEXAS MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6251-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12121502
Totals 292043.60 0.00 0.00 0.0

CountyBANDERA
Highway SH0016
From VARIOUS LOCATIONS IN
To BANDERA AND MEDINA COUNTIES
CSJ 6251-93-001
Proj ID RMC - 625193001
Work Type MOWING
 
0.001 258113.80 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 103
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6251-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12121503
Totals 258113.80 0.00 0.00 0.0

CountyKERR
Highway IH0010
From VARIOUS LOCATIONS IN
To KERR COUNTY
CSJ 6251-94-001
Proj ID RMC - 625194001
Work Type MOWING
 
0.001 358413.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 143
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SOUTH TEXAS MAINTENANCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6251-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12121504
Totals 358413.60 0.00 0.00 0.0

CountyUVALDE
Highway US0090
From VARIOUS LOCATIONS IN
To UVALDE COUNTY
CSJ 6251-95-001
Proj ID RMC - 625195001
Work Type MOWING
 
0.001 353924.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 148
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6251-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12121505
Totals 353924.00 0.00 0.00 0.0

CountyKENDALL
Highway IH0010
From VARIOUS LOCATIONS IN
To KENDALL COUNTY
CSJ 6251-96-001
Proj ID RMC - 625196001
Work Type MOWING
 
0.001 309438.12 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 139
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6251-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12121506
Totals 309438.12 0.00 0.00 0.0

CountyUVALDE
Highway US0090
From US 90
To US 90
CSJ 6252-85-001
Proj ID SUP - 625285001
Work Type JANITORIAL SERVICES
 
0.001 4221.00 351.75 1769.65 41.9
Work Order 11-16-12
Work Began 11-24-12
Work Completed  
Time Computed 11-23-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 159
Percent Time Used 43
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6252-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11121530
Totals 4221.00 351.75 1769.65 41.9

CountyMEDINA
Highway SH0173
From SH 173
To SH 173
CSJ 6252-91-001
Proj ID SUP - 625291001
Work Type JANITORIAL SERVICES
 
0.001 5058.84 210.79 1981.38 39.1
Work Order 11-19-12
Work Began 11-23-12
Work Completed  
Time Computed 11-23-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 159
Percent Time Used 43
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6252-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11121531
Totals 5058.84 210.79 1981.38 39.1

CountyFRIO
Highway FM0140
From FM 140
To FM 140
CSJ 6252-93-001
Proj ID SUP - 625293001
Work Type JANITORIAL SERVICES
 
0.001 5055.60 421.30 2211.83 43.7
Work Order 11-23-12
Work Began 11-23-12
Work Completed  
Time Computed 11-23-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 159
Percent Time Used 43
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6252-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11121532
Totals 5055.60 421.30 2211.83 43.7

CountyBEXAR
Highway SH0016
From VARIOUS LOCATIONS ON SH 16, FM 471 AND
To SP 421
CSJ 6254-56-001
Proj ID RMC - 625456001
Work Type SIGNALS
 
0.001 199044.00 0.00 0.00 0.0
Work Order 03-12-13
Work Began 03-19-13
Work Completed  
Time Computed 03-19-13
Contract Working Days 130
Addl Days Granted 0
Working Days Charged 43
Percent Time Used 33
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6254-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02131501
Totals 199044.00 0.00 0.00 0.0