Monthly State Let Maintenance Report For Pharr District As Of Apr 10, 2017 Page 2 Of 2

Last Update: Monday, April 10, 2017
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHIDALGO
HighwayFM0907
FromFM 907 AT MAIN FLOODWAY
ToSP 115 AT MAIN FLOODWAY
CSJ6282-63-001
Proj IDBPM - 628263001
Work TypeBRIDGE PREVENTIVE MAINTENANCE
 
0.010792684.28767102.2896.7
Work Order08-01-16
Work Began09-29-16
Work Completed
Time Computed10-03-16
Contract Working Days80
Addl Days Granted10
Working Days Charged90
Percent Time Used100
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 6282-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06164208
Totals792684.2851711.65767102.2896.7

CountyHIDALGO
HighwayIH0002
FromDISTRICT WIDE
ToDISTRICT WIDE
CSJ6286-48-001
Proj IDRMC - 628648001
Work TypePAVEMENT REPAIRS
 
0.0103599099.365134579.3299.9
Work Order07-13-15
Work Began00-00-00
Work Completed
Time Computed08-03-15
Contract Working Days220
Addl Days Granted220
Working Days Charged146
Percent Time Used33
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6286-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06154207
Totals3599099.36258565.515134579.3299.9

CountyCAMERON
HighwayFM0106
From0.05 MI WEST OF ARROYO BLVD
ToROBERTSON RD
CSJ6287-23-001
Proj IDRMC - 628723001
Work TypeREHABILITATION
 
0.010482939.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days100
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS CORDIA CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6287-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03174013
Totals482939.000.000.000.0

CountyHIDALGO
HighwayIH0002
FromHIDALGO COUNTY
ToHIDALGO COUNTY
CSJ6288-85-001
Proj IDRMC - 628885001
Work TypeCLEANING AND SWEEPING, DEBRIS REMOVAL
 
0.010994971.60687536.8069.1
Work Order11-16-15
Work Began01-04-16
Work Completed
Time Computed01-01-16
Contract Working Days378
Addl Days Granted0
Working Days Charged282
Percent Time Used74
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6288-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10154014
Totals994971.6046425.60687536.8069.1

CountyCAMERON
HighwayIH0069E
FromCAMERON COUNTY
ToTO IH 69E/IH 2 (US 77/US 83)
CSJ6288-87-001
Proj IDRMC - 628887001
Work TypeCLEANING AND SWEEPING, DEBRIS REMOVAL
 
0.010914541.60626850.0068.5
Work Order11-24-15
Work Began01-04-16
Work Completed
Time Computed01-01-16
Contract Working Days378
Addl Days Granted0
Working Days Charged316
Percent Time Used83
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6288-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10154015
Totals914541.6041790.00626850.0068.5

CountyHIDALGO
HighwayFM1921
FromFM 1015
To2 MILES EAST OF FM 1015
CSJ6288-89-001
Proj IDRMC - 628889001
Work TypeREHAB AND WIDENING
 
0.010755966.191134051.3599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-10-13
Work Completed
Time Computed00-00-00
Contract Working Days100
Addl Days Granted97
Working Days Charged111
Percent Time Used56
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6288-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08154211
Totals755966.190.001134051.3599.9

CountyHIDALGO
HighwayIH0002
FromDISTRICT WIDE
ToVARIOUS ROADWAYS
CSJ6291-59-001
Proj IDRMC - 629159001
Work TypePAVEMENT MARKINGS
 
0.0101338301.151521624.6999.9
Work Order03-15-16
Work Began03-15-16
Work Completed
Time Computed03-15-16
Contract Working Days120
Addl Days Granted120
Working Days Charged130
Percent Time Used54
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6291-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11154211
Totals1338301.15372580.391521624.6999.9

CountyHIDALGO
HighwaySH0336
FromEDCOUCH, MISSION & PHARR MAINTENANCE
ToVARIOUS ROADWAYS (FM ROADS)
CSJ6291-90-001
Proj IDRMC - 629190001
Work TypeCLEANING & SWEEPING OF HIGHWAYS
 
0.0101215303.10842428.4069.3
Work Order12-09-15
Work Began01-11-16
Work Completed
Time Computed01-04-16
Contract Working Days420
Addl Days Granted0
Working Days Charged202
Percent Time Used48
Contractor(s)
PANNELL INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6291-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10154215
Totals1215303.1056588.60842428.4069.3

CountyHIDALGO
HighwayIH0002
FromDISTRICT WIDE
ToVARIOUS
CSJ6295-89-001
Proj IDRMC - 629589001
Work TypeMAINTENANCE & REPAIR OF SAFETY LIGHTING
 
0.010353685.00223074.3063.0
Work Order04-04-16
Work Began04-04-16
Work Completed
Time Computed04-04-16
Contract Working Days220
Addl Days Granted60
Working Days Charged228
Percent Time Used81
Contractor(s)
STAR OPERATIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6295-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12154217
Totals353685.0072730.00223074.3063.0

CountyCAMERON
HighwayFM1419
FromVARIOUS
ToVARIOUS
CSJ6295-90-001
Proj IDBPM - 629590001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010455673.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6295-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03174214
Totals455673.000.000.000.0

CountyHIDALGO
HighwaySH0336
FromSH 336 OVER HACKNEY LAKE FLOODWAY
ToFM 2061 OVER MCALLEN LATERAL DRAIN
CSJ6295-91-001
Proj IDBPM - 629591001
Work TypeBRIDGE PREVENTIVE MAINTENANCE
 
0.010344250.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
VALLEY INFRASTRUCTURE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6295-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174234
Totals344250.000.000.000.0

CountyCAMERON
HighwaySH0004
From4,850 FT. EAST OF FM 1419
ToEND OF STATE MAINTENANCE
CSJ6295-93-001
Proj IDRMC - 629593001
Work TypeREHABILITATION ON SH 04
 
0.0103036343.55888421.5929.2
Work Order11-22-16
Work Began01-09-17
Work Completed
Time Computed01-02-17
Contract Working Days120
Addl Days Granted0
Working Days Charged53
Percent Time Used44
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6295-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164217
Totals3036343.55437804.02888421.5929.2

CountyCAMERON
HighwayFM1847
FromVARIOUS LOCTIONS
ToIN PHARR DISTRICT
CSJ6296-43-001
Proj IDRMC - 629643001
Work TypeSEAL COAT
 
0.0102420595.572319569.3395.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged53
Percent Time Used88
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12154215
Totals2420595.570.002319569.3395.8

CountyCAMERON
HighwayBU0083S
FromVARIOUS LOCATIONS
ToCAMERON COUNTY (SAN BENITO/BROWNSVILLE)
CSJ6296-66-001
Proj IDRMC - 629666001
Work TypeCLEANING AND SWEEPING OF HIGHWAYS
 
0.010634812.75344414.0054.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-08-16
Work Completed
Time Computed00-00-00
Contract Working Days380
Addl Days Granted0
Working Days Charged284
Percent Time Used74
Contractor(s)
PANNELL INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12154016
Totals634812.750.00344414.0054.2

CountyCAMERON
HighwayBU0077X
FromDISTRICT WIDE
ToVARIOUS
CSJ6296-77-001
Proj IDRMC - 629677001
Work TypeOVERLAY, PLANING AND PAVEMENT MARKINGS
 
0.0104207370.102788851.8566.2
Work Order06-03-16
Work Began10-30-16
Work Completed
Time Computed10-31-16
Contract Working Days100
Addl Days Granted17
Working Days Charged69
Percent Time Used58
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05164205
Totals4207370.1079383.252788851.8566.2

CountyHIDALGO
HighwayUS0281
FromVARIOUS LOCATIONS
ToIN PHARR DISTRICT
CSJ6296-78-001
Proj IDRMC - 629678001
Work TypeSEAL COAT
 
0.0102846120.05149625.665.2
Work Order12-07-16
Work Began03-31-17
Work Completed
Time Computed04-01-17
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6296-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164217
Totals2846120.05149625.66149625.665.2

CountyHIDALGO
HighwayIH0069C
FromVARIUOS LOCATIONS
ToDISTRICT WIDE
CSJ6306-96-001
Proj IDRMC - 630696001
Work TypeCRACK SEAL
 
0.010436478.00391153.8089.6
Work Order11-03-16
Work Began02-13-17
Work Completed
Time Computed01-30-17
Contract Working Days50
Addl Days Granted0
Working Days Charged44
Percent Time Used88
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6306-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164018
Totals436478.00203859.80391153.8089.6

CountyHIDALGO
HighwayFM0490
FromHIDALGO COUNTY
ToVARIOUS ROADWAYS
CSJ6309-44-001
Proj IDRMC - 630944001
Work TypeFM MOWING
 
0.010522619.67173200.9533.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-06-17
Work Completed
Time Computed00-00-00
Contract Working Days150
Addl Days Granted0
Working Days Charged10
Percent Time Used6
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6309-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164220
Totals522619.670.00173200.9533.1

CountyCAMERON
HighwayFM1847
FromCAMERON_COUNTY
ToWILLACY COUNTY
CSJ6309-45-001
Proj IDRMC - 630945001
Work TypeFM MOWING
 
0.010576600.950.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-06-17
Work Completed
Time Computed00-00-00
Contract Working Days150
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6309-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164219
Totals576600.950.000.000.0